Vous êtes sur la page 1sur 20

Chapter 13

Design for
Constructability

National Steel
Bridge Alliance STEELBRIDGEDESIGNHANDBOOK
Disclaimer
All data, specifications, suggested practices, and drawings presented herein, are based on the best
available information and delineated in accordance with recognized professional engineering princi-
ples and practices, and are published for general and procedural information only. Procedures and
products, suggested or discussed, should not be used without first securing competent advice respect-
ing their suitability for any given application.

Publication of the material herein is not to be construed as a warranty on the part of the National Steel
Bridge Alliance - or that of any person named herein - that these data and suggested practices are suit-
able for any general or particular use, or of freedom from infringement on any patent or patents.
Further, any use of these data or suggested practices can only be made with the understanding that
the National Steel Bridge Alliance makes no warranty of any kind respecting such use and the user
assumes all liability arising therefrom.
Table of Contents

Introduction........................................................................................................1

General ..............................................................................................................1
Equipment ....................................................................................................1
Erection ........................................................................................................3
Site Considerations .......................................................................................7

Design Considerations ........................................................................................8


Construction Loads.......................................................................................8
Deck Placement ..........................................................................................10
Stability ......................................................................................................12
Fit-up..........................................................................................................15
Erection Engineering and Drawings ............................................................17
Design for
Constructability
INTRODUCTION expertise of the erection contractor. In the Mobile Hydraulic Crane
following paragraphs, basic erection
As time has passed, technological advance-
equipment is discussed with specific exam-
ments and heightened environmental
ples shown for different bridge types
awareness have led bridge designers to
including considerations regarding the
increase the maximum span lengths typi-
access to and topography of the construc-
cally associated with a particular bridge
tion site.
type. For example, with the introduction of
High Performance Steels over the last
Equipment
decade, steel plate girder bridges are
Cranes come in various types and sizes.
becoming the structure of choice for spans
Each type of crane has specific advantages
up to 500 feet in length. The use of these
and disadvantages depending on numer-
higher strength steels in obtaining such
ous variables such as pick weight, pick
long spans creates the need for designers
height and radius, number of picks, site
to consider additional aspects associated
access, site location, constraints, etc. The
with the construction of the bridge. All too
following crane types are used in typical
often, bridge designers concern them-
bridge erection:
selves only with checking the stability and
member stress levels in the structure for Mobile hydraulic cranes are used for light- to
the in-service condition after erection of medium-weight picks up to 650 tons.
the entire superstructure is complete. But These cranes are used where the site is
many times the critical stress in a particular readily accessible via existing roadways,
component is encountered during the where pick heights are relatively low, and
erection of the bridge where large where crane area is limited. A typical appli-
unbraced lengths affect the stability of the cation would be in the replacement of an
partially completed structure. This chapter existing grade separation bridge. These
describes typical erection methods and cranes come in a wide variety of sizes such
procedures and highlights some of the that the appropriate crane can be used for
aspects that should be considered by the the given pick weight and space availabili-
designer. With this basic knowledge, the ty. The set-up and tear down is quick
bridge designer can determine which, if through the use of telescoping hydraulic
any, of these aspects are a concern for outriggers. In addition, the mobility and
his/her particular design situation. reach is versatile due to the telescoping
boom and 360 degree rotational capability.
GENERAL Mobile lattice boom cranes are used for
Bridge erection takes on many forms based light-to medium-weight picks up to 300
on the site, the complexity of the structure, tons. These cranes are used when the site
the availability of equipment, and the is accessible via existing roadways and

