Académique Documents
Professionnel Documents
Culture Documents
SECTION C- PART 2
1. MEETINGS
1. KICK - OFF MEETING
2. PROGRESS MEETINGS
3. POST MEETINGS
4. RECORD OF THE MEETINGS
1. Progress meetings shall be held monthly. The time and location of the
progress meetings shall be as directed by the Engineer. The Engineer
shall chair these meetings.
2. The Engineer shall prepare the agenda and submit it to the Contractor a
minimum of three (3) working days prior to the meeting.
3. Progress Meetings shall be attended by the Engineer and the Contractor
including respective representatives. Sub-contractors may attend as and
when required and when involved in the Matters to be discussed or
resolved but only when requested by the Engineer. In addition to the
attendees named herewith, Government departments and authorities and
any other regulatory agencies having jurisdiction over the Project, if
required, and such other persons the Engineer may designate may also
attend the meetings.
4. The Contractor shall submit the information itemized below to the Engineer
on each progress meeting:
(a) A list of activities (Work Order = WO's)
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)2 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
(b) A list of current activities (WO's) with an estimate of time required for
completion
(c) A list of changes to planned activities starting dates and durations
(d) A list of all outstanding activities
(e) A list of activities planned to start in the next period
(f) Any other information required by the Engineer’s Representative.
1. Post meetings can be held on requisition bases on both parties. The time
and location of the post meetings shall be as directed by the Engineer. The
Engineer shall chair these meetings.
2. The requester shall prepare the agenda and submit it minimum of three (3)
working days prior to the meeting.
2. SUBMITTAL
1. SUBMITTAL PROCEDURES
2. PROGRAMME
3. ORGANIZATION CHARTS
4. PLANS
5. REPORTS
6. MATERIALS APPROVALS
7. SAMPLES
8. CERTIFICATES
9. GUARANTEES & WARRANTIES
10. METHOD STATEMENTS / PROCEDURES / INSPECTION AND TEST
PLAN (ITP) / OPERATION AND MAINTENANCE MANUAL /
DRAWINGS (WORKING DRAWINGS & SHOP DRAWINGS) ETC.
11. INTERNAL / EXTERNAL AUDIT
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)3 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
2.2 PROGRAMME
2.2.1 Programme of Works
1. The Contractor shall prepare and submit to the Engineer a Programme of
Works.
2. When instructed by the Engineer, the Contractor shall prepare and submit
a detailed programme for a particular section of the Works. The detailed
programme shall be an elaboration of the overall programme and shall be
in an appropriate form.
3. The Contractor shall incorporate the times of occupation of all sub-
contractors in the programme and shall make provisions for the access of
other Contractors as required by the Engineer.
2.3 ORGANIZATION CHARTS
2.5 REPORTS:
2.5.1 Technical Reports:
1. Where relevant, reports should be referenced to the Programme of
Works / QA Plan / ITP etc. (Detail refer to QA Section). To be submitted by
contractor on time.
2. Laboratory Report and any extra report (incase) if requested by Engineer
by written, should be submitted without any extra charge(s) (refer to
Operation Section)
3. TPA certification i.e.; Crane SWL, NDT etc. to be submitted by contractor
on time.
4. The Contractor shall submit one copy of each report unless otherwise
specified.
2.5.2 Progress Report:
1. The Contractor shall prepare and submit a monthly Report throughout the
duration of the Contract. The report shall be submitted to the Engineer
before the third day of each month. The report shall include the following:
Manpower List
Man hour List
Material list that contractor used and changed during
construction/repair Period and/or reporting stage
The date of commencement and completion of WO's
Status of RO's / Permits and/or Municipalities clearance certificates.
Details of problem areas
Accidents to anyone working on the Site which required medical
attention
Details of monthly progress and status of the Works
Details of current or anticipated causes of delay along with their
estimated impact on progress and the corrective measures taken or
proposed.
Status of Completion Certificates and Maintenance Certificates (MC).
Photographs (if required).
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)6 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
2.7 SAMPLES
Samples Definition: Samples are physical examples illustrating materials,
equipment, or workmanship and shall be used to establish standards by which
the work will be judged.
