Académique Documents
Professionnel Documents
Culture Documents
Project-No.: 2006289-1E-KES
1. PROJECT
Regarding the above mentioned project we have been asked to do base course design under
consideration of the application of a base reinforcement. The design is performed for both an asphalt
paved road and an unpaved road.
The aim of using a base reinforcement geogrid is to increase the bearing capacity, respectively the
reduction of the required base course thickness, particularly at subgrades with low bearing capacities.
When having inhomogeneous subgrades, constant loads can lead to irregular settlements. Our
geogrids for base reinforcement can bridge these weaknesses, thus providing a viable and
sustainable, level surface.
The existing typical cross section consisting of two mixed in place levels and a geosynthetic reinforced
aggregate layer below an unreinforced aggregate layer is shown in Figure 1.
2. INPUT PARAMETERS
Project-No.: 2006289-1E-KES
Contact: M.-T. van Keßel, M.Sc.
Phone: +49 25 42 / 701-304
E-Mail: vankessel@HUESKER.de Page 2 of 6
Wind Park Alibunar, Serbia
Project-No.: 2006289-1E-KES
Contact: M.-T. van Keßel, M.Sc.
Phone: +49 25 42 / 701-304
E-Mail: vankessel@HUESKER.de Page 3 of 6
Wind Park Alibunar, Serbia
For a subgrade with a modulus of deformation Ev2 = 27 MPa, the thickness of the sand or sand-gravel
layer should be at least 0.15 m to reach Ev2 = 45 MN/m², when using a geosynthetic reinforcement.
According to our experience with reinforced embankments in roads, highways, parking lots and other
areas, we recommend for fine graded soils or soils with a higher water content to use a geocomposite
layer type Base 40 B15 as base reinforcement. The base reinforcement can be installed directly onto
the existing subgrade.
Base 40 B15 is a geocomposite, which combines a reinforcement grid with a factory-applied
nonwoven geotextile for roadbuilding applications. Its flexible, biaxial geogrid presents high tensile
strength in conjunction with low strain, providing reliable long-term reinforcement for base courses.
The separation and filtration properties of the integral nonwoven also considerably increase stability,
reducing the need for soil replacement (see A.2).
Figure 3: Base bearing layer thickness according to subgrade bearing capacity [2]
Project-No.: 2006289-1E-KES
Contact: M.-T. van Keßel, M.Sc.
Phone: +49 25 42 / 701-304
E-Mail: vankessel@HUESKER.de Page 4 of 6
Wind Park Alibunar, Serbia
Base 40 B 15
Base 40 B 15
4. INSTALLATION
To achieve a sufficient bearing capacity we recommend the following set-up:
1. Earth works (to achieve the designed project level) and construction of a base grade.
2. Installation of Base 40 B15 directly onto the existing base. The overlap of adjacent lanes
should not be less than 0.50 m.
Project-No.: 2006289-1E-KES
Contact: M.-T. van Keßel, M.Sc.
Phone: +49 25 42 / 701-304
E-Mail: vankessel@HUESKER.de Page 5 of 6
Wind Park Alibunar, Serbia
3. Installation and compaction of the base course material, done in separate layers. The
installation has to be constructed ahead, so the geogrid is not trafficked by construction
vehicles. The compaction must be done carefully to avoid that the existing bearing capacity of
the subgrade is decreased. Therefore compaction should be done without vibration.
We also recommend, to build a small test field of at least 5m x 10m to react on local characteristics.
The test field can stay in place as part of the construction afterwards. Please let the soil always rest for
at least 3-4 days after compaction before executing the plate compaction test. Otherwise the system
cannot reach its recommended stiffness.
5. SUMMARY
The design procedure and assumptions of a base course design under consideration of the
application of a base reinforcement were demonstrated in this document for both asphalt paved roads
and unpaved roads within the project “Alibunar Wind Park”.
The estimated base course thickness and reinforcement product are summarized in Table 3. In
comparison to the initial layer set up (Figure 1) the use of a hydraulic binder is not necessary and the
total thickness of 0.8 m can be reduced to 0.4 m for unpaved roads or 0.6 m for asphalt paved roads.
Table 3: Summary of required base course thickness and required geosynthetic product.
Ev2 Ev2 Reinforced base
Planned Granular Reinforcement
on top granular Subgrade course thickness
set-up material product
layer [MN/m²] [MN/m²] [cm]
45 sandy gravel 15
Asphalt
27 crushed Base 40 B15
pavement 100 25
stone
45 sandy gravel 15
Unpaved
27 crushed Base 40 B15
roads 100 25
stone
6. LIST OF REFERENCES
[1] Recommendations for Design and Analysis of Earth Structures using Geosynthetic
Reinforcements – EBGEO
[2] Richtlinien für die Standardisierung des Oberbaus von Verkehrsflächen (RStO 12),
Forschungsgesellschaft für Straßen- und Verkehrswesen, Ausgabe 2012
7. APPENDICES
[A.1] Installation Guidelines HUESKER Geogrids as Base Reinforcement
[A.2] Datasheet Base 40 B15
Project-No.: 2006289-1E-KES
Contact: M.-T. van Keßel, M.Sc.
Phone: +49 25 42 / 701-304
E-Mail: vankessel@HUESKER.de Page 6 of 6