STEELBRIDGEDESIGNHANDBOOK 13-1
Mobile Lattice Boom Crane Lattice Boom Crawler Crane Lattice Ringer Crane Tower Crane

where pick heights are high. Through the unfinished open terrain and where pick
use of telescoping hydraulic outriggers and heights are high (up to 400 feet). Typically,
self-assembly capabilities, the set-up and once assembled the crane is immobile due
tear down is quick compared to other to the track work used to support the mas-
crane types, generally one to two days for sive counterweights. A typical application
assembly of multiple trailer loads. In addi- would be the erection of a new bridge over
tion, the reach is versatile with 360 degree a wide river or bay where the crane could
rotational capability. be mounted onto a barge. By mounting
It should be noted that mobile lattice the crane on a barge, it becomes mobile
boom cranes and mobile hydraulic cranes increasing it versatility and ultimately mak-
cannot move once the pick is lifted. ing it more productive. The set-up and
tear-down is long and labor intensive due
Lattice boom crawler cranes are used for to the number of components that must
light-to medium-weight picks up to 300 be site-assembled to meet hauling
tons. These cranes are used where the site restrictions.
is typically unfinished terrain and where
pick heights are high (up to 400 feet). A Tower cranes are used for lightweight picks
typical application would be in the erection up to 20 tons. These cranes are used where
of a new bridge over a stream valley. These no mobility is required and excessive verti-
cranes come in a wide variety of sizes such cal heights must be overcome. A typical
that the appropriate crane can be used for application would be in the construction of
the given pick weight and height require- a tower for a suspension or cable stayed
ments. The set-up and tear-down is long bridge. These cranes come in a wide vari-
and labor intensive due to the number of ety of sizes to meet the need for a particu-
components that must be site-assembled lar height and reach. The setup and tear-
to meet hauling and site access restrictions. down are extremely long due to the assem-
Once assembled, the mobility and reach is bly process. Quite often, a separate foun-
versatile with 360 degree rotational capa- dation must be constructed to support the
bility. In addition, crawler cranes are able to base of the tower leg. Once in place the
travel with the load lifted. crane can be highly productive in deliver-
ing materials to the elevation required.
Lattice ringer cranes are used for heavy- Some models come with self jacking tower
weight picks up to 1,400 tons. These legs that allow the crane to adjust its
cranes are used where the site is typically height as construction progresses.

13-2 DESIGN FOR CONSTRUCTABILITY


Timber Crane Mat Pier Brackets

Along with these different crane types, var- ture and facilitate removal.
ious erection accessories are typically used Temporary pier brackets are often used in
to maximize the crane’s capabilities and the erection of river/water crossings to
function. Some of these accessories are increase the number of brace and reaction
described in the following paragraphs. points provided by the permanent pier.
Temporary Bent
Crane mats are series of timber or steel Pier brackets are typically comprised of a
members assembled in sections beneath series of steel members assembled into a
the crane to provide a level sound base to frame and temporarily attached to the face
support the crane during lifting opera- of the permanent pier. The configuration
tions. Most often large timbers are used, can vary greatly based on the geometry of
since they are widely available, inexpensive the permanent pier and the intended func-
and easily transported and assembled. If tion of the bracket. The brackets allow
existing ground conditions are poor (such individual members to be erected onto the
that proper support of the crane would be pier with the use of a single crane. The
marginal), the use of a more complex sys- erected member is attached to the perma-
tem of steel framing or other custom nent bearing and to the pier bracket for
designed site-cast crane pad could be stability during the erection of the remain-
implemented to span the poor soils. ing portion of the spans.
Temporary bents are often used in conjunc- Hydraulic jacks are often used in combina-
tion with cranes to aid in the erection tion with the temporary bents and pier
process. Standard scaffolding is widely brackets to allow for flexibility in vertical
available for use in creating these tempo- and horizontal location of the erected
rary supports. Each section of scaffolding is member. These jacks are readily available in
assembled into a geometric configuration a wide variety of sizes and capacities to
that can achieve the required elevation meet the requirements of each particular
and load carrying capacity needed for situation. Some other uses for hydraulic
each individual situation. Temporary bents jacks include longitudinally aligning a con-
are commonly used where it is necessary tinuous multi-span girder bridge with mul-
to provide support for a longer period of tiple fixed piers to ensure proper bearing/
time during complex erection and when pier alignment; aligning the ends of long
foundation conditions are favorable, due span continuous trusses and simple span
to shallow rock or good soil. Other arches to ensure proper fit-up for the clo-
instances where temporary bents are used sure members; and launching completed
include long-span bridge erection, and/or bridges into their final location as described
a situation where fit-up is to be at the “no in the erection section that follows.
load” condition and where site constraints
limit the placement of cranes. It is impor- Erection
tant to note that the temporary bent must The art of bridge erection has evolved over
be able to be lowered once erection is time to keep pace with technological
complete to transfer the load to the struc- advancements in machinery and accessories.

