Ti=0 dias 102/147

K=45
37/44
INICIO D=7 97/102 252/297
60/67 I=5
297/327
213/217
217/297 M=30
67/97
L=80
G=30 297/327
0/30 30/37 37/67 217/297
67/97 97/217
A=30 B=7 E=30
J=120
0/30 30/37 37/67
97/217

30/40 40/43
C=10 F=3
327/341
54/64 64/67
N=14

327/341

40/50
H=10
341/362 362/365
317/327 O=21 P=3

341/362 362/365

CONCLUSION:

LA RUTA CRITICA ES A_B_E_G_J_L_M_N_O_P CON UNA DURACION FINAL

DEL PROYECTO DE 365 DIAS.

FIN

Tf= 365 dias


Ti=0 dias 101/146
K=45
37/44
INICIO D=7 96/101 252/297
60/67 I=5
296/326
213/217
216/296 M=30
66/96
L=80
G=30 296/326
0/30 30/37 37/66 216/296
66/96 96/216
A=30 B=7 E=29
J=120
0/30 30/37 37/66
96/216

30/40 40/43
C=10 F=3
326/340
54/64 64/67
N=14

326/340
2
40/50
H=10
340/361 361/364
317/327 O=21 P=3

340/361 361/364

CONCLUSION:

LA RUTA CRITICA ES A_B_E_G_J_L_M_N_O_P CON UNA DURACION

REDUCIDA EN 1 DIA EN TOTAL 364 DIAS.

FIN

Tf= 364 dias


Ti=0 dias 101/146
37/44 K=45

INICIO D=7 96/101 252/297


60/67 I=5
296/326
213/217
216/296 M=30
66/96
L=80
G=30 296/326
0/30 30/37 37/66 216/296
66/96 96/216
A=30 B=7 E=29
J=120
0/30 30/37 37/66
96/216

30/40 40/43
C=10 F=3
326/340
54/64 64/67
N=14

326/340
2
40/50
H=10
340/360 360/363
317/327 O=22 P=3

340/360 360/363

CONCLUSION:

LA RUTA CRITICA ES A_B_E_G_J_L_M_N_O_P CON UNA DURACION

REDUCIDA EN 1 DIA EN TOTAL 363 DIAS.

FIN

Tf= 363 dias


Ti=0 dias 100/146
37/44 K=45

INICIO D=7 95/100 250/295


60/67 I=5
295/325
210/215
215/295 M=30
65/95
L=80
G=30 295/325
0/30 30/37 37/65 215/295
65/95 95/215
A=30 B=7 E=28
J=120
0/30 30/37 37/65
96/216

30/40 40/43
C=10 F=3
325/339
54/64 64/67
N=14

325/339

40/50
H=10
339/359 359/362
317/327 O=22 P=3

339/359 359/362

CONCLUSION:

LA RUTA CRITICA ES A_B_E_G_J_L_M_N_O_P CON UNA DURACION

REDUCIDA EN 1 DIA EN TOTAL 362 DIAS.

FIN

Tf= 362 dias