DESIGNER'S OBSERVATION

(Based on PROGRESS REPORT FOR INCLINOMETER & ROD SETTLEMENT GAUGE NO. 8 - MAY 2018)

Current Designed Current


Cumulative
Embankment Surcharge Surcharge Degree of
Item DSG No. Covered Chainage Date Installed Settlement SH/SV Designer's Observation
Level Level Period Consolidation
(mm)
(m) (m) (days)
embankment fill has reached surcharge level. At current embankment height, the ground has
SG 55 @ CH 6100
1 Ch 6+050 - Ch 6+100 (LHS) 18/Dec/17 5.2502 4.953 m 42 89.59 0% 0.47 achieved approximately 64% and 80% degree of consolidation respectively. Therefore, it is
(LHS)
recommended to continue monitoring.
embankment fill has reached surcharge level. At current embankment height, the ground has
SG 57 @ CH 6200
2 Ch 6+100 - Ch 6+300 (LHS) 18/Dec/17 4.9767 4.645 m 35 96.28 - 0.43 achieved approximately 64% and 80% degree of consolidation respectively. Therefore, it is
(LHS)
recommended to continue monitoring.
from the records the embankment has not reached surcharge level. At current embankment
SG 58 @ CH 6250 height, the ground has achieved approximately 89% degree of consolidation. Therefore, it is
3 Ch 6+225 - Ch 6+400 (RHS) 18/Dec/17 4.6332 4.783 m - 44.43 - 1.76
(RHS) advisable to continue backfilling at constant rate of 300mm per week to final surcharge level
and at the same time continue with monitoring.
from the records the embankment has not reached surcharge level. At the current
SG 59 @ CH 6400 embankment height , the current ground has achieved approximately 74% degree of
4 Ch 6+300 - Ch 6+450 (LHS) 18/Dec/17 4.7954 4.912 m - 121.08 - 0.35
(LHS) consolidation. Therefore, it is advisable to continue backfilling at constant rate of 300mm per
week to final surcharge level and at the same time continue with monitoring.
from the records the embankment has not reached surcharge level. At the current embankment
SG 60 @ CH 6425 height the ground has achieved approximately 72% degree of consolidation. Therefore, it is
5 Ch 6+400 - Ch 6+500 (RHS) 18/Dec/17 4.5202 4.794 m - 65.43 - 1.20
(RHS) advisable to continue backfilling at constant rate of 300mm per week to final surcharge level
and at the same time continue with monitoring.
the degree of consolidation achieved is 96%. The degree of consolidation from 30th April 2018
SG 61 @ CH 6500 till 25th June 2018 is consistent throughout and the monitoring period the rate of settlement is
6 Ch 6+450 - Ch 6+500 (LHS) 18/Dec/17 4.4994 4.438 m 77 73.94 96% 0.56
(LHS) very small (i.e highest recorded is 1.9mm). Therefore, it is considered safe to remove the
surcharge.

SG 62 @ CH 6625 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
7 Ch 6+575 - Ch 6+700 (LHS) 18/Dec/17 4.5065 5.037 m - 40.43 - 1.04
(LHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 63 @ CH 6625 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
8 Ch 6+500 - Ch 6+700 (RHS) 7/May/18 3.4486 5.037 m - 3.80 - 24.43
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 64 @ CH 6800 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
9 Ch 6+700 - Ch 6+850 (LHS) 18/Dec/17 4.4258 5.423 m - 41.41 - 1.02
(LHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 65 @ CH 6800 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
10 Ch 6+700 - Ch 6+825 (RHS) 7/May/18 3.6355 5.423 m - 3.60 - 20.05
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 66 @ CH 6850 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
11 Ch 6+825 - Ch 6+875 (RHS) 7/May/18 3.5267 5.246 m - 0.90 - 86.88
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 67 @ CH 6925 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
12 Ch 6+875 - Ch 6+950 (RHS) 7/May/18 3.6175 4.98 m - 3.70 - 24.43
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 67A @ CH 6975 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
13 Ch 6+950 - Ch 7+000 (RHS) 7/May/18 3.6096 4.81 m - 3.80 - 22.34
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 68 @ CH 7025 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
14 Ch 7+000 - Ch 7+100 (RHS) 7/May/18 3.6705 4.881 m - 24.40 - 3.18
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 69 @ CH 7200 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
15 Ch 7+100 - Ch 7+300 (RHS) 7/May/18 3.788 5.397 m - 41.30 - 4.16
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.
SG 70 @ CH 7400 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
16 Ch 7+300 - Ch 7+450 (RHS) 7/May/18 3.8002 4.205 m - 34.30 - 6.68
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 71 @ CH 7475 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
17 Ch 7+450 - Ch 7+500 (RHS) 7/May/18 3.8117 4.506 m - 43.80 - 4.80
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 72 @ CH 7600 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
18 Ch 7+550 - Ch 7+650 (RHS) 7/May/18 3.0649 4.997 m - 26.00 - 26.06
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 73 @ CH 7600 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
19 Ch 7+500 - Ch 7+650 (LHS) 18/Dec/17 4.4628 4.997 m - 107.4 - 0.41
(LHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 74 @ CH 7700 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
20 Ch 7+650 - Ch 7+750 (RHS) 7/May/18 3.4457 4.75 m - 26 - 22.34
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 75 @ CH 7800 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
21 Ch 7+750 - Ch 7+825 (RHS) 7/May/18 3.4475 4.452 m - 27 - 21.13
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

at current embankment level the ground has achieved approximately 65% degree of
SG 76 @ CH 7875 consolidation. Since the embankment is at surcharge level, it is recommended to continue with
22 Ch 7+850 - Ch 7+900 (LHS) 18/Dec/17 4.6935 4.756 m 98 90.96 65% 0.50
(LHS) monitoring works until the degree of consolidation has achieved 90% or more degree of
consolidation.
from the records the embankment has reached its surcharge level at day 140. The last
SG 77 @ CH 8450 recorded cumulative settlement is 62.4mm. It is recommended to continue with monitoring
23 Ch 7+900 - Ch 8+500 (LHS) 18/Dec/17 6.3435 5.717 m 0.80
(LHS) works to establish the consolidation pattern thus will enable us to predict the current degree of
settlement.
from the records the embankment has reached its surcharge level at day 154. The last
SG 78 @ CH 8525 recorded cumulative settlement is 122.29mm. It is recommended to continue with monitoring
24 Ch 8+500 - Ch 8+600 (LHS) 18/Dec/17 6.2111 5.442 m 7 122.29 124% 0.38
(LHS) works to establish the consolidation pattern thus will enable us to predict the current degree of
settlement.

SG 79 @ CH 8700 Since the DSG located along the failure stretch of Ch 8700 to Ch 8800, it is recommended to
25 Ch 8+600 - Ch 8+825 (LHS) 18/Dec/17 5.6199 5.792 m - 141.82 - 0.38
(LHS) continue monitoring until the degree of consolidation exceeds 90%.

SG 80 @ CH 9100 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
26 Ch 9+075 - Ch 9+125 (LHS) 7/May/18 4.1103 5.097 m - 5 - 32.49
(LHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 81 @ CH 9150 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
27 Ch 9+100 - Ch 9+200 (RHS) 7/May/18 4.3815 4.989 m - 9.6 - 13.03
(RHS) rate of 300mm per week to final surcharge level and continue with monitoring.

SG 82 @ CH 9175 Embankment level has not reached surcharge level. Therefore, continue backfilling at constatnt
28 Ch 9+125 - Ch 9+200 (LHS) 7/May/18 3.987 4.884 m - 10.6 - 5.71
(LHS) rate of 300mm per week to final surcharge level and continue with monitoring.
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 55 @ CH 6100 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.5358 4.8698 0.0 0.0 0.00


2 18-Dec-17 0 3.8007 4.8698 0.0 0.0 0.26
3 21-Dec-17 3 3.7699 4.8692 -0.6 -0.6 0.23
4 25-Dec-17 7 3.7729 4.8685 -0.7 -1.3 0.24
5 28-Dec-17 10 3.7842 4.8681 -0.4 -1.7 0.25
6 2-Jan-18 15 3.7705 4.8683 0.1 -1.5 0.24
7 4-Jan-18 17 4.1335 4.8647 -3.6 -5.1 0.60
8 8-Jan-18 21 4.1283 4.8631 -1.5 -6.7 0.60
9 11-Jan-18 24 4.1285 4.8625 -0.6 -7.3 0.60
10 15-Jan-18 28 4.1163 4.8615 -1.0 -8.3 0.59
11 18-Jan-18 31 4.6834 4.8483 -13.2 -21.5 1.17

12 18-Jan-18 31 4.6834 5.8538 0.0 -21.5 1.17


13 22-Jan-18 35 4.6931 5.8524 -1.4 -22.9 1.18
14 25-Jan-18 38 4.6873 5.8510 -1.4 -24.3 1.18
15 29-Jan-18 42 4.6804 5.8498 -1.2 -25.5 1.17
16 1-Feb-18 45 4.6807 5.8478 -2.1 -27.5 1.17
17 5-Feb-18 49 4.6710 5.8467 -1.0 -28.6 1.16
18 12-Feb-18 56 4.6614 5.8453 -1.4 -30.0 1.16
19 19-Feb-18 63 4.6597 5.8442 -1.1 -31.1 1.16
20 26-Feb-18 70 4.6276 5.8424 -1.8 -32.9 1.12
21 5-Mar-18 77 4.6262 5.8421 -0.3 -33.2 1.12
22 12-Mar-18 84 4.6435 5.8397 -2.4 -35.6 1.14
23 19-Mar-18 91 4.6392 5.8379 -1.8 -37.4 1.14
24 26-Mar-18 98 4.6581 5.8358 -2.1 -39.5 1.16
25 2-Apr-18 105 4.6532 5.8341 -1.7 -41.2 1.16
26 9-Apr-18 112 4.6392 5.8328 -1.3 -42.5 1.15
27 16-Apr-18 119 4.6402 5.8319 -0.9 -43.4 1.15
28 23-Apr-18 126 4.6461 5.8312 -0.7 -44.1 1.15
29 30-Apr-18 133 4.6419 5.8301 -1.1 -45.2 1.15
30 7-May-18 140 4.6431 5.8292 -0.9 -46.1 1.15
31 14-May-18 147 4.9924 5.8130 -16.2 -62.3 1.52
32 21-May-18 154 5.2412 5.7868 -26.2 -88.5 1.79
33 28-May-18 161 5.2502 5.7857 -1.1 -89.6 1.80
34 4-Jun-18 168 5.2473 5.7850 -0.7 -90.3 1.80
35 11-Jun-18 175 5.2432 5.7842 -0.8 -91.1 1.80
36 19-Jun-18 183 5.2303 5.7812 -3.0 -94.1 1.79
37 25-Jun-18 189 5.2252 5.7798 -1.4 -95.5 1.78
38 2-Jul-18 196 5.2234 5.7787 -1.1 -96.6 1.78
39 9-Jul-18 203 5.2216 5.7769 -1.8 -98.4 1.78
40 16-Jul-18 210 5.2219 5.7762 -0.7 -99.1 1.79
41 23-Jul-18 217 5.2174 5.7754 -0.8 -99.9 1.78
42 30-Jul-18 224 5.2149 5.7747 -0.7 -100.6 1.78
TORING

UNGAI BULOH KE ASSAM JAWA

4.953 m
3.53579 m
3.55860 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work

Backfilling & compaction work //


Before rod extension
Extension of rod 1.0055 m

Backfilling & compaction work


Backfilling & compaction work
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6100 - LHS (SG 55)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

6
SURCHARGE
LEVEL
4

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
10

-10

-20

-30

-40

-50

-60

-70

-80

-90

-100
-70

-80

-90

-100
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 55 @ CH 6100 (LHS)

Last Settlement Reading, A = 100.590 ASAOKA Plot


Intersection Settlement Reading, B = 105.000 180.00
Degree of consolidation, U = A/B = 96%

Elapsed f(x) = 0.8820349321x + 12.5667299695


Date Sn Sn-1 U
Days 160.00
14/May/18 147 62.29
21/May/18 154 88.49 -
28/May/18 161 89.59
4/Jun/18 168 90.29 140.00
11/Jun/18 175 91.09 90.29

Sn
19/Jun/18 183 94.09 91.09
25/Jun/18 189 95.49 94.09
2/Jul/18 196 96.59 95.49 120.00
9/Jul/18 203 98.39 96.59
16/Jul/18 210 99.09 98.39
23/Jul/18 217 99.89 99.09
30/Jul/18 224 100.59 99.89 100.00

80.00

60.00
60.00 80.00 100.00 120.00 140.00 160.00 180.00

Sn-1
95

160.00 180.00

(45 degree line.)


0 0
500 500

B (Intercept)
105.000 105.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 57 @ CH 6200 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.2621 4.6246 0.0 0.0 0.00


2 18-Dec-17 0 3.7436 4.6246 0.0 0.0 0.48
3 21-Dec-17 3 3.7692 4.6239 -0.7 -0.7 0.51
4 25-Dec-17 7 3.7491 4.6230 -0.8 -1.6 0.49
5 28-Dec-17 10 3.7444 4.6231 0.1 -1.5 0.48
6 2-Jan-18 15 3.7510 4.6237 0.5 -0.9 0.49
7 4-Jan-18 17 4.0392 4.6007 -23.0 -23.9 0.80
8 8-Jan-18 21 4.0558 4.5994 -1.3 -25.2 0.82
9 11-Jan-18 24 4.0312 4.5989 -0.5 -25.7 0.79
10 15-Jan-18 28 4.0397 4.5979 -1.0 -26.7 0.80
11 18-Jan-18 31 4.5600 4.5863 -11.7 -38.3 1.34

12 18-Jan-18 31 4.5600 5.5956 0.0 -38.3 1.34


13 22-Jan-18 35 4.5478 5.5945 -1.1 -39.4 1.33
14 25-Jan-18 38 4.5422 5.5922 -2.3 -41.7 1.32
15 29-Jan-18 42 4.5262 5.5912 -1.0 -42.7 1.31
16 1-Feb-18 45 4.5205 5.5901 -1.1 -43.8 1.30
17 5-Feb-18 49 4.5271 5.5895 -0.6 -44.4 1.31
18 12-Feb-18 56 4.5302 5.5880 -1.5 -45.9 1.31
19 19-Feb-18 63 4.5313 5.5868 -1.2 -47.0 1.32
20 26-Feb-18 70 4.5394 5.5862 -0.6 -47.6 1.32
21 5-Mar-18 77 4.4808 5.5840 -2.2 -49.9 1.27
22 12-Mar-18 84 4.4859 5.5820 -2.0 -51.9 1.28
23 19-Mar-18 91 4.4873 5.5808 -1.2 -53.1 1.28
24 26-Mar-18 98 4.5249 5.5795 -1.3 -54.4 1.32
25 2-Apr-18 105 4.5217 5.5777 -1.8 -56.2 1.32
26 9-Apr-18 112 4.5206 5.5764 -1.3 -57.5 1.32
27 16-Apr-18 119 4.5186 5.5756 -0.8 -58.3 1.31
28 23-Apr-18 126 4.5137 5.5746 -1.0 -59.3 1.31
29 30-Apr-18 133 4.5002 5.5742 -0.4 -59.7 1.30
30 7-May-18 140 4.5048 5.5732 -1.0 -60.7 1.30
31 14-May-18 147 4.4433 5.5711 -2.1 -62.8 1.24
32 21-May-18 154 4.9942 5.5376 -33.5 -96.3 1.83
33 28-May-18 161 4.9767 5.5365 -1.1 -97.4 1.81
34 4-Jun-18 168 4.9722 5.5358 -0.7 -98.1 1.81
35 11-Jun-18 175 4.9404 5.5350 -0.8 -98.9 1.78
36 19-Jun-18 183 4.9653 5.5323 -2.7 -101.6 1.80
37 25-Jun-18 189 4.9621 5.5304 -1.9 -103.5 1.80
38 2-Jul-18 196 4.9610 5.5293 -1.1 -104.6 1.80
39 9-Jul-18 203 4.9574 5.5280 -1.3 -105.9 1.80
40 16-Jul-18 210 4.9539 5.5273 -0.7 -106.6 1.80
41 23-Jul-18 217 4.9503 5.5265 -0.8 -107.4 1.80
42 30-Jul-18 224 4.9483 5.5257 -0.8 -108.2 1.79
TORING

UNGAI BULOH KE ASSAM JAWA

4.645 m
3.26208 m
3.29792 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work

Backfilling & compaction work //


Before rod extension
Extension of rod 1.0093 m

Backfilling & compaction work


PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6200 - LHS (SG 57)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
10
0
-10
-20
-30
-40
-50
-60
-70
-80
-90
-100
-110
-120
-130
-140
-150
-110
-120
-130
-140
-150
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 57 @ CH 6200 (LHS)

Last Settlement Reading, A = 108.180 ASAOKA Plot


Intersection Settlement Reading, B = 130.000 160.00
Degree of consolidation, U = A/B = 83%

Elapsed
Date Sn Sn-1 U
Days
140.00
21/May/18 154 96.28
28/May/18 161 97.38 96.28 -
4/Jun/18 168 98.08 97.38
11/Jun/18 175 98.88 98.08
19/Jun/18 183 101.58 98.88
120.00
25/Jun/18 189 103.48 101.58

Sn
2/Jul/18 196 104.58 103.48
9/Jul/18 203 105.88 104.58
16/Jul/18 210 106.58 105.88
23/Jul/18 217 107.38 106.58
100.00
30/Jul/18 224 108.18 107.38

80.00

60.00
60.00 80.00 100.00 120.00 140.00 160.00

Sn-1
140.00 160.00

(45 degree line.)


