DOUBLING OF NAJRAN - SULAYYIL ROAD PROJECT

AT L = 40.40 KMS , SECTION - 03

PROGRESS WORK ACCOMPLISHMENT


PERIOD COVERED : UP TO THE END OF SHABAN 1428H
A. STRAIGHT LINE DIAGRAM

S T A T I O N I N G S
ITEMS DESCRIPTION OF WORKS
316+104.867 320+000 325+000 3330+000 335+000

4050301 Bit. Wearing Course

4050101 Bit. Binder Course

START OF PROJECT
4020102 Meduim Curing -I

MATCH LINE
3030101 Aggte. Base Course

Sub grade - II
20601
Sub grade - I

Bottom of Sub grade


EMBK.

20501
Layers

S T A T I O N I N G S
ITEMS DESCRIPTION OF WORKS
335+000 340+000 345+000 350+000 355+000

4050301 Bit. Wearing Course

4050101 Bit. Binder Course

4020102 Meduim Curing -I

END OF PROJECT
STA. 355+500.00
MATCH LINE

3030101 Aggte. Base Course

Sub grade - II
20601
Sub grade - I

Bottom of Sub grade


EMBK.

20501
Layers

B. DETAILS

TOTAL LENGTH TOTAL WORK ACCOMPLISHMENT IN KMS. REMAINING BAL. LEGEND :


ITEMS DESCRIPTION OF WORKS REMARKS
( KMS. ) Previous This Month To Date ( Kms. )
4050301 Bit. Wearing Course = SCHEDULE
4050101 Bit. Binder Course
4020102 Meduim Curing - I = PREVIOUS
3030101 Aggte. Base Course 39.00
Sub grade - II 13.000 8.000 21.000 18.000 = THIS MONTH
20601
39.00

20601
Sub grade - I 14.000 11.000 25.000 14.000
20501 Bottom Sub grade 27.000 3.000 30.000 9.000
DOUBLING OF NAJRAN - SULAYYIL ROAD PROJECT
AT L = 39.00 KMS , SECTION - 03

PROGRESS WORK ACCOMPLISHMENT


PERIOD COVERED : UP TO THE END OF RAMADAN 1428H
A. STRAIGHT LINE DIAGRAM

S T A T I O N I N G S
ITEMS DESCRIPTION OF WORKS
316+104.867 320+000 325+000 3330+000 335+000

4050301 Bit. Wearing Course

4050101 Bit. Binder Course

START OF PROJECT
4020102 Meduim Curing -I

MATCH LINE
3030101 Aggte. Base Course

Sub grade - II
20601
Sub grade - I

Bottom of Sub grade


EMBK.

20501
Layers

S T A T I O N I N G S
ITEMS DESCRIPTION OF WORKS
335+000 340+000 345+000 350+000 355+000

4050301 Bit. Wearing Course

4050101 Bit. Binder Course

4020102 Meduim Curing -I

END OF PROJECT
STA. 355+150
MATCH LINE

3030101 Aggte. Base Course

Sub grade - II
20601
Sub grade - I

Bottom of Sub grade


EMBK.

20501
Layers

B. DETAILS

TOTAL LENGTH TOTAL WORK ACCOMPLISHMENT IN KMS. REMAINING BAL. LEGEND :


ITEMS DESCRIPTION OF WORKS REMARKS
( KMS. ) Previous This Month To Date ( Kms. )
4050301 Bit. Wearing Course = SCHEDULE
4050101 Bit. Binder Course
4020102 Meduim Curing - I = PREVIOUS
3030101 Aggte. Base Course 39.00 0.000 6.095 6.095 32.905
Sub grade - II 21.000 3.000 24.000 15.000 = THIS MONTH
20601
39.00

20601
Sub grade - I 25.000 3.500 28.500 10.500
20501 Bottom Sub grade 30.000 2.500 32.500 6.500
Completion of Ring Road in Al-Ehsa
(Southern, Eastern & Northern sides)
Length = 15.00 KMS

PROGRESS WORK ACCOMPLISHMENT


PERIOD COVERED: UP TO THE END OF Shuban 1429 H
A. STRAIGHT LINE DIAGRAM

S T A T I O N I N G S
ITEMS DESCRIPTION OF WORKS
74+000 75+000 76+000 77+000 78+000 79+000 80+000 81+000 82+000 83+000 84+000 84+700

L/S
4050301 Bit. Wearing Course
R/S

L/S
4050101 Bit. Binder Course
R/S

L/S
4020102 Meduim Curing -I
R/S

L/S
3030101 Aggte. Base Course
R/S

L/S
Sub grade - II
R/S
20601
L/S
Sub grade - I
R/S

L/S
20501 T.O.Embankment
R/S

B. DETAILS

TOTAL LENGTH TOTAL WORK ACCOMPLISHMENT IN KMS. REMAINING BAL REMARKS LEGEND :
ITEMS DESCRIPTION OF WORKS
KMS PREVIOUS THIS MONTH TO DATE KMS

4050301 Bit. Wearing Course = SCHEDULE


4050101 Bit. Binder Course
4020102 Meduim Curing - I = PREVIOUS
3030101 Aggte. Base Course 10.70
Sub grade - II 3.30 7.40 = THIS MONTH
20601
10.70

20601
Sub grade - I 3.40 7.30
20501 Bottom Sub grade 9.00 1.70