1. Each submittal shall include two sets of samples. One set of approved
samples and all disapproved samples will be returned to the Contractor.
2. Samples shall be taken in accordance with the provisions of relevant
standards where appropriate.
3. Samples shall be labeled and properly identified with the following:
(a) Date
(b) Part(s) of the Works for which offered
(c) Specification Section, Part and applicable Paragraph numbers
(d) Supplier/manufacturer
(e) Product identification (trade name).
2.8 CERTIFICATES
1. When stated in the Contract Documentation or requested by the
Engineer in writing, the Contractor shall submit manufacturer’s
certificates indicating that test results, component manufacture or
installation complies with the requirements of the Contract
Documentation.
2. A statement from the Contractor, sub-contractor, equipment supplier, or
agent indicating the product installation complies with the requirements
of the Contract Documentation shall not be considered as a certificate.
3. All the required Procedures as per QA Section are subjected for submittal
under this section requirement.
4. Each submitted drawing shall be complete with respect to dimensions,
design criteria, materials, connections, bases, foundations, anchors, and
the like, and shall be accompanied by technical and performance data and
by calculations as necessary to support the Information shown on the
drawings.
3. QUALITY ASSURANCE
1. CONTRACTOR’ S RESPONSIBILITY
2. DOCUMENTATION
3. CONTRACTOR'S MANAGEMENT RESPONSIBILITY
4. RESOURCE MANAGEMENT
5. OPERATION AND MAINTENANCE REALIZATION
6. DRAINAGE NETWORKS OPERATION AND MAINTENANCE
DEPARTMENT OF ASSETS AFFAIRS RELATED PROCESSES:
INSPECTING AND TESTING
8. The Contractor shall impose all quality assurance requirements upon sub-
contractors, suppliers, manufacturers and any other parties associated
with the Contractor who are involved in the Project.
3.2 DOCUMENTATION
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)9 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
ii. The Organization Plan shall provide the name, qualifications, and
experience of key staff.
Note: Manpower qualification requirements are detailed on Qualification
section.
iii. The Organization Plan shall show the organization of Contractor’s team
and shall include, but not be limited to, the following:
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)11 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
(a) indicate and describe the area of responsibility and authority of each
individual in the team.
(b) identify the Quality Assurance Representative / Safety officer showing
that the position is independent of the job supervisory staff with clear
lines of authority
(c) an organization chart identifying communications.
3.6.1 General
i) QA Programme of Contractor shall clearly state; Determination of
requirements related to O&M Services, Review of requirements related to
the O&M Service, and client communication.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)12 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)13 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
4.1 General
)i The Contractor shall provide equipment, instruments, qualified
personnel, and facilities necessary to inspect the work and perform the
tests required by the contract Documentation.
)ii The Contractor shall carry out all inspection and testing as per the
inspection and testing Section requirements under clause 3.8.
vi) The Contractor shall clearly document and identify the inspections and
test status of material or equipment throughout maintenance. Identification
may be by means of stamps, tags, or other control devices attached to, or
accompanying, the material or equipment.
5. MATERIALS
Handling and Storage of Materials
.1 The Contractor shall establish procedures for handling and
storage of materials and equipment.
.2 The Contractor’ s storage and handling procedures shall be
designed to prevent damage, deterioration, distortion of shape or
dimension, loss, degradation, loss of identification, or substitution.
.3 The handling procedures shall address the use, inspection and
maintenance of special devices such as crates, boxes, containers,
dividers, slings, material handling and transportation equipment and other
facilities.
.4 The Contractor shall identify equipment and/or material
requiring special handling or storage.
.5 Lifting Equipment of Contractor must be safe and meet the
requirements International Lifting Equipment SWL.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)15 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
7.2.1 NCR
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)16 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
ii) The Contractor shall establish and maintain a non-conformance log. The
log shall contain the following information as a minimum:
(a) Sequential reference number
(b) Date issued
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)17 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
(c) Originator
(d) Description of item deemed to be in non-conformance
(e) Description of non-conformance
(f) Recommended and final disposition
(g) Date closed
(h) Remarks, as applicable.