0 0
500 500

B (Intercept)
130.000 130.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 58 @ CH 6250 (RHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 2.9385 4.2552 0.0 0.0 0.00


2 21-Dec-17 3 2.9272 4.2547 -0.5 -0.5 -0.01
3 25-Dec-17 7 2.9311 4.2544 -0.3 -0.8 -0.01
4 28-Dec-17 10 2.9303 4.2545 0.1 -0.7 -0.01
5 2-Jan-18 15 2.9281 4.2542 -0.3 -1.0 -0.01
6 4-Jan-18 17 3.2836 4.2394 -14.8 -15.8 0.36
7 8-Jan-18 21 3.2957 4.2395 0.1 -15.7 0.37
8 11-Jan-18 24 3.2986 4.2388 -0.7 -16.4 0.38
9 15-Jan-18 28 3.3065 4.2380 -0.9 -17.3 0.39
10 18-Jan-18 31 3.2792 4.2375 -0.5 -17.8 0.36
11 22-Jan-18 35 3.2823 4.2376 0.1 -17.6 0.36
12 25-Jan-18 38 3.2782 4.2371 -0.5 -18.2 0.36
13 29-Jan-18 42 3.2932 4.2364 -0.6 -18.8 0.37
14 1-Feb-18 45 3.8981 4.2221 -14.3 -33.1 0.99

15 1-Feb-18 45 3.8981 5.5318 0.0 -33.1 0.99


16 5-Feb-18 49 3.8984 5.5313 -0.4 -33.6 0.99
17 12-Feb-18 56 3.8992 5.5305 -0.9 -34.5 1.00
18 19-Feb-18 63 3.8953 5.5293 -1.2 -35.6 0.99
19 26-Feb-18 70 4.6458 5.1896 0.0 -35.6 1.74
20 5-Mar-18 77 - - - - -
21 12-Mar-18 84 4.6497 4.8806 0.0 -35.6 1.75
22 19-Mar-18 91 4.6514 4.8794 -1.2 -36.8 1.75
23 26-Mar-18 98 4.6426 4.8789 -0.5 -37.3 1.74
24 2-Apr-18 105 4.6382 4.8779 -1.0 -38.3 1.74
25 9-Apr-18 112 4.6403 4.8768 -1.1 -39.4 1.74
26 16-Apr-18 119 4.6492 4.8758 -1.0 -40.4 1.75
27 23-Apr-18 126 4.6550 4.8747 -1.1 -41.5 1.76
28 30-Apr-18 133 4.6716 4.8735 -1.2 -42.7 1.78
29 7-May-18 140 4.6693 4.8725 -1.0 -43.7 1.77
30 14-May-18 147 4.6585 4.8727 0.2 -43.5 1.76
31 21-May-18 154 4.6301 4.8720 -0.7 -44.2 1.74
32 28-May-18 161 4.6332 4.8718 -0.2 -44.4 1.74
33 4-Jun-18 168 4.6301 4.8713 -0.5 -44.9 1.74
34 11-Jun-18 175 4.6318 4.8710 -0.3 -45.2 1.74
35 19-Jun-18 183 4.6297 4.8712 0.2 -45.0 1.74
36 25-Jun-18 189 4.6261 4.8712 0.0 -45.0 1.73
37 2-Jul-18 196 4.6273 4.8710 -0.2 -45.2 1.73
38 9-Jul-18 203 4.6240 4.8708 -0.2 -45.4 1.73
39 16-Jul-18 210 4.6259 4.8705 -0.3 -45.7 1.73
40 23-Jul-18 217 4.6284 4.8707 0.2 -45.5 1.74
41 30-Jul-18 224 4.6282 4.8706 -0.1 -45.6 1.74
42
TORING

UNGAI BULOH KE ASSAM JAWA

4.783 m
2.93845 m
2.95158 m

Remarks

Existing Ground Level

Backfilling & compaction work

Backfilling & compaction work //


Before rod extension
Rod extension of 1.3097 m

Repaired and new baseline reading


Damaged
Repaired and new baseline reading
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6250 - RHS (SG 58)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 58 @ CH 6250 (RHS)

Last Settlement Reading, A = 45.030 ASAOKA Plot


Intersection Settlement Reading, B = 48.000 70.00
Degree of consolidation, U = A/B = 94%
f(x) = 0.9196913885x + 3.8641813411
Elapsed
Date Sn Sn-1 U
Days
18/Dec/17 0 0.00
21/Dec/17 3 0.51 - 60.00
25/Dec/17 7 0.82
28/Dec/17 10 0.72
2/Jan/18 15 1.00
4/Jan/18 17 15.84

Sn
8/Jan/18 21 15.70
11/Jan/18 24 16.42 50.00
15/Jan/18 28 17.27
18/Jan/18 31 17.77
22/Jan/18 35 17.65
25/Jan/18 38 18.17
29/Jan/18 42 18.80
1/Feb/18 45 33.10 40.00
5/Feb/18 49 33.58
12/Feb/18 56 34.46
19/Feb/18 63 35.63
26/Feb/18 70 35.63
12/Mar/18 84 35.63 35.63
19/Mar/18 91 36.83 35.63 30.00
26/Mar/18 98 37.33 36.83 30.00 40.00 50.00 60.00 70.00
2/Apr/18 105 38.33 37.33
9/Apr/18 112 39.43 38.33
Sn-1
16/Apr/18 119 40.43 39.43
23/Apr/18 126 41.53 40.43
30/Apr/18 133 42.73 41.53
7/May/18 140 43.73 42.73
14/May/18 147 43.53 43.73
21/May/18 154 44.23 43.53
28/May/18 161 44.43 44.23
4/Jun/18 168 44.93 44.43
11/Jun/18 175 45.23 44.93
19/Jun/18 183 45.03 45.23
25/Jun/18 189 45.03 45.03
2/Jul/18 196 45.23 45.03
9/Jul/18 203 45.43 45.23
16/Jul/18 210 45.73 45.43
23/Jul/18 217 45.53 45.73
30/Jul/18 224 45.63 45.53
1

60.00 70.00

(45 degree line.)


0 0
500 500

B (Intercept)
48.000 48.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 59 @ CH 6400 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.2582 4.6077 0.0 0.0 0.00


2 18-Dec-17 0 3.5487 4.6077 0.0 0.0 0.29
3 21-Dec-17 3 3.5460 4.6068 -0.8 -0.8 0.29
4 25-Dec-17 7 3.5463 4.6059 -0.9 -1.7 0.29
5 28-Dec-17 10 3.5558 4.6052 -0.7 -2.4 0.30
6 2-Jan-18 15 3.5420 4.6049 -0.3 -2.8 0.29
7 4-Jan-18 17 3.7862 4.5781 -26.8 -29.6 0.56
8 8-Jan-18 21 3.8592 4.5776 -0.5 -30.1 0.63
9 11-Jan-18 24 3.2042 4.5371 0.0 -30.1 0.03
10 11-Jan-18 24 3.7322 4.5371 0.0 -30.1 0.56
11 15-Jan-18 28 3.7407 4.5362 -0.9 -30.9 0.57
12 18-Jan-18 31 3.7946 4.5357 -0.5 -31.4 0.62
13 22-Jan-18 35 3.7724 4.5351 -0.7 -32.1 0.60
14 25-Jan-18 38 4.0383 4.5277 -7.3 -39.4 0.87
15 29-Jan-18 42 4.0638 4.5259 -1.8 -41.2 0.90
16 1-Feb-18 45 4.0761 4.5253 -0.6 -41.8 0.91
17 5-Feb-18 49 4.0776 4.5242 -1.1 -42.9 0.92
18 12-Feb-18 56 4.0598 4.5229 -1.3 -44.3 0.90
19 19-Feb-18 63 4.0706 4.5215 -1.5 -45.7 0.91
20 26-Feb-18 70 4.3612 4.4822 -39.2 -84.9 1.24

21 26-Feb-18 70 4.3612 5.4844 0.0 -85.0 1.24


22 5-Mar-18 77 4.4252 5.4815 -2.9 -87.9 1.31
23 12-Mar-18 84 4.8580 5.4615 -20.0 -107.9 1.76
24 19-Mar-18 91 4.8514 5.4601 -1.4 -109.3 1.76
25 26-Mar-18 98 4.8574 5.4586 -1.5 -110.8 1.76
26 2-Apr-18 105 4.8522 5.4566 -2.0 -112.8 1.76
27 9-Apr-18 112 4.8500 5.4551 -1.5 -114.3 1.76
28 16-Apr-18 119 4.8527 5.4546 -0.5 -114.8 1.76
29 23-Apr-18 126 4.8488 5.4538 -0.8 -115.6 1.76
30 30-Apr-18 133 4.8397 5.4529 -0.9 -116.5 1.75
31 7-May-18 140 4.8351 5.4517 -1.2 -117.7 1.75
32 14-May-18 147 4.8481 5.4503 -1.4 -119.1 1.76
33 21-May-18 154 4.7987 5.4492 -1.1 -120.2 1.71
34 28-May-18 161 4.7954 5.4483 -0.9 -121.1 1.71
35 4-Jun-18 168 4.7903 5.4476 -0.7 -121.8 1.71
36 11-Jun-18 175 4.7876 5.4469 -0.7 -122.5 1.71
37 19-Jun-18 183 4.7824 5.4448 -2.1 -124.6 1.70
38 25-Jun-18 189 4.7786 5.4437 -1.1 -125.7 1.70
39 2-Jul-18 196 4.7743 5.4426 -1.1 -126.8 1.70
40 9-Jul-18 203 4.7706 5.4414 -1.2 -128.0 1.69
41 16-Jul-18 210 4.7684 5.4406 -0.8 -128.8 1.69
42 23-Jul-18 217 4.7702 5.4398 -0.8 -129.6 1.70
43 30-Jul-18 224 4.7724 5.4391 -0.7 -130.3 1.70
TORING

UNGAI BULOH KE ASSAM JAWA

4.912 m
3.25817 m
3.28636 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work

Re-install with new baseline reading


After filling

Backfilling & compaction work

Compaction work

Backfilling & compaction work //


Before rod extension
Extension of rod 1.0022 m
Backfilling & compaction work
GI Pipe was disturbed
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6400 - LHS (SG 59)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300
10
0
-10
-20
-30
-40
-50
-60
-70
-80
-90
-100
-110
-120
-130
-140
-150
-110
-120
-130
-140
-150
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 59 @ CH 6400 (LHS)

Last Settlement Reading, A = 130.280 ASAOKA Plot


Intersection Settlement Reading, B = 140.000 180
Degree of consolidation, U = A/B = 93%
f(x) = 0.9193464052x + 11.2212235294
Elapsed 170
Date Sn Sn-1 U
Days
18/Dec/17 0 0.00
21/Dec/17 3 0.85 - 160
25/Dec/17 7 1.74
28/Dec/17 10 2.44
2/Jan/18 15 2.79 150
4/Jan/18 17 29.60

Sn
8/Jan/18 21 30.09
11/Jan/18 24 30.09 140
15/Jan/18 28 30.95
18/Jan/18 31 31.44
MENT FILL DID NOT REACHED SURCHARGE LEVEL.

22/Jan/18 35 32.11 130


25/Jan/18 38 39.45
29/Jan/18 42 41.25
1/Feb/18 45 41.85 120
5/Feb/18 49 42.95
12/Feb/18 56 44.28
19/Feb/18 63 45.73 110
26/Feb/18 70 84.94
5/Mar/18 77 87.92
12/Mar/18 84 107.88 100
19/Mar/18 91 109.28 100.00 110.00 120.00 130.00 140.00 150.00 160.00 170.00 180.00
26/Mar/18 98 110.78
2/Apr/18 105 112.78
Sn-1
9/Apr/18 112 114.28
16/Apr/18 119 114.78
23/Apr/18 126 115.58
EMBANKMENT FILL DID
30/Apr/18 133 116.48
7/May/18 140 117.68
14/May/18 147 119.08
21/May/18 154 120.18
28/May/18 161 121.08
4/Jun/18 168 121.78
11/Jun/18 175 122.48 121.78
19/Jun/18 183 124.58 122.48
25/Jun/18 189 125.68 124.58
2/Jul/18 196 126.78 125.68
9/Jul/18 203 127.98 126.78
16/Jul/18 210 128.78 127.98
23/Jul/18 217 129.58 128.78
30/Jul/18 224 130.28 129.58
94

160.00 170.00 180.00

(45 degree line.)


0 0
500 500

B (Intercept)
140.000 140.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 60 @ CH 6425 (RHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.0069 4.3535 0.0 0.0 0.00


2 18-Dec-17 0 3.3048 4.3535 0.0 0.0 0.30
3 21-Dec-17 3 3.2728 4.3528 -0.8 -0.8 0.27
4 25-Dec-17 7 3.3083 4.3522 -0.6 -1.3 0.30
5 28-Dec-17 10 3.2996 4.3523 0.1 -1.2 0.29
6 2-Jan-18 15 3.2861 4.3525 0.1 -1.1 0.28
7 4-Jan-18 17 3.2953 4.3515 -1.0 -2.1 0.29
8 8-Jan-18 21 3.2970 4.3518 0.3 -1.8 0.29
9 11-Jan-18 24 3.2912 4.3507 -1.0 -2.8 0.29
10 15-Jan-18 28 3.2965 4.3500 -0.7 -3.5 0.29
11 18-Jan-18 31 3.2888 4.3491 -0.9 -4.4 0.29
12 22-Jan-18 35 3.2653 4.3486 -0.5 -4.9 0.26
13 25-Jan-18 38 3.2532 4.3475 -1.1 -6.0 0.25
14 29-Jan-18 42 3.2360 4.3462 -1.3 -7.3 0.24
15 1-Feb-18 45 3.6283 4.3422 -4.0 -11.4 0.63
16 5-Feb-18 49 3.6261 4.3410 -1.2 -12.6 0.63
17 12-Feb-18 56 3.6305 4.3396 -1.3 -13.9 0.64
18 19-Feb-18 63 3.6048 4.3385 -1.1 -15.0 0.61
19 26-Feb-18 70 4.0731 4.3072 -31.4 -46.4 1.11
20 26-Feb-18 70 4.0731 5.2956 0.0 -46.3 1.11
21 5-Mar-18 77 4.5139 5.2914 -4.2 -50.5 1.56
22 12-Mar-18 84 4.5004 5.2896 -1.8 -52.3 1.55
23 19-Mar-18 91 4.5063 5.2892 -0.4 -52.7 1.55
24 26-Mar-18 98 4.5214 5.2871 -2.1 -54.8 1.57
25 2-Apr-18 105 4.5188 5.2852 -1.9 -56.7 1.57
26 9-Apr-18 112 4.5218 5.2839 -1.3 -58.0 1.57
27 16-Apr-18 119 4.5514 5.2827 -1.2 -59.2 1.60
28 23-Apr-18 126 4.5509 5.2818 -0.9 -60.1 1.60
29 30-Apr-18 133 4.5576 5.2807 -1.1 -61.2 1.61
30 7-May-18 140 4.5536 5.2797 -1.0 -62.2 1.61
31 14-May-18 147 4.5216 5.2785 -1.2 -63.4 1.58
32 21-May-18 154 4.5259 5.2773 -1.2 -64.6 1.58
33 28-May-18 161 4.5202 5.2765 -0.8 -65.4 1.58
34 4-Jun-18 168 4.5169 5.2758 -0.7 -66.1 1.58
35 11-Jun-18 175 4.5136 5.2749 -0.9 -67.0 1.57
36 19-Jun-18 183 4.5093 5.2736 -1.3 -68.3 1.57
37 25-Jun-18 189 4.5076 5.2725 -1.1 -69.4 1.57
TORING

UNGAI BULOH KE ASSAM JAWA

4.794 m
3.00687 m
3.04343 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work

Backfilling & compaction work //


Before rod extension
Extension of rod 0.9884 m
Backfilling & compaction work
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6425 - RHS (SG 60)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

-10

-20

-30

-40

-50

-60

-70

-80

-90

-100
-70

-80

-90

-100
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 60 @ CH 6425 (RHS)

Last Settlement Reading, A = 69.430 ASAOKA Plot


Intersection Settlement Reading, B = 96.000 150
Degree of consolidation, U = A/B = 72%
f(x) = 0.9646725312x + 3.3074778678
140
Elapsed
Date Sn Sn-1 U
Days
130
18/Dec/17 0 0.00
21/Dec/17 3 0.75 -
25/Dec/17 7 1.30 120
28/Dec/17 10 1.20
2/Jan/18 15 1.07
110
4/Jan/18 17 2.05

Sn
8/Jan/18 21 1.77
11/Jan/18 24 2.82 100
BANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.

15/Jan/18 28 3.55
18/Jan/18 31 4.42
90
22/Jan/18 35 4.91
25/Jan/18 38 6.00
29/Jan/18 42 7.33 80
1/Feb/18 45 11.36
5/Feb/18 49 12.58
70
12/Feb/18 56 13.92
19/Feb/18 63 15.00
26/Feb/18 70 46.38 60
5/Mar/18 77 50.53
12/Mar/18 84 52.33 50.53 50
19/Mar/18 91 52.73 52.33 50.00 60.00 70.00 80.00 90.00 100.00 110.00 120.00 130.00 140.00 150.00
26/Mar/18 98 54.83 52.73
2/Apr/18 105 56.73 54.83
Sn-1
9/Apr/18 112 58.03 56.73
16/Apr/18 119 59.23 58.03
23/Apr/18 126 60.13 59.23
EMBANKMENT FI
30/Apr/18 133 61.23 60.13
7/May/18 140 62.23 61.23
14/May/18 147 63.43 62.23
21/May/18 154 64.63 63.43
28/May/18 161 65.43 64.63
4/Jun/18 168 66.13 65.43
11/Jun/18 175 67.03 66.13
19/Jun/18 183 68.33 67.03
25/Jun/18 189 69.43 68.33
8

.00 130.00 140.00 150.00

(45 degree line.)


