Académique Documents
Professionnel Documents
Culture Documents
net/publication/245408157
CITATIONS READS
3 827
2 authors:
Some of the authors of this publication are also working on these related projects:
Forecast model for the evaluation of tunnel inflows in crystalline rocks of the high plateau of Eastern Antioquia (Colombia) View project
Performance of Urban Cofferdams Braces with Segmental Steel and Reinforced Concrete Ring Beams View project
All content following this page was uploaded by Lindsey Sebastian Bryson on 12 July 2016.
Paper GE-D-08-00045
Received 12/08/2008
Accepted 21/10/2009
L. Sebastian Bryson David G. Zapata-Medina
Keywords: diaphragm walls/ Assistant Professor, Former Research Assistant,
excavation/retaining walls Department of Civil Department of Civil
Engineering, University of Engineering, University of
Kentucky, Lexington, USA Kentucky, Lexington, USA
A common practice in the USA for excavation support evaluating the wall installation process and the related ground
system design is to assume that the complete support movements, a three-dimensional (3D) finite-element model is
system is ‘wished in place’. This implies that the required for a realistic analysis. The finite-element software
construction of the in situ wall component and the Plaxis 3DFoundation version 2.0 beta was used to model the
installation of the supports do not cause any movements installation sequences. The Chicago and State excavation was
or changes in the in situ stress state. However, the used as a reference case. This excavation is well documented
installation can cause appreciable changes in the in situ (Bryson, 2002; Finno and Bryson, 2002; Finno et al., 2002),
soil stress conditions, which result in significant and is one of the few cases in the literature that include a
movements in the surrounding ground. This paper sizable amount of detail regarding the wall installation
presents the results of efforts to evaluate the factors activities and possible influences of adjacent and underground
that influence movements associated with excavation structures. Although several researchers (Gourvenec and
support wall installation, using a series of three- Powrie, 1999; Ng and Yan, 1999; Schafer and Triantafyllidis,
dimensional finite-element models. These analyses 2004, 2006) have presented 3D numerical models of wall
demonstrated that soil responses and the processes that installation effects, those efforts concerned only diaphragm
produce them are three-dimensional in nature. Thus it walls. The research presented in this paper adds the case of a
can be concluded that fully three-dimensional analyses 3D numerical analyses of a secant pile wall.
are required to provide insight into these complex
relationships. 2. CHICAGO AND STATE EXCAVATION SUPPORT
WALL INSTALLATION
1. INTRODUCTION Details of the Chicago and State excavation and support system
Construction projects involving deep excavations are prevalent performance have been presented by Finno and his co-workers
in many urban areas around the world. Stiff excavation (Finno and Bryson, 2002; Finno et al., 2002). However, specific
support systems, which typically involve the construction of in information about the case is presented in this paper to provide
situ retaining walls such as secant and contiguous pile walls a frame of reference for the modelling assumptions and
and diaphragm walls, are widely used to minimise lateral and simulation choices used for this research.
vertical ground movements. A common practice for excavation
support system design in the USA is to assume that the 2.1. Description of the site
complete support system is ‘wished in place’ (WIP). This implies The Chicago Avenue and State Street subway renovation
that the construction of the in situ wall component and the project in Chicago, IL, included a 13 m excavation in soft to
installation of the supports do not cause any movements or medium clay to expose the existing subway station and
changes in the in situ stress state. However, the installation tunnels. The crown of the tunnels was located approximately
process can cause appreciable changes in the in situ soil stress 5.8 m below ground surface. Field instrumentation was
conditions, which result in significant movements in the installed prior to constructing the support wall to monitor the
surrounding ground (Gourvenec and Powrie, 1999; Ng, 1992; performance of the excavation support system and the
Ng and Yan, 1999). Finno et al. (2002) observed this to be the excavation-induced response of the adjacent Frances Xavier
case during the excavation for the Chicago Avenue and State Warde School. The structural response of the Warde School
Street subway renovation project in Chicago, Illinois. The was of particular interest because of its close proximity to the
lateral deformations recorded during wall installation were excavation. The basement wall of the school was located
approximately 25% of the total displacement measured during approximately 2.1 m from the centreline of the support wall
the excavation. Thus the assumption of a WIP system would (i.e. a clear distance between the support wall and the wall of
have led to a significant underestimation of excavation-related the school is 1.65 m). See Bryson (2002) for a complete
lateral movements for this case. description of the adjacent structures.