STEELBRIDGEDESIGNHANDBOOK 13-3
Even with today’s weight and capacity of the girder, the erec-
advanced computer tion crane could use either a single lift
controlled equipment, point located at the center of gravity of the
the most important member or two lift points centered about
aspect of bridge erec- the center of gravity utilizing a spreader
tion lies in the experi- beam. Based on the overall size and com-
ence of the personnel plexity associated with the bridge erection,
performing the work. the individual girder erection could incor-
Since the objective of porate the use of temporary bents, tempo-
I-Girder Erection Using a safely assembling the rary pier brackets or hold cranes to provide
Spreader Beam. structure into its stability to the member until a sufficient
required configuration number of girder lines are erected and con-
remains unchanged, nected via permanent cross frames or
the experience neces- diaphragms to form a stable system.
sary to achieve this Box girder erection is often accomplished
goal is paramount to using a pair of erection cranes working in
success. The following tandem during the lift. The cranes are typ-
paragraphs discuss dif- ically rigged with a spreader beam that
ferent rigging contains two beam clamps each. The beam
schemes that are tradi- clamps are attached to the top flanges of
tionally used in bridge the box girder near the ends of the mem-
Box Girder Erection Using
erection along with ber. Unlike I-girders, an individual box gird-
Two Crawler Cranes.
various methods of er may be stable once it is erected onto its
erection available for I- permanent supports, due to the internal
girder, box girder, bracing system.
truss, arch and cable
supported structures. An alternate girder erection method that
has been gaining popularity consists of
The rigging of a mem- launching the completely assembled
ber in preparation for bridge longitudinally across the permanent
erection can take on supports. This method of erection can be
many forms based on utilized for both I-girder and box girder
the size, weight, bridges. To accomplish a girder launch, the
I-Girder Bridge Launching. geometry and capaci- superstructure is assembled on a roller sys-
ty of the individual member as well as the tem behind one of the abutments in seg-
size, capacity and location of the erection ments of sufficient length to maintain sta-
crane. In its simplest form, rigging could bility during the launching. Once a seg-
consist of a single vertical sling hooked to ment is assembled, hydraulic jacks are used
the crane and attached to the member to move the structure across the abutment
with a beam clamp or through the use of a until it reaches the first pier support. After
wire rope sling around the member. In a the girders are properly aligned on the first
more complex form, rigging could consist pier, additional segments are assembled on
of a multi-point erection frame attached to the roller system behind the abutment and
the member with beam clamps or slings the hydraulic jacks advance the structure
and lifted using multiple cranes attached at until it reaches the next pier. This launching
different locations along the frame. With process is continued until the entire struc-
both rigging options, tag lines attached to ture rests on its permanent supports. This
the ends of the member are used for hand erection procedure requires minimal equip-
guidance to ensure safe placement. ment to perform, but the girders must be
I-girder erection is often accomplished using specifically designed both globally and
a single erection crane. Based on the size, locally to handle the large forces generated