0 0
500 500

B (Intercept)
96.000 96.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 61 @ CH 6500 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.0774 4.4343 0.0 0.0 0.00


2 18-Dec-17 0 3.4969 4.4343 0.0 0.0 0.42
3 21-Dec-17 3 3.5040 4.4341 -0.2 -0.2 0.43
4 25-Dec-17 7 3.5016 4.4337 -0.4 -0.6 0.42
5 28-Dec-17 10 3.5069 4.4344 0.7 0.1 0.43
6 2-Jan-18 15 3.5116 4.4341 -0.3 -0.3 0.43
7 4-Jan-18 17 3.6741 4.4174 -16.7 -16.9 0.61
8 8-Jan-18 21 3.6781 4.4145 -2.9 -19.8 0.62
9 11-Jan-18 24 3.6433 4.4123 0.0 -19.8 0.59
10 15-Jan-18 28 3.6502 4.4116 -0.6 -20.4 0.59
11 18-Jan-18 31 3.6855 4.4121 0.4 -20.0 0.63
12 22-Jan-18 35 3.6848 4.4118 -0.3 -20.3 0.63
13 25-Jan-18 38 3.9591 4.4111 -0.6 -20.9 0.90
14 29-Jan-18 42 3.9721 4.4101 -1.1 -22.0 0.92
15 1-Feb-18 45 4.0935 4.4032 -6.9 -28.8 1.04
16 5-Feb-18 49 4.0662 4.4017 -1.5 -30.3 1.02
17 12-Feb-18 56 4.0597 4.4005 -1.2 -31.5 1.01
18 19-Feb-18 63 4.0529 4.3995 -1.1 -32.6 1.01
19 26-Feb-18 70 4.5412 4.3713 -28.2 -60.8 1.52

20 26-Feb-18 70 4.5412 5.3495 0.0 -60.8 1.52


21 5-Mar-18 77 4.5376 5.3461 -3.4 -64.1 1.52
22 12-Mar-18 84 4.5205 5.3446 -1.5 -65.6 1.51
23 19-Mar-18 91 4.5021 - - -65.6 1.51
24 26-Mar-18 98 4.5287 5.3231 0.0 -65.6 1.52
25 2-Apr-18 105 4.5249 5.3210 -2.1 -67.7 1.52
26 9-Apr-18 112 4.5177 5.3197 -1.3 -69.0 1.51
27 16-Apr-18 119 4.5201 5.3187 -1.0 -70.0 1.51
28 23-Apr-18 126 4.5176 5.3176 -1.1 -71.1 1.51
29 30-Apr-18 133 4.5111 5.3168 -0.8 -71.9 1.51
30 7-May-18 140 4.5125 5.3158 -1.0 -72.9 1.51
31 14-May-18 147 4.5068 5.3148 -1.0 -73.9 1.50
32 21-May-18 154 4.5099 5.3138 -1.0 -74.9 1.51
33 28-May-18 161 4.4994 5.3127 -1.1 -76.0 1.50
34 4-Jun-18 168 4.4958 5.3121 -0.6 -76.6 1.50
35 11-Jun-18 175 4.4916 5.3115 -0.6 -77.2 1.49
36 19-Jun-18 183 4.4879 5.3097 -1.8 -79.0 1.49
37 25-Jun-18 189 4.4838 5.3078 -1.9 -80.9 1.49
38 2-Jul-18 196 4.4806 5.3066 -1.2 -82.1 1.49
39 9-Jul-18 203 4.4789 5.3055 -1.1 -83.2 1.48
40 16-Jul-18 210 4.4764 5.3044 -1.1 -84.3 1.48
41 23-Jul-18 217 4.4728 5.3035 -0.9 -85.2 1.48
42 30-Jul-18 224 4.4674 5.3024 -1.1 -86.3 1.48
TORING

UNGAI BULOH KE ASSAM JAWA

4.438 m
3.07737 m
3.11958 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work

Repaired and new baseline reading

Backfilling & compaction work

Compaction work

Backfilling & compaction work //


Before rod extension
Extension of rod 0.9782 m
Compaction work

GI Pipe is damaged
Re-installed with new baseline reading
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6500 -LHS (SG 61)

Embankment RL (m) vs Elapsed Day


10

6
SURCHARGE LEVEL
4

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
10

-10

-20

-30

-40

-50

-60

-70

-80

-90

-100
-70

-80

-90

-100
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 61 @ CH 6500 (LHS)

Last Settlement Reading, A = 80.940 ASAOKA Plot


Intersection Settlement Reading, B = 91.500 100.00
Degree of consolidation, U = A/B = 88%
f(x) = 0.8808467742x + 11.0395846774
Elapsed
Date Sn Sn-1 U
Days
26/Feb/18 70 60.76
5/Mar/18 77 64.14 - 90.00
12/Mar/18 84 65.64 98%
19/Mar/18 91 65.64 95%
26/Mar/18 98 65.64 96%
2/Apr/18 105 67.74 97%

Sn
9/Apr/18 112 69.04 97%
16/Apr/18 119 70.04 97% 80.00
23/Apr/18 126 71.14 97%
30/Apr/18 133 71.94 97%
7/May/18 140 72.94 97%
14/May/18 147 73.94 96%
21/May/18 154 74.94 96%
28/May/18 161 76.04 97% 70.00
4/Jun/18 168 76.64 95%
11/Jun/18 175 77.24 91%
19/Jun/18 183 79.04 77.24
25/Jun/18 189 80.94 79.04
2/Jul/18 196 82.14 80.94
9/Jul/18 203 83.24 82.14 60.00
16/Jul/18 210 84.34 83.24 60.00 70.00 80.00 90.00 100.00
23/Jul/18 217 85.24 84.34
30/Jul/18 224 86.34 85.24
Sn-1
74

90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
91.500 91.500
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 62 @ CH 6625 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 2.9587 4.3039 0.0 0.0 0.00


2 18-Dec-17 0 3.2551 4.3039 0.0 0.0 0.30
3 21-Dec-17 3 3.2311 4.3033 -0.7 -0.7 0.27
4 25-Dec-17 7 3.2276 4.3035 0.2 -0.4 0.27
5 28-Dec-17 10 3.2355 4.3035 0.0 -0.4 0.28
6 2-Jan-18 15 3.2282 4.3032 -0.3 -0.7 0.27
7 4-Jan-18 17 3.2262 4.3017 -1.5 -2.2 0.27
8 8-Jan-18 21 3.2342 4.3013 -0.4 -2.7 0.28
9 11-Jan-18 24 3.2506 4.3006 -0.6 -3.3 0.30
10 15-Jan-18 28 3.2468 4.3000 -0.6 -3.9 0.29
11 18-Jan-18 31 3.2124 4.2993 -0.7 -4.6 0.26
12 22-Jan-18 35 3.2679 4.2979 -1.4 -6.0 0.32
13 25-Jan-18 38 3.2208 4.2965 -1.4 -7.4 0.27
14 29-Jan-18 42 3.2764 4.2951 -1.4 -8.8 0.33
15 1-Feb-18 45 3.6775 4.2832 -11.9 -20.7 0.74
16 5-Feb-18 49 3.6574 4.2821 -1.1 -21.8 0.72
17 12-Feb-18 56 3.6309 4.2806 -1.4 -23.3 0.70
18 19-Feb-18 63 3.6292 4.2796 -1.0 -24.3 0.69
19 26-Feb-18 70 3.6362 4.2772 -2.4 -26.7 0.70
20 26-Feb-18 70 3.6362 5.2439 0.0 -26.7 0.70
21 5-Mar-18 77 - - - - -
22 12-Mar-18 84 4.5450 5.0843 0.0 -26.7 1.61
23 19-Mar-18 91 4.5393 5.0833 -1.0 -27.7 1.61
24 26-Mar-18 98 4.5361 5.0815 -1.8 -29.5 1.61
25 2-Apr-18 105 4.5316 5.0796 -1.9 -31.4 1.60
26 9-Apr-18 112 4.5346 5.0783 -1.3 -32.7 1.61
27 16-Apr-18 119 4.5295 5.0773 -1.0 -33.7 1.60
28 23-Apr-18 126 4.5236 5.0761 -1.2 -34.9 1.60
29 30-Apr-18 133 4.5306 5.0751 -1.0 -35.9 1.61
30 7-May-18 140 4.5281 5.0742 -0.9 -36.8 1.61
31 14-May-18 147 4.5145 5.0726 -1.6 -38.4 1.59
32 21-May-18 154 4.5094 5.0714 -1.2 -39.6 1.59
33 28-May-18 161 4.5065 5.0706 -0.8 -40.4 1.59
34 4-Jun-18 168 4.5029 5.0699 -0.7 -41.1 1.59
35 11-Jun-18 175 4.5005 5.0692 -0.7 -41.8 1.58
36 19-Jun-18 183 4.4972 5.0671 -2.1 -43.9 1.58
37 25-Jun-18 189 4.4947 5.0654 -1.7 -45.6 1.58
38 2-Jul-18 196 4.4916 5.0643 -1.1 -46.7 1.58
39 9-Jul-18 203 4.4881 5.0631 -1.2 -47.9 1.58
40 16-Jul-18 210 4.4856 5.0622 -0.9 -48.8 1.58
41 23-Jul-18 217 4.4698 5.0611 -1.1 -49.9 1.56
42 30-Jul-18 224 4.4639 5.0601 -1.0 -50.9 1.56
TORING

UNGAI BULOH KE ASSAM JAWA

5.037 m
2.95870 m
2.97141 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work

Before rod extension


Extension of rod 0.9667 m
Damaged
Repaired with new baseline reading
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6625 -LHS (SG 62)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 62 @ CH 6625 (LHS)

Last Settlement Reading, A = 45.630 ASAOKA Plot


Intersection Settlement Reading, B = 56.000 100.00
Degree of consolidation, U = A/B = 81%

Date
Elapsed
Sn Sn-1 U 90.00 f(x) = 0.8619671744x + 7.7049202976
Days
18/Dec/17 0 0.00
21/Dec/17 3 0.66 -
25/Dec/17 7 0.43 80.00

28/Dec/17 10 0.39
2/Jan/18 15 0.70
4/Jan/18 17 2.23 70.00

Sn
8/Jan/18 21 2.66
11/Jan/18 24 3.28
15/Jan/18 28 3.89
18/Jan/18 31 4.62 60.00
22/Jan/18 35 5.98
25/Jan/18 38 7.42
29/Jan/18 42 8.84 50.00
1/Feb/18 45 20.70
5/Feb/18 49 21.85
12/Feb/18 56 23.28
19/Feb/18 63 24.32 40.00
26/Feb/18 70 26.70
19/Mar/18 91 27.73
26/Mar/18 98 29.53 30.00
2/Apr/18 105 31.43 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00
9/Apr/18 112 32.73
16/Apr/18 119 33.73
Sn-1
23/Apr/18 126 34.93
30/Apr/18 133 35.93
7/May/18 140 36.83
14/May/18 147 38.43
21/May/18 154 39.63
28/May/18 161 40.43
4/Jun/18 168 41.13
11/Jun/18 175 41.83
19/Jun/18 183 43.93 41.83
25/Jun/18 189 45.63 43.93
2/Jul/18 196 46.73 45.63
9/Jul/18 203 47.93 46.73
16/Jul/18 210 48.83 47.93
23/Jul/18 217 49.93 48.83
30/Jul/18 224 50.93 49.93
6

0.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
56.000 56.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 63 @ CH 6625 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.4564 3.7864 0.0 0.0 0.00


2 7-May-18 0 2.9766 3.7864 0.0 0.0 0.52
3 10-May-18 3 2.9751 3.7866 0.2 0.2 0.52
4 14-May-18 7 2.9728 3.7862 -0.4 -0.2 0.52
5 17-May-18 10 2.9719 3.7858 -0.4 -0.6 0.52
6 21-May-18 14 2.9674 3.7850 -0.8 -1.4 0.51
7 24-May-18 17 3.2474 3.7841 -0.9 -2.3 0.79
8 28-May-18 21 3.2503 3.7832 -0.9 -3.2 0.80
9 31-May-18 24 3.4486 3.7826 -0.6 -3.8 1.00
10 31-May-18 24 3.4486 4.6258 0.0 -3.8 1.00
11 4-Jun-18 28 3.4522 4.6252 -0.6 -4.4 1.00
12 7-Jun-18 31 3.9124 4.5982 -27.0 -31.4 1.49
13 11-Jun-18 35 3.9716 4.5955 -2.7 -34.1 1.55
14 13-Jun-18 37 3.9742 4.5947 -0.8 -34.9 1.55
15 19-Jun-18 43 3.9707 4.5927 -2.0 -36.9 1.55
16 25-Jun-18 49 3.9743 4.5912 -1.5 -38.4 1.56
TORING

UNGAI BULOH KE ASSAM JAWA

5.037 m
2.45638 m
2.48809 m

Remarks

Existing Ground Level


After filling

Rod Extension of 0.8432m


Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6625 -RHS (SG 63)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 63 @ CH 6625 (RHS)

Last Settlement Reading, A = 38.400 ASAOKA Plot


Intersection Settlement Reading, B = 111.902 100.00
Degree of consolidation, U = A/B = 34% f(x) = 0.9704914935x + 3.3011385769
90.00
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 -0.20 0.00 -
14/May/18 7 0.20 -0.20 70.00
17/May/18 10 0.60 0.20
21/May/18 14 1.40 0.60

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 2.30 1.40

Sn
28/May/18 21 3.20 2.30
31/May/18 24 3.80 3.20 50.00
4/Jun/18 28 4.40 3.80
7/Jun/18 31 31.40 4.40
40.00
11/Jun/18 35 34.10 31.40
13/Jun/18 37 34.90 34.10
19/Jun/18 43 36.90 34.90 30.00
25/Jun/18 49 38.40 36.90
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
9

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
111.902 111.902
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 64 @ CH 6800 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.1036 4.4383 0.0 0.0 0.00


2 18-Dec-17 0 3.3093 4.4383 0.0 0.0 0.21
3 21-Dec-17 3 3.2181 4.4386 0.3 0.3 0.11
4 25-Dec-17 7 3.3161 4.4381 -0.5 -0.2 0.21
5 28-Dec-17 10 3.3204 4.4389 0.8 0.6 0.22
6 2-Jan-18 15 3.3187 4.4384 -0.4 0.1 0.21
7 4-Jan-18 17 3.3216 4.4380 -0.5 -0.3 0.22
8 8-Jan-18 21 3.3308 4.4376 -0.3 -0.6 0.23
9 11-Jan-18 24 3.5815 4.4359 -1.7 -2.4 0.48
10 15-Jan-18 28 3.5764 4.4353 -0.6 -3.0 0.48
11 18-Jan-18 31 3.5935 4.4345 -0.8 -3.8 0.49
12 22-Jan-18 35 4.1440 4.4176 -16.9 -20.7 1.06
13 25-Jan-18 38 4.1564 4.4173 -0.3 -21.0 1.07
14 29-Jan-18 42 4.1259 4.4163 -0.9 -21.9 1.04
15 29-Jan-18 42 4.1259 5.4189 0.0 -22.0 1.04
16 1-Feb-18 45 4.1245 5.4181 -0.9 -22.8 1.04
17 5-Feb-18 49 4.1197 5.4171 -0.9 -23.8 1.04
18 12-Feb-18 56 4.1236 5.4158 -1.3 -25.0 1.05
19 19-Feb-18 63 4.1207 5.4149 -0.9 -26.0 1.04
20 26-Feb-18 70 4.0945 5.4128 -2.1 -28.1 1.02
21 5-Mar-18 77 - - - - -
22 12-Mar-18 84 4.8591 5.0270 0.0 -28.1 1.78
23 19-Mar-18 91 4.8494 5.0251 -1.9 -30.0 1.78
24 26-Mar-18 98 4.8516 5.0240 -1.1 -31.1 1.78
25 2-Apr-18 105 4.8451 5.0221 -1.9 -33.0 1.77
26 9-Apr-18 112 4.8422 5.0208 -1.3 -34.3 1.77
27 16-Apr-18 119 4.8391 5.0197 -1.1 -35.4 1.77
28 23-Apr-18 126 4.8412 5.0185 -1.2 -36.6 1.77
29 30-Apr-18 133 4.8452 5.0176 -0.9 -37.5 1.78
30 7-May-18 140 4.8481 5.0168 -0.8 -38.3 1.78
31 14-May-18 147 4.7649 5.0155 -1.3 -39.6 1.70
32 21-May-18 154 4.7294 5.0143 -1.2 -40.8 1.67
33 28-May-18 161 4.4258 5.0137 -0.6 -41.4 1.36
34 4-Jun-18 168 4.7228 5.0129 -0.8 -42.2 1.66
35 11-Jun-18 175 4.7204 5.0122 -0.7 -42.9 1.66
36 19-Jun-18 183 4.7104 5.0097 -2.5 -45.4 1.65
37 25-Jun-18 189 4.7064 5.0075 -2.2 -47.6 1.65
38 2-Jul-18 196 4.7024 5.0065 -1.0 -48.6 1.65
39 9-Jul-18 203 4.7002 5.0052 -1.3 -49.9 1.65
40 16-Jul-18 210 4.6947 5.0042 -1.0 -50.9 1.64
41 23-Jul-18 217 4.6906 5.0033 -0.9 -51.8 1.64
42 30-Jul-18 224 4.6854 5.0022 -1.1 -52.9 1.63
TORING

UNGAI BULOH KE ASSAM JAWA

5.423 m
3.10360 m
3.11648 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work

Before rod extension


Rod extension of 1.0026 m

G. I Pipe was disturbed


Repaired with new baseline
Backfilling & compaction work
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6800 - LHS (SG 64)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

SURCHARGE LEVEL
6

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 64 @ CH 6800 (LHS)

Last Settlement Reading, A = 47.610 ASAOKA Plot


Intersection Settlement Reading, B = 64.000 100.00
Degree of consolidation, U = A/B = 74%
90.00
f(x) = 0.9208446547x + 5.0912443623
Elapsed
Date Sn Sn-1 U
Days
80.00
18/Dec/17 0 0.00
21/Dec/17 3 -0.30 -
25/Dec/17 7 0.15 70.00
28/Dec/17 10 -0.60
2/Jan/18 15 -0.15
60.00
4/Jan/18 17 0.31

Sn
8/Jan/18 21 0.64
11/Jan/18 24 2.36 50.00
15/Jan/18 28 3.00
18/Jan/18 31 3.78
40.00
22/Jan/18 35 20.71
25/Jan/18 38 21.02
29/Jan/18 42 21.93 30.00
1/Feb/18 45 22.81
5/Feb/18 49 23.76
20.00
12/Feb/18 56 25.04
19/Feb/18 63 25.97
26/Feb/18 70 28.11 10.00
19/Mar/18 91 30.01
26/Mar/18 98 31.11 0.00
2/Apr/18 105 33.01 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00
9/Apr/18 112 34.31
16/Apr/18 119 35.41
Sn-1
23/Apr/18 126 36.61
30/Apr/18 133 37.51
7/May/18 140 38.31
14/May/18 147 39.61
21/May/18 154 40.81
28/May/18 161 41.41
4/Jun/18 168 42.21
11/Jun/18 175 42.91 42.21
19/Jun/18 183 45.41 42.91
25/Jun/18 189 47.61 45.41
2/Jul/18 196 48.61 47.61
9/Jul/18 203 49.91 48.61
16/Jul/18 210 50.91 49.91
23/Jul/18 217 51.81 50.91
30/Jul/18 224 52.91 51.81
3

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
64.000 64.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 65 @ CH 6800 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.4637 3.8016 0.0 0.0 0.00


2 7-May-18 0 3.0929 3.8016 0.0 0.0 0.63
3 10-May-18 3 3.0964 3.8013 -0.3 -0.3 0.63
4 14-May-18 7 3.1383 3.8008 -0.5 -0.8 0.68
5 17-May-18 10 3.1417 3.8006 -0.2 -1.0 0.68
6 21-May-18 14 - - - -1.0 0.68
7 24-May-18 17 3.4732 3.7989 -1.7 -2.7 1.01
8 28-May-18 21 3.4779 3.7977 -1.2 -3.9 1.02
9 31-May-18 24 3.6355 3.7980 0.3 -3.6 1.18
10 31-May-18 24 3.6355 4.7982 0.0 -3.6 1.18
11 4-Jun-18 28 3.6381 4.7977 -0.5 -4.1 1.18
12 7-Jun-18 31 - - - -4.1 1.18
13 11-Jun-18 35 - - - -4.1 1.18
14 13-Jun-18 37 - - - -4.1 1.18
15 19-Jun-18 43 - - - -4.1 1.18
16 25-Jun-18 49 - - - -4.1 1.18
TORING