8.1 Inspection
8.1.1 General
i) The Contractor shall provide equipment, instruments, qualified personnel,
and facilities necessary to inspect the work and perform the tests required
by the contract Documentation.
ii) The Contractor shall repeat tests and inspections after correcting non-
conforming work until all work complies with the requirements. All re-
testing and re-inspections shall be performed at no additional cost to the
Client.
iii) Inspections and tests conducted by persons or agencies other than the
Contractor shall not in any way relieve the Contractor of his responsibility
and obligation to meet all Specifications and referenced standards.
iii. The Contractor shall furnish the Engineer with a signed and
stamped inspection report for each item of work to be inspected. The
report shall indicate whether the item of work, material and/or equipment
complies with all the inspection/test criteria, within max 2 days after test.
This must be supported by photographic evidence of tags installed.
iv. The Contractor shall clearly document and identify the
inspections and test status of activities.
All materials used in contact with sewage or its atmosphere must withstand
corrosion and satisfactory evidence of test result to be submitted (all as per
QCS Section 5 and 8 requirements).
2. Laboratory reports for civil material compaction tests and etc. are to be
submitted to the Engineer.
5. Company External Audit (if any) report as periodically as obtained from the
Auditors to be submitted for Engineer information and review.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)20 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)21 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
SECTION 2
Content List :
A) Introduction:
B) Summary:
C) Brief Description:
D) Technical Specification:
F) Materials Specification:
H) Handing-over of site
I) Pre-tender Clarifications
J) Contractor's Personnel
PROJECT CO-ORDINATOR / CIVIL ENGINEER
SAFETY ENGINEER / OFFICER with QA/QC Background
SURVEYOR
CIVIL FOREMAN
EXPERIENCED LABOURER
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)22 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
A) Introduction
This contract is for supply and install of barcoded asset tags (works). This contract
incorporates section C General Specifications, detailed technical specification of the
tags and includes the fixing and installation method of the tags. The scope is to
supply and install 3,000 asset tags.
B) Summary
1) The Asset Tagging contract is basically; "Supply and Fix and/or Install” of any
of the above mentioned required work's field, as per the DNO&MD
requisitions.
2) This contract is for supply and install of barcoded asset tags (works). This
contract incorporates section C General Specifications, detailed technical
specification of the tags and includes the fixing and installation method of the
tags. The scope is to supply and install 3,000 asset tags.
3) This contract is "on-call" basis and all the activities are re-measurable by
Engineer.
4) DNO&MD reserves right to supply any item from BOQ or any items listed/not
listed in this scope of work, from store which has to be collected by contractor,
with approval from the Engineer.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)23 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
C) Brief Description
1) The work shall be performed in accordance with the standards of the DOM.
2) The scope of works mainly are for the following disciplines:
a) Civil
b) Mechanical
c) Electrical
3) The Contractor shall supervise and attend to the work at all times to ensure
the quality of the work and the safety of all workers on site during
performance of the activities.
4) The Contractor shall use materials from DOM approved manufacturers and
suppliers. All required material’s testing shall be conducted by DOM
approved Materials Testing Laboratories.
5) The Contractor shall properly dispose of surplus materials (as defined by
DOM).
6) The Contractor shall comply with all Qatar Construction Standards (QCS),
and Public Works Authority (Ashghal/PWA) standards.
7) The Contractor shall return and deliver all salvage materials to designated
DOM stockyards.
8) The Contractor may not assign, or sublet, the works, or any part thereof, to
any subcontractor without prior written approval from the PWA designated
administrator so named in the award document.
10)The Engineer reserves his right to supply any item from BOQ or any items
listed/not listed in this scope of work, from the Engineer’s store which has to
be collected by the Contractor.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)24 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
D) Technical Specification
1) Objective
This section provides guidance on the detailed technical specifications to enable the
procurement of high quality Asset Tags which meet Ashghal/PWA Tagging
requirements and standards. These specifications, requirements and standards
provide a basis for implementation of a tagging system of operational assets, within
the O & M drainage facilities.
