Académique Documents
Professionnel Documents
Culture Documents
Features
MBCI Pilot wire differential A
protection relay
B
● High stability for through faults
C
● High speed operation for in-zone
faults
Trip Trip
● Simultaneous tripping of relays at Rpp Rpp
T2 T2
each line end T1 T1
Tr Tr
● Low current transformer Rs Tt øc øc Rs
requirements To To
Pilot wires
● Low earth fault settings RVD Ro Ro RVD
Ts
● Designed for the unit protection of V V
2
Application detect short circuit and cross- Emergency use for overcurrent
connected pilot conditions which protection
The Translay S differential schemes would not otherwise be detected. In the event of a pilot failure which
have been designed for the unit Indication is also provided for loss of cannot quickly be rectified, the
protection of overhead and the supervision supply. Translay S scheme may be adapted
underground feeders and transformer for use as a definite time overcurrent
feeders. Destabilising/intertripping
relay as follows:
When the protected line is connected
Plain Feeders to a busbar system, a fault on the If overcurrent relay is fitted
Differential protection busbars will in general be cleared by ● disconnect pilot wires and leave
Differential feeder protection requires the busbar protection by opening terminals open circuited
a comparison of the currents entering some or all of the local circuit
● set Kt to 3(300ms)
and leaving the protected zone. For breakers. Although such faults will
usually appear to the feeder ● check that overcurrent elements are
faults occurring within the protected
protection as through faults, with on the required setting above
feeder it is desirable to trip the circuit
resultant stability of the feeder maximum anticipated load current.
breakers at each end to isolate the
fault. Two MBCI relays are therefore protection, it may be desirable to If overcurrent relay is not fitted
required, one for each end of the open the remote line circuit breaker ● disconnect pilot wires and connect
feeder. A pair of pilot wires is used to also, to clear the line completely. a 1kΩ resistor across pilot terminals
transmit information between the two The remote unit of the differential of relay
relays so that each may be able to feeder protection can be caused to ● set padding resistors Rpp to
compare the current flowing at its operate, provided sufficient line maximum (600Ω)
respective end with the current at the current is flowing, by open circuiting
● set Kt to 3 (300ms)
other. the pilots. If line current is not flowing,
the remote unit can be operated ● set Ks to required open circuit
The relays at both line ends operate
(intertripped) by injecting a current setting: Ks = 1 gives three phase
simultaneously, providing rapid fault
into the pilots. equal to rated load Ιn.
clearance irrespective of whether the
NOTE: Other fault settings will
fault current is fed from both line ends
Overcurrent check/starting depend upon the summation ratio.
or only one line end.
Although the supervision scheme
When applying this protection to
provides indication of pilot failure it
overhead lines the limiting factor is
does not prevent the protection
generally the length of the pilot
operating if primary current above
circuits: for cable feeders the limiting
setting is flowing. Where this hazard
factors are more likely to be the level
is unacceptable it is necessary to add
of line charging current and the
an overcurrent check feature.
method of system earthing.
The current transformer requirements
Pilot supervision are not modified by the addition of
Correct interchange of information overcurrent elements since they
over the pilot circuit is essential for the present a very low burden.
proper functioning of any differential When the starting feature is used the
feeder protection. overall operation time of the scheme
Pilots may be exposed to hazards and is increased by 3-5ms. However,
some risk of damage and failure there is no increase in the overall
always exists. The most common pilot operation time when the overcurrent
failure is to the open circuit state, protection performs a check function
caused by the accidental excavation only.
of buried pilots or storm damage to When overcurrent relays are used the
overhead pilots. With the pilots open protection cannot be intertripped by
circuited the differential protection will ac injection into the pilots, and
be unstable and will trip the feeder if destabilising the protection will result
sufficient through current is flowing. in tripping only if an overcurrent
For this reason the circulating current condition exists simultaneously.