UNGAI BULOH KE ASSAM JAWA

5.423 m
2.46366 m
2.50440 m

Remarks

Existing Ground Level


After filling

Rod Extension of 1.0002m

Damaged
Damaged
Damaged
Damaged
Damaged
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6800 -RHS (SG 65)

Embankment RL (m) vs Elapsed Day


10

SURCHARGE LEVEL
6

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 65 @ CH 6800 (RHS)

Last Settlement Reading, A = 4.100 ASAOKA Plot


Intersection Settlement Reading, B = 10.469 100.00
Degree of consolidation, U = A/B = 39%
90.00 f(x) = 0.941770971x + 0.6093057607
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.30 0.00 -
14/May/18 7 0.80 0.30 70.00
17/May/18 10 1.00 0.80
21/May/18 14 1.00 1.00

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 2.70 1.00

Sn
28/May/18 21 3.90 2.70
31/May/18 24 3.60 3.90 50.00
4/Jun/18 28 4.10 3.60
40.00

30.00

20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
10.469 10.469
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 66 @ CH 6850 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.7151 4.0378 0.0 0.0 0.00


2 7-May-18 0 3.2516 4.0378 0.0 0.0 0.54
3 10-May-18 3 3.2489 4.0377 -0.1 -0.1 0.53
4 14-May-18 7 3.2447 4.0373 -0.4 -0.5 0.53
5 17-May-18 10 3.2459 4.0369 -0.4 -0.9 0.53
6 21-May-18 14 - - - -0.9 0.53
7 24-May-18 17 3.5267 - - -0.9 0.81
8 28-May-18 21 - - - -0.9 0.81
9 31-May-18 24 - - - -0.9 0.81
10 4-Jun-18 28 - - - -0.9 0.81
11 11-Jun-18 35 - - - -0.9 0.81
12 13-Jun-18 37 - - - -0.9 0.81
13 19-Jun-18 43 - - - -0.9 0.81
14 25-Jun-18 49 - - - -0.9 0.81
TORING

UNGAI BULOH KE ASSAM JAWA

5.246 m
2.71506 m
2.73762 m

Remarks

Existing Ground Level


After filling

G.I. Pipe was disturbed


Damaged
Damaged
Damaged
Damaged
Damaged
Damaged
Damaged
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6850 -RHS (SG 66)

Embankment RL (m) vs Elapsed Day


10

SURCHARGE LEVEL
6

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 66 @ CH 6850 (RHS)

Last Settlement Reading, A = 0.900 ASAOKA Plot


Intersection Settlement Reading, B = 100.00
Degree of consolidation, U = A/B = f(x) = 1.4285714286x + 0.2142857143
90.00
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.10 0.00 -
14/May/18 7 0.50 0.10 70.00
17/May/18 10 0.90 0.50

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00

Sn
50.00

40.00

30.00

20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
3

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
0.000 0.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 67 @ CH 6925 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.6956 4.0191 0.0 0.0 0.00


2 7-May-18 0 3.1388 4.0191 0.0 0.0 0.44
3 10-May-18 3 3.1382 4.0193 0.2 0.2 0.44
4 14-May-18 7 3.1359 4.0187 -0.6 -0.4 0.44
5 17-May-18 10 3.1337 4.0185 -0.2 -0.6 0.44
6 21-May-18 14 - - - -0.6 0.44
7 24-May-18 17 3.4469 4.0170 -1.5 -2.1 0.75
8 28-May-18 21 3.4491 4.0159 -1.1 -3.2 0.76
9 31-May-18 24 3.6175 4.0154 -0.5 -3.7 0.93
10 31-May-18 24 3.6175 5.0046 0.0 -3.7 0.93
11 4-Jun-18 28 3.6194 5.0039 -0.7 -4.4 0.93
12 7-Jun-18 31 4.0179 5.0025 -1.4 -5.8 1.33
13 11-Jun-18 35 4.0144 5.0018 -0.7 -6.5 1.33
14 13-Jun-18 37 4.0178 5.0013 -0.5 -7.0 1.33
15 19-Jun-18 43 4.0205 5.0001 -1.2 -8.2 1.33
16 25-Jun-18 49 4.0162 4.9991 -1.0 -9.2 1.33
TORING

UNGAI BULOH KE ASSAM JAWA

4.98 m
2.69558 m
2.71660 m

Remarks

Existing Ground Level


After filling

Rod extension of 0.9892m


Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6925 -RHS (SG 67)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 67 @ CH 6925 (RHS)

Last Settlement Reading, A = 9.200 ASAOKA Plot


Intersection Settlement Reading, B = 100.00
Degree of consolidation, U = A/B = f(x) = 1.0697156608x + 0.4280771146
90.00
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 -0.20 0.00 -
14/May/18 7 0.40 -0.20 70.00
17/May/18 10 0.60 0.40
21/May/18 14 0.60 0.60

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 2.10 0.60

Sn
28/May/18 21 3.20 2.10
31/May/18 24 3.70 3.20 50.00
31/May/18 24 3.70 3.70
4/Jun/18 28 4.40 3.70
40.00
7/Jun/18 31 5.80 4.40
11/Jun/18 35 6.50 5.80
13/Jun/18 37 7.00 6.50 30.00
19/Jun/18 43 8.20 7.00
25/Jun/18 49 9.20 8.20
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
6

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
0.000 0.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 67A @ CH 6975 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.6499 3.9842 0.0 0.0 0.00


2 7-May-18 0 3.1906 3.9842 0.0 0.0 0.54
3 10-May-18 3 3.1862 3.9844 0.2 0.2 0.54
4 14-May-18 7 3.1821 3.9840 -0.4 -0.2 0.53
5 17-May-18 10 3.1810 3.9836 -0.4 -0.6 0.53
6 21-May-18 14 - - - -0.6 0.53
7 24-May-18 17 3.4638 3.9819 -1.7 -2.3 0.82
8 28-May-18 21 3.4702 3.9807 -1.2 -3.5 0.82
9 31-May-18 24 3.6096 3.9804 -0.3 -3.8 0.96
10 31-May-18 24 3.6096 4.9416 0.0 -3.8 0.96
11 4-Jun-18 28 3.6107 4.9410 -0.6 -4.4 0.97
12 7-Jun-18 31 4.0014 4.9393 -1.7 -6.1 1.36
13 11-Jun-18 35 4.0037 4.9386 -0.7 -6.8 1.36
14 13-Jun-18 37 4.0013 4.9383 -0.3 -7.1 1.36
15 19-Jun-18 43 4.0037 4.9371 -1.2 -8.3 1.36
16 25-Jun-18 49 4.0047 4.9361 -1.0 -9.3 1.36
TORING

UNGAI BULOH KE ASSAM JAWA

4.81 m
2.64994 m
2.68098 m

Remarks

Existing Ground Level


After filling

Rod extension of 0.9612m


PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 6975 -RHS (SG 67A)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 67A @ CH 6975 (RHS)

Last Settlement Reading, A = 9.300 ASAOKA Plot


Intersection Settlement Reading, B = 100.00
Degree of consolidation, U = A/B = f(x) = 1.0575153424x + 0.4699660217
90.00
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 -0.20 0.00 -
14/May/18 7 0.20 -0.20 70.00
17/May/18 10 0.60 0.20
21/May/18 14 0.60 0.60

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 2.30 0.60

Sn
28/May/18 21 3.50 2.30
31/May/18 24 3.80 3.50 50.00
31/May/18 24 3.80 3.80
4/Jun/18 28 4.40 3.80
40.00
7/Jun/18 31 6.10 4.40
11/Jun/18 35 6.80 6.10
13/Jun/18 37 7.10 6.80 30.00
19/Jun/18 43 8.30 7.10
25/Jun/18 49 9.30 8.30
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
7

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
0.000 0.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 68 @ CH 7025 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.6857 4.0497 0.0 0.0 0.00


2 7-May-18 0 3.3048 4.0497 0.0 0.0 0.62
3 10-May-18 3 3.3094 4.0495 -0.2 -0.2 0.62
4 14-May-18 7 3.3120 4.0492 -0.3 -0.5 0.63
5 17-May-18 10 3.3137 4.0487 -0.5 -1.0 0.63
6 21-May-18 14 3.6699 4.0272 -21.5 -22.5 1.01
7 24-May-18 17 3.6714 4.0260 -1.2 -23.7 1.01
8 28-May-18 21 3.6771 4.0251 -0.9 -24.6 1.02
9 31-May-18 24 3.6705 4.0252 0.1 -24.5 1.01
10 31-May-18 24 3.6705 5.0123 0.1 -24.4 1.01
11 4-Jun-18 28 3.6721 5.0120 -0.3 -24.7 1.01
12 7-Jun-18 31 4.0125 5.0001 -11.9 -36.6 1.36
13 11-Jun-18 35 4.0164 4.9993 -0.8 -37.4 1.37
14 13-Jun-18 37 4.0183 4.9988 -0.5 -37.9 1.37
15 19-Jun-18 43 4.0148 4.9973 -1.5 -39.4 1.37
16 25-Jun-18 49 4.0131 4.9964 -0.9 -40.3 1.37
TORING

UNGAI BULOH KE ASSAM JAWA

4.881 m
2.68566 m
2.74950 m

Remarks

Existing Ground Level


After filling

Rod extension of 0.9870m


Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7025 -RHS (SG 68)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 68 @ CH 7025 (RHS)

Last Settlement Reading, A = 40.400 ASAOKA Plot


Intersection Settlement Reading, B = 45.050 100.00
Degree of consolidation, U = A/B = 90%

Elapsed
90.00
f(x) = 0.8791103719x + 5.4466125275
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.20 0.00 -
14/May/18 7 0.50 0.20 70.00
17/May/18 10 1.00 0.50
21/May/18 14 22.50 1.00

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 23.70 22.50

Sn
28/May/18 21 24.60 23.70
31/May/18 24 24.50 24.60 50.00
31/May/18 24 24.40 24.50
4/Jun/18 28 24.70 24.40
40.00
7/Jun/18 31 36.60 24.70
11/Jun/18 35 37.40 36.60
13/Jun/18 37 37.90 37.40 30.00
19/Jun/18 43 39.40 37.90
25/Jun/18 49 40.30 39.40
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
5

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
45.050 45.050
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 69 @ CH 7200 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.8579 4.1748 0.0 0.0 0.00


2 7-May-18 0 3.3520 4.1748 0.0 0.0 0.49
3 10-May-18 3 3.3486 4.1746 -0.2 -0.2 0.49
4 14-May-18 7 3.3489 4.1743 -0.3 -0.5 0.49
5 17-May-18 10 3.3156 4.1739 -0.4 -0.9 0.46
6 21-May-18 14 3.3303 4.1579 -16.0 -16.9 0.49
7 24-May-18 17 3.3346 4.1572 -0.7 -17.6 0.49
8 28-May-18 21 3.3381 4.1560 -1.2 -18.8 0.50
9 31-May-18 24 3.7880 4.1335 -22.5 -41.3 0.97
10 4-Jun-18 28 3.7844 4.1328 -0.7 -42.0 0.97
11 7-Jun-18 31 3.7882 4.1319 -0.9 -42.9 0.97
12 11-Jun-18 35 3.7903 4.1312 -0.7 -43.6 0.98
13 13-Jun-18 37 3.7882 4.1308 -0.4 -44.0 0.97
14 19-Jun-18 43 3.7864 4.1297 -1.1 -45.1 0.97
15 25-Jun-18 49 3.7849 4.1287 -1.0 -46.1 0.97
TORING

UNGAI BULOH KE ASSAM JAWA

5.397 m
2.85792 m
2.87807 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7200 -RHS (SG 69)

Embankment RL (m) vs Elapsed Day


10

SURCHARGE LEVEL
6

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 69 @ CH 7200 (RHS)

Last Settlement Reading, A = 46.100 ASAOKA Plot


Intersection Settlement Reading, B = 61.300 100.00
Degree of consolidation, U = A/B = 75%
90.00
f(x) = 0.9046396983x + 5.8480048217
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.20 0.00 -
14/May/18 7 0.50 0.20 70.00
17/May/18 10 0.90 0.50
21/May/18 14 16.90 0.90

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 17.60 16.90

Sn
28/May/18 21 18.80 17.60
31/May/18 24 41.30 18.80 50.00
4/Jun/18 28 42.00 41.30
7/Jun/18 31 42.90 42.00
40.00
11/Jun/18 35 43.60 42.90
13/Jun/18 37 44.00 43.60
19/Jun/18 43 45.10 44.00 30.00
25/Jun/18 49 46.10 45.10
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
7

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
61.300 61.300
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 70 @ CH 7400 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.6067 3.9231 0.0 0.0 0.00


2 7-May-18 0 2.8274 3.9231 0.0 0.0 0.22
3 10-May-18 3 2.8316 3.9229 -0.2 -0.2 0.23
4 14-May-18 7 2.8286 3.9226 -0.3 -0.5 0.22
5 17-May-18 10 2.8270 3.9224 -0.2 -0.7 0.22
6 21-May-18 14 3.3871 3.9134 -9.0 -9.7 0.79
7 24-May-18 17 3.3849 3.9127 -0.7 -10.4 0.79
8 28-May-18 21 3.3817 3.9114 -1.3 -11.7 0.79
9 31-May-18 24 3.8002 3.8948 -16.6 -28.3 1.22
10 4-Jun-18 28 3.8026 3.8933 -1.5 -29.8 1.23
11 7-Jun-18 31 3.8108 3.8922 -1.1 -30.9 1.24
12 11-Jun-18 35 3.8085 3.8914 -0.8 -31.7 1.23
13 13-Jun-18 37 3.8053 3.8909 -0.5 -32.2 1.23
14 19-Jun-18 43 3.8084 3.8898 -1.1 -33.3 1.24
15 25-Jun-18 49 3.8072 3.8888 -1.0 -34.3 1.23
TORING

UNGAI BULOH KE ASSAM JAWA

4.205 m
2.60667 m
2.61972 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7400 -RHS (SG 70)

Embankment RL (m) vs Elapsed Day


10

6
SURCHARGE LEVEL
4

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 70 @ CH 7400 (RHS)

Last Settlement Reading, A = 34.300 ASAOKA Plot


Intersection Settlement Reading, B = 53.882 100.00
Degree of consolidation, U = A/B = 64%
90.00
f(x) = 0.9286984708x + 3.8418119616
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.20 0.00 -
14/May/18 7 0.50 0.20 70.00
17/May/18 10 0.70 0.50
21/May/18 14 9.70 0.70

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 10.40 9.70

Sn
28/May/18 21 11.70 10.40
31/May/18 24 28.30 11.70 50.00
4/Jun/18 28 29.80 28.30
7/Jun/18 31 30.90 29.80
40.00
11/Jun/18 35 31.70 30.90
13/Jun/18 37 32.20 31.70
19/Jun/18 43 33.30 32.20 30.00
25/Jun/18 49 34.30 33.30
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
6

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
53.882 53.882
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 71 @ CH 7475 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.6475 3.9740 0.0 0.0 0.00


2 7-May-18 0 2.6755 3.9740 0.0 0.0 0.03
3 10-May-18 3 3.0249 3.9738 -0.2 -0.2 0.38
4 14-May-18 7 3.0271 3.9733 -0.5 -0.7 0.38
5 17-May-18 10 3.0283 3.9730 -0.3 -1.0 0.38
6 21-May-18 14 3.3842 3.9593 -13.7 -14.7 0.75
7 24-May-18 17 3.3891 3.9584 -0.9 -15.6 0.76
8 28-May-18 21 3.3907 3.9577 -0.7 -16.3 0.76
9 31-May-18 24 3.8117 3.9365 -21.2 -37.5 1.20
10 4-Jun-18 28 3.8101 3.9347 -1.8 -39.3 1.20
11 7-Jun-18 31 3.8162 3.9336 -1.1 -40.4 1.21
12 11-Jun-18 35 3.8183 3.9328 -0.8 -41.2 1.21
13 13-Jun-18 37 3.8144 3.9324 -0.4 -41.6 1.21
14 19-Jun-18 43 3.8114 3.9312 -1.2 -42.8 1.21
15 25-Jun-18 49 3.8129 3.9302 -1.0 -43.8 1.21
TORING

UNGAI BULOH KE ASSAM JAWA

4.506 m
2.64749 m
2.67549 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7475 -RHS (SG 71)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 71 @ CH 7475 (RHS)

Last Settlement Reading, A = 43.800 ASAOKA Plot


Intersection Settlement Reading, B = 61.807 100.00
Degree of consolidation, U = A/B = 71%
90.00
f(x) = 0.9145267899x + 5.2844881614
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.20 0.00 -
14/May/18 7 0.70 0.20 70.00
17/May/18 10 1.00 0.70
21/May/18 14 14.70 1.00

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 15.60 14.70

Sn
28/May/18 21 16.30 15.60
31/May/18 24 37.50 16.30 50.00
4/Jun/18 28 39.30 37.50
7/Jun/18 31 40.40 39.30
40.00
11/Jun/18 35 41.20 40.40
13/Jun/18 37 41.60 41.20
19/Jun/18 43 42.80 41.60 30.00
25/Jun/18 49 43.80 42.80
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
4

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
61.807 61.807
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 72 @ CH 7600 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 2.7828 4.1214 0.0 0.0 0.00


2 7-May-18 0 3.0649 4.1214 0.0 0.0 0.28
3 10-May-18 3 3.0681 4.1211 -0.3 -0.3 0.29
4 14-May-18 7 3.0647 4.1208 -0.3 -0.6 0.28
5 17-May-18 10 3.0638 4.1205 -0.3 -0.9 0.28
6 21-May-18 14 3.0606 4.1197 -0.8 -1.7 0.28
7 24-May-18 17 3.0637 4.1190 -0.7 -2.4 0.28
8 28-May-18 21 3.0649 4.1184 -0.6 -3.0 0.29
9 31-May-18 24 - - - -3.0 0.29
10 4-Jun-18 28 3.5725 4.1007 -17.7 -20.7 0.81
11 7-Jun-18 31 3.6134 4.0992 -1.5 -22.2 0.85
12 11-Jun-18 35 3.6167 4.0983 -0.9 -23.1 0.86
13 13-Jun-18 37 3.6194 4.0978 -0.5 -23.6 0.86
14 19-Jun-18 43 3.6166 4.0963 -1.5 -25.1 0.86
15 25-Jun-18 49 3.6128 4.0954 -0.9 -26.0 0.86
TORING

UNGAI BULOH KE ASSAM JAWA

4.997 m
2.78278 m
2.82319 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7600 -RHS (SG 72)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 72 @ CH 7600 (RHS)

Last Settlement Reading, A = 26.000 ASAOKA Plot


Intersection Settlement Reading, B = 47.623 100.00
Degree of consolidation, U = A/B = 55%
90.00
f(x) = 0.9471721243x + 2.5144622352
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.30 0.00 -
14/May/18 7 0.60 0.30 70.00
17/May/18 10 0.90 0.60
21/May/18 14 1.70 0.90