2) Data Requirements
A full list of operational assets (Asset Types) including Tag references have been
developed and will be made available to the bidders during the tender process.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)25 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
3) Technical Specification
This section the detailed technical specifications to enable the acquisition of high
quality Asset Tags which meet Ashghal/PWA’s needs.
.No Characteristics Specification Comments
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)26 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)27 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
12 Quantity Tags – Supply and install 3000 Bidders to allow cost for
supplying additional
.tags
14 Scope of Supply and install 3000 Asset Bidders to price for this
Services Tags. Site visits .scope
/investigation/reports
production/quality check/photo
graphic evidence. Design and
development of bar coding
.system
16 :Fixing Requirements
Where necessary and as directed by Ashghal, the tag shall be fixed directly to
the asset by mechanical attachment and/or as close as possible to the asset
functional location for specific identification of the asset, by contractor, such
:that the tag
.Can be clearly located and identified (1
Does not obscure displays, dials, gauges or any other form of (2
.visual level indicator
.Does not obscure the asset manufacturer’s nameplate (3
Does not hinder the operation and maintenance of the asset in (4
.any form
.Will not peel away (5
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)28 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)29 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
The Bar Code is a fundamental feature of the Asset Tag Design and bidders shall
include in their price the 1D bar code system as per the Asset Tag Design
Specification.
Bidders will include in their price the 1 D bar code systems as per the Asset Tag
Design specification.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)30 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
2) Contractor must ensure that required materials are available and deliver to site
to comply with the programme requirements.
3) Contractor is responsible and must ensure that materials are available at every
stage of the programme.
4) Contractor to price for each item as defined in the BOQ and technical
specification including costs of procurement, storage up to delivery to the
installation site.
7) DNO&MD reserves right to supply any item from BOQ or any items listed/not
listed in this scope of work, from store which has to be collected by contractor,
with approval of Engineer. The corresponding deduction will be made from the
contractor payment for the materials supplied by the Engineer.
8) Contractor has to procure required materials and arrange in his stores taking all
possible precautions against defects and damage. Any damage or defect
occurring to the materials shall be the sole responsibility of the Contractor and
he shall remain responsible for any damage to the materials supplied and
replace them with good quality.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)31 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
9) Contractor has to store all materials in his stores under cover, clean and tidy as
per manufacturers’ recommendation, and transport to site safely whenever
necessary.
11) As soon as materials are delivered in his stores; Contractor has to notify the
Engineer officially to inspect them. Final receipt shall be acknowledged after
those materials having been inspected by the Engineer. Only after obtaining
Engineer’s approval, materials can to be used on site.
12)After inspection and final acceptance, the Contractor shall re-arrange the
supplied items in their final position in the store, as directed by the Engineer.
13)The Contractor shall be responsible for any defects that may appear in the
materials after final receipt.
14)The Engineer reserves the right to accept or reject the whole supplied materials
or part thereof, if after inspection, they are found to be incompatible with tender
specification and approved samples submitted by the CONTRACTOR. The
Engineer even can reject any materials when they have been brought to the site
for laying/installation, if found defective.
15)The CONTRACTOR shall replace those materials which are rejected by the
Engineer within a reasonable duration or as instructed by the Engineer to
safeguard the scope of work or without causing delay to any issued WO's.
16)Should supply of all materials or part thereof be unduly delayed beyond agreed
delivery date as specified herein above of this Contract, which also includes
replacement of rejected materials, then the Contractor must do his best to bring
them as soon as possible, without causing delay to any issued WO's.
17)At the end of contract, the Contractor shall deliver the complete quantity of
materials as stated in the MINIMUM STOCK REQUIREMENT BOQ to PWA
store or to a location as directed by the Engineer. Accepting of these materials
will be subjected to re-inspection at the site by the Engineer.
Note: Payment of these materials will be based on the rate under the Minimum
Stock Requirements related BOQ up to maximum of the quantity mentioned in
the Minimum Stock Requirements BOQ.