system is often preferred as such
schemes will fail safe and trip so that
attention is immediately drawn to the
fault. The addition of pilot supervision
will not prevent tripping for pilot faults
but will indicate the cause. It will also
3
Protected Zone Protected Zone
P1 P2 P2 P1
A
S1 S2 S2 S1
B
C
12
See
RS Note 5 RS
MBCI 13 + MBCI
Power
23 Supply VX
Circuits 14
ΙA –
See
Note 4
24
25
& Enable 11
See
23
24 ΙA
Squarer Kt 1
ΙB
RL1
2 Note 2 25
RL1–1 3
26
5 26 ΙB
27 Enable
A 27
ΙC 2
Level RL2 28 ΙC
ΙN 28 2 RL1–2 4
C B Detector 6 ΙN
Phase OP
Trip/
&
RL3
Rotation 1 Alarm
KS RES 7
RO Outputs
RL2–1 9
Squarer
Case Earth
See Note 3 8
Case earth
RL2–2
1 2
3 4
10
RPP 17
5 6
7 8
9 10 18 Pilot
11 12
Wires
13 14 19
15 16
17 18
Notes
19 20
1. (a) C.T. shorting links make before (b) & (c) disconnect. 3. Earthing connections are typical only.
21 22 Module
23 24 terminal block (b) Short terminals break before (c) 4. C.T. connections are typical only.
25 26
viewed from (c) Long terminal. 5. For overcurrent start schemes, terminal 12 must be
rear connected directly to D.C. +VE to provide a supply for
27 28
2. Link terminals 11 and 13 except when used with overcurrent the L.E.D. and reset circuits.
check replay type MCRI.
17 17
18 18
17 18 17 18
19
Case 20
Earth MRTP02
20
RL2 OP RL7
2 1 Supply
19 Reset
Fail
A.C. 27 OP
A.C. RL1 RL3 RL6 1
Auxiliary 2 2 1 Pilot
28 Power Reset RL4–1 3
Supply Supply S/C Output
13 OP RL8
5 Contacts
D.C. Reset 1 Pilot 2 Change
Case earth Vx 14 Power O/C RL4–2 4 state for
Supply
1 2 RL4 6 pilot fail
3 4 2
7
5 6
RL5–1 9 Output
7 8
9 10 11
Contacts
11 12
MRTP01 Change
8
13 14 +VE
RL5 state for
2 RL5–2 10
supply
15 16
RL1 RL2 RL3 RL1 RL2 RL3 12
17 18 Case fail
–1 –1 –1 Start –2 –2 –2
19 20
Earth t
21 22
23 24
25 26 Module terminal block Note 1.
27 28
viewed from rear (a) C.T. shorting links make before (b) & (c) disconnect.
(b) Short terminals break before (c).
(c) Long terminal.
Figure 3: Application diagram: pilot supervision relay and injection filter type MRTP 01
4
Pilot isolation Pilot isolation
transformer transformer
P6 S2 S1 P1
17 17
P5
P4 X2 X1
P3
P2
MBCI Pilots MBCI
P2
X2 P3
X1 P4
P1 S1 S2 P5
18 18
P6
S1 S2 Supervision
isolation
P1 P2 transformer
20 OP
RL2 RL7
2 1 Supply
19 Reset See
Fail
A.C. 27 OP Note 7
A.C. RL1 RL3 RL6 1
Auxiliary 2 2 1 Pilot
28 Power Reset RL4–1 3
Supply Supply S/C Output
13 OP RL8
5 Contacts
D.C. Reset 1 Pilot 2 Change
Vx 14 Power O/C RL4–2 4 state for
Case earth Supply
RL4 6 pilot fail
1 2 2
3 4
7
RL5–1 9
Output
5 6
Contacts
7 8 11
9 10 MRTP 03 Change
8
11 12 +VE
RL5 state for
13 14
2 RL5–2 10
supply
16
RL1 RL2 RL3 RL1 RL2 RL3 12 fail
15 Case –1 –1 –1 Start –2 –2 –2
17 18
Earth t
19 20
21 22
23 24 Note 1.