This paper presents the results of efforts to evaluate the factors Figure 1 shows a plan view of the Chicago and State
that influence movements associated with excavation support excavation support wall in reference to the field
wall installation. Because of the complexity associated with instrumentation locations, the tunnel, and the Warde School.
Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina 209
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
These potentially significant
Chicago Avenue effects were evaluated by
N modelling the construction of
5 the tunnel and the school,
0 5
and including those
Scale: m
modelling phases in the
overall model of the wall
State Street
Frances Xavier installation. Realistic models
4 1 Warde School
of the tunnel and school
constructions were possible
because of the comprehensive
nature of the case data
Secant pile wall presented by Bryson (2002)
and the historic data recorded
Inclinometer for the original construction
location 2
Subway
of the Chicago and State
Piezometer
location tunnel subway station and tunnel
(Terzaghi, 1943).
210 Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
Elevation:
m CCD Su: kPa Moisture content: %
Secant pile 0 50 100 150 0 10 20 30 40 50
5 wall
and fill
Sand
Fill
0
clay
Stiff
Soft clay
Blodgett
⫺5 Med.
clay
Deerfield
Medium
clay
⫺10
Park Ridge
Stiff clay
⫺15
Tinley
Hard
clay
0·0048 m
tf
Supporting
plate
de
Depth, d x
Steel ribs
1·0 m
tw
bf 0·61 m
(a) (b)
node. Both floor and wall elements allow for plate deflections 3.2. Modelling the school
due to shearing as well as bending. In addition, the plate The Warde School is a three-storey concrete frame building
elements can change length when an axial force is applied. For supported on shallow foundations. The floor slabs are
further reference see Brinkgreve and Broere (2004). An elastic supported by columns at interior locations and masonry
modulus of concrete Ec ¼ 21 3 106 kPa was assumed for both bearing walls around the perimeter. The interior columns rest
wall and floor elements of the permanent liner. on reinforced concrete spread footings, which are 0.76 m thick
Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina 211
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
0·6 m 80
0·6 m Columns footing
loads (typ)
136 106 117
1·3 m
0·75 m
108 116
80
71 72 62
0·8 m
80
90
Figure 4. Permanent support liner
Footing loads
in kPa
106
and vary in size from 3 m 3 3 m to 4.5 m 3 4.5 m. The 74
bearing walls rest on a 2.75 m tall reinforced concrete
80
basement wall, which is supported by a continuous footing N
0.2 m thick and 1.2 m wide. The average depth of the 110 91
foundations was found to be at 3.7 m below ground surface 73 Scale: m
(i.e. +0.6 m CCD). Figure 5 shows a plan view of the school’s Strip footing
loads (typ) 0 5
foundation, and indicates the input footing loads used in the
finite-element model simulation. 80
Floor and wall elements were used to model the footings and Figure 5. Frances Xavier Warde School foundation plan and
reinforced concrete basement wall respectively. In addition, a applied loads
floor slab resting on the ground at an elevation of +1.5 m CCD
was included in the analysis to model the final basement floor
and avoid basal heave of the soil. An elastic modulus of calculation time and modelling effort, a simplified geometry of
concrete Ec ¼ 25 3 106 kPa was assumed for all the elements rectangular slots was used to model the secant pile wall.
of the school. Table 1 presents the floor and wall material
parameters assigned to the structural elements of the tunnel The construction of a single segment of the wall was simulated
and school. In the table, d is element thickness; ª is bulk unit in the finite-element model using two construction-stage
weight; E1 and E2 are Young’s modulus in the major and calculations. In the first calculation stage the soil within the
minor principal directions respectively; and is Poisson’s ratio. slot was removed, and a load per unit area was applied to the
exposed faces. These loads modelled the hydrostatic pressure of
3.3. Modelling the wall construction the support fluid (i.e. water or bentonite) acting on the faces of
The secant pile wall was constructed with overlapping drilled the excavated slot. This pressure ensured the stability of the
shafts 915 mm in diameter and 18.3 m long, filled with 7 MPa excavated hole. In addition, some models were completed
strength concrete. Each shaft overlapped adjacent shafts by without applying hydrostatic loads, in order to model an
150 mm. W24 3 55 steel sections were placed in alternating unsupported hole. This was the case during the wall
shafts to provide additional stiffness to the wall (Finno et al., construction at the Chicago and State excavation. In the
2002). Figure 6 shows the construction sequence of the secant second calculation stage the applied loads were deactivated,
pile wall. Due to the high number of elements required to and the slot clusters were filled with a linear elastic grout
model circular shafts, and the consequent increase in material.