13-4 DESIGN FOR CONSTRUCTABILITY


during the launch. In some cases the erec- usually on temporary
tion forces in the girders are minimized bents, and then float-
through the use of an erection nose ed into position and
attached to the leading end of the girders, lifted onto the perma-
thus reducing the cantilever length, or nent piers using
through the use of a cable tie-back system hydraulics. This
attached to the top of the girders to coun- method of erection is
teract the cantilever moments. The cable advantageous where
tie-back system is also used to control waterway traffic can-
deflections of the cantilever end to ensure not be impeded, the
proper position as each permanent sup- erection contractor I-Girder Launch with Cable
port is reached. This erection method has the heavy lifting Tie-Backs.
becomes feasible where the bridge height equipment on hand,
is excessive or when environmental and/or or where temporary
topographical constraints limit the access bents are not feasible
for erection cranes. due to poor founda-
Truss erection methods can vary greatly tion material or exces-
based on the number of spans, span conti- sive water depth.
nuity, site topography, truss type, etc. Arch bridge erection is
Methods that have been used successfully typically performed
over the years are cantilever erection for using a temporary stay
Cantilever Erection of a
continuous trusses and float-in erection of tower located at the
the completely assembled bridge for sim- spring line (end pier Continuous Truss using
ple spans. The cantilever method of erec- for tied arches) with Barge Mounted Cranes.
tion for continuous trusses starts with stay cables connecting
assembling the sections over an interior the partially complet-
pier using temporary bents or pier brackets ed arch to the tower
to stabilize the panels. Once the initial pier on the leading end
panels are erected, new panels are added and the tower to
to each end in an alternating fashion until counterweights or
mid-span or the abutment is reached. The ground anchors on
same procedure is repeated again until the the trailing end.
ends of the two cantilevers are ready for Erection begins at
the installation of the closure pieces. each spring line and
Erecting a truss in this fashion can be per- progresses toward the
formed using standard erection equipment crown. As arch pieces
or traveling derricks. In addition, erection are erected, additional
can proceed simultaneously from each stay cables are added
interior pier, and truss geometry and to provide temporary
deflection can be controlled using support until the clo-
hydraulic jacks at the temporary supports. sure piece is in place
Another commonly used method is to and the arches are self
assemble truss section components off site, supporting. Arch
thus, providing erection of assemblies pieces can be erected
into place by cable and winch systems Cantilever Erection of a
while filling in smaller members piece by
attached to the leading end of the previ- Continuous Truss using
piece with smaller equipment.
ous segment or by cranes located beneath Derricks.
Simple span truss erection over navigable the bridge, if feasible. Using temporary
water can be performed using a scheme stay towers is the most common erection
where the truss is fully erected on barges, method since arch bridges are predomi-

STEELBRIDGEDESIGNHANDBOOK 13-5
installation until the end pier or mid-span is
reached. This procedure is repeated for
each tower of the bridge. When two adja-
cent cantilever ends are completed, the
closure pieces are installed and the erection
is finished. This erection method is com-
mon, since all of the erection forces are
resisted by permanent bridge components.
Only simple beam and winch erection
equipment attached to the cantilever ends
or deck mounted derricks are necessary to
lift the members into place.
Suspension bridge erection is performed by
using the permanent bridge members for
support of the partially completed super-
structure. After the main towers are con-
structed and the main suspension cables
Arch Erection using Stay are strung, the superstructure erection
nantly used to span deep canyons (true
begins at the tower.
Towers and Cables. arch) or wide bodies of water (tied arch).
One method of erecting the deck members
Another method of true arch erection that
follows the cantilever scheme where mem-
has been employed uses the canyon walls
bers are erected directly at the tower and
to support the arch as a cantilever. With
attached using temporary supports. After
this method the arch is erected from each
the first members are stabilized, additional
spring line simultaneously towards the
pieces are cantilevered from each end in an
crown. As each arch member is erected it is
alternating fashion until the location of the
“tied” back into the canyon wall using a
first permanent suspender is passed. At this
temporary connection. The tie member
point, the first set of suspenders is installed
can be part of the permanent structure (as
to connect the cantilevers to the main
shown below) or a temporary member/
cable. Alternating cantilever erection of
cable used solely for erection support.
members continues along with suspender
Once the arch is closed and erection com-
installation until the end pier or mid-span is
plete, the temporary tie members/connec-
reached. This procedure is repeated for
tions are removed and the arch is self sup-
each tower of the bridge. In addition to
porting.
erecting the pieces as balanced cantilevers
Cable stayed bridge erection is performed at each individual tower, the erection of the
utilizing a permanent tower to support all pieces at each tower along the length of
loads during the assembly of the super- the bridge must be considered relative to
structure. After the majority of the tower each other to maintain the shape of the
Arch Bridge Erection using
construction is completed, the first super- main suspension cables. This will prevent
the Floor System as a
structure segments are erected directly at large, unbalanced horizontal forces in the
Erection Tie to the Canyon the tower using temporary supports main suspension cables at the towers.
Wall. attached to the tower’s cross strut. After
A second method of erecting the deck
the first segment is stabilized, additional
members is to load the main cables in a
members are cantilevered from each end in
manner to try and mimic the final geome-
an alternating fashion until the location of
try of the cable. With this method individ-
the first permanent cable stay is passed. At
ual pieces are supported from the main
this point, the first set of stay cables is
cables at specific locations prior to con-
installed. Alternating cantilever erection of
necting any of the pieces to each other.
segments continues along with stay cable