25 26
(a) C.T. shorting links make before (b) & (c) disconnect.
27 28
Module terminal block (b) Short terminals break before (c).
viewed from rear (c) Long terminal.
Figure 4: Application diagram: pilot supervision relay 15kV isolation type MRTP 03
P1 P2
A A
S1 S2
B
C C B +
D.C. _
See Phase
Note 4 Rs Rotation
See Note 2(B)
13 See Note
Power 23 11
2(A)
supply 24
14 13
circuits 25
23 ΙS (A) 26 14
27
Case earth 24 28
1 2
25
3 4 ΙS ( ) RL1
5 6 2 5
26 RL1–1 1 MBCI
7 8
27 3
9 10
ΙS (C)
11 12 6
13 14 RL1–2 2
28
15 16 Case earth MCRI 4
17 18 See Note 3
19 20
Case earth
21 22
See Note 3
23 24 Notes
25 26
1. (a) C.T. shorting links make before (b) & (c) disconnect. 2. (A) Connection for overcurrent start
27 28
Module terminal block (b) Short terminals break before (c). (B) Connection for overcurrent check
viewed from rear (c) Long terminals. 3. Earthing connections are typical only
4. C.T. connections are typical only
5
Transformer Feeders
Scheme Pilot Supervision O/C
(Use of transformer inrush current Insulation Start/Check Arrangement of Equipment
detector) Level (kV) (Viewed from front)
In the case of transformer feeders
A 5kV — —
where there is no circuit breaker 1 1
side only.
1 8 4 9 7 1 8
When the feeder transformer is L 15kV ●
energised any resulting inrush current
M 5kV — 1 8 1 8
will be detected by the MCTH relay,
the output blocking unit of which will
N 15kV — 1 8 1 8
pick-up causing the pilot wires of the
Translay S to be short-circuited. This 1 8 2 1 8 3
O 5kV ●
will stabilise the differential relay and
prevent it from responding to what 1 8 4 1 8
P 15kV ●
would otherwise appear to be an in-
zone fault. Table 2. Typical scheme arragements for transformer feeders. See key below.
The immunity to operation due to No. Type of relay
inrush current is coupled with fast fault
1 MBCI 01/02 Differential
clearance times and the built-in
2 MRTP 01 Pilot supervision and injection filter
overcurrent detectors of the MCTH
3 MRTP 02 Injection filter
relay ensure that the blocking feature
4 MRTP 03 Pilot supervision
is overridden if a fault is detected in
5 MCRI 01 Overcurrent start/check
one phase whilst inrush is present in
another. 6 MVTW 01 Destabilising
7 MVTW 03 Destabilising and Intertripping
Symbols: Schemes A to D can be fitted with relay types 6 or 7.
Schemes E to H can be fitted with type 6 which will provide
destabilising if the overcurrent start/check relays (MCRI 01)
have operated. Schemes I to L must use type 7 or 8.
15kV Isolating transformer 8 MCTH 01 Transformer inrush current detector
9 MFAC 14 High impedance earth fault relay
10 MMLG Test plug/block
It is advisable on all schemes to include the test unit to
15kV Isolating transformer with facilitate commissioning and routine testing. The unit will be
injection filter situated on the right–hand side of the scheme.
6
Description faults ΙX=ΙY). The expressions are of Pilot supervision
opposite sign for values of ΙY which Figure 3 shows the arrangement for
Differential protection are negative relative to ΙX and are pilot supervision in a pilot circuit
The differential feeder protection between 0.5ΙX and 2ΙX in value. The insulated for 5kV. In this instance the
circuit is derived from the well known system is stable with this relative injection filters and the supervision
Merz-Price circulating current system polarity and operates for all values of unit are assembled with the relay
but employs phase comparators as the ΙY outside the limits. case. (Types MRTP 01/02). Figure 4
measuring elements. This novel The phase comparator has angular shows the similar arrangement for
combination provides high stability limits of ± 90° giving a circular bias pilot circuits insulated for 15kV (Type
performance for external faults with characteristic in the complex plane. MRTP 03). The injection filters are
the minimum of bias (restraint) If the pilots are open circuited, current then assembled as part of the isolation
quantity thereby ensuring that the low input will tend to operate the relay. transformer and have to be isolated
earth fault settings are effectively Conversely, short-circuited pilots will from the supervision relay. The
retained even when load current is cause the relay to restrain, holding its supervision isolation transformer
flowing. contacts open. provides the necessary 15kV isolation
Figure 1 shows the basic circuit barrier. For further technical
Transformers T1 and T2 also provide
arrangement. A summation current information see Publication R6026.