d: mm ª: kN/m3 E1 ¼ E2 : kN/m2
Table 1. Floor and wall material parameters for school and tunnel
212 Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
Model parameters Input values
Secondary shafts
(complete within 48 h
of primary shafts) Type Non-porous
ª: kN/m3 24
k x ¼ k y ¼ k z : m/day 0
Eg : kN/m2 8.9 3 106
0.2
Rinterf 1
1·524 m
Table 2. Linear-elastic material parameters for secant pile wall
6·15 m
modulus of the grout, Eg , is a composite value that includes
0·75 m the contribution of the steel sections.
The input HSM values used for this research are given in Table
The input parameters used for modelling the wall material are 3. These values were determined from extensive triaxial
presented in Table 2. These parameters are the unit weight of laboratory testing of samples taken from Chicago soils
the grout material ª, the hydraulic conductivity k (the (Roboski, 2001). The friction angle , cohesion c and dilatancy
subscripts denote direction), and the interface strength Rinterf . angle ł are estimated assuming Mohr–Coulomb failure
Note that Rinterf ¼ 1.0 for a rigid interface (i.e. the interface has criteria. The secant stiffness at 50% stress level in a standard
the same strength as the associated soil layer) and Rinterf , 1.0 drained triaxial test, E ref50 , the tangent stiffness for primary
for a flexible interface (i.e. the interface has a strength less oedometer loading, E ref oed , and the unloading–reloading
than that of the associated soil layer). The elastic stiffness stiffness, E ref
ur , are stiffness parameters corresponding to a
Hardening soil model Upper Lower Deerfield Park Ridge Hard clay
parameters Blodgett Blodgett
Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina 213
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
reference stress (pref ¼ 100 kPa), and are used to write stress- obtained using inverse modelling techniques at a different
dependent hyperbolic relationships for E50 , Eoed and Eur . The excavation site in the Chicago area with the same lithology
amount of stress dependence is given by the power m. These (Blackburn, 2005). Unfortunately, because the sand fill and clay
relations are given as crust data were obtained using inverse analyses at a different
site, direct comparison of the parameters is not strictly valid.
However, the Mohr–Coulomb and HSM input parameters, as
c cos 93 sin m
1 E i ¼ E ref complete sets, will tend to adequately reflect the behaviour of
i
c cos þ p ref sin
the sand fill and clay crust layers.
where Ei ¼ E50 , Eoed and Eur , and 93 is the confining stress in 4. CALCULATION PHASES
the triaxial test. The Poisson’s ratio for unloading—reloading, The calculation phases used for the simulation of the tunnel,
ur , is usually set between 0.15 and 0.3. For this study a value Warde School, and wall construction are given in Table 5. The
of ur ¼ 0.2 was typically used. The parameter K NC 0 was
initial phase calculates the initial stress field by means of the
0 ¼ 1 sin )
estimated using Jaky’s empirical relationship (K NC simplified K0 procedure. This procedure generates initial
and the peak friction angle. The failure ratio Rf is given as qf / stresses on the basis of soil weight and K0 input. Deformations
qa , where qf is the ultimate deviatoric stress and qa is the calculated in this phase are not considered to be relevant, and
asymptotic value of the shear strength. are reset to zero at the beginning of the next calculation phase.
The plastic calculations refer to the elastic-plastic small
The sand fill and the clay crust layers were modelled using the deformation analyses associated with staged construction
classical Mohr–Coulomb soil model. Table 4 lists the model loading conditions. These calculations are considered
parameters, along with other input data required for the finite- appropriate for these stages because the timescale of
element model. These data were obtained from laboratory data construction does not allow much dissipation of excess pore
and inverse modelling, and were developed in support of the pressures in these strata. The consolidation phase is a coupled
plane-strain modelling efforts of the Chicago and State analysis, which controls the development and dissipation of
excavation (Calvello, 2002). The inverse modelling here refers excess pore pressures as a function of time.