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 2.40 1.70

Sn
28/May/18 21 3.00 2.40
31/May/18 24 3.00 3.00 50.00
4/Jun/18 28 20.70 3.00
7/Jun/18 31 22.20 20.70
40.00
11/Jun/18 35 23.10 22.20
13/Jun/18 37 23.60 23.10
19/Jun/18 43 25.10 23.60 30.00
25/Jun/18 49 26.00 25.10
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
2

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
47.623 47.623
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 73 @ CH 7600 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.1443 4.4963 0.0 0.0 0.00


2 18-Dec-17 0 3.4275 4.4963 0.0 0.0 0.28
3 21-Dec-17 3 3.4247 4.4955 -0.8 -0.8 0.28
4 25-Dec-17 7 3.4132 4.4957 0.2 -0.6 0.27
5 28-Dec-17 10 3.4377 4.4954 -0.4 -0.9 0.29
6 2-Jan-18 15 3.4362 4.4956 0.2 -0.7 0.29
7 4-Jan-18 17 3.4080 4.4949 -0.7 -1.4 0.27
8 8-Jan-18 21 3.6720 4.4829 -12.0 -13.4 0.54
9 11-Jan-18 24 4.1151 4.4669 -16.0 -29.4 1.00
10 15-Jan-18 28 4.1073 4.4662 -0.7 -30.1 0.99
11 15-Jan-18 28 4.1073 5.2602 0.0 -30.1 0.99
12 18-Jan-18 31 4.0136 5.2590 -1.2 -31.3 0.90
13 22-Jan-18 35 4.0116 5.2579 -1.1 -32.4 0.90
14 25-Jan-18 38 4.0865 5.2573 -0.6 -33.0 0.98
15 29-Jan-18 42 4.1306 5.2561 -1.2 -34.2 1.02
16 1-Feb-18 45 4.0820 5.2547 -1.4 -35.6 0.97
17 5-Feb-18 49 4.1057 5.2535 -1.2 -36.8 1.00
18 12-Feb-18 56 4.1048 5.2523 -1.2 -38.0 1.00
19 19-Feb-18 63 4.1013 5.2511 -1.2 -39.2 1.00
20 26-Feb-18 70 4.1004 5.2497 -1.4 -40.6 1.00
21 5-Mar-18 77 4.3454 5.2002 -49.5 -90.1 1.29
22 12-Mar-18 84 4.3794 5.1982 -2.0 -92.1 1.33
23 19-Mar-18 91 4.3815 5.1967 -1.5 -93.6 1.33
24 26-Mar-18 98 4.3786 5.1949 -1.8 -95.4 1.33
25 2-Apr-18 105 4.3826 5.1928 -2.1 -97.5 1.34
26 9-Apr-18 112 4.3857 5.1914 -1.4 -98.9 1.34
27 16-Apr-18 119 4.3891 5.1902 -1.2 -100.1 1.34
28 23-Apr-18 126 4.3425 5.1895 -0.7 -100.8 1.30
29 30-Apr-18 133 4.4050 5.1883 -1.2 -102.0 1.36
30 7-May-18 140 - - - -102.0 -
31 14-May-18 147 - - - -102.0 -
32 21-May-18 154 4.7608 5.5611 0.0 -102.0 1.72
33 28-May-18 161 4.4628 5.5607 -0.4 -102.4 1.42
34 4-Jun-18 168 4.7615 5.5602 -0.5 -102.9 1.72
35 11-Jun-18 175 4.7584 5.5593 -0.9 -103.8 1.72
36 19-Jun-18 183 4.7539 5.5577 -1.6 -105.4 1.72
37 25-Jun-18 189 4.7505 5.5557 -2.0 -107.4 1.71
TORING

UNGAI BULOH KE ASSAM JAWA

4.997 m
3.14428 m
3.17412 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work


Backfilling & compaction work
Before rod extension
Extension rod of 0.7940 m

Backfilling & compaction work


Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7600 - LHS (SG 73)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10
0
-10
-20
-30
-40
-50
-60
-70
-80
-90
-100
-110
-120
-130
-140
-150
-110
-120
-130
-140
-150
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 73 @ CH 7600 (LHS)

Last Settlement Reading, A = 107.400 ASAOKA Plot


Intersection Settlement Reading, B = 148.040 200
Degree of consolidation, U = A/B = 73%
180
Elapsed
Date Sn Sn-1 U
Days
160
18/Dec/17 0 0.00
21/Dec/17 3 0.80 0.00 -
25/Dec/17 7 0.58 0.80 140
28/Dec/17 10 0.94 0.58
2/Jan/18 15 0.70 0.94
120
4/Jan/18 17 1.40 0.70
EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.

Sn
8/Jan/18 21 13.38 1.40
11/Jan/18 24 29.43 13.38 100 f(x) = 0.9646758334x + 5.2258275278
15/Jan/18 28 30.11 29.43
18/Jan/18 31 31.34 30.11
80
22/Jan/18 35 32.39 31.34
25/Jan/18 38 33.02 32.39
29/Jan/18 42 34.23 33.02 60
1/Feb/18 45 35.58 34.23
5/Feb/18 49 36.78 35.58
40
12/Feb/18 56 38.00 36.78
19/Feb/18 63 39.24 38.00
26/Feb/18 70 40.60 39.24 20
5/Mar/18 77 90.10 40.60
12/Mar/18 84 92.10 90.10 0
19/Mar/18 91 93.60 92.10 0.00 20.00 40.00 60.00 80.00 100.00 120.00 140.00 160.00 180.00 200.00
26/Mar/18 98 95.40 93.60
2/Apr/18 105 97.50 95.40
Sn-1
9/Apr/18 112 98.90 97.50
16/Apr/18 119 100.10 98.90
23/Apr/18 126 100.80 100.10
EMBANKME
30/Apr/18 133 102.00 100.80
7/May/18 140 102.00 102.00
14/May/18 147 102.00 102.00
21/May/18 154 102.00 102.00
28/May/18 161 102.40 102.00
4/Jun/18 168 102.90 102.40
11/Jun/18 175 103.80 102.90
19/Jun/18 183 105.40 103.80
25/Jun/18 189 107.40 105.40
8

.00 160.00 180.00 200.00

(45 degree line.)


0 0
500 500

B (Intercept)
148.040 148.040
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 74 @ CH 7700 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 3.2166 4.5354 0.0 0.0 0.00


2 7-May-18 0 3.4513 4.5354 0.0 0.0 0.23
3 10-May-18 3 3.4531 4.5351 -0.3 -0.3 0.24
4 14-May-18 7 3.4553 4.5348 -0.3 -0.6 0.24
5 17-May-18 10 3.4537 4.5343 -0.5 -1.1 0.24
6 21-May-18 14 3.4498 4.5335 -0.8 -1.9 0.24
7 24-May-18 17 3.4483 4.5327 -0.8 -2.7 0.23
8 28-May-18 21 3.4457 4.5319 -0.8 -3.5 0.23
9 31-May-18 24 - - - -3.5 0.23
10 4-Jun-18 28 3.9864 4.5142 -17.7 -21.2 0.79
11 7-Jun-18 31 3.9927 4.5131 -1.1 -22.3 0.80
12 11-Jun-18 35 3.9946 4.5123 -0.8 -23.1 0.80
13 13-Jun-18 37 4.0002 4.5117 -0.6 -23.7 0.81
14 19-Jun-18 43 4.0024 4.5101 -1.6 -25.3 0.81
15 25-Jun-18 49 4.0009 4.5094 -0.7 -26.0 0.81
TORING

UNGAI BULOH KE ASSAM JAWA

4.75 m
3.21660 m
3.23731 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7700 -RHS (SG 74)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 74 @ CH 7700 (RHS)

Last Settlement Reading, A = 26.000 ASAOKA Plot


Intersection Settlement Reading, B = 45.469 100.00
Degree of consolidation, U = A/B = 57%
90.00
f(x) = 0.9436636704x + 2.5598964447
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.30 0.00 -
14/May/18 7 0.60 0.30 70.00
17/May/18 10 1.10 0.60
21/May/18 14 1.90 1.10

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 2.70 1.90

Sn
28/May/18 21 3.50 2.70
31/May/18 24 3.50 3.50 50.00
4/Jun/18 28 21.20 3.50
7/Jun/18 31 22.30 21.20
40.00
11/Jun/18 35 23.10 22.30
13/Jun/18 37 23.70 23.10
19/Jun/18 43 25.30 23.70 30.00
25/Jun/18 49 26.00 25.30
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
7

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
45.469 45.469
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 75 @ CH 7800 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 3.1858 4.5095 0.0 0.0 0.00


2 7-May-18 0 3.4675 4.5095 0.0 0.0 0.28
3 10-May-18 3 3.4629 4.5092 -0.3 -0.3 0.28
4 14-May-18 7 3.4581 4.5087 -0.5 -0.8 0.27
5 17-May-18 10 3.4588 4.5084 -0.3 -1.1 0.27
6 21-May-18 14 3.4521 4.5074 -1.0 -2.1 0.27
7 24-May-18 17 3.4492 4.5065 -0.9 -3.0 0.27
8 28-May-18 21 3.4462 4.5058 -0.7 -3.7 0.26
9 31-May-18 24 3.4475 4.5052 -0.6 -4.3 0.27
10 4-Jun-18 28 3.9714 4.4872 -18.0 -22.3 0.81
11 7-Jun-18 31 3.9764 4.4861 -1.1 -23.4 0.81
12 11-Jun-18 35 3.9813 4.4853 -0.8 -24.2 0.82
13 13-Jun-18 37 3.9802 4.4847 -0.6 -24.8 0.82
14 19-Jun-18 43 3.9813 4.4829 -1.8 -26.6 0.82
15 25-Jun-18 49 3.9839 4.4825 -0.4 -27.0 0.83
TORING

UNGAI BULOH KE ASSAM JAWA

4.452 m
3.18583 m
3.20830 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7800 -RHS (SG 75)

Embankment RL (m) vs Elapsed Day


10

6
SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 75 @ CH 7800 (RHS)

Last Settlement Reading, A = 27.000 ASAOKA Plot


Intersection Settlement Reading, B = 48.470 100.00
Degree of consolidation, U = A/B = 56%
90.00
f(x) = 0.9453399513x + 2.6512740497
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.30 0.00 -
14/May/18 7 0.80 0.30 70.00
17/May/18 10 1.10 0.80
21/May/18 14 2.10 1.10

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 3.00 2.10

Sn
28/May/18 21 3.70 3.00
31/May/18 24 4.30 3.70 50.00
4/Jun/18 28 22.30 4.30
7/Jun/18 31 23.40 22.30
40.00
11/Jun/18 35 24.20 23.40
13/Jun/18 37 24.80 24.20
19/Jun/18 43 26.60 24.80 30.00
25/Jun/18 49 27.00 26.60
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
7

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
48.470 48.470
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 76 @ CH 7875 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.4356 4.7605 0.0 0.0 0.00


2 18-Dec-17 0 3.7005 4.7605 0.0 0.0 0.26
3 21-Dec-17 3 3.6671 4.7596 -0.8 -0.8 0.23
4 25-Dec-17 7 3.6782 4.7597 0.1 -0.8 0.24
5 28-Dec-17 10 3.7034 4.7589 -0.8 -1.5 0.27
6 2-Jan-18 15 3.6795 4.7586 -0.3 -1.8 0.25
7 4-Jan-18 17 3.6668 4.7579 -0.8 -2.6 0.23
8 8-Jan-18 21 3.9708 4.7434 -14.5 -17.1 0.55
9 11-Jan-18 24 4.3930 4.7326 -10.8 -27.9 0.99
10 15-Jan-18 28 4.3871 4.7312 -1.3 -29.2 0.98
11 18-Jan-18 31 4.3429 4.7305 -0.7 -30.0 0.94
12 18-Jan-18 31 4.3429 5.7304 0.0 -29.9 0.94
13 22-Jan-18 35 4.3602 5.7293 -1.2 -31.1 0.96
14 25-Jan-18 38 4.3648 5.7283 -1.0 -32.1 0.96
15 29-Jan-18 42 4.3077 5.7269 -1.4 -33.5 0.91
16 1-Feb-18 45 4.3252 5.7252 -1.7 -35.2 0.92
17 5-Feb-18 49 4.2992 5.7239 -1.3 -36.5 0.90
18 12-Feb-18 56 4.2967 5.7228 -1.1 -37.6 0.90
19 19-Feb-18 63 4.8121 5.6953 -27.5 -65.1 1.44
20 26-Feb-18 70 4.8244 5.6941 -1.2 -66.3 1.46
21 5-Mar-18 77 4.7776 5.6920 -2.1 -68.4 1.41
22 12-Mar-18 84 4.7683 5.6901 -1.9 -70.3 1.40
23 19-Mar-18 91 4.7643 5.6886 -1.5 -71.8 1.40
24 26-Mar-18 98 4.7590 5.6866 -2.0 -73.8 1.40
25 2-Apr-18 105 4.7492 5.6844 -2.2 -76.0 1.39
26 9-Apr-18 112 4.7439 5.6827 -1.7 -77.7 1.39
27 16-Apr-18 119 4.7382 5.6824 -0.3 -78.0 1.38
28 23-Apr-18 126 4.7346 5.6812 -1.2 -79.2 1.38
29 30-Apr-18 133 4.7293 5.6802 -1.0 -80.2 1.37
30 7-May-18 140 4.7315 5.6788 -1.4 -81.6 1.38
31 14-May-18 147 4.7264 5.6774 -1.4 -83.0 1.37
32 21-May-18 154 4.6951 5.6763 -1.1 -84.1 1.34
33 28-May-18 161 4.6935 5.6752 -1.1 -85.2 1.34
34 4-Jun-18 168 4.6917 5.6746 -0.6 -85.8 1.34
35 11-Jun-18 175 4.6873 5.6737 -0.9 -86.7 1.34
36 19-Jun-18 183 4.6814 5.6716 -2.1 -88.8 1.33
37 25-Jun-18 189 4.6770 5.6694 -2.2 -91.0 1.33
TORING

UNGAI BULOH KE ASSAM JAWA

4.756 m
3.43556 m
3.44431 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work


Backfilling & compaction work

Before rod extension


Extension of rod 0.9999 m

Backfilling & compaction work


PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 7875 - LHS (SG 76)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

-10

-20

-30

-40

-50

-60

-70

-80

-90

-100
-70

-80

-90

-100
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 76 @ CH 7875 (LHS)

Last Settlement Reading, A = 90.960 ASAOKA Plot


Intersection Settlement Reading, B = 140.000 200.00
Degree of consolidation, U = A/B = 65%

Elapsed
180.00 f(x) = 0.9789060465x + 3.0867798272
Date Sn Sn-1 U
Days
160.00
19/Feb/18 63 65.11
26/Feb/18 70 66.29 -
5/Mar/18 77 68.36 108% 140.00
12/Mar/18 84 70.26 68.36 122%
19/Mar/18 91 71.76 70.26 1329%
120.00
26/Mar/18 98 73.76 71.76 210%

Sn
2/Apr/18 105 75.96 73.76 178%
9/Apr/18 112 77.66 75.96 492% 100.00
16/Apr/18 119 77.96 77.66 74%
23/Apr/18 126 79.16 77.96 77%
80.00
30/Apr/18 133 80.16 79.16 80%
7/May/18 140 81.56 80.16 78%
14/May/18 147 82.96 81.56 75% 60.00
21/May/18 154 84.06 82.96 77%
28/May/18 161 85.16 84.06 77%
40.00
4/Jun/18 168 85.76 85.16 82%
11/Jun/18 175 86.66 85.76 83%
19/Jun/18 183 88.76 86.66 74% 20.00
25/Jun/18 189 90.96 88.76 58%
0.00
0.00 20.00 40.00 60.00 80.00 100.00 120.00 140.00 160.00 180.00 200.00

Sn-1
2

.00 160.00 180.00 200.00

(45 degree line.)


0 0
500 500

B (Intercept)
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 77 @ CH 8450 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.8905 5.2314 0.0 0.0 0.00


2 18-Dec-17 0 4.1263 5.2314 0.0 0.0 0.24
3 21-Dec-17 3 4.1263 5.2310 -0.5 -0.5 0.24
4 25-Dec-17 7 4.1186 5.2309 0.0 -0.5 0.23
5 28-Dec-17 10 4.1319 5.2312 0.3 -0.2 0.24
6 2-Jan-18 15 4.1297 5.2310 -0.3 -0.4 0.24
7 4-Jan-18 17 4.1270 5.2303 -0.6 -1.1 0.24
8 8-Jan-18 21 4.4464 5.2234 -6.9 -8.0 0.56
9 11-Jan-18 24 4.8313 5.2015 0.0 -8.0 0.95
10 15-Jan-18 28 4.8280 5.2009 -0.6 -8.6 0.95
11 18-Jan-18 31 4.8098 5.1999 -1.0 -9.6 0.93
12 18-Jan-18 31 4.8098 6.1713 0.0 -9.6 0.93
13 22-Jan-18 35 4.8140 6.1704 -0.9 -10.5 0.93
14 25-Jan-18 38 4.8019 6.1693 -1.1 -11.6 0.92
15 29-Jan-18 42 4.8475 6.1684 -0.9 -12.5 0.97
16 1-Feb-18 45 4.8044 6.1667 -1.7 -14.2 0.93
17 5-Feb-18 49 4.8267 6.1657 -1.0 -15.2 0.95
18 12-Feb-18 56 4.8250 6.1645 -1.2 -16.4 0.95
19 19-Feb-18 63 5.5729 6.4098 0.0 -16.4 1.70
20 26-Feb-18 70 5.5691 6.4079 -1.9 -18.3 1.70
21 5-Mar-18 77 5.5713 6.4062 -1.7 -20.0 1.70
22 12-Mar-18 84 5.5398 6.4038 -2.4 -22.4 1.67
23 19-Mar-18 91 5.5417 6.4020 -1.8 -24.2 1.68
24 26-Mar-18 98 5.5387 6.3998 -2.2 -26.4 1.67
25 2-Apr-18 105 5.5318 6.3969 -2.9 -29.3 1.67
26 9-Apr-18 112 5.5282 6.3951 -1.8 -31.1 1.67
27 16-Apr-18 119 5.5202 6.3932 -1.9 -33.0 1.66
28 23-Apr-18 126 5.5186 6.3914 -1.8 -34.8 1.66
29 30-Apr-18 133 5.5240 6.3892 -2.2 -37.0 1.67
30 7-May-18 140 5.7516 6.3751 -14.1 -51.1 1.91
31 14-May-18 147 - - - -51.1 1.91
32 21-May-18 154 6.3416 7.0909 0.0 -51.1 2.50
33 28-May-18 161 6.3435 7.0892 -1.7 -52.8 2.51
34 4-Jun-18 168 6.3412 7.0881 -1.1 -53.9 2.50
35 7-Jun-18 171 6.3402 7.0861 -2.0 -55.9 2.51
36 19-Jun-18 183 6.3206 7.0823 -3.8 -59.7 2.49
37 25-Jun-18 189 6.3153 7.0796 -2.7 -62.4 2.49
TORING

UNGAI BULOH KE ASSAM JAWA

5.717 m
3.89052 m
3.92298 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work


Repaired and new baseline reading

Before rod extension


Extension of rod 0.9714 m

Repaired and new baseline reading


Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 8450 - LHS (SG 77)

Embankment RL (m) vs Elapsed Day


10

SURCHARGE LEVEL
6

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

-10

-20

-30

-40

-50

-60

-70

-80

-90

-100
-70

-80

-90

-100
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 77 @ CH 8450 (LHS)

Last Settlement Reading, A = 62.390 ASAOKA Plot


Intersection Settlement Reading, B = 43.030 200.00
Degree of consolidation, U = A/B = 145%
180.00
Date
Elapsed
Sn Sn-1 U f(x) = 1.1941898827x - 8.3563608871
Days
160.00
7/May/18 140 51.09
28/May/18 161 52.79 51.09 -
4/Jun/18 168 53.89 52.79 96% 140.00
7/Jun/18 171 55.89 53.89 193%
19/Jun/18 183 59.69 55.89 122%
120.00
25/Jun/18 189 62.39 59.69 145%

Sn
100.00

80.00

60.00

40.00

20.00

0.00
0.00 20.00 40.00 60.00 80.00 100.00 120.00 140.00 160.00 180.00 200.00

Sn-1
71

.00 160.00 180.00 200.00

(45 degree line.)