Permits
1) The Engineer is responsible to submit the permit for the work from different
Authorities except the Police Permission which will be the contractor's
responsibility.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)32 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
2) Contractor has to prepare RO-1 for all types of service, and conduct site
survey for critical cases before raising RO-1 and gather data for the required
work and submit the same to engineer.
3) PWA will provide RO-2, before opening the ground for any purpose, the
Contractor must be fully aware of underground services existing in that
particular vicinity by reviewing concerned drawings and make trial pits, if
necessary.
Traffic control
1) The traffic control at road work to protect the public and the men working on
site while undertaking the works is the sole responsibility of the contractor.
The contractor is to make sure that traffic control devices are in place and
well maintained throughout the duration of the works to the satisfaction of
the traffic police.
2) The traffic signs must guide traffic clearly and safely during night or in
inclement weather through the length of the works to the satisfaction of the
traffic police.
3) The use of any methods of traffic control must be agreed with the traffic
police.
4) All excavations/obstructions on or near the foot way must be fenced off and
signed for pedestrian protection.
5) Each sign used by the contractor must have his identity clearly marked
together with telephone numbers which may be used in case of emergency.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)33 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
take the measurement and the Engineer measurement is final and shall be
used for payment purposes.
3) Contractor is responsible to supply and fix any facility required to deal with shut
down.
Safety
1) Contractor shall follow strictly the safety procedure while working, safety at
the site for the public and for the Contractor’s staff or the properties is the
sole responsibility of the Contractor.
Note: Detail of safety requirement is in Section 3 herein.
2) Contractor has to make available all the time all required Personnel
Protection Equipment (PPE) such as; calibrated gas monitor, safety
harnesses, access ladder, air blower, etc. on site. All work shall be under
monitoring of qualified safety officer of Contractor.
Note: Detail of safety requirement is in Section 3 herein.
Reporting
Contractor is responsible to submit weekly report, monthly report / evaluation
and case by case report supported by high resolution photos for the work to
the Engineer.
F) Materials Specification
General
a) Proposed material for supplying by contractor, are subjected for approval of
Engineer as per submittal procedure, prior to use/procurement by Contractor.
b) Material shall hold technical data sheets, test certificate and certificate of
originality, which must be traceable to the delivered material.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)34 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
d) Material supplied by Contractor and their inspection and test requirements shall
meet requirements of this scope of work, Qatar Construction Specification
(QCS).
4.1 There are two (2) types of WO form to be used during the execution of the
work namely,
Form No. 1 – Estimated WO: Contractor will be instructed using this Form
which contains the initial details and instructions of the work to be performed.
Form No. 2 – Actual WO: Upon completion of the works within the stipulated
and agreed requirements, Contractor will submit this Form to obtain the
Engineer approval and to finalise the said works for payment purposes.
4.2 The Contractor will be requested to execute any work through a WO (Form
No. 1) that describe the SCOPE OF WORK and TIME LIMIT of the entrusted
work depending on its nature and aligned with the overall programme of the
works. A specimen WO (Form No. 1) is attached in Section B.
4.3 The contractor will receive the work instruction at least one day before the
work; in some urgent cases the work instruction will be in the same day, the
contractor has to be ready to execute the work immediately.
4.5 The Contractor shall render his scope/services through Work Order (WO's).
Each WO excluding or including reinstatement works (where and if applicable)
has to be completed within stipulated Time Limit as specified in the WO. The
Contractor has to agree with the Engineer on Time Limit against each WO in
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)35 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
days/weeks depending on its nature and site conditions aligned with the
programme of works.
5.On the normal cases, one calendar week is the maximum time to reply/agree about
the Time Limit from contractor side.
6.Contractor shall mobilize his resources immediately after the Contract Effective Date
and each day to attend as much as WO's as possible without affecting
progress.
7.The work will be on re-measurement basis, the contractor representative and the
Engineer representative shall measure the work immediately after completing
each phase of the work, if the contractor representative fail to attend the
measurement, the Engineer will take the measurement of his representative
as the approved/agreed one.
