CRONOGRAMA VALORIZADO DE OBRA

PROYECTO :REHABILITACION Y MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DE LAS CALLES PERTENECIENTES A LA SUBZONA 5A


DISTRITO :MIRAFLORES-LIMA-LIMA

PRECIO PARCIAL MES 01 MES 02 MES 03 TOTAL


ITEM DESCRIPCION UNID METRADO UNITARIO S/ 15 30 15 30 15 30
01 OBRAS PROVISIONALES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS (SUBCONTRATO) est 1.00 12,000.00 12,000.00 6,000.00 6,000.00 12,000.00
01.02 ALMACEN, OFICINA,CASETA DE GUARDIANIA,Y SSHH m2 60.00 87.13 5,227.80 5,227.80 5,227.80
01.03 CARTEL DE OBRA und 2.00 1,429.79 2,859.58 2,859.58 2,859.58
01.04 MANTENIMIENTO DE TRANSITO - PLAN DE DESVIO glb 1.00 15,695.37 15,695.37 3,139.07 3,139.07 3,139.07 3,139.07 3,139.07 - 15,695.37
02 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO m2 9,158.99 4.81 44,054.74 22,027.37 22,027.37 44,054.74
02.02 DEMOLICION DE VEREDAS E=10 cm CON EQUIPO m2 5,777.41 14.52 83,887.99 20,972.00 20,972.00 20,972.00 20,972.00 83,887.99
02.03 DEMOLICION DE SARDINEL DE CONCRETO CON EQUIPO m 2,525.07 11.54 29,139.31 7,284.83 7,284.83 7,284.83 7,284.83 29,139.31
02.04 DEMOLICION DE PAVIMENTO ASFALTICO E=2" m2 3,199.04 9.41 30,102.97 7,525.74 7,525.74 7,525.74 7,525.74 30,102.97
02.05 DEMOLICION DE PAVIMENTO DE CONCRETO E=0.15 M m2 2,891.13 32.28 93,325.68 23,331.42 23,331.42 23,331.42 23,331.42 93,325.68
02.06 FRESADO DE PAVIMENTO DE ASFALTO e=2" m2 990.35 8.64 8,556.62 - - - 8,556.62 8,556.62
02.07 ELIMINACION MASIVA MATERIAL DE CORTE PROVENIENTE DE LA DEMOLCION m3 1,653.58 32.96 54,502.00 13,625.50 13,625.50 13,625.50 13,625.50 54,502.00
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO CON EQUIPO m3 515.68 9.32 4,806.14 1,201.54 1,201.54 1,201.54 1,201.54 4,806.14
03.02 EXCAVACION MANUAL EN TERRENO NORMAL m3 683.21 39.44 26,945.80 6,736.45 6,736.45 6,736.45 6,736.45 26,945.80
03.03 ELIMINACION DE MATERIAL EXCEDENTE DM=20 km m3 1,439.07 28.89 41,574.73 10,393.68 10,393.68 10,393.68 10,393.68 41,574.73
03.04 NIVELACION RIEGO Y COMPACTACION DE LA SUB-RASANTE m2 2,932.35 4.90 14,368.52 3,592.13 3,592.13 3,592.13 3,592.13 14,368.52
03.05 NIVELACION RIEGO Y COMPACTACION PARA RECIBIR BASE DE AFIRMADO PARA VERE m2 5,784.57 3.61 20,882.30 6,960.77 6,960.77 6,960.77 20,882.30
03.06 BASE GRANULAR E=0.20 m m2 2,552.62 19.16 48,908.20 16,302.73 16,302.73 16,302.73 48,908.20
03.07 BASE E=0.10M PARA VEREDAS m2 6,044.10 25.14 151,948.67 50,649.56 50,649.56 50,649.56 151,948.67
04 PAVIMENTOS
04.01 IMPRIMACION ASFALTICA m2 2,906.58 3.80 11,045.00 5,522.50 5,522.50 11,045.00
04.02 CARPETA ASFALTICA EN CALIENTE DE 2" m2 2,639.89 28.82 89,043.49 44,521.75 44,521.75 89,043.49
04.03 CARPETA ASFALTICA EN CALIENTE DE 1 1/2" m2 1,278.28 25.29 38,604.06 19,302.03 19,302.03 38,604.06
04.04 COLOCACION DE GEOMALLA m2 990.38 14.61 14,469.45 14,469.45 14,469.45
04.05 CONCRETO PREMEZCLADO LOSAS f'c=210 kg/cm2 (E=0.20 m) m2 76.95 72.87 5,607.35 5,607.35 5,607.35
04.06 ADOQUINADO DE CONCRETO COLOR PLOMO DE ALTA RESISTENCIA 10x20x8 m2 74.90 57.35 4,295.52 4,295.52 4,295.52
04.07 ADOQUINADO DE CONCRETO COLOR NEGRO DE ALTA RESISTENCIA 10x20x8 m2 283.10 57.35 16,235.79 16,235.79 16,235.79
05 TRABAJOS CON CONCRETO Y OTROS
05.01 VEREDAS
05.01.01 VEREDAS DE CONCRETO f´c=175 kg/cm2, E=10 cm m2 1,522.15 41.03 62,453.81 20,817.94 20,817.94 20,817.94 62,453.81
05.01.02 ADOQUINADO DE CONCRETO DE COLOR NEGRO10x20x4 CM m2 283.60 46.56 13,204.42 4,401.47 4,401.47 4,401.47 13,204.42