0 0
500 500

B (Intercept)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC. 13 SG 55 @ CH 6100 (LHS) SG 57 @ CH 6200 (LHS) SG 59 @ CH 6400 (LHS) SG 61 @ CH 6500 (LHS)
CH 6625 (L) SV SH SV SH SV SH SV
No. Date SH SV SV SV
(mm) (mm) (mm) (mm) (mm)

1 18-Dec-17 Installation Date Installation Date Installation Date Installation Date


2 21-Dec-17 -28.00 -0.60 46.67 -0.72 38.89 -0.85 32.94 -0.23
3 25-Dec-17 -24.04 -1.27 18.93 -1.56 15.41 -1.74 13.82 -0.60
4 28-Dec-17 -24.05 -1.67 14.40 -1.46 16.47 -2.44 9.86 0.07
5 2-Jan-18 -23.22 -1.53 15.18 -0.93 24.97 -2.79 8.32 -0.26
6 4-Jan-18 -24.96 -5.14 4.86 -23.91 1.04 -29.60 0.84 -16.92
7 8-Jan-18 -24.60 -6.65 3.70 -25.17 0.98 -30.09 0.82 -19.78
8 11-Jan-18 -23.07 -7.30 3.16 -25.67 0.90 -30.09 0.77 -19.78
9 15-Jan-18 -23.75 -8.28 2.87 -26.65 0.89 -30.09 0.79 -20.42
10 18-Jan-18 -23.02 -21.52 1.07 -38.29 0.60 -31.44 0.73 -19.97
11 22-Jan-18 -23.66 -22.93 1.03 -39.39 0.60 -32.11 0.74 -20.28
12 25-Jan-18 -24.08 -24.30 0.99 -41.68 0.58 -39.45 0.61 -20.92
13 29-Jan-18 -24.31 -25.46 0.95 -42.72 0.57 -41.25 0.59 -21.98
14 1-Feb-18 -27.99 -27.54 1.02 -43.79 0.64 -41.85 0.67 -28.84
15 5-Feb-18 -29.01 -28.59 1.01 -44.41 0.65 -42.95 0.68 -30.34
16 12-Feb-18 -31.42 -30.02 1.05 -45.87 0.68 -44.28 0.71 -31.52
17 19-Feb-18 -31.52 -31.10 1.01 -47.04 0.67 -45.73 0.69 -32.57
18 26-Feb-18 -34.10 -32.92 1.04 -47.64 0.72 -84.94 0.40 -60.77
19 5-Mar-18 -32.21 -33.19 0.97 -49.86 0.65 -84.97 0.38 -60.76
20 12-Mar-18 -33.02 -35.59 0.93 -51.88 0.64 -87.92 0.38 -64.14
21 19-Mar-18 -32.48 -37.39 0.87 -53.08 0.61 -107.88 0.30 -65.64
22 26-Mar-18 -33.80 -39.49 0.86 -54.38 0.62 -109.28 0.31 -65.64
23 2-Apr-18 -33.76 -41.19 0.82 -56.18 0.60 -110.78 0.30 -65.64
24 9-Apr-18 -35.55 -42.49 0.84 -57.48 0.62 -112.78 0.32 -67.74
25 16-Apr-18 -36.98 -43.39 0.85 -58.28 0.63 -114.28 0.32 -69.04
26 23-Apr-18 -38.12 -44.09 0.86 -59.28 0.64 -114.78 0.33 -70.04
27 30-Apr-18 -37.46 -45.19 0.83 -59.68 0.63 -115.58 0.32 -71.14
28 7-May-18 -37.75 -46.09 0.82 -60.68 0.62 -116.48 0.32 -71.94
29 14-May-18 -38.81 -62.29 0.62 -62.78 0.62 -117.68 0.33 -72.94
30 21-May-18 -39.47 -88.49 0.45 -96.28 0.41 -119.08 0.33 -73.94
31 28-May-18 -42.24 -89.59 0.47 -97.38 0.43 -120.18 0.35 -74.94
32 4-Jun-18 -39.32 -90.29 0.44 -98.08 0.40 -121.08 0.32 -76.04
33 11-Jun-18 -43.37 -91.09 0.48 -98.88 0.44 -121.78 0.36 -76.64
34 19-Jun-18 -43.81 -94.09 0.47 -101.58 0.43 -122.48 0.36 -77.24
35 25-Jun-18 -44.24 -95.49 0.46 -103.48 0.43 -124.58 0.36 -79.04
36 2-Jul-18 -45.77 -96.59 0.47 -104.58 0.44 -125.68 0.36 -80.94
37 9-Jul-18 -48.44 -98.39 0.49 -105.88 0.46 -126.78 0.38 -82.14
38 16-Jul-18 -47.79 -99.09 0.48 -106.58 0.45 -127.98 0.37 -83.24
39 23-Jul-18 -51.16 -99.89 0.51 -107.38 0.48 -128.78 0.40 -84.34
40 30-Jul-18 -51.95 -100.59 0.52 -108.18 0.48 -129.58 0.40 -85.24
41
42
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC.
SG 61
13 @ CH 6500 (LHS) SG 62 @ CH 6625 (LHS) SG 64 @ CH 6800 (LHS) SG 73 @ CH 7600 (LHS)
CH 6625 (L) SH SV SH SV SH SV SH
No. Date SH SV SV SV SV
(mm) (mm) (mm) (mm)

1 18-Dec-17 Installation Date Installation Date Installation Date Installation Date


2 21-Dec-17 -28.00 121.74 -0.66 42.42 0.30 -93.33 -0.80 35.00
3 25-Dec-17 -24.04 40.07 -0.43 55.91 -0.15 160.27 -0.58 41.45
4 28-Dec-17 -24.05 -343.57 -0.39 61.67 0.60 -40.08 -0.94 25.59
5 2-Jan-18 -23.22 89.31 -0.70 33.17 0.15 -154.80 -0.70 33.17
6 4-Jan-18 -24.96 1.48 -2.23 11.19 -0.31 80.52 -1.40 17.83
7 8-Jan-18 -24.60 1.24 -2.66 9.25 -0.64 38.44 -13.38 1.84
8 11-Jan-18 -23.07 1.17 -3.28 7.03 -2.36 9.78 -29.43 0.78
9 15-Jan-18 -23.75 1.16 -3.89 6.11 -3.00 7.92 -30.11 0.79
10 18-Jan-18 -23.02 1.15 -5.98 3.85 -20.71 1.11 -31.34 0.73
11 22-Jan-18 -23.66 1.17 -7.42 3.19 -21.02 1.13 -32.39 0.73
12 25-Jan-18 -24.08 1.15 -8.84 2.72 -21.93 1.10 -33.02 0.73
13 29-Jan-18 -24.31 1.11 -20.70 1.17 -21.95 1.11 -34.23 0.71
14 1-Feb-18 -27.99 0.97 -21.85 1.28 -22.81 1.23 -35.58 0.79
15 5-Feb-18 -29.01 0.96 -23.28 1.25 -23.76 1.22 -36.78 0.79
16 12-Feb-18 -31.42 1.00 -24.32 1.29 -25.04 1.25 -38.00 0.83
17 19-Feb-18 -31.52 0.97 -26.70 1.18 -25.97 1.21 -39.24 0.80
18 26-Feb-18 -34.10 0.56 -26.73 1.28 -28.11 1.21 -40.60 0.84
19 5-Mar-18 -32.21 0.53 - - - - -90.10 0.36
20 12-Mar-18 -33.02 0.51 -26.73 1.24 -28.11 1.17 -92.10 0.36
21 19-Mar-18 -32.48 0.49 -27.73 1.17 -30.01 1.08 -93.60 0.35
22 26-Mar-18 -33.80 0.51 -29.53 1.14 -31.11 1.09 -95.40 0.35
23 2-Apr-18 -33.76 0.51 -31.43 1.07 -33.01 1.02 -97.50 0.35
24 9-Apr-18 -35.55 0.52 -32.73 1.09 -34.31 1.04 -98.90 0.36
25 16-Apr-18 -36.98 0.54 -33.73 1.10 -35.41 1.04 -100.10 0.37
26 23-Apr-18 -38.12 0.54 -34.93 1.09 -36.61 1.04 -100.80 0.38
27 30-Apr-18 -37.46 0.53 -35.93 1.04 -37.51 1.00 -102.00 0.37
28 7-May-18 -37.75 0.52 -36.83 1.02 -38.31 0.99 -102.00 0.37
29 14-May-18 -38.81 0.53 -38.43 1.01 -39.61 0.98 -102.00 0.38
30 21-May-18 -39.47 0.53 -39.63 1.00 -40.81 0.97 -102.00 0.39
31 28-May-18 -42.24 0.56 -40.43 1.04 -41.41 1.02 -102.40 0.41
32 4-Jun-18 -39.32 0.52 -41.13 0.96 -42.21 0.93 -102.90 0.38
33 11-Jun-18 -43.37 0.57 -41.83 1.04 -42.91 1.01 -103.80 0.42
34 19-Jun-18 -43.81 0.57 -43.93 1.00 -45.41 0.96 -105.40 0.42
35 25-Jun-18 -44.24 0.56 -45.63 0.97 -47.61 0.93 -107.40 0.41
36 2-Jul-18 -45.77 0.57 -46.73 0.98 -48.61 0.94 0.00 #DIV/0!
37 9-Jul-18 -48.44 0.59 -47.93 1.01 -49.91 0.97 0.00 #DIV/0!
38 16-Jul-18 -47.79 0.57 -48.83 0.98 -50.91 0.94 0.00 #DIV/0!
39 23-Jul-18 -51.16 0.61 -49.93 1.02 -51.81 0.99 0.00 #DIV/0!
40 30-Jul-18 -51.95 0.61 -50.93 1.02 -52.91 0.98 0.00 #DIV/0!
41
42
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC. 13 SG 76 @ CH 7875 (LHS) SG 77 @ CH 8450 (LHS) SG 78 @ CH 8525 (LHS) SG 79 @ CH 8700 (LHS)
CH 6625 (L) SV SH SV SH SV SH SV
No. Date SH SV SV SV
(mm) (mm) (mm) (mm) (mm)

1 18-Dec-17 Installation Date Installation Date Installation Date Installation Date


2 21-Dec-17 -28.00 -0.84 33.33 -0.46 60.87 -0.93 30.11 -0.94
3 25-Dec-17 -24.04 -0.78 30.82 -0.49 49.06 -1.35 17.81 -1.03
4 28-Dec-17 -24.05 -1.54 15.62 -0.19 126.58 -1.74 13.82 -0.93
5 2-Jan-18 -23.22 -1.83 12.69 -0.45 51.60 -1.49 15.58 -1.10
6 4-Jan-18 -24.96 -2.61 9.56 -1.09 22.90 -2.15 11.61 -1.09
7 8-Jan-18 -24.60 -17.10 1.44 -8.03 3.06 -2.47 9.96 -1.37
8 11-Jan-18 -23.07 -27.90 0.83 -8.03 2.87 -13.41 1.72 -16.90
9 15-Jan-18 -23.75 -29.24 0.81 -8.61 2.76 -14.18 1.67 -17.88
10 18-Jan-18 -23.02 -29.92 0.77 -9.63 2.39 -34.69 0.66 -18.94
11 22-Jan-18 -23.66 -31.08 0.76 -10.51 2.25 -35.91 0.66 -20.19
12 25-Jan-18 -24.08 -32.08 0.75 -11.58 2.08 -37.09 0.65 -21.86
13 29-Jan-18 -24.31 -33.46 0.73 -12.50 1.94 -38.00 0.64 -22.96
14 1-Feb-18 -27.99 -35.17 0.80 -14.20 1.97 -40.01 0.70 -24.31
15 5-Feb-18 -29.01 -36.46 0.80 -15.22 1.91 -41.18 0.70 -25.65
16 12-Feb-18 -31.42 -37.60 0.84 -16.43 1.91 -42.49 0.74 -27.22
17 19-Feb-18 -31.52 -65.11 0.48 -16.43 1.92 -77.82 0.41 -27.22
18 26-Feb-18 -34.10 -66.29 0.51 -18.28 1.87 -79.53 0.43 -28.71
19 5-Mar-18 -32.21 -68.36 0.47 -19.99 1.61 -81.39 0.40 -31.42
20 12-Mar-18 -33.02 -70.26 0.47 -22.39 1.47 -82.89 0.40 -35.72
21 19-Mar-18 -32.48 -71.76 0.45 -24.19 1.34 -85.39 0.38 -43.62
22 26-Mar-18 -33.80 -73.76 0.46 -26.39 1.28 -88.39 0.38 -59.22
23 2-Apr-18 -33.76 -75.96 0.44 -29.29 1.15 -92.69 0.36 -78.22
24 9-Apr-18 -35.55 -77.66 0.46 -31.09 1.14 -96.49 0.37 -79.62
25 16-Apr-18 -36.98 -77.96 0.47 -32.99 1.12 -99.29 0.37 -80.82
26 23-Apr-18 -38.12 -79.16 0.48 -34.79 1.10 -103.39 0.37 -89.22
27 30-Apr-18 -37.46 -80.16 0.47 -36.99 1.01 -107.19 0.35 -98.92
28 7-May-18 -37.75 -81.56 0.46 -51.09 0.74 -109.79 0.34 -104.72
29 14-May-18 -38.81 -82.96 0.47 -51.09 0.76 -109.79 0.35 -104.72
30 21-May-18 -39.47 -84.06 0.47 -51.09 0.77 -109.79 0.36 -104.72
31 28-May-18 -42.24 -85.16 0.50 -52.79 0.80 -111.49 0.38 -111.72
32 4-Jun-18 -39.32 -85.76 0.46 -53.89 0.73 -113.29 0.35 -115.62
33 11-Jun-18 -43.37 -86.66 0.50 -55.89 0.78 -114.79 0.38 -119.92
34 19-Jun-18 -43.81 -88.76 0.49 -59.69 0.73 -119.49 0.37 -131.92
35 25-Jun-18 -44.24 -90.96 0.49 -62.39 0.71 -122.29 0.36 -141.82
36 2-Jul-18 -45.77 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00
37 9-Jul-18 -48.44 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00
38 16-Jul-18 -47.79 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00
39 23-Jul-18 -51.16 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00
40 30-Jul-18 -51.95 0.00 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0! 0.00
41
42
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC.
SG 79
13 @ CH 8700 (LHS) SG 80 @ CH 9100 (LHS) SG 82 @ CH 9175 (LHS)
CH 6625 (L) SH SV SH SV SH
No. Date SH SV SV SV
(mm) (mm) (mm)

1 18-Dec-17 Installation Date


2 21-Dec-17 -28.00 29.79
3 25-Dec-17 -24.04 23.34
4 28-Dec-17 -24.05 25.86
5 2-Jan-18 -23.22 21.11
6 4-Jan-18 -24.96 22.90
7 8-Jan-18 -24.60 17.96
8 11-Jan-18 -23.07 1.37
9 15-Jan-18 -23.75 1.33
10 18-Jan-18 -23.02 1.22
11 22-Jan-18 -23.66 1.17
12 25-Jan-18 -24.08 1.10
13 29-Jan-18 -24.31 1.06
14 1-Feb-18 -27.99 1.15
15 5-Feb-18 -29.01 1.13
16 12-Feb-18 -31.42 1.15
17 19-Feb-18 -31.52 1.16
18 26-Feb-18 -34.10 1.19
19 5-Mar-18 -32.21 1.03
20 12-Mar-18 -33.02 0.92
21 19-Mar-18 -32.48 0.74
22 26-Mar-18 -33.80 0.57
23 2-Apr-18 -33.76 0.43
24 9-Apr-18 -35.55 0.45
25 16-Apr-18 -36.98 0.46
26 23-Apr-18 -38.12 0.43
27 30-Apr-18 -37.46 0.38
28 7-May-18 -37.75 0.36 Installation Date Installation Date
29 14-May-18 -38.81 0.37 -0.30 129.37 -1.70 22.83
30 21-May-18 -39.47 0.38 -0.30 131.57 -5.70 6.92
31 28-May-18 -42.24 0.38 -1.30 32.49 -7.40 5.71
32 4-Jun-18 -39.32 0.34 -1.80 21.84 -8.20 4.80
33 11-Jun-18 -43.37 0.36 -2.30 18.86 -8.90 4.87
34 19-Jun-18 -43.81 0.33 -4.20 10.43 -9.80 4.47
35 25-Jun-18 -44.24 0.31 -5.00 8.85 -10.60 4.17
36 2-Jul-18 -45.77 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
37 9-Jul-18 -48.44 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
38 16-Jul-18 -47.79 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
39 23-Jul-18 -51.16 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
40 30-Jul-18 -51.95 #DIV/0! 0.00 #DIV/0! 0.00 #DIV/0!
41
42
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 78 @ CH 8525 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.9285 5.2829 0.0 0.0 0.00


