Bill of Quantities

Description of Material Quantity Unit Unit Cost Total Cost

Concrete Ramp
Materials 100,806.00
Portland Cement; 40kg/bag; REPUBLIC brand 236 bags 255.00 60,180.00
Sand; S1 14 m3 700.00 9,800.00
Gravel or Crushed Stone; 3/4mm 27 m3 700.00 18,900.00
Steel Reinforcing Bars, Deformed (UNISTEEL brand)
10mm x 6.00 meters 43 pc 105.00 4,515.00
Tie Wire; No. 16 3 kg 52.00 156.00
Common Nail
50mm (2") 1.5 kg 90.00 135.00
75mm (3") 1 kg 80.00 80.00
100mm (4") 1 kg 80.00 80.00
Form; Plywood 1.2m x 2.4m 7 pc 880.00 6,160.00
Form Lumber; Good Lumber (L=6m) 8 pc 100.00 800.00

Equipment and Tools 6,000.00


One-bagger mixer 1 day 3,000.00 3,000.00
Tools 1 l.s 3,000.00 3,000.00

Labor 5,560.00
Foreman 1 day 980.00 980.00
Carpenter 2 day 800.00 1,600.00
Mason 2 day 800.00 1,600.00
Laborer 2 day 690.00 1,380.00

Construction Cost ₱ 112,366.00


Contingency, 10% ₱ 123,602.60
Concrete Ramp Dimension

Formworks

Concrete
Length Height Area Width Volume
Item
(m) (m) (m2) (m) (m3)
A 3.000 1.545 4.635 3.000 13.905
B 4.755 1.545 3.673 3.000 11.020
TOTAL VOLUME = 24.925

Formworks
Length Height Quantity Total Area
Item
(m) (m) (pcs) (m2)
FACE-1a 4.755 1.545 2.000 7.346
FACE-1b 3.000 1.545 2.000 9.270
FACE-2 3.000 1.545 1.000 4.635
TOTAL AREA = 21.251
Reinforcing Bar Calculation

Bar Diameter Bend Dimensions (mm) Length No. of Total Length Unit Wt. Weight
Mark (mm) Type a b c (mm) Bars (m) (kg/m) (kg)
Rebar-A 10 A 2925 2925 14 40.95 0.617 25.25
Rebar-B 10 B 2850 2850 37 105.45 0.617 65.03
Rebar-C 10 C 4350 1650 6000 14 84.00 0.617 51.80
GROSS TOTAL 10mmØ = 142.080
GRAND TOTAL incl. WASTAGE = 156.288