13-6 DESIGN FOR CONSTRUCTABILITY


After a sufficient number of pieces are sus-
pended from the main cables, the pieces
are connected to each other and the
remaining pieces erected. This method of
erection is used in extremely long span sus-
pension bridges to minimize the jacking
forces required to erect the closure pieces.
For both methods, only simple beam and
winch erection equipment, typically
attached to the main cables (cable travelers),
are necessary to lift the members into place.
Since cable-supported structures are typical-
ly used for extremely long spans over rivers
and open water, delivery of members for
erection is accomplished using barges. The
cable travelers are used to lift roadway sub
assemblies into place directly off of barges.
to completely span the waterway with a Suspension Bridge Erection
Site Considerations simple span truss, thus allowing the con- using Cable Travelers.
Often the most challenging obstacle in the tractor unrestricted access to the construc-
design of a bridge is a result of the geo- tion site. Even though the material costs
graphical location of the structure. Bridge would be greater, the construction time
construction often occurs in heavily popu- would be greatly reduced and the contrac-
lated urban areas where land use is high or tor’s productivity increased, ultimately
scenic rural areas where environmental reducing his overall cost. For additional dis-
issues are of paramount importance. Since cussion on bridge layout and cost, see
construction in these areas can dramatical- Chapter 8(1).
ly affect the final cost of the bridge, care-
Another scenario could be the replacement
ful consideration must be given to provid-
of an existing bridge that spans commuter
ing adequate access for the contractor and
rail lines in a congested urban area. Again,
the equipment necessary to perform the
due to required rail clearances the recom-
work. In the following paragraphs the
mended solution would be to construct a
issues of contractor access and equipment
new multi-span girder bridge based on
areas are discussed.
least material cost. If the commuter rail line
Contractor access into and out of the con- imposes restrictions on the construction
struction site can have a dramatic effect on times with extreme penalties associated
the overall cost of the project if not prop- with violating track outage criteria, the
erly addressed in the design process. For contractor may need to include a large
instance, if a new low-level bridge is to be contingency to cover the potential fines. A Cantilever Cable Stayed
constructed over a non-navigable water- more economical solution may be to Bridge Erection using Deck
way 400 feet in width, the structure type design a single span structure to limit the Mounted Derricks.
most often recommended (based on mate- construction work over and adjacent to the
rial cost) would be a 3-span continuous rail lines. The entire simple span structure
girder bridge having two piers in the could be completely erected on the adja-
water. If environmental constraints due to cent roadway and lifted into position dur-
the sensitive nature of the waterway allow ing a brief off-peak closure of the rail line.
the contractor access to the pier founda- Again, the construction time would be
tions for only one month out of the entire greatly reduced, the contractor’s risk
year, a more economical solution may be would decrease, his productivity would

