This document provides a checklist for pre-commissioning tests of a wave trap installed at a substation. It includes details of the wave trap such as manufacturer, rating, and identification number. The checklist tests that the wave trap is clean, structurally sound, properly installed and labeled. Insulation resistance and contact resistance tests are performed to check electrical integrity. Final documentation review verifies that pre-commissioning checks were approved and necessary documents are available for operation and maintenance.
This document provides a checklist for pre-commissioning tests of a wave trap installed at a substation. It includes details of the wave trap such as manufacturer, rating, and identification number. The checklist tests that the wave trap is clean, structurally sound, properly installed and labeled. Insulation resistance and contact resistance tests are performed to check electrical integrity. Final documentation review verifies that pre-commissioning checks were approved and necessary documents are available for operation and maintenance.
This document provides a checklist for pre-commissioning tests of a wave trap installed at a substation. It includes details of the wave trap such as manufacturer, rating, and identification number. The checklist tests that the wave trap is clean, structurally sound, properly installed and labeled. Insulation resistance and contact resistance tests are performed to check electrical integrity. Final documentation review verifies that pre-commissioning checks were approved and necessary documents are available for operation and maintenance.
CORPORATE OPERATION SERVICES SUB STATION : BAY NO : PRE-COMMISSIONING OF WAVE TRAP EQUIPMENT IDENTIFICATION NO : COMMISSIONING FORMATS DATE OF TESTING :
I REGION :
II DATE OF III DATE OF
I ERECTION : ENERGISATION :
IV DETAILS OF EQUIPMENT :
LOA NO :
MAKE :
TYPE :
SL NO. : R - PHASE : Y - PHASE : B - PHASE :
YEAR OF MANUFACTURE :
FEEDER NAME :
V RATING :
VOLTAGE RATING :
mH RATING :
CURRENT RATING : BAND WIDTH :
VI DETAILS : CHECKLIST / TESTING
SL. DESCRIPTION STATUS REMARK
NO YES NO RECORD DEFICIENCIES, IF ANY 1 EQUIPMENT IS FREE FROM DIRT / DUST FOREIGN MATERIALS ETC.
2 EQUIPMENT IS FREE FROM ALL VISIBLE
DEFECTS ON PHYSICAL INSPECTION
3 SUPPORT STRUCTURES HAS BEEN
PROVIDED WITH DOUBLE EARTH
4 ALL NUTS AND BOLTS ARE TIGHTENED
CORRECTLY AS PER SPECIFIED TORQUE
5 PERMANENT LAVELLING AND
IDENTIFICATION IS DONE
6 LEVELLING AND ALIGNMENT OF STRUCTURE
AND BASE FRAME IS CHECKED
7 ALL INSULATORS & LINE MATCHING UNIT
ARE FREE FROM ANY PHYSICAL DEFECTS
8 TIGHTNESS OF NUTS / BOLTS OF TERMINAL
1 OF 2 WAVE TRAP POWER GRID CORPORATION OF INDIA LIMITED DOC NO. :MR/CF/WT/09/R-0 DATED: 01/08/07 CORPORATE OPERATION SERVICES SUB STATION : BAY NO : PRE-COMMISSIONING OF WAVE TRAP EQUIPMENT IDENTIFICATION NO : COMMISSIONING FORMATS DATE OF TESTING :
CONNECTORS ARE CHECKED
SL. DESCRIPTION STATUS REMARK
NO YES NO RECORD DEFICIENCIES, IF ANY
9 ERECTION COMPLETION CERTIFICATE ALONG
WITH LIST OF OUTSTANDING ACTIVITIES REVIEWED
10 CHECK THAT THE TUNING UNIT AND
ARRESTOR ARE PROPERLY TIGHTENED AND FREE FROM ANY DAMAGE
VII INSULATION RESISTANCE MEASUREMENT :
SL. NO BETWEEN MEGGER PHASE PERMISSIVE
R-PHASE Y-PHASE B-PHASE VALUE 1 UPPER TEMINAL 5000 V 1000 M.OHM AND EARTH 2 LA OF THE 500 V 1 M.OHM WAVE TRAP
VIII CONTACT RESISTANCE MEASUREMENT
THE VALUE SHOULD NOT MORE THAN 5 MICRO-OHMS PER CONNECTOR / JOINT
MANNUALS ETC AVAILABLE AT SITE FOR O & M PURPOSE YES NO
C AFTER MODIFICATION, IF ANY, "AS BUILT DRAWINGS"
ARE AVAILABLE AT SITE YES NO
SIGNATURE : SIGNATURE : SIGNATURE : SIGNATURE :
NAME : NAME : NAME : NAME : DESIGNATION : DESIGNATION : DESIGNATION : DESIGNATION : ORGANISATION : ORGANISATION : ( SUPPLIER REPRESENTATIVE ) ( ERECTION AGENCY ) (POWERGRID SITE I/C)( POWERGRID COMM TEAM )