2 18-Dec-17 0 4.2425 5.2829 0.0 0.0 0.31
3 21-Dec-17 3 4.2476 5.2820 -0.9 -0.9 0.32
4 25-Dec-17 7 4.2265 5.2815 -0.4 -1.4 0.30
5 28-Dec-17 10 4.2301 5.2812 -0.4 -1.7 0.30
6 2-Jan-18 15 4.2318 5.2814 0.2 -1.5 0.30
7 4-Jan-18 17 4.2274 5.2807 -0.7 -2.2 0.30
8 8-Jan-18 21 4.2427 5.2804 -0.3 -2.5 0.32
9 11-Jan-18 24 4.2012 5.2695 -10.9 -13.4 0.29
10 15-Jan-18 28 4.2268 5.2687 -0.8 -14.2 0.31
11 18-Jan-18 31 4.7487 5.2482 -20.5 -34.7 0.85

12 18-Jan-18 31 4.7487 6.2454 0.0 -34.7 0.85


13 22-Jan-18 35 4.7210 6.2442 -1.2 -35.9 0.83
14 25-Jan-18 38 4.7957 6.2430 -1.2 -37.1 0.90
15 29-Jan-18 42 4.7607 6.2421 -0.9 -38.0 0.87
16 1-Feb-18 45 4.7813 6.2401 -2.0 -40.0 0.89
17 5-Feb-18 49 4.7760 6.2389 -1.2 -41.2 0.89
18 12-Feb-18 56 4.7805 6.2376 -1.3 -42.5 0.89
19 19-Feb-18 63 5.3740 6.2023 -35.3 -77.8 1.52
20 26-Feb-18 70 5.3499 6.2006 -1.7 -79.5 1.50
21 5-Mar-18 77 5.3347 6.1987 -1.9 -81.4 1.49
22 12-Mar-18 84 5.4156 6.1972 -1.5 -82.9 1.57
23 19-Mar-18 91 5.4092 6.1947 -2.5 -85.4 1.57
24 26-Mar-18 98 5.3875 6.1917 -3.0 -88.4 1.55
25 2-Apr-18 105 5.3752 6.1874 -4.3 -92.7 1.54
26 9-Apr-18 112 5.3594 6.1836 -3.8 -96.5 1.53
27 16-Apr-18 119 5.3602 6.1808 -2.8 -99.3 1.53
28 23-Apr-18 126 5.3562 6.1767 -4.1 -103.4 1.53
29 30-Apr-18 133 5.3505 6.1729 -3.8 -107.2 1.53
30 7-May-18 140 5.3536 6.1703 -2.6 -109.8 1.53
31 14-May-18 147 - - - -109.8 1.53
32 21-May-18 154 6.2139 6.7475 0.0 -109.8 2.40
33 28-May-18 161 6.2111 6.7458 -1.7 -111.5 2.39
34 4-Jun-18 168 6.2102 6.7440 -1.8 -113.3 2.39
35 11-Jun-18 175 6.2076 6.7425 -1.5 -114.8 2.39
36 19-Jun-18 183 6.2012 6.7378 -4.7 -119.5 2.39
37 25-Jun-18 189 6.2047 6.7350 -2.8 -122.3 2.40
TORING

UNGAI BULOH KE ASSAM JAWA

5.442 m
3.92850 m
3.96058 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work


Backfilling & compaction work

Backfilling & compaction work //


Before rod extension
Extension of rod 0.9972 m

Backfilling & compaction work


Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 8525 - LHS (SG 78)

Embankment RL (m) vs Elapsed Day


10

SURCHARGE LEVEL
6

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10
0
-10
-20
-30
-40
-50
-60
-70
-80
-90
-100
-110
-120
-130
-140
-150
-110
-120
-130
-140
-150
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 78 @ CH 8525 (LHS)

Last Settlement Reading, A = 122.290 ASAOKA Plot


Intersection Settlement Reading, B = 98.817 300
Degree of consolidation, U = A/B = 124% f(x) = 1.1675510649x - 16.5622846551
Elapsed
Date Sn Sn-1 U
Days 250
21/May/18 154 109.79
28/May/18 161 111.49 109.79 -
4/Jun/18 168 113.29 111.49 140%
11/Jun/18 175 114.79 113.29 82% 200
19/Jun/18 183 119.49 114.79 111%
25/Jun/18 189 122.29 119.49 124%

Sn
150

100

50

0
0.00 50.00 100.00 150.00 200.00 250.00 300.00

Sn-1
6551

250.00 300.00

(45 degree line.)


0 0
500 500

B (Intercept)
98.817 98.817
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 79 @ CH 8700 (LHS) Surcharge Level :


Date Installed 18/Dec/17 R/L Ground Level :
Date of Base Reading 18/Dec/17 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 18-Dec-17 0 3.5083 4.8530 0.0 0.0 0.00


2 18-Dec-17 0 3.7664 4.8530 0.0 0.0 0.26
3 21-Dec-17 3 3.7646 4.8521 -0.9 -0.9 0.26
4 25-Dec-17 7 3.7704 4.8520 -0.1 -1.0 0.26
5 28-Dec-17 10 3.7703 4.8521 0.1 -0.9 0.26
6 2-Jan-18 15 3.7556 4.8519 -0.2 -1.1 0.25
7 4-Jan-18 17 3.7689 4.8519 0.0 -1.1 0.26
8 8-Jan-18 21 3.7774 4.8516 -0.3 -1.4 0.27
9 11-Jan-18 24 4.4557 4.8361 -15.5 -16.9 0.96
10 15-Jan-18 28 4.4671 4.8351 -1.0 -17.9 0.98
11 18-Jan-18 31 4.4340 4.8341 -1.0 -18.9 0.94
12 18-Jan-18 31 4.4340 5.8181 0.0 -18.9 0.94
13 22-Jan-18 35 4.4422 5.8168 -1.3 -20.2 0.95
14 25-Jan-18 38 4.3922 5.8151 -1.7 -21.9 0.91
15 29-Jan-18 42 4.3638 5.8140 -1.1 -23.0 0.88
16 1-Feb-18 45 4.3667 5.8127 -1.3 -24.3 0.88
17 5-Feb-18 49 4.3614 5.8113 -1.3 -25.6 0.88
18 12-Feb-18 56 4.3581 5.8098 -1.6 -27.2 0.88
19 19-Feb-18 63 5.0667 5.1602 0.0 -27.2 1.59
20 26-Feb-18 70 5.0614 5.1587 -1.5 -28.7 1.58
21 5-Mar-18 77 5.0417 5.1560 -2.7 -31.4 1.56
22 12-Mar-18 84 4.9575 5.1517 -4.3 -35.7 1.48
23 19-Mar-18 91 4.9567 5.1438 -7.9 -43.6 1.49
24 26-Mar-18 98 4.9364 5.1282 -15.6 -59.2 1.49
25 2-Apr-18 105 4.9201 5.1092 -19.0 -78.2 1.49
26 9-Apr-18 112 4.9137 5.1078 -1.4 -79.6 1.49
27 16-Apr-18 119 4.9093 5.1066 -1.2 -80.8 1.48
28 23-Apr-18 126 4.9027 5.0982 -8.4 -89.2 1.48
29 30-Apr-18 133 4.8835 5.0885 -9.7 -98.9 1.47
30 7-May-18 140 4.8761 5.0827 -5.8 -104.7 1.47
31 14-May-18 147 - - - -104.7 1.47
32 21-May-18 154 5.6288 5.9689 0.0 -104.7 2.23
33 28-May-18 161 5.6199 5.9619 -7.0 -111.7 2.22
34 4-Jun-18 168 5.6200 5.9580 -3.9 -115.6 2.23
35 11-Jun-18 175 5.6161 5.9537 -4.3 -119.9 2.23
36 19-Jun-18 183 5.6013 5.9417 -12.0 -131.9 2.22
37 25-Jun-18 189 5.5984 5.9318 -9.9 -141.8 2.23
TORING

UNGAI BULOH KE ASSAM JAWA

5.792 m
3.50825 m
3.53501 m

Remarks

Existing Ground Level


After filling

Backfilling & compaction work


Backfilling & compaction work

Before rod extension


Extension of rod 0.9840 m

Repaired and new baseline reading

Backfilling & compaction work


PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 8700 - LHS (SG 79)
Embankment RL(m)

Embankment RL (m) vs Elapsed Day


10

SURCHARGE LEVEL
6

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10
0
-10
-20
-30
-40
-50
-60
-70
-80
-90
-100
-110
-120
-130
-140
-150
-110
-120
-130
-140
-150
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 79 @ CH 8700 (LHS)

Last Settlement Reading, A = 141.820 ASAOKA Plot


Intersection Settlement Reading, B = 200
Degree of consolidation, U = A/B = f(x) = 1.0330409355x + 2.5516407602
180
Elapsed
Date Sn Sn-1 U
Days
160
18/Dec/17 0 -0.01
21/Dec/17 3 0.94 -0.01 -
25/Dec/17 7 1.03 0.94 140
28/Dec/17 10 0.93 1.03
2/Jan/18 15 1.10 0.93
120

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


4/Jan/18 17 1.09 1.10

Sn
8/Jan/18 21 1.37 1.09
11/Jan/18 24 16.90 1.37 100
15/Jan/18 28 17.88 16.90
18/Jan/18 31 18.92 17.88
80
22/Jan/18 35 20.19 18.92
25/Jan/18 38 21.86 20.19
29/Jan/18 42 22.96 21.86 60
1/Feb/18 45 24.31 22.96
5/Feb/18 49 25.65 24.31
40
12/Feb/18 56 27.22 25.65
26/Feb/18 70 28.71 27.22
5/Mar/18 77 31.42 28.71 20
12/Mar/18 84 35.72 31.42
19/Mar/18 91 43.62 35.72 0
26/Mar/18 98 59.22 43.62 0.00 20.00 40.00 60.00 80.00 100.00 120.00 140.00 160.00 180.00 200.00
2/Apr/18 105 78.22 59.22
9/Apr/18 112 79.62 78.22
Sn-1
16/Apr/18 119 80.82 79.62
23/Apr/18 126 89.22 80.82
30/Apr/18 133 98.92 89.22
EMBANKM
7/May/18 140 104.72 98.92
14/May/18 147 104.72 104.72
21/May/18 154 104.72 104.72
28/May/18 161 111.72 104.72
4/Jun/18 168 115.62 111.72
11/Jun/18 175 119.92 115.62
19/Jun/18 183 131.92 119.92
25/Jun/18 189 141.82 131.92
2

.00 160.00 180.00 200.00

(45 degree line.)


0 0
500 500

B (Intercept)
0.000 0.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 80 @ CH 9100 (LHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 3.5031 4.8781 0.0 0.0 0.00


2 7-May-18 0 3.9844 4.8781 0.0 0.0 0.48
3 10-May-18 3 3.9806 4.8778 -0.3 -0.3 0.48
4 14-May-18 7 - - - -0.3 0.48
5 17-May-18 10 3.6427 4.9102 0.0 -0.3 0.00
6 21-May-18 14 4.1064 4.9102 0.0 -0.3 0.60
7 24-May-18 17 4.1073 4.9098 -0.4 -0.7 0.60
8 28-May-18 21 4.1084 4.9092 -0.6 -1.3 0.61
9 31-May-18 24 4.1103 4.9092 0.0 -1.3 0.61
10 4-Jun-18 28 4.1139 4.9087 -0.5 -1.8 0.61
11 7-Jun-18 31 4.1152 4.9082 -0.5 -2.3 0.61
12 11-Jun-18 35 4.1146 4.9082 0.0 -2.3 0.61
13 13-Jun-18 37 4.1139 4.9079 -0.3 -2.6 0.61
14 19-Jun-18 43 4.1364 4.9063 -1.6 -4.2 0.64
15 25-Jun-18 49 4.1352 4.9055 -0.8 -5.0 0.64
TORING

UNGAI BULOH KE ASSAM JAWA

5.097 m
3.50314 m
3.52314 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 9100 -LHS (SG 80)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 80 @ CH 9100 (LHS)

Last Settlement Reading, A = 5.000 ASAOKA Plot


Intersection Settlement Reading, B = 100.00
Degree of consolidation, U = A/B = f(x) = 1.1903085178x + 0.1255030181
90.00
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.30 0.00 -
14/May/18 7 0.30 0.30 70.00
17/May/18 10 0.30 0.30
21/May/18 14 0.30 0.30

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 0.70 0.30

Sn
28/May/18 21 1.30 0.70
31/May/18 24 1.30 1.30 50.00
4/Jun/18 28 1.80 1.30
7/Jun/18 31 2.30 1.80
40.00
11/Jun/18 35 2.30 2.30
13/Jun/18 37 2.60 2.30
19/Jun/18 43 4.20 2.60 30.00
25/Jun/18 49 5.00 4.20
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
1

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
0.000 0.000
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 81 @ CH 9150 (RHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 3.4349 4.7408 0.0 0.0 0.00


2 7-May-18 0 3.8330 4.7408 0.0 0.0 0.40
3 10-May-18 3 3.8317 4.7406 -0.2 -0.2 0.40
4 14-May-18 7 4.3875 4.7290 -11.6 -0.2 0.95
5 17-May-18 10 4.3903 4.7269 -2.1 -2.3 0.96
6 21-May-18 14 4.3862 4.7254 -1.5 -3.8 0.96
7 24-May-18 17 4.3897 4.7244 -1.0 -4.8 0.96
8 28-May-18 21 4.3862 4.7232 -1.2 -6.0 0.96
9 31-May-18 24 4.3815 4.7227 -0.5 -6.5 0.95
10 4-Jun-18 28 4.3807 4.7225 -0.2 -6.7 0.95
11 7-Jun-18 31 4.3785 4.7221 -0.4 -7.1 0.95
12 11-Jun-18 35 4.3787 4.7218 -0.3 -7.4 0.95
13 13-Jun-18 37 4.3803 4.7216 -0.2 -7.6 0.95
14 19-Jun-18 43 4.3767 4.7205 -1.1 -8.7 0.95
15 25-Jun-18 49 4.3781 4.7196 -0.9 -9.6 0.95
TORING

UNGAI BULOH KE ASSAM JAWA

4.989 m
3.43487 m
3.44568 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 9150 -RHS (SG 81)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 81 @ CH 9150 (RHS)

Last Settlement Reading, A = 9.600 ASAOKA Plot


Intersection Settlement Reading, B = 21.571 100.00
Degree of consolidation, U = A/B = 45%
90.00
f(x) = 0.9562320268x + 0.9448443657
Elapsed
Date Sn Sn-1 U
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.20 0.00 -
14/May/18 7 0.20 0.20 70.00
17/May/18 10 2.30 0.20
21/May/18 14 3.80 2.30

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 4.80 3.80

Sn
28/May/18 21 6.00 4.80
31/May/18 24 6.50 6.00 50.00
4/Jun/18 28 6.70 6.50
7/Jun/18 31 7.10 6.70
40.00
11/Jun/18 35 7.40 7.10
13/Jun/18 37 7.60 7.40
19/Jun/18 43 8.70 7.60 30.00
25/Jun/18 49 9.60 8.70
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
7

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
21.571 21.571
ROD SETTLEMENT GAUGE MONITORING
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 82 @ CH 9175 (LHS) Surcharge Level :


Date Installed 07/May/18 R/L Ground Level :
Date of Base Reading 07/May/18 R/L Top of Base Plate :

Elapsed Embankment Top of Rod Settlement Thickness


No. Date Days RL RL Incremental Cumulative of Fill
(m) (m) (mm) (mm) (m)

1 7-May-18 0 3.3295 4.6497 0.0 0.0 0.00


2 7-May-18 0 3.7991 4.6497 0.0 0.0 0.47
3 10-May-18 3 3.7824 4.6495 -0.2 -0.2 0.45
4 14-May-18 7 3.9897 4.6480 -1.5 -1.7 0.66
5 17-May-18 10 3.9876 4.6463 -1.7 -3.4 0.66
6 21-May-18 14 3.9875 4.6440 -2.3 -5.7 0.66
7 24-May-18 17 3.9869 4.6432 -0.8 -6.5 0.66
8 28-May-18 21 3.9848 4.6423 -0.9 -7.4 0.66
9 31-May-18 24 3.9870 4.6420 -0.3 -7.7 0.67
10 4-Jun-18 28 3.9886 4.6415 -0.5 -8.2 0.67
11 7-Jun-18 31 3.9847 4.6413 -0.2 -8.4 0.66
12 11-Jun-18 35 3.9863 4.6408 -0.5 -8.9 0.67
13 13-Jun-18 37 3.9847 4.6405 -0.3 -9.2 0.66
14 19-Jun-18 43 3.9821 4.6399 -0.6 -9.8 0.66
15 25-Jun-18 49 3.9848 4.6391 -0.8 -10.6 0.67
TORING

UNGAI BULOH KE ASSAM JAWA

4.884 m
3.32949 m
3.34728 m

Remarks

Existing Ground Level


After filling
Embankment RL(m)
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA DAERAH KUALA SELANGOR, SELANGOR : CH 9175 -LHS (SG 82)

Embankment RL (m) vs Elapsed Day


10

6 SURCHARGE LEVEL

0 0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Elapsed Days
C u m m u lative S ettlem en t (m m )

Cumulative Settlement (mm) vs Elapsed Day


Chart Title
Elapsed Days
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
10

0
-5

-10
-15

-20
-25

-30

-35

-40

-45
-50
-35

-40
-45

-50
ASAOKA ANALYSIS
CLIENT : RAFULIN, AKTIF UNGGUL SDN BHD
PROJECT : PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT 54 DARI SUNGAI BULOH KE ASSAM JAWA
DAERAH KUALA SELANGOR, SELANGOR

Instruments ID. SG 82 @ CH 9175 (LHS)

Last Settlement Reading, A = 10.600 ASAOKA Plot


Intersection Settlement Reading, B = 14.604 100.00
Degree of consolidation, U = A/B = 73%
90.00
Date
Elapsed
Sn Sn-1 U
f(x) = 0.9060164865x + 1.3727791457
Days
80.00
7/May/18 0 0.00
10/May/18 3 0.20 0.00 -
14/May/18 7 1.70 0.20 70.00
17/May/18 10 3.40 1.70
21/May/18 14 5.70 3.40

EMBANKMENT FILL DID NOT REACHED SURCHARGE LEVEL.


60.00
24/May/18 17 6.50 5.70

Sn
28/May/18 21 7.40 6.50
31/May/18 24 7.70 7.40 50.00
4/Jun/18 28 8.20 7.70
7/Jun/18 31 8.40 8.20
40.00
11/Jun/18 35 8.90 8.40
13/Jun/18 37 9.20 8.90
19/Jun/18 43 9.80 9.20 30.00
25/Jun/18 49 10.60 9.80
20.00

10.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00

Sn-1
EMBANK
7

00 80.00 90.00 100.00

(45 degree line.)