STEELBRIDGEDESIGNHANDBOOK 13-7
increase, and consequently his overall cost Some general statements are provided say-
would go down. ing that investigations should be made for
Another important consideration deals handling, transportation and erection, but
with equipment and storage areas. If the no quantification is given. Some guidance
construction site has limited open areas is provided for the application of load fac-
within its boundaries, the contractor may tors for dead loads, dynamic effects
need to mobilize the same equipment (impact) and wind, but specific load com-
numerous times to and from the site as binations are not explicitly defined.
construction progresses. These multiple Construction loads that should be evaluat-
mobilization costs could make a longer ed during the design include deck form-
span or more complex structure more eco- work, overhang formwork and brackets,
nomical than a structure that is the most screed rail loads, walkways, handrails, con-
economical based on material cost alone. struction live loads, screed live loads, wind
During the design process the bridge loads on the structure and equipment, and
designer must be cognizant of the issues any other anticipated loads specific to the
that cause contractors to increase their cost particular bridge being designed. In addi-
without adding value. If the bridge design- tion, permanent loads, such as the weight
er properly addresses these potential con- of the uncured deck concrete, need to be
straints and adjusts his design to minimize considered in combination with the con-
or eliminate their impact, the most cost struction loads.
effective bridge solution will be realized. Construction equipment loads can be esti-
mated based on bridge construction meth-
DESIGN ods typically used by contractors in the
CONSIDERATIONS region. Construction equipment could
consist of power screeds used for concrete
Various factors must be evaluated by the
deck placement, work bridges used to sup-
bridge designer to ensure the con-
port personnel performing deck placement
structability of the bridge. In the following
activities, bridge-mounted erection sys-
paragraphs, basic design topics dealing
tems (used more often in large, specialized
with construction loads, deck placement,
bridge construction), bridge-supported
stability, and member fit-up are discussed
concrete delivery systems, etc. The antici-
as they relate to construction of the bridge.
pated equipment loads should be deter-
In addition, a brief overview of erection
mined for each individual bridge based on
engineering and erection drawings is pro-
bridge type, member size, site location,
vided. All assumptions made during the
etc. For example, a typical I-girder bridge
design relating to construction loads and
would usually be subjected to only screed
construction methods should be docu-
and work bridge loads.
mented on the drawings for the contractor
to use in developing his/her detailed con- Wind loads during construction can be one
struction plans. of the most critical aspects to evaluate for
conventional girder bridges, since the con-
Construction Loads crete deck is typically used to transmit
The AASHTO LRFD Bridge Design these force effects back to the support loca-
Specifications (Specifications)(2) do not com- tions. Until the deck is placed and cured,
pletely address the loadings that should be the individual girders must be capable of
considered during construction of steel transmitting these loads back to the sup-
bridges. Requirements for deck placement ports through lateral flange bending. If the
sequences and overhang deck brackets are girders are not capable of resisting the
supplied, but other conditions are not. wind loads on their own, a permanent