the necessary insulation barriers for
transformer T1 at each line end static circuitry. Destabilise and Intertrip Facilities
produces a single phase current
The input circuits of the phase MVTW01
proportional to the summated three
comparator are tuned to the power
phase currents in the protected line. Refer to Figure 6.
frequency so that the threshold of
The neutral section of the summation Operation of the destabilising relay
operation increases with frequency.
winding is tapped to provide (UN) results in the summation current
This de-sensitises the relay to the
alternative sensitivities for earth faults. transformer in the differential relay
transient high frequency charging
The secondary winding supplies current that flows into the line when it being short circuited and the local
current to the relay and the pilot is energised. A further advantage relay prevented from tripping. The
circuit in parallel with a non-linear provided by the tuned input is that the remote relay then sees a single end
resistor (RVD). The non-linear resistor waveform of the derived signal, which feed condition and trips, provided the
can be considered to be non- may be severely distorted by current through current exceeds the no-load
conducting at load current levels. transformer saturation, is improved, fault setting of the protection (see
Under heavy fault conditions it ensuring high speed operation under Table 5 page 16). Typical operating
conducts an increasing current and adverse conditions. times are shown in Figure 7.
thereby limits the maximum secondary In order to maintain the bias Terminals 17 and 20 should normally
voltage. At normal current levels the characteristic at the designed value it be linked together on the destabilising
secondary current flows through the is necessary to pad the pilot loop relay. However, the operating level of
operating winding To on transformer resistance to 1kΩ. the remote equipment can be reduced
T2 and then divides into two separate to one half of the normal fault setting
A padding resistor Rpp is provided in
paths, one through Ro and the other (under destabilising operation only) if
the relay for this purpose.
through the restraint winding Tr of T2, this link is omitted.
the pilot circuit and resistor Ro of the Pilot isolation transformers It should be noted that, with this link
remote relay. omitted, if the destabilising relay UN
When pilot isolation transformers are
The resultant of the currents flowing in used, the range of primary taps is operated for longer than the
Tr and To is delivered by the third enables pilots of loop resistance up to supervision time delay (6-10 seconds)
winding on T2 to the phase 2.5kΩ to be matched to the relay. an indication of pilot failure will be
comparator and is compared with the The pilot insulation level is also raised given. This does not apply if pilot
voltage across Tt of Transformer T1. to 15kV by these transformers. isolating transformers are used.
The emf developed across Tt is in When overcurrent elements are used
phase with that across the secondary Telephone type pilots to provide a starting or check function
winding Ts which is in turn When the pilots to be used are of the there is no advantage in removing this
substantially the voltage across Ro. telephone type, an alternative limiter link since, for operation, the through
Taking into account the relative values based on a zener diode is available current must exceed the overcurrent
of winding ratios and circuit to ensure that the maximum voltage setting.
resistance values, it can be shown that which can appear on the pilot system
the quantities delivered for is within prescribed limits. Pilot
comparison in phase are: isolating transformers can be used in
(ΙX + 2ΙY) and 2ΙX + ΙY) this arrangement also, both to provide
insulation to 15kV and also indirectly
where ΙX and ΙY are the currents fed
to enable pilots of relatively high
into the line at each end (for through
resistance to be used.
