Académique Documents
Professionnel Documents
Culture Documents
October 2012, Vol. 25, Issue 8 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 21
[(Figure_1)TD$IG]
22 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 The Electricity Journal
[(Figure_2)TD$IG]
1. Demonstrate the viability of switches installed throughout Figure 3 shows the installation of
Perfect Power at IIT; campus to automatically a HRDS switch at IIT.
2. Allow for a decrease of 50
percent of grid electricity
demand;
isolate ground faults in feeder
segments while maintaining
service to all buildings on the
F or a building to experience a
complete outage due to
failure of the campus grid, at
3. Create a permanent 20 loop, and least two coincident and
percent decrease in peak demand Increased ease of deployment unrelated failures would have to
from the 2007 level; of on-site generation and storage occur in feeder segments on the
4. Defer planned substation to meet critical loads even in the same loop. Even though the
investments through demand absence of utility feed (i.e., island project did not call for
reduction; mode). replacement of the entire
5. Demonstrate the economic Figure 2 depicts the seven-loop campus infrastructure, the
benefits of Perfect Power, and configuration established at IIT in chances of two such failures
6. Offer a design that can be which each loop, connected to one occurring simultaneously is far
replicated on any other microgrid. of the two substations, is less than the chances of one
The microgrid design equipped with HRDS switches. occurring, thus increasing
addresses three areas of service [(Figure_3)TD$IG]
including reliability, efficiency,
sustainability, as discussed
below.
A. Reliability
October 2012, Vol. 25, Issue 8 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 23
[(Figure_4)TD$IG]
B. Sustainability
24 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 The Electricity Journal
[(Figure_6)TD$IG]
interaction with the grid services. campus operators can input relay the real-time usage
desired performance parameters information to the master
C. Efficiency and establish load priorities that controller, as opposed to
the master controller will then use standard meters that convey
An increased awareness of to make decisions to keep the usage only after the fact. The
campus electricity needs, coupled campus load under the desired Siemens building controllers and
with increased control over loads, profile. The IIT microgrid is the smart feeders with real-time
would give the operations and equipped with 12-phase monitoring and control systems
maintenance staff and end users measurement units (PMUs) that can respond to higher electricity
more information, which would [(Figure_8)TD$IG]
lead to more effective use of the
electricity. In real time, the
university would need to avoid
load increases that would push
the campus beyond the capacity
of the current substations and
require IIT to build another
substation. Figure 4 shows that
the campus is equipped with a
three-level hierarchical control
for managing the load at normal
and emergency conditions. IIT Figure 8: Charging Station
October 2012, Vol. 25, Issue 8 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 25
[(Figure_9)TD$IG]
The entire IIT campus is Galvin Center has been very Grid education and research
regarded as a living laboratory for proactive in soliciting external laboratories on the 16th floor of the
Smart Grid education and funds for the procurement and IIT Tower and in Siegel Hall.
training. The microgrid the installation of intelligent Figure 9 depicts one of the Power
installation at IIT includes a devices at IIT, and will continue System Operator Training rooms
digital-based metering system, a its mission of raising funds for at the Galvin Center. Figure 10
monitoring system based on training and education of the next shows the tabletop model of the
PMUs, HRDS switches, campus generation of the Smart Grid campus that is in use at the Galvin
master controller, gas-fired power workforce. The Galvin Center, at Center for demonstrating the
plant, solar and storage units, www.galvinc enter.org, with benefits of applying the reliability
wind generating unit, charging Department of Energy support, loops to the IIT microgrid.
stations for electric vehicles, and has established a microgrid Figure 11 shows a wind unit
building control system serviced training center which prepares training facility at IIT, with an
by Siemens. The benefits of the workforce and the next experimental wind unit that is
microgrid implementation at IIT generation of professionals that identical to the wind unit installed
hinge on the ability of the Office of will build and maintain at the IIT soccer field. The
Facilities Maintenance microgrids in the United States. laboratory unit is equipped with a
Management to use the new tools
and establish procedures for
preventative maintenance. The
I n addition, the Galvin Center
has set up several microgrid
demonstration rooms and Smart
flywheel, which simulates the
variable wind speed for
generating the electricity in the
26 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 The Electricity Journal
[(Figure_1)TD$IG]
V. Summary and
Figure 12: Wind Unit Data Conclusions
October 2012, Vol. 25, Issue 8 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 27
partnered with Cook County to program has lead a cross- members relate to this campus
implement a student-generated curricular process to build and where they study, work, and
composting process on campus, a manage an urban farm on play. Beyond the research
group of students has developed campus. Bursting forth from this dollars received and the
a utility management model that simple idea to improve the awards won, the change in the
promotes energy efficiency and reliability of the campus campus environment and the
serves as an inspiration for the electricity infrastructure comes a creation of a true living lab
present model of organization for freight train seeking to make stand as the strongest benefits
that department, and the Master’s rapid and lasting change in the of implementing a microgrid
in Landscape Architecture way students, faculty, and staff at IIT.&
IIT has opened the campus as a living laboratory – not just for research but for the implementation
of ideas coming from students, faculty, and staff.
28 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., http://dx.doi.org/10.1016/j.tej.2012.09.015 The Electricity Journal