13-8 DESIGN FOR CONSTRUCTABILITY


lateral bracing system or another tempo- from the bridge, temporary safety lines
rary system designed to resist these loads and supports, temporary shielding to pro-
must be provided. The magnitude of the tect traffic below the bridge, overhang
wind loads must be evaluated based on brackets, temporary hand rails, screed rails,
site specific data. The specific data needed and form work. Examples of permanent
to determine appropriate wind loads attachments include inspection walkways
include the friction velocity, friction length and handrails, utilities, etc.
and wind velocity based on the bridge Site considerations that could be evaluated
location and the height of the structure depending on geographic location, in
(see Article 3.8.1 of the Specifications). If addition to the wind loads previously
this data cannot be obtained, the design described, relate to the effects of ice and
wind velocity could be estimated from snow during construction.
bridge crossing information. For example,
if a typical girder bridge is being designed The operational importance of the bridge
over a stream, a design wind velocity of 70 as it relates to construction should be con-
mph may be appropriate for use. On the sidered based on location. For example, if
other hand, if the same bridge is being the bridge site is located in a highly popu-
designed over an active freeway, a design lated urban area where pedestrian and
wind velocity of 80 mph may be more vehicular traffic on or under the bridge will
appropriate. be at risk due to construction activities, a
higher level of safety may be necessary to
Once the design wind velocity is deter- minimize the potential for injury. The steps
mined, the design wind pressure is calcu- used to account for this in the design could
lated using equation (3.8.1.2.1-1) of the include a blanket increase in the impor-
Specifications. tance factor (ηi, see Chapter 9 for addition-
PD=PB VDZ2/10,000 al discussion(5)) that will result in a higher
Some owners give the minimum design level of safety through the use of greater
wind pressure to use in the design. One loads, or localized provisions incorporated
state mandates the use of 25 psf as a stan- into the design of protection systems adja-
dard and 30 psf for bridges over traffic. cent to the areas of concern. Good engi-
Since these values relate to maximum neering judgment must to be used to
design wind velocities during construction determine the site-specific effects associat-
(after erection), lower values should be ed with each bridge and the appropriate
used to evaluate member stress and stabil- level of design to be performed.
ity during the erection of the bridge. Construction live loads should also be con-
Reasonable estimates must be made to sidered in evaluating the adequacy of the
correspond with the probable wind veloci- bridge. This loading is intended to cover all
ty during the short erection timeframe. miscellaneous equipment and personnel
Typical wind velocity ranges for setting ini- that cannot easily be quantified at the time
tial girders are 25-50 mph for highway of design. Often a blanket allowance of 10
bridges. Additional information on wind psf is used to account for these loadings.
loads can be found in ASCE/SEI 7-05(3) and Load combinations must be evaluated to
AASHTO’s Guide Design Specifications for capture all critical conditions during con-
Bridge Temporary Works(4). struction of the bridge after a thorough
Temporary and permanent attachments to determination of all anticipated construc-
the bridge should be evaluated and includ- tion loads is complete. In the 2005 inter-
ed in the dead load effects. Examples of ims, Article 3.4.2 of the Specifications calls
various types of temporary attachments for the use of Strength Load Combinations
include temporary scaffolding suspended I, III and V during construction. In evaluat-

STEELBRIDGEDESIGNHANDBOOK 13-9
ing these combina- bridge is being loaded with the majority of
tions, engineering its dead load while only discrete bracing
judgment must be stabilizes the most vulnerable top compres-
exercised to ensure sion flange components. The following
that the maximum paragraphs describe typical interior deck
feasible forces are forming, standard overhang bracket sys-
being evaluated. tems, deck finishing machines (screeds),
Some sample load deck pouring sequences, and considera-
combinations are: tions for half-width construction.
SIP Forms Attached to a Top
γp(DC+DW) + 1.5(CEL+CLL) for STR I Deck forming between interior girders typi-
Flange in a Tension Region.
Where: cally consists of corrugated metal stay-in-
place (SIP) members attached to the top
- γp is the load factor for dead load 0.9 flange of the girders. The SIP forms are sup-
min and 1.25 max (see Chapter 9 for ported by angles attached to the edges of
a detailed explanation). the girders’ top flange using a strapping
- DC includes all dead load associated detail spanning the flange (in tension and
with the bridge members and all form stress reversal areas) or by a direct weld to
work, attachments, deck, etc. the flange (in compression areas). The SIP
- DW includes all utilities. forms are usually attached to the angles
using self tapping screws. Typical SIP forms
- CEL includes all construction equip- can be used with girder spacings up to
ment loads such as screeds, etc. approximately 14 feet. SIP forms are avail-
- CLL is the construction live load. able in a wide variety of types and sizes to
γp(DC+DW) + 1.5(CEL) + 1.4(WS) for STR III meet the individual needs associated with
each bridge. There are numerous suppliers
Where: of the products, making them widely avail-
- WS is the wind on the exposed height able for use. For additional information
of the structure including all forming. about SIP forms, see the Steel Deck
γp(DC+DW) + 1.5(CEL) + 1.35(CLL) + Institute website at www.sdi.org.
0.4(WS) +1.0(WCEL) for STR V As an alternative to SIP forms, traditional
Where: removable formwork can be utilized
between the flanges of the interior girders.
- WCEL is the wind on construction Removable formwork usually consists of
equipment (screeds, etc). plywood attached to timber supports or
If there are varying stages of structural con- prefabricated metal forms, either of which
figuration associated with the design, addi- would be held in position by blocking
tional construction load combinations down to the bottom flanges or hangers
should be evaluated to ensure that all per- attached to the top flanges. Although this
tinent conditions are checked. For exam- method of forming is more labor-intensive,
ple, if the girders behave as simply support- some owners require inspection access to
ed for self weight and continuous for all the underside of the concrete deck or are
other dead and construction loads, then concerned about consolidation of the con-
both conditions should be evaluated using crete in the SIP form valleys. To mitigate
the appropriate loadings and capacities. this concern some owners permit the
placement of Styrofoam strips in the val-
Deck Placement leys. This has an added benefit since it
Typically, the most critical stage in the con- lightens the deck dead load.
struction of girder bridges occurs during
Overhang brackets are typically used to sup-
placement of the concrete deck, since the
port deck forms in the area beyond the