7
MVTW 03
Pilot isolation transformer P6 S2
A circuit diagram for the MVTW 03 17
type relay which depicts the Pilots
destabilising, intertrip and inverter P1 S1
function is shown in Figure 8. MBCI
On energising the relay, a green led 17 UN-1
illuminates and the normally closed
18
contacts of RL1 open to indicate the 18 UN-2
supply is healthy and the inverter is 19
19
operating. UN-3
20
The MVTW 03 incorporates a full Case earth
1 2
bridge inverter, which receives 11 UN
3 4 Vx(1)+ 3
complementary square wave signals 5 6
Vx(2)+
12
7 8 13
from the oscillator circuit at a 9 10
Vx(3)+
14
frequency of 80Hz. This frequency 11 12
13 14
was chosen because it lies sufficiently 15 16 MVTW 01
far from the pilot frequency of 50 or 17 18
8
Pilot isolation transformer P6 S2
17
Pilots
P1 S1
MBCI
17
18
18
19
19
11+VE
Trip send
Case earth RL2
2
1 2 RL2-2
3 4
5 6
7 8
9 10 RL2-1
11 12 13+VE
13 14 RL1-1 1
Power
15 16 Vx RL1
2 Supply fail
14–VE supply 1
17 18 MVTW 03
19 20
Supply
21 22
23 Case earth See note 2 healthy
24
25 26
27 28 Notes
1. (a) CT shorting links make 2. Earthing connections as shown is typical only
before (b) & (c) disconnect
Module terminal block
(b) Short terminals break before (c)
viewed from rear
(c) Long terminals
P2 P2 P1
A I i A
S1 S2 S2 S1
B II ii B
C III iii C
yn
N.E.R.
23 MCTH MCTH 23
24 24
17 17
25 25
26 26
19 19
27 27
28 28
23 MBCI 17 17 MBCI 23
24 24
25 Pilots 25
26 26
27 18 18 17 18 27
28 19 19 28
MVTW03
MFAC14 1
27
RVD3 3
28 11
Note1: It is essential that the current transformer connections are earthed at one point only.
9
N = 6 A–N
15 3
10 2
N = 3 B–N
5 1
A–C
A–B
1 2 1A relay
0
5 10 5A relay
Current in summation current transformer primary – Amps
200 Metrosil
Limiter
160
Pilot Voltage (V Peak)
120
Zener
80
Limiter
40
0 10 20 30
A-N fault current (x In)
10
2.0
1.8
1.4
1.2
1.0
0 1 2 3 4 5
Pilot intercore capacitance -µF
Figure 12: Effect of pilot capacitance and pilot isolating transformers on setting
20 10
Figure 13: Minimum earth fault current for operation with through load
11
CTs
CTs
RL RL RL
CTs
End A End B
Pilots
Relay Relay
240
200
Operation time (Milliseconds)
160
120
80 Kt = 6
Kt = 14
40 Kt = 20
Kt = 40
0
1 2 3 4 5 6 10 20 30 40 50 60 80 100
Current (multiples of setting)
60
Induced pilot loop voltage to operate
40
20
0
0.5 1.0 1.5 2.0
Setting multiplier – Ks
12
Transformer (Dy 11)
Feeder
Delta Star
23 25 27 17 17 23 25 27
MFAC N.E.R.
MCTH MCTH
inrush A B C REF inrush A B C
detector detector
24 26 28 19 19 24 26 28
MBCI MBCI
23 23
25 1.25 17 17 1.25 25
27 1 1 27
24 6 6 24
18 Pilots 18
26 26
28 28
Figure 17: Overall protection of transformer feeders showing connections to MBCI relays
13
Contacts
Contact arrangements 2 make and 2 change-over
(See Figure 2)
Contact ratings
Make and carry for 0.2s 7500VA subject to maxima of 30A
and 300V ac or dc
Carry continuously 5A ac or dc
Break ac 1250VA
dc 50W resistive
25W inductive
L/R = 0.045s
subject to maxima of 5A and 300V
Durability
Loaded contact 10,000 operations minimum
Unloaded contact 100,000 operations minimum
Reset time Less than 100ms
Indication A non-volatile led trip indicator is used.