to an iterative process by which a back-analysis is performed
using observed data to update the input parameters to the 4.1. Tunnel construction
finite-element code. The iterations are continued until the input As presented in Table 5, phase 2 models the installation of the
parameters produce a satisfactory match to the observed permanent concrete liner. Phase 3 represents a plastic nil-step
behaviour. To account for the increase in stiffness with depth, stage where no additional loads or elements are included. It is
the increase in Young’s modulus per unit depth, Einc , is used. used to eliminate possible out-of-balance forces that may have
The stiffness is set to the value of the reference modulus, Eref , been generated during the previous phases. In phase 4, the
at the reference depth yref . Table 4 also lists HSM input values water table at the tunnel location is lowered to the bottom
for the sand fill and clay crust layers (the latter referred to as tunnel elevation. The original design (Terzaghi, 1943) shows
the upper ‘stiff clay layer’ in Figure 2). These values were the void behind the liner plates filled with pea gravel. Thus it is
Table 4. Constitutive model parameters for sand fill and clay crust (data from Calvello, 2002 and
Blackburn, 2005)
214 Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
Element Phase Identification Calculation Load input
presumed that the tunnel tubes act as drains. Finally, phase 5 total of 34 calculation phases were necessary to model the
simulates the consolidation of the clay layers between the end installation of the secant pile wall. In phase 12 the
of tunnel construction (late 1930s) and the construction of the displacements were reset to zero during a plastic nil-step stage.
school (late 1950s). An ultimate time load input condition of Phases 13 to 27 model the construction of the east portion of
19 years (6940 days) was specified to terminate the the wall along State Street. In phases 27 to 41 the west section
consolidation calculation. of the secant pile wall along State Street is installed. Phases 41
to 45 model the construction of the north wall along the
4.2. School construction Chicago Avenue. No consolidation phases were included in the
Table 5 shows that six phases were used to simulate the wall construction stage. The complete 3D input model for the
construction of the Francis Xavier Warde School. In phase 6 Chicago and State wall installation model is shown in Figure 7.
the displacements are reset to zero during a plastic nil-step
stage. Phase 7 models the stepped excavation for the school 5. PERFORMANCE OF MODELS
basement and its footings. In phase 8 the structural elements of
the school (basement wall, floor and footings) are placed, and 5.1. Effects of adjacent structures and soil model
the soil around the school is backfilled. In phase 9 the footing Analyses were performed to investigate the effects of modelling
loads, which represent the weight of the school, are activated. adjacent structures and the effects of the employed soil
Phase 10 is a plastic nil-step stage, and as with other nil steps constitutive model on the lateral deformations due to wall
is required after a calculation phase in which large loadings are installation. The results of these analyses are shown in Figure
activated. Lastly, phase 11 simulates the consolidation of the 8. For such purposes, three models were used
clay layers between the end of the school construction and the
beginning of the wall installation. An ultimate time load input (a) a model that simulates the wall installation for free field
condition of 40 years (14 610 days) was specified to terminate conditions (i.e. tunnel and school not modelled)
the consolidation calculation. (b) a complete model including the tunnel, school and wall
installation sequence, using the Mohr–Coulomb soil
4.3. Wall construction constitutive model for the sand fill and clay crust layers
The modelling procedure for the wall construction consisted (c) a complete model using the hardening soil model (HSM)
principally of two calculation stages. for all of the layers.
(a) Four alternating slots were excavated to a depth of 18.3 m Figure 8 shows the lateral deformations for the three
below ground surface (14 m CCD). The slots were kept aforementioned models and compares those results with the
unsupported during the calculation stage in order to measured deformations. The deformations are given at the
resemble closely the actual installation procedure at the locations of inclinometers 1 and 4. Inclinometer 1 was located
Chicago and State Street excavation (Finno et al., 2002). between the Warde School and the excavation support wall,
(b) The stage 1 slots were filled with an elastic grout material and therefore represents constrained conditions, whereas
that had the composite material properties described inclinometer 4 represents free-field conditions.
earlier, and the next four alternating slots were excavated.
The figure shows that including the adjacent structures (i.e.
