INICIO
28-May 0.00%
4-Jun 3.00%
11-Jun 6.00%
18-Jun 9.00%
CURVA S
25-Jun 12.00%
2-Jul 16.00%
AVANCE PROGRAMADO
% DE AVANCE ACUMULADO
9-Jul 22.00%
16-Jul 32.00%
120.00%
23-Jul 45.00%
30-Jul 57.00%
6-Aug 71.00%
13-Aug 85.00%
20-Aug 95.00% 100.00%
27-Aug 98.00% 100.00% 98.00%
4-Oct 100.00% 95.00%
85.00%
80.00%
71.00%
28-May 0.00%
4-Jun 3.42%
11-Jun 6.48% 60.00% 57.00%
18-Jun 12.28%
25-Jun 19.24%
2-Jul 19.30%
45.00%
9-Jul 19.30%
16-Jul 22.56%
AVANCE EJECUTADO
40.00%
23-Jul 26.63%
30-Jul 32.07% 32.00% 32.07%
6-Aug
26.63%
13-Aug
22.00% 22.56%
20-Aug
19.24% 19.30% 19.30%
27-Aug 20.00%
16.00%
4-Oct
12.00%
12.28%
6.00% 9.00%
6.48%
3.42%
3.00%
0.00%
96.94
0.00% 0.00%
5/28/2017
6/4/2017
6/18/2017
6/25/2017
7/2/2017
7/9/2017
7/30/2017
8/6/2017
8/13/2017
8/20/2017
8/27/2017
10/4/2017
6/11/2017
7/16/2017
7/23/2017
INICIO
1.00 OBRA "CONSTRUCCION DEL CENTRO DE INSTRUCCIÓN TECNICA COMUNIDAD CAMPESINA SEGUN
4.00 UBICACIÓN:
DISTRITO YAULI
PROVINCIA LA OROYA
DEPARTAMENTO JUNIN
S/.201,797.17+IGV
5.00 PRESUPUESTO INC. IGV
Feb-17 Mar-17
PORCENTAJE PARCIAL 6.68% 9.19%
PORCENTAJE ACUMULADO 6.68% 15.88%
ESINA SEGUNDA ETAPA"
PLAZO DE EJECUCION: 120
INICIO DE OBRA: 2/1/2017
Apr-17 May-17
66.22% 17.90%
82.10% 100.00%