11. All drawings associated with this tender are appended in Section "E" and
Contractor has to approach the Engineer to obtain any other drawings or
details which are not enclosed but necessary to execute the work.
12. Should the Contractor require further drawings that may be necessary for the
execution of the WO he shall when instructed by the Engineer to prepare and
submit such detailed drawings with adequate notes in writing for the approval
of the Engineer. The Engineer may within a reasonable period approve,
amend or change these drawings or may require the Contractor to produce
amended drawings. No drawing shall be valid unless it is approved and signed
by the Engineer.
13. Contractor must obtain necessary permits/RO from the concerned authorities
to proceed with the work.
14. Particular care must be taken to avoid damage to all underground services
(Public Utilities and Services) during the execution of the works. Although the
Engineer will provide RO-2, before opening the ground for any purpose, the
Contractor must be fully aware of underground services existing in that
particular vicinity by reviewing concerned drawings and make trial pits, if
necessary. The Contractor shall be responsible for any damages caused to
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)36 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
such utility services due to his negligence and shall pay fully all charges and
keep the Engineer informed against all consequences and works.
15. Contractor must submit necessary site clearance certificate from the
Municipalities/concerned Authorities (if applicable) for the process of the
Completion Certificate.
16. On completion of any works, Contractor shall submit WO (Form No. 2) and
ensure the submission of all related As-built, record sheets, laboratory reports
and other inspection related certificates during performing of the job to the
Engineer for his approval. Engineer is responsible to advise GIS Department
any changes to these approved As-built and record sheets.
H) Handing-over of Site
All sites proposed in this tender shall be considered as handed-over to the Contractor
on the date of award. It is therefore, the responsibility of the Contractor to depute his
Surveyor/Engineer to receive the locations/sites as early as possible upon receiving
WO's from the Engineer. The Engineer shall determine priority of each site for
execution during the contract.
I) Pre-tender Clarifications
Before submitting the tender, Tenderer must make independent inquiries as to the
scope of works by visiting the site, the prevailing local conditions and generally obtain
their own information on all matters that may in any way affect their pricing, completion
period, risks and obligations and assess themselves for the extent of work involved.
The tender price shall be deemed to include all that is necessary to supply and carry
out the works to an acceptable level and in a safe manner observing all associated
government regulations. No claim will be considered on the ground due to lack of
information.
J) Contractor's Personnel
All Contractor personnel must have appropriate trade qualification or University
degrees in the applicable disciplines and must have sufficient years of experience in
the assigned scope, as per following requirements but not limited to;
All the contractors staff qualification are subjected for Engineer review and approval.
1) Project Co-ordinator
QUALIFICATIONS/SKILL
The suitable applicant shall be qualified with a B.Sc. Civil Engineering Degree
from a recognized University. Background of construction project controlling and
leadership capability.
EXPERIENCE
He should have had experiences in field of water and/or wastewater with relevant
experience in Asset Tagging.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)37 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
2)Technician
Qualifications/Skill
QUALIFICATIONS/SKILL
Sound physical condition with basic literacy in English.
EXPERIENCE
Previous experience in a sewage treatment works or pumping station or in the
construction would be an advantage.
The Contractor shall obtain a photographic and video record showing the
progress of work every week and month, and / or as necessary, in order to
provide sufficient visual evidence of the progress and to record the specialized
events features of the works or other matters of interest in connection with the
works or their surroundings of the project. Such media documentation shall be
submitted to the Engineer in the form of an accepted media documental
presentation, as and when required during the progress of works and as a
complete package at the completion of the project.
Upon approval from Engineer's representative on any road closure for the
purpose of carrying out the Works of PWA, the Contractor shall place a
sufficient notification to the general public in local newspapers both in Arabic
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)38 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
and English languages at least one (1) week prior to the road closure. The
contents of notification shall be approved by the Engineer and the extent shall
not be less than a quarter of the standard size page of a reputed local
newspaper. In order to evident the notification the Contractor shall submit to the
Engineer a copy as appeared on the newspaper on the same day of the
notification.