05.01.03 ADOQUINADO DE CONCRETO COLOR ROJO 10x20x4 CM m2 2,461.00 45.16 111,138.76 37,046.25 37,046.25 37,046.25 111,138.76
05.01.04 SARDINEL REFORZADO PARA VEREDAS (15x40 CM) F'C=210 KG/CM2, 1 var. 1/2" + 1 var. 3/ m 2,594.86 43.14 111,942.26 37,314.09 37,314.09 37,314.09 111,942.26
05.01.05 JUNTAS ASFALTICAS m 295.74 5.08 1,502.36 1,502.36 1,502.36
05.02 MARTILLOS
05.02.01 SARDINEL REFORZADO (15x40 CM) F'C=210 KG/CM2, 1 var. 1/2" + 1 var. 3/8" @ 30 cm. m 624.95 43.06 26,910.35 8,970.12 8,970.12 8,970.12 26,910.35
05.02.02 ADOQUINADO DE CONCRETO COLOR ROJO 10x20x4 CM m2 894.35 45.16 40,388.85 13,462.95 13,462.95 13,462.95 40,388.85
05.02.03 RAMPA Y JUNTAS DE CONCRETO f´c=175 kg/cm2, E=10 cm m2 101.10 64.12 6,482.53 2,160.84 2,160.84 2,160.84 6,482.53
06 SEÑALIZACION
06.01 PINTURA DE TRAFICO BLANCA PARA: CEBRAS PEATONALES, LINEAS DE RETENCION, LI m2 366.51 19.82 7,520.70 7,520.70 7,520.70
06.02 PINTURA DE TRAFICO BLANCA PARA: SIMBOLOS, LEYENDAS, FLECHAS DIRECCIONALES m2 74.65 21.38 4,243.93 4,243.93 4,243.93
06.03 PINTURA DE TRAFICO AMARILLA PARA SARDINEL DE VEREDA m2 761.87 21.28 15,299.47 15,299.47 15,299.47
07 ILUMINACION ORNAMENTAL
07.01 TRAZO Y REPLANTEO m2 258.72 4.81 1,244.44 311.11 311.11 311.11 311.11 1,244.44
07.02 DEMOLICION DE PAVIMENTO ASFALTICO m2 21.20 9.41 199.49 49.87 49.87 49.87 49.87 199.49
07.03 DEMOLICION DE PAVIMENTO DE CONCRETO m2 21.20 32.28 684.34 171.09 171.09 171.09 171.09 684.34
07.04 EXCAVACION MANUAL DE ZANJAS PARA CABLEADO m3 129.36 39.44 5,101.96 1,275.49 1,275.49 1,275.49 1,275.49 5,101.96
07.05 RED PRINCIPAL Y EMPALMES Y ACOMETIDAS m 646.81 41.24 27,166.02 6,791.51 6,791.51 6,791.51 6,791.51 27,166.02
07.06 RELLENO COMPACTADO CON MATERIAL PROPIO m3 129.36 56.60 7,321.78 1,830.45 1,830.45 1,830.45 1,830.45 7,321.78
07.07 POSTE PEDESTAL GALVANIZADO DE 4" und 58.00 531.22 30,810.76 15,405.38 15,405.38 30,810.76
07.08 LUMINARIA ORNAMENTAL COMPLETA CON EQUIPO PARA LAMPARA DE 70 W und 116.00 530.06 61,486.96 30,743.48 30,743.48 61,486.96
07.09 TABLEROS DE CONTROL Y PROTECCION AL EXTERIOR A SER INSTALADOS und 2.00 1,857.70 3,715.40 3,715.40 3,715.40
07.10 POZO DE TIERRA und 2.00 1,996.35 3,992.70 3,992.70 3,992.70
08 VARIOS
08.01 NIVELACION DE BUZONES und 17.00 112.33 1,909.61 954.81 954.81 1,909.61
08.02 ENCIMADO DE CAJAS DE AGUA Y DESAGUE und 174.00 44.31 7,709.94 3,854.97 3,854.97 7,709.94
08.03 SUMIINISTRO E INSTALACION DE TAPAS DE ALCORQUES und 20.00 731.35 14,627.00 7,313.50 7,313.50 14,627.00
08.04 SUMINISTRO E INSTALACION DE BOLARDOS und 103.00 507.99 52,322.97 26,161.49 26,161.49 52,322.97
08.05 SUMINISTRO E INSTALACION DE PAPELERAS BASCULANTES und 13.00 496.17 6,450.21 3,225.11 3,225.11 6,450.21
09 LIMPIEZA EN OBRA
09.01 LIMPIEZA MANUAL DEL TERRENO DURANTE LA EJECUCION m2 9,158.99 0.59 5,403.80 1,080.76 1,080.76 1,080.76 1,080.76 1,080.76 5,403.80
09.02 LIMPIEZA FINAL DE OBRA m2 9,158.99 0.59 5,403.80 5,403.80 5,403.80
10 IMPLEMENTOS DE SEGURIDAD
10.01 EQUIPO DE PROTECCION INDIVIDUAL glb 1.00 9,000.00 9,000.00 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 9,000.00
10.02 PROTECCION COLECTIVAS glb 1.00 5,000.00 5,000.00 833.33 833.33 833.33 833.33 833.33 833.33 5,000.00
Costo Directo S/. 1,518,725.70 S/. 144,168.58 S/. 218,396.16 S/. 366,647.92 S/. 515,085.33 S/. 239,626.47 S/. 34,801.23 S/. 1,518,725.70
Gastos generales S/. 106,680.09
Utilidad S/. 151,872.57

SUBTOTAL S/. 1,777,278.36


Impuesto IGV(18%) S/. 319,910.10

PRESUPUESTO TOTAL S/. 2,097,188.46