The calculation phases were advanced in four-slot intervals, tunnel and school) in the wall installation model increases the
because that was the approximate number of piles completed amount of lateral deformation predicted. This behaviour
in 1 day for the Chicago and State wall construction (Bryson, highlights the dependence of soil response on the initial stress
2002). Following the aforementioned modelling procedure, a conditions at the time of wall construction, and shows the
Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina 215
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
Secant pile wall Francis Xavier
Chicago and State Street Warde School
subway tunnel station
N
Sand fill
Clay crust
Upper Blodgett
Lower Blodgett
Deerfield
Park Ridge
Hard clay
Figure 7. Complete input for the Chicago and State wall installation model
effects of constructing the tunnel and the school on the overall deformations associated with the critical relative stress values
ground movements. In investigations of relative shear stresses at the end of tunnel construction, but also did not include the
(i.e. the ratio between the current shear stress and shear stress added stiffness in the soil mass due to the presence of the
at failure for the current value of mean normal stress), it was school.
observed that models that included the tunnel construction
produced relative shear stresses near failure in the soil adjacent 5.2. Effects of stress relief
to the tunnel. This was due to the stress relief associated with Although no time effects were included in the wall
the excavation. It was observed that the most critical values of construction stage, the influence of stress relief was a concern.
relative shear occurred at a distance from the tunnel equal to The amount of unloading or stress relief of the ground may be
approximately 15% of the tunnel base width (0.15B). This related to the number of rectangular slots (i.e. augered holes)
places the most critical value of relative shear at the open at any one time. From a numerical standpoint, the ability
approximate locations of the east and west secant pile walls. to increase the number of shafts per calculation phase
Thus, when the tunnel construction is included in the wall decreases the number of phases required to install the wall, and
installation model, the soil appears to exhibit localised post- consequently reduces the computational time required for the
yield behaviour, characterised by larger deformations. wall installation stage. The concern was that increasing the
Including the school will further modify the behaviour of the number of shafts per phase would also increase the magnitude
soil. Son and Cording (2005) concluded that excavation-related of stress relief associated with wall construction. This increase
ground movements will be less near an adjacent structure than in stress relief could possibly lead to a corresponding increase
are observed for free-field conditions. This is because the soil– in lateral deformations. In order to investigate the effects of
structure interactions will produce a stiffening effect in the soil construction rate on the lateral deformations, three different
mass. Hence the predicted responses and the measured response cases were modelled: (a) four slots per phase; (b) half wall per
shown in Figure 8 are greater at the inclinometer 4 location (i.e phase; and (c) whole wall per phase. These models did not
free-field conditions) than at the inclinometer 1 location, where include construction of the tunnel or the school, and used a
the soil mass is constrained. Mohr–Coulomb failure criterion to model the sand and clay
crust layers (see the ‘just excavation’ model shown in Figure 8).
All of the models underpredicted the lateral deformations in
the clay layers for the constrained conditions, and Figure 9 shows the lateral deformations for the three
overpredicted the maximum lateral deformations for the free- aforementioned cases, and compares those results with the
field conditions. However, using the HSM for all layers and measured deformations. At the inclinometer 1 location, the
including the tunnel and school construction yielded the better half-wall-per-phase model overestimates the maximum lateral
performance for free-field conditions. The lateral deformations deformation by approximately 220%, and the whole-wall-per-
in the Blodgett stratum were underpredicted by approximately phase model overestimates the maximum lateral deformation
9% only, and the model response in the Park Ridge stratum by approximately 290%! At the inclinometer 4 location, the
virtually matched the measured response. For the constrained half- and whole-wall-per-phase models overestimate the lateral
condition, using the Mohr–Coulomb model for the sand and deformations by 59% and 100% respectively. The four-slots-
clay crust layers and not including the tunnel and school per-phase model agreed well with the measured inclinometer 1
produced the better performance. This was most likely due to data, most probably because it closely modelled the actual
the net sum of factors influencing lateral movements. The ‘just construction sequence and rate. However, at inclinometer 4, the
wall installation’ model did not include the greater lateral deformations given by the four-slots-per-phase model
216 Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
Lateral deformation: mm Lateral deformation: mm
0 5 10 15 20 0 5 10 15 20 25 30 35
0 0
5 5
10 10
15 15
Depth: m
Depth: m
N 5
N 5
20 20
Frances Xavier
Frances Xavier
Warde School
Warde School
4 1 4 1
25 25
30 30
2
2
35 35
(a) (a)
5 5
10 10
15 15
Depth: m
Depth: m
20 20
35 35
(b)
(b)
Figure 8. Effects of adjacent structures and constitutive soil Figure 9. Effects of stress relief: (a) inclinometer 1;
model: (a) inclinometer 1; (b) inclinometer 2 (b) inclinometer 2
underestimate the measured deformations by approximately that the west wall was constructed at a faster rate than the east
47%. This is attributable to the fact that neither the tunnel nor wall. Thus, in effect, more than four slots were opened at one
the school was modelled in this case, and thus the influences of time. If it is assumed that the west wall was constructed at a
these activities on the deformations are not included. rate of about 1.9 times faster than the east wall, and the
Furthermore, the construction records (Bryson, 2002) indicate predicted values for the four-slots-per-phase model are
Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina 217
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
multiplied by this number, the predicted values match the Lateral deformation: mm
measured response relatively well. ⫺20 ⫺10 0 10 20 30 40
0
5.3. Effects of construction techniques
The secant pile wall was constructed by first auguring down to
the clay crust and installing temporary steel casing to provide 5
support for the sand fill during construction. Then the
remainder of each shaft was drilled uncased and unsupported.