0 0
500 500

B (Intercept)
14.604 14.604
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC. 12 SG 58 @ CH 6250 (RHS) SG 60 @ CH 6425 (RHS) SG 63 @ CH 6625 (RHS) SG 65 @ CH 6800 (RHS)
CH 6625 (R) SV SH SV SH SV SH SV
No. Date SH SV SV SV
(mm) (mm) (mm) (mm) (mm)

1 18-Dec-17 Installation Date Installation Date


2 21-Dec-17 -23.83 -0.51 46.73 -0.75 31.77
3 25-Dec-17 -15.84 -0.82 19.32 -1.30 12.18
4 28-Dec-17 -16.42 -0.72 22.81 -1.20 13.68
5 2-Jan-18 -15.85 -1.00 15.85 -1.07 14.81
6 4-Jan-18 -8.29 -15.84 0.52 -2.05 4.04
7 8-Jan-18 -15.53 -15.70 0.99 -1.77 8.77
8 11-Jan-18 -15.95 -16.42 0.97 -2.82 5.66
9 15-Jan-18 -15.07 -17.27 0.87 -3.55 4.25
10 18-Jan-18 -16.40 -17.65 0.93 -4.91 3.34
11 22-Jan-18 -16.75 -18.17 0.92 -6.00 2.79
12 25-Jan-18 -15.14 -18.80 0.81 -7.33 2.07
13 29-Jan-18 -15.87 -33.10 0.48 -11.36 1.40
14 1-Feb-18 -16.04 -33.13 0.48 -12.58 1.28
15 5-Feb-18 -17.53 -33.58 0.52 -13.92 1.26
16 12-Feb-18 -17.39 -34.46 0.50 -15.00 1.16
17 19-Feb-18 -17.55 -35.63 0.49 -46.38 0.38
18 26-Feb-18 -18.24 -35.63 0.51 -46.35 0.39
19 5-Mar-18 -22.27 - - -50.53 0.44
20 12-Mar-18 -21.25 -35.63 0.60 -52.33 0.41
21 19-Mar-18 -22.39 -36.83 0.61 -52.73 0.42
22 26-Mar-18 -25.03 -37.33 0.67 -54.83 0.46
23 2-Apr-18 -24.36 -38.33 0.64 -56.73 0.43
24 9-Apr-18 -24.85 -39.43 0.63 -58.03 0.43
25 16-Apr-18 -27.35 -40.43 0.68 -59.23 0.46
26 23-Apr-18 -30.93 -41.53 0.74 -60.13 0.51
27 30-Apr-18 -32.84 -42.73 0.77 -61.23 0.54
28 7-May-18 -25.66 -43.73 0.59 -62.23 0.41 Installation Date Installation Date
29 14-May-18 -30.40 -43.53 0.70 -63.43 0.48 -0.20 152.00 -0.80
30 21-May-18 -39.44 -44.23 0.89 -64.63 0.61 -1.40 28.17 -1.00
31 28-May-18 -78.19 -44.43 1.76 -65.43 1.20 -3.20 24.43 -3.90
32 4-Jun-18 -64.40 -44.93 1.43 -66.13 0.97 -3.80 16.95 -3.60
33 11-Jun-18 - -45.23 - -67.03 - -4.40 - -4.10
34 18-Jun-18 - -45.03 - -68.33 - -31.40 - -4.10
35 25-Jun-18 - -45.03 - -69.43 - -34.10 - -4.10
36 2-Jul-18 - -45.23 - 0.00 - -34.90 - -4.10
37 9-Jul-18 - -45.43 - 0.00 - -36.90 - -4.10
38 16-Jul-18 - -45.73 - 0.00 - -38.40 - -4.10
39 23-Jul-18 - -45.53 - 0.00 - 0.00 - 0.00
40 30-Jul-18 - -45.63 - 0.00 - 0.00 - 0.00
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC.
SG 65
12 @ CH 6800 (RHS) SG 66 @ CH 6850 (RHS) SG 67 @ CH 6925 (RHS) SG 67A @ CH 6975 (RHS)
CH 6625 (R) SH SV SH SV SH SV SH
No. Date SH SV SV SV SV
(mm) (mm) (mm) (mm)

1 18-Dec-17
2 21-Dec-17 -23.83
3 25-Dec-17 -15.84
4 28-Dec-17 -16.42
5 2-Jan-18 -15.85
6 4-Jan-18 -8.29
7 8-Jan-18 -15.53
8 11-Jan-18 -15.95
9 15-Jan-18 -15.07
10 18-Jan-18 -16.40
11 22-Jan-18 -16.75
12 25-Jan-18 -15.14
13 29-Jan-18 -15.87
14 1-Feb-18 -16.04
15 5-Feb-18 -17.53
16 12-Feb-18 -17.39
17 19-Feb-18 -17.55
18 26-Feb-18 -18.24
19 5-Mar-18 -22.27
20 12-Mar-18 -21.25
21 19-Mar-18 -22.39
22 26-Mar-18 -25.03
23 2-Apr-18 -24.36
24 9-Apr-18 -24.85
25 16-Apr-18 -27.35
26 23-Apr-18 -30.93
27 30-Apr-18 -32.84
28 7-May-18 -25.66
Installation Date Installation Date Installation Date Installation Date
29 14-May-18 -30.40 38.00 -0.50 60.80 -0.40 76.00 -0.20 152.00
30 21-May-18 -39.44 39.44 -0.90 43.82 -0.60 65.73 -0.60 65.73
31 28-May-18 -78.19 20.05 -0.90 86.88 -3.20 24.43 -3.50 22.34
32 4-Jun-18 -64.40 17.89 -0.90 71.56 -3.70 17.41 -3.80 16.95
33 11-Jun-18 - - -0.90 - -4.40 - -4.40 -
34 18-Jun-18 - - -0.90 - -5.80 - -6.10 -
35 25-Jun-18 - - -0.90 - -6.50 - -6.80 -
36 2-Jul-18 - - -0.90 - -7.00 - -7.10 -
37 9-Jul-18 - - 0.00 - -8.20 - -8.30 -
38 16-Jul-18 - - 0.00 - -9.20 - -9.30 -
39 23-Jul-18 - - 0.00 - 0.00 - 0.00 -
40 30-Jul-18 - - 0.00 - 0.00 - 0.00 -
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC. 12 SG 68 @ CH 7025 (RHS) SG 69 @ CH 7200 (RHS) SG 70 @ CH 7400 (RHS) SG 71 @ CH 7475 (RHS)
CH 6625 (R) SV SH SV SH SV SH SV
No. Date SH SV SV SV
(mm) (mm) (mm) (mm) (mm)

1 18-Dec-17
2 21-Dec-17 -23.83
3 25-Dec-17 -15.84
4 28-Dec-17 -16.42
5 2-Jan-18 -15.85
6 4-Jan-18 -8.29
7 8-Jan-18 -15.53
8 11-Jan-18 -15.95
9 15-Jan-18 -15.07
10 18-Jan-18 -16.40
11 22-Jan-18 -16.75
12 25-Jan-18 -15.14
13 29-Jan-18 -15.87
14 1-Feb-18 -16.04
15 5-Feb-18 -17.53
16 12-Feb-18 -17.39
17 19-Feb-18 -17.55
18 26-Feb-18 -18.24
19 5-Mar-18 -22.27
20 12-Mar-18 -21.25
21 19-Mar-18 -22.39
22 26-Mar-18 -25.03
23 2-Apr-18 -24.36
24 9-Apr-18 -24.85
25 16-Apr-18 -27.35
26 23-Apr-18 -30.93
27 30-Apr-18 -32.84
28 7-May-18 -25.66 Installation Date Installation Date Installation Date Installation Date
29 14-May-18 -30.40 -0.50 60.80 -0.50 60.80 -0.50 60.80 -0.70
30 21-May-18 -39.44 -22.50 1.75 -16.90 2.33 -9.70 4.07 -14.70
31 28-May-18 -78.19 -24.60 3.18 -18.80 4.16 -11.70 6.68 -16.30
32 4-Jun-18 -64.40 -24.40 2.64 -42.00 1.53 -29.80 2.16 -39.30
33 11-Jun-18 - -24.70 - -42.90 - -30.90 - -40.40
34 18-Jun-18 - -36.60 - -43.60 - -31.70 - -41.20
35 25-Jun-18 - -37.40 - -44.00 - -32.20 - -41.60
36 2-Jul-18 - -37.90 - -45.10 - -33.30 - -42.80
37 9-Jul-18 - -39.40 - -46.10 - -34.30 - -43.80
38 16-Jul-18 - -40.30 - 0.00 - 0.00 - 0.00
39 23-Jul-18 - 0.00 - 0.00 - 0.00 - 0.00
40 30-Jul-18 - 0.00 - 0.00 - 0.00 - 0.00
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC.
SG 71
12 @ CH 7475 (RHS) SG 72 @ CH 7600 (RHS) SG 74 @ CH 7700 (RHS) SG 75 @ CH 7800 (RHS)
CH 6625 (R) SH SV SH SV SH SV SH
No. Date SH SV SV SV SV
(mm) (mm) (mm) (mm)

1 18-Dec-17
2 21-Dec-17 -23.83
3 25-Dec-17 -15.84
4 28-Dec-17 -16.42
5 2-Jan-18 -15.85
6 4-Jan-18 -8.29
7 8-Jan-18 -15.53
8 11-Jan-18 -15.95
9 15-Jan-18 -15.07
10 18-Jan-18 -16.40
11 22-Jan-18 -16.75
12 25-Jan-18 -15.14
13 29-Jan-18 -15.87
14 1-Feb-18 -16.04
15 5-Feb-18 -17.53
16 12-Feb-18 -17.39
17 19-Feb-18 -17.55
18 26-Feb-18 -18.24
19 5-Mar-18 -22.27
20 12-Mar-18 -21.25
21 19-Mar-18 -22.39
22 26-Mar-18 -25.03
23 2-Apr-18 -24.36
24 9-Apr-18 -24.85
25 16-Apr-18 -27.35
26 23-Apr-18 -30.93
27 30-Apr-18 -32.84
28 7-May-18 -25.66
Installation Date Installation Date Installation Date Installation Date
29 14-May-18 -30.40 43.43 -0.60 50.67 -0.60 50.67 -0.80 38.00
30 21-May-18 -39.44 2.68 -1.70 23.20 -1.90 20.76 -2.10 18.78
31 28-May-18 -78.19 4.80 -3.00 26.06 -3.50 22.34 -3.70 21.13
32 4-Jun-18 -64.40 1.64 -20.70 3.11 -21.20 3.04 -22.30 2.89
33 11-Jun-18 - - -22.20 - -22.30 - -23.40 -
34 18-Jun-18 - - -23.10 - -23.10 - -24.20 -
35 25-Jun-18 - - -23.60 - -23.70 - -24.80 -
36 2-Jul-18 - - -25.10 - -25.30 - -26.60 -
37 9-Jul-18 - - -26.00 - -26.00 - -27.00 -
38 16-Jul-18 - - 0.00 - 0.00 - 0.00 -
39 23-Jul-18 - - 0.00 - 0.00 - 0.00 -
40 30-Jul-18 - - 0.00 - 0.00 - 0.00 -
PROJEK MENAIKTARAF JALAN PERSEKUTUAN FT54 DARI SUNGAI BILOH KE ASSAM JAWA, DAERAH KUALA
SELANGOR, SELANGOR SECARA REKA DAN BINA.

SUMMARY OF SH/SV VALUE MONITORING.


INC. 12 SG 81 @ CH 9150 (RHS)
CH 6625 (R) SV SH
No. Date SH SV
(mm) (mm)

1 18-Dec-17
2 21-Dec-17 -23.83
3 25-Dec-17 -15.84
4 28-Dec-17 -16.42
5 2-Jan-18 -15.85
6 4-Jan-18 -8.29
7 8-Jan-18 -15.53
8 11-Jan-18 -15.95
9 15-Jan-18 -15.07
10 18-Jan-18 -16.40
11 22-Jan-18 -16.75
12 25-Jan-18 -15.14
13 29-Jan-18 -15.87
14 1-Feb-18 -16.04
15 5-Feb-18 -17.53
16 12-Feb-18 -17.39
17 19-Feb-18 -17.55
18 26-Feb-18 -18.24
19 5-Mar-18 -22.27
20 12-Mar-18 -21.25
21 19-Mar-18 -22.39
22 26-Mar-18 -25.03
23 2-Apr-18 -24.36
24 9-Apr-18 -24.85
25 16-Apr-18 -27.35
26 23-Apr-18 -30.93
27 30-Apr-18 -32.84
28 7-May-18 -25.66 Installation Date
29 14-May-18 -30.40 -0.20 152.00
30 21-May-18 -39.44 -3.80 10.38
31 28-May-18 -78.19 -6.00 13.03
32 4-Jun-18 -64.40 -6.70 9.61
33 11-Jun-18 - -7.10 -
34 18-Jun-18 - -7.40 -
35 25-Jun-18 - -7.60 -
36 2-Jul-18 - -8.70 -
37 9-Jul-18 - -9.60 -
38 16-Jul-18 - 0.00 -
39 23-Jul-18 - 0.00 -
40 30-Jul-18 - 0.00 -
DESIGNED
CURRENT SH/SV
SURCHARGE Diff. DSG No. REMARKS
FILLING LEVEL VALUE
LEVEL
3/5/2018

Ch 6075 5.040 4.376 -0.664


Ch 6100 4.953 4.656 -0.297 SG55
Ch 6125 4.865 4.538 -0.327
Ch 6150 4.776 4.668 -0.108
Ch 6175 4.688 4.608 -0.080
Ch 6200 4.645 4.530 -0.115 SG57
Ch 6225 4.692 4.598 -0.094
Ch 6250 4.783 4.790 0.007
Ch 6275 4.875 4.754 -0.121
Ch 6300 4.967 4.936 -0.031
Ch 6325 5.032 4.987 -0.045
Ch 6350 5.045 5.097 0.052
Ch 6375 5.005 5.143 0.138
Ch 6400 4.912 4.856 -0.056 SG59
Ch 6425 4.794 4.714 -0.080
Ch 6450 4.675 4.585 -0.090
Ch 6475 4.556 4.555 -0.001
Ch 6500 4.438 4.533 0.095 SG61
Ch 6525
Ch 6550
Ch 6575 4.812 4.423 -0.389
Ch 6600 4.925 4.409 -0.516
Ch 6625 5.037 4.653 -0.384 SG62
Ch 6650 5.150 4.639 -0.511
Ch 6675 5.262 4.680 -0.582
Ch 6700 5.375 4.842 -0.533
Ch 6725 5.462 4.800 -0.662
Ch 6750 5.499 4.849 -0.650
Ch 6775 5.486 4.968 -0.518
Ch 6800 5.423 4.961 -0.462 SG64
Ch 6825 5.334 4.870 -0.464
Ch 6850 5.246 4.615 -0.631
Ch 6875
Ch 6900
Ch 6925
Ch 6950
Ch 6975
Ch 7000
Ch 7025
Ch 7050
Ch 7075
Ch 7100
Ch 7125
Ch 7150
Ch 7175
Ch 7200
Ch 7225
Ch 7250
Ch 7275
Ch 7300
Ch 7325
Ch 7350
Ch 7375
Ch 7400
Ch 7425
Ch 7450
Ch 7475
Ch 7500 4.625 4.466 -0.159
Ch 7525 4.744 4.578 -0.166
Ch 7550 4.862 4.611 -0.251
Ch 7575 4.955 4.534 -0.421
Ch 7600 4.997 4.439 -0.558 SG73
Ch 7625 4.987 4.475 -0.512
Ch 7650 4.925 4.361 -0.564
Ch 7675
Ch 7700
Ch 7725
Ch 7750
Ch 7775
Ch 7800
Ch 7825
Ch 7850 4.637 4.616 -0.021
Ch 7875 4.756 4.804 0.048 SG76
Ch 7900
Ch 7925 4.994 4.918 -0.076
Ch 7950 5.613 5.293 -0.320
Ch 7975 5.705 5.557 -0.148
Ch 8000 5.747 5.482 -0.265
Ch 8025 5.737 5.268 -0.469
Ch 8050 5.675 5.624 -0.051
Ch 8075 5.589 4.864 -0.725
Ch 8100 5.500 4.977 -0.523
Ch 8125 5.413 5.086 -0.327
Ch 8150 5.325 5.132 -0.193
Ch 8175 5.237 5.447 0.210
Ch 8200 5.195 5.520 0.325
Ch 8225 5.244 5.366 0.122
Ch 8250 5.338 5.288 -0.050
Ch 8275 5.431 5.537 0.106
Ch 8300 5.525 5.521 -0.004
Ch 8325 5.619 5.558 -0.061
Ch 8350 5.713 5.425 -0.288
Ch 8375 5.805 5.609 -0.196
Ch 8400 5.844 5.642 -0.202
Ch 8425 5.807 5.540 -0.267
Ch 8450 5.717 5.465 -0.252 SG77
Ch 8475 5.625 5.517 -0.108
Ch 8500 5.533 5.360 -0.173
Ch 8525 5.442 5.438 -0.004 SG78
Ch 8550 5.396 5.492 0.096
Ch 8575 5.442 5.472 0.030
Ch 8600 5.533 5.551 0.018
Ch 8625 5.625 5.541 -0.084
Ch 8650 5.717 5.580 -0.137
Ch 8675 5.781 5.349 -0.432
Ch 8700 5.792 4.922 -0.870 SG79
Ch 8725 5.748 5.200 -0.548
Ch 8750 5.650 5.819 0.169
Ch 8775 5.525 5.841 0.316
Ch 8800 5.400 5.704 0.304
Ch 8825 5.275 5.469 0.194
Ch 8850
Ch 8875
Ch 8900
Ch 8925
Ch 8950
Ch 8975
Ch 9000
CURRENT
Diff. DSG No. REMARKS
FILLING LEVEL
3/5/2018

4.596 -0.096
4.676 -0.107 SG58
4.880 0.005
4.885 -0.082
4.843 -0.189
4.879 -0.166
4.686 -0.319

4.531 -0.263 SG60


4.400 -0.275
4.443 -0.113
4.479 0.041
TECHNICAL SUBMISSION NO. : AU/SITE/FT54-090/TS

COMMENTS:

1. Inclinometer No. 14 @ Ch 8+000 (LHS) and Inclinometer No. 15 @ Ch 8+700 were damaged
and considered failed.

2. SG 58 : Please check the 'Thickness of Fill' in the table from 26/02/18 till 28/05/18…

3. SG 62 : Please check the 'Thickness of Fill' in the table from 12/03/18 till 28/05/18…

4. SG 64 : Please check the 'Thickness of Fill' in the table from 12/03/18 till 28/05/18 and
'Embankment RL' reading on 28/05/18 drop 300mm from previous reading… Why?

5. The contractor may proceed with the installation of Surface Settlement Markers at SG55,
SG57, SG61, SG76, SG77 & SG78…

6. Refer attachements for Designer's Observation.