Submittals shall meet the requirements of BOQ items 2.1, 2.2 and of this
Section.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)39 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
The name of the Employer shall be Public Works Authority and the name of the
Engineer shall be Director of Assets Management Affairs.
Specifications
The Tenderer is to note that all the specifications stated in the Tender
Document are to be considered the minimum specifications and requirements
required.
All work to be executed under this Contract shall be carried out in accordance
with the QCS amplified or amended by the Project Specifications of the Tender
Document.
General Requirements
Safety
Safety at the site is sole responsibility of the contractor. Work should comply with
QCS, Roads, Traffic police, Municipality, Drainage Affairs Standards & all
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)40 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
necessary safety measures. Contractor has to keep the Works Site secure all the
time including safety barriers, traffic signs, warning lights etc.
Method statement
After award of the Contract, the Contractor shall submit a method statement
incorporating the risk assessment and plan for the work for the Engineer’s
approval.
Materials
All materials shall be from approved suppliers as per Assets Management Affairs
approved list or of the best quality.
Laboratory Testing
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)41 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
SECTION 3
HEALTH AND SAFETY
1.0 GENERAL
1.1 Responsibility
1.2 Safety Engineer
1.3 Reporting Accidents
1.4 General Sanitation
1.5 Safety Notice Board
1.6 Compensation for Damage
1.0 GENERAL
1.1 Responsibility
1. It is the Contractors responsibility to conduct his operations in such a manner so
as to avoid danger or injury to the public and personnel employed at the work or
any other persons or even damage to property. The Contractor shall take
precautionary measures for protection against such risks and shall inspect
safety conditions where the works are being executed.
2. Contractor shall insure the safety of pedestrians, vehicle, traffic and properties
near the working area and especially if there work inside live sewers or any
excavation, pipe laying or aboveground construction as part of this Contract.
3. All Contractor’s personnel must be able to work safely at all times within the
strict environment of sour gas and their key/Senior staff shall be certified in the
use of breathing apparatus / Gas Detectors and precaution action on confined
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)42 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
4. Throughout the contract duration and any extensions thereof, Contractor shall
keep the sites clean and free from all unnecessary obstruction and shall store or
dispose of contractors’ plant equipment and hand-tools in a safe and orderly
manner.
5. The Contractor shall conform to all Acts, Orders and Regulations made by any
official authority of Qatar with respect to health and safety.
2. The Contractor shall notify the Engineer of any claim made against him which is
in any way connected to the Contract.
1. The Contractor shall submit a Safety Plan to the Engineer for approval within
ten (10) Days of the award of the Contract.
2. The Safety Plan shall include the Contractor’s proposals for the maintenance of
safety on the Site. These proposals shall address the safety measures
applicable with respect to all tasks to be undertaken.
3. The Safety Plan shall include the Contractor’s proposals for accident
prevention. Accident prevention shall include but not be limited to training,
monitoring and review of safety related procedures, enforcement of safety
related matters and promoting safety awareness.
2.4.1 General
1 The Contractor shall take all necessary precautions against fire as required by
the insurance company insuring the Works, the Department of Civil Defence
and the Engineer.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)44 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
3 Except as otherwise provided herein, the Contractor shall not permit fires to be
built or open type heating devices to be used in any part of the Site.
4 The Contractor shall maintain fire fighting equipment in the site offices, the
stores and about the Works where applicable. The type, amount and location of
fire fighting equipment shall be to the requirements of the Department of Civil
Defense. The Contractor shall confirm to the Engineer in writing that the
requirements of the Department of Civil Defence have been met, enclosing the
approval letter from Civil Defence Dept.
5 The Contractor shall make arrangements with the Department of Civil Defence
to inspect the Works and promptly carry out their recommendations at his own
expense if requested to do so by the Engineer.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)46 JUNE 2013
TECHNICAL SUBMISSION PROJECT SPECIFICATIONS
SECTION C- PART 2
The Contractor shall provide GSM (mobile telephone) to all Engineers and Key
Staff.
AA DOM 13/14M/1570-2.06/G
Asset Tagging C (2)47 JUNE 2013