If the auxiliary supply is lost the led will
return to the same state when the supply
is restored.
Stability level The stability of the protection for through
faults is greater than 50Ιn
High voltage withstand
Dielectric withstand
IEC 255-5: 1977 2.0kV rms for 1 minute between all
terminals and case earth.
2.0kV rms for 1 minute between all
terminals of independent circuits, with
terminals on each independent circuit
connected together.
5.0kV rms for 1 minute between pilot
terminals and all other terminals and
case earth.
1.0kV rms for 1 minute across
normally open contacts.
High voltage impulse
IEC 255-5: 1977 Three positive and three negative
impulses of 5.0kV peak, 1.2/50µs,
0.5J between all terminals and all
terminals and case earth.
Electrical environment
DC supply interruption
IEC 255-11: 1979 The unit will withstand a 10ms
interruption in the auxiliary supply,
under normal operating conditions,
without de-energising.
AC ripple on dc supply
IEC 255-11: 1979 The unit will withstand 12% ac ripple
on the dc supply.
High frequency disturbance
IEC 255-22-1: 1988 Class III 2.5kV peak between independent
circuits and case.
1.0kV peak across terminals of the
same circuit.
14
Fast transient disturbance
IEC 255-22-4: 1992 Class IV 4.0kV, 2.5kHz applied directly to
auxiliary supply.
IEC 801-4: 1988 Level 4 4.0kV, 2.5kHz applied to all inputs.
Surge immunity
IEC 1000-4-5: 1995 Level 3 2.0kV peak, 1.2/50µs between all
groups and case earth.
2.0kV peak, 1.2/5-µs between
terminals of each group.
EMC compliance
89/336/EEC Compliance to the European
Commission Directive on EMC is
claimed via the Technical Construction
File route.
EN 50082-2: 1994 Generic Standards were used to
EN 50082-2: 1995 establish conformity.
Product safety
73/23/EEC Compliance with European Commission
Low Voltage Directive.
EN 61010-1: 1993/A2: 1995 Compliance is demonstrated by
EN 60950: 1992/A3: 1995 reference to generic safety standards.
Atmospheric environment
Temperature
IEC 255-6: 1988 Storage and transit –25°C to +70°C
Operating –25°C to +55°C
IEC 68-2-1: 1990 Cold
IEC 68-2-2: 1974 Dry heat
Humidity
IEC 68-2-3: 1969 56 days at 93% RH and 40°C
Enclosure protection
IEC 529: 1989 IP50 (dust protected)
Mechanical environment
Vibration
IEC 255-21-1: 1988 Response Class 1
Pilots
Pilots isolation
Pilot isolation transformers are required when any longitudinally induced voltage
in the pilot circuit is likely to exceed 5kV: in effect this means when protecting
feeders operating at voltages in excess of 33kV, unless these are short in length.
The use of pilot isolation transformers also extends the acceptable range of pilots.
This is achieved by the matching ratios available as shown in Table 4.
Pilots
KM 0.8 1.0 1.2 1.5 2.5 Matching ratio
Loop resistance 800 1000 1200 1500 2500 Ω
Capacitance 6.25 5 4.2 3.3 2 µF
Terminals P1-P6 P1-P5 P1-P4 P1-P3 P1-P2
Table 4
15
Rp
The optimum value for KM is the nearest value in Table 4, where Rp is the
1000
measured pilot loop resistance.
There are two types of pilot isolation transformers: ZC0244-002 for schemes
without pilot supervision: HN0068-001 for schemes with pilot supervision.
The latter includes the injection filter for the pilot supervision circuit.
1 R
The pilot padding resistor (Rpp) at each end should be set to: 1000 – p
2 KM
Pilot voltage
The voltage applied across the pilots varies with fault current as shown in
Figure 12. For normal through load conditions the peak pilot voltage will be in
the order of 50V rising to a maximum of: 200V for MBCI 01, 80V for MBCI 02
under fault conditions.