Grout was typically placed within 2 h of completing the hole, 10
but occasionally longer intervals resulted from delays in grout
delivery. Of interest was the influence of excavation techniques
employed in the construction of the support walls. Three
15
different construction techniques were investigated:
Depth: m
(a) excavation under bentonite slurry head
20
(b) excavation under hydrostatic pressure N 5
(c) unsupported excavation.
Frances Xavier
Warde School
Unit weights of 12 kN/m3 and 9.8 kN/m3 were assumed for the 25 4 1
bentonite and water respectively. For these simulations, the
secant pile wall was modelled as a series of trenches
approximately 0.9 m wide, 18.3 m deep and 6.2 m long. The 30
length of the trench was intended to approximate the 2
simultaneous opening of four slots.
35
Lateral deformations at the end of wall installation are shown (a)
in Figure 10. Where lateral pressures were used (e.g. excavation
under slurry head and hydrostatic pressure), negative values Lateral deformation: mm
⫺20 ⫺10 0 10 20 30 40
between approximately 0 m and 8 m of depth were observed.
0
This response is most likely due to the use of an average
pressure to represent the hydrostatic pressure, as opposed to
using a pressure that varies with depth. Regardless, the
5
simulations allow for a qualitative evaluation for the influence
of various construction techniques.
used for many of the shafts on the west side. Other matches are
not possible, because holding times were not included in the
simulations. This may be of interest for future investigations, 20
because Poh and Wong (1998) presented data showing that
Measured
lateral displacements tend to increase as a function of (Chicago and State)
increasing holding time. Of final note, the figure does show 25
that the heavier fluid causes the depth at which the maximum Excavation under
slurry head
lateral deformation occurs to shift downwards. This implies
that a different stress history will be imparted in the stratum, Excavation under
30 hydrostatic pressure
depending on the construction technique used.
Unsupported excavation
6. CONCLUSIONS
35
This paper presents the procedures used and the results of (b)
efforts to develop a three-dimensional model of a well-
documented, secant pile wall installation case history. From the Figure 10. Effects of construction techniques: (a) inclinometer
information presented, the following conclusions can be drawn. 1; (b) inclinometer 2
(a) Including the Chicago and State subway tunnel and Warde
School constructions in the wall installation models
highlights the dependence of the initial stress conditions at (b) The stress relief associated with the tunnel construction
the time of wall construction on soil response. The analyses produced relative shear stresses near failure in the soil
showed that including the adjacent structures increases the adjacent to the tunnel. The most critical values of relative
amount of lateral deformations predicted. shear occurred at a distance from the tunnel equal to
218 Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
approximately 15% of the tunnel base width excavation, Calvello M (2002) Inverse Analysis of a Supported Excavation
which is the approximate location of the east and west through Chicago Glacial Clays. PhD thesis, Northwestern
secant pile walls. Thus, when the tunnel construction is University, Evanston, IL.
included in the wall installation model, the soil appears to Chung CK and Finno RJ (1992) Influence of depositional
exhibit localised post-yield behaviour, characterised by processes on the geotechnical parameters of Chicago glacial
larger deformations. clays. Engineering Geology 32(4): 225–242.