When pilot isolation transformers are used this value of voltage is multiplied
by √ KM.
Note: Types MBCI 01 and 02 are not compatible. Relays should be of the same
type at either end.
Pilot current
The pilot current is typically 30mA for normal through load conditions and rises
to a maximum of 300mA under through fault conditions.
16
phases involved in the fault. The minimum earth fault current (Ιf) should be greater
than twice the least sensitive earth fault setting to ensure rapid fault clearance.
The range setting of fault settings is shown in Table 5.
Differential
(Summation ratio = 1.25/1/N) Fault Settings
N=3 N=6
Ks is a setting multiplier A–N 0.19Ks.Ιn 0.12Ks.Ιn
and may be varied B–N 0.25Ks.Ιn 0.14Ks.Ιn
from 0.5-2.0 C–N 0.33Ks.Ιn 0.17Ks.Ιn
Ιn is the A–B 0.8Ks.Ιn
rated relay B–C 1.0Ks.Ιn
current C–A 0.44Ks.Ιn
A–B–C 0.5Ks.Ιn
Table 5
The minimum operating current of the relay will be increased by any shunt
impedance connected across the pilot wires, for example, pilot capacitance and
the magnetising path of the pilot isolation transformers. The effect of the pilot
capacitance is shown in Figure 12.
Values of Ks from 0.5 to 1.0 are provided to achieve effective fault setting equal
to the nominal value indicated in Table 5. This is achieved by single end injection
tests during commissioning. Values of Ks from 1.0 to 2.0 are used to increase the
setting when the application demands. Refer to section: Line Charging current.
17
Magnetising current:
In order that the minimum effective operating current of the relay remains low, it
is necessary to apply a limit to the value of the magnetising current demanded
by the line current transformers:
10
IM ≤ 0.05 In at V
In
Mesh type switchgear arrangements
The relay may be fed by parallel connected current transformers as shown in
Figure 15. It is essential to balance the lead resistance in the circulating
secondary current path to ensure stability for a through busbar fault. Connecting
the current transformers as shown in Figure 15 will result in the required balance
being obtained. It is essential that the current transformers at the same end
should have similar magnetising characteristics. The value of RCT to be used in
calculations should be the resistance of one current transformer plus the
resistance of one lead between the two parallel connected current transformers.
The value of RL should be the resistance of a single lead from the common
connection of the current transformers to the relay.
Methods of reducing the current transformer requirements:
In general the larger the current transformer the better the overall performance.
However, when current transformer size is critical the following notes should
prove helpful.
● The operation time varies with fault current as shown in Figure 16. Stability is
maintained with smaller current transformers if the value of Kt is reduced. This
will of course result in the operation time increasing, typical operation times
being:
Kt 40 20 14 6 3
Time at 5x setting 30 50 65 90 300 (ms)
● Kt= 20 will suit most current transformers on distribution systems
Kt = 40 is the preferred setting for EHV systems where high speed operation
is required
● It should be noted that the knee point requirement increases with the nominal
current rating Ιn. Advantage is therefore obtained by using a low value of
rated current eg. 1A or even 0.5A.
● Wires may be connected in parallel to reduce the lead resistant (RL ) and
hence the current transformer requirements.
● If the relay is fed from delta connected line current transformer then N = 1.
● If one relay is used per phase then assume N = 1
Stabilising resistance
VK 12
Rs = Ω but not greater than Ω
40 In In2
Note: This resistor is not required for single phase protection or when Translay S
is fed from delta connected current transformers.
Additional requirements:
● It is a stability requirement that the relays at both ends have the same value of
N & Kt selected.
● It is preferred, although not absolutely essential, that the equipment at the two
line ends have the same rated current Ιn.
18
current in the relay: this current must cause the fuse to operate quickly enough to
discriminate. Most fusing time curves show pre-arcing time and some allowance
must be made for the arcing period.