(c) The presence of the Warde School along the east side most Finno RJ and Bryson LS (2002) Response of building adjacent
likely caused smaller deformations than predicted because to stiff excavation support system in soft clay. Journal of
the soil–structure interactions produced a stiffening effect Performance of Constructed Facilities, ASCE 16(1): 10–20.
in the soil mass along that side. However, the various Finno RJ, Bryson LS and Calvello M (2002) Performance of a
models were unable to adequately match the observed stiff support system in soft clay. Journal of Geotechnical and
behaviour. Better matches may possibly be achieved by Geoenvironmental Engineering, ASCE 128(8): 660–671.
using a soil constitutive model that captures soil stiffness Gourvenec SM and Powrie W (1999) Three-dimensional finite-
behaviour at the relatively low strain levels. element analysis of diaphragm wall installation.
(d ) The stress history in the soil mass at the beginning of the Géotechnique 49(6): 801–823.
excavation will depend on the construction technique used Ng CWW (1992) An Evaluation of Soil–structure interaction
to install the wall. Thus including the construction Associated with a Multi-propped Excavation. PhD thesis,
technique actually used or anticipated will result in more University of Bristol, UK.
realistic predictions. Ng CWW and Yan RWM (1999) Three-dimensional modelling
of a diaphragm wall construction sequence. Géotechnique
There may be a tendency to conclude that the accuracy of the 49(6): 825–834.
results does not justify the added complexity of the three- Poh TY and Wong IH (1998) Effects of construction of
dimensional model. It is conceded that for standard design diaphragm wall panels on adjacent ground: field trial.
purposes, without the benefit of advanced laboratory data Journal of Geotechnical and Geoenvironmental Engineering,
required as input for advanced constitutive models, plane- ASCE 124(8): 749–756.
strain analysis will most likely suffice. However, the modelling Roboski JF (2001) Soil Parameters for Constitutive Models of
efforts performed for these evaluations clearly demonstrated Compressible Chicago Glacial Clays. Masters thesis,
that soil responses and the processes that produced them are Northwestern University, Evanston, IL.
three-dimensional in nature. Thus fully three-dimensional Schafer R and Triantafyllidis T (2004) Modelling of earth and
analyses are required to provide insight into these complex water pressure development during diaphragm wall
relationships. Well-documented case histories such as this construction in soft clay. International Journal of Numerical
enable better predictions to be achieved as constitutive models and Analytical Methods in Geomechanics 28(13): 1305–
are developed and improved. 1326.
Schafer R and Triantafyllidis T (2006) The influence of the
ACKNOWLEDGEMENTS construction process on the deformation behaviour of
The material presented in this paper is based upon work diaphragm walls in soft clayey ground. International Journal
supported by the National Science Foundation under grant No. of Numerical and Analytical Methods in Geomechanics
CMS 06-50911 under programme director Dr R. Fragaszy. 30(7): 563–576.
Without this support, this work could not have been done. Schanz T, Vermeer PA and Bonnier PG (1999) The hardening
soil model: formulation and verification. Proceedings of the
REFERENCES Plaxis Symposium ‘Beyond 2000 in Computational
Blackburn JT (2005) Automated Sensing and Three-dimensional Geotechnics: 10 Years of PLAXIS’. Balkema, Rotterdam, pp.
Analysis of Internally Braced Excavations. PhD thesis, 281–296.
Northwestern University, Evanston, IL. Son M and Cording EJ (2005) Estimation of building damage
Brinkgreve RBJ and Broere W (2004) Finite Element Code for due to excavation-induced ground movements. Journal of
Soil and Rock Analysis, Plaxis 3DFoundation, Version 1.6 Geotechnical and Geoenvironmental Engineering, ASCE
Manual. Balkema, Rotterdam. 131(2): 162–177.
Bryson LS (2002) Performance of a Stiff Excavation Support Terzaghi K (1943) Liner-plate tunnels on the Chicago, IL
System in Soft Clay and the Response of an Adjacent subway. Transactions of the American Society of Civil
Building. PhD thesis, Northwestern University, Evanston, IL. Engineers 108: 970–1007.
Geotechnical Engineering 163 Issue GE4 Finite-element analysis of secant pile wall installation Bryson • Zapata-Medina 219
Delivered by ICEVirtualLibrary.com to:
IP: 128.163.155.166
On: Sun, 21 Aug 2011 01:55:38
View publication stats