To accommodate the largest teed load, use may be made of the Ks (setting
multiplier) adjustment, and/or selection of a value of Kt corresponding to a lower
operating speed.
The particulars tabulated below for teed loads connected to a fused 11kV feeder
may be helpful as a general example.
Feeder 11kV 300A rating
Tee Transformer rating(kVA) Fuse rating (A) Ks Kt
300 20 1 40
400 25 1.7 40
400 25 1.5 6
500 30 1.75 3
Table 6
The table above refers to individual teed loads. When smaller loads are connected
at separate locations, on the basis that only one will be subject to a fault at any
instant, the aggregate load may be greater. For example twelve 100kVA
transformers each protected by 10A fuses could be connected to the above line,
with main protection settings Ks = 1 and Kt = 40. Similarly for ten 300kVA
transformers each protected by 20A fuses, relay settings Ks = 2.0 and Kt = 20
would be suitable. In general the aggregate tee-off load should not exceed 0.25Ks x
current transformer rating.
19
Line Current Transformer Requirements for Transformer Feeders:
Operating times less than 80ms will be achieved and through fault stability assured
provided the following CT requirements are satisfied (Kt = 14):
Vs = If (I3 + R
n2
)
CT + RL
The effective primary operating circuit (Ιop) of the MFAC 14 is given by:
Iop = n(IR + NIIu)
Where IR = relay operating current and metrosil current at setting voltage
(see MFAC publication)
Iu = current transformer magnetising current at setting voltage (A)
Nl = number of connected current transformers
n = current transformer turns ratio
The following notes on this application are also important:
– A setting of 14 is recommended for Kt to ensure sufficient time for inrush blocking.
Tripping for internal faults will then occur (typically) within
60-80 ms.
– The N = 6 setting on the MBCI relay must be used to achieve increased sensitivity.
– Where the CT lead resistance is a predominant part of the CT burden at one, or
both, line ends then the use of 1A line CT’s is recommended. The selected rating
of current transformers must be the same as the relays (MBCI and MCTH) which
they supply.
– Additional conductors may be connected in parallel in order to reduce the lead
resistance (RL) and, hence, the current transformer requirements.
– The pilot resistance should not exceed 700Ω.
20
– With 15kV pilots, the MCTH output contacts should be connected on the relay
side of the isolating transformer to terminate numbers 17 and 18 of the MBCI
relay.
– The MCTH overcurrent settings for each phase, set by 3 front-mounted
potentiometers (one per phase), should be set at least 50% above the
maximum possible load current.
– The steady state magnetising current must not exceed the three phase fault
setting of the MCBI relay. For a Ks = 1 setting, the three phase fault setting is
14% of rated current. If the transformer is likely to be subjected to overfluxing,
with the corresponding increase in steady state magnetising current, then the
three phase setting must be permanently set above this higher magnetising
current by increasing Ks.
Cases
103.6
Relay type MBCI is provided in case 149 4 holes 4.4
23.5
size 6 as shown in Figure 18.
21
P1 2.5 1.5
1.2 1.0 0.9 S1 S2
Injections 172 mm
Inputs
X1 X2
340 mm
64.5 mm
154 mm
30 mm 116 mm 9 mm
176 mm
Figure 19: Pilot isolation transformer with filter. With insulation for 15kV
244 mm
176 mm 190 mm
45 mm
171.5 mm
8-M6 Terminals
9 mm
4 Fixing holes, M6 clearance
64.5 mm
30 mm 116 mm
Figure 20: Pilot isolation transformer without filter. With insulation for 15kV
22
19 mm 134 mm 19 mm 69 mm
S2
98 mm
S2
2 off M5 studs
2 off M5 studs
52 mm 69 mm
8.5 mm 50 mm 52 mm
Figure 21: Pilot supervision isolation transformer. With insulation for 15kV
2BA connection
screws
354 mm
48 mm
2 holes
6.5 mm 310 mm 48
mm
342 mm
23