13-10 DESIGN FOR CONSTRUCTABILITY


edges of the fascia girders. Standard over- eral flange bending effect, the designer
hang brackets consist of three steel mem- must also include all vertical loads associat-
bers connected in a triangular shape that ed with the overhang bracket into the
are suspended from the top flange and capacity checks for the exterior girders.
supported by the girder web. The brackets Detailed information on the required
are normally spaced on three to four foot capacity checks can be found in the
centers along the length of the bridge and Specification. For additional information on
support traditional wood forming. In addi- overhang brackets and bridge deck form-
tion to supporting the form work for the work, see the AASHTO Construction
deck overhang, the brackets usually carry Handbook for Bridge Temporary Works(6).
an access walkway and screed rail to allow Deck finishing machine (screed) loads can
for deck placement machinery and person- also have a dramatic effect in the design of
nel. The overhang brackets can create sig- the fascia girders, since the loads are typi-
nificant lateral flange bending forces in the cally supported by the overhang brackets
top and bottom flanges of the fascia girder as previously described. Therefore, an esti-
due to the eccentricity of the loads and the mate of the machine loads should be per-
hanger connection to the flange. Since formed and included in the capacity evalu-
these lateral flange bending loads can ations. A good estimate of the machinery
often control the design of the top flange, weight can be made by simply selecting an
the designer must calculate the magnitude
of these loads and verify the capacity of the
girder. The Specifications provides a
method for determining the lateral flange
bending moments in the commentary of
Article 6.10.3.4. If the web depth is such
that the bottom of the overhang bracket
would likely rest against the web a signifi-
cant distance above the flange to web
intersection, constructability stiffeners are SCREED
often shown on the plans for the fascia
girders to resist the bracket loading. The WALKWAY
contractor could choose to thicken the
web to avoid the additional stiffeners or SCREED RAIL
perform a refined analysis to verify the
effects on the web, but discussion with the
engineer is essential. In addition to the lat-

HANGER

OVERHANG BRACKET

Above and right: FASCIA GIRDER


Typical Overhang Bracket.

STEELBRIDGEDESIGNHANDBOOK 13-11
bridge replacement or rehabilitation proj-
ects where traffic must be maintained on
the bridge throughout all construction
stages. A simple example would be the
replacement of an existing bridge that car-
ries two 12-foot wide travel lanes, two 12-
foot wide outside shoulders, and a single
turning lane. The ideal condition would be
to maintain a single lane of traffic in each
direction on half of the existing bridge
while the other half is removed and
replaced. Once this first stage of construc-
Sample Deck Placement appropriately sized piece of equipment tion is complete, traffic would be trans-
Sequence. based on the width of the bridge and the ferred onto the new bridge while the
placement sequence developed for the remaining portion of the existing bridge is
design. With this information, actual removed and replaced. The difficulty asso-
weights can be readily obtained from local ciated with this procedure lies in the con-
equipment suppliers in the region of the nection of the first half of the new structure
bridge. to the second half; particularly how to place
the concrete deck in the connecting region.
A deck placement sequence must be devel-
One method of performing this work is to
oped by the designer to ensure that the
build most of the second half of the bridge
girders are capable of supporting the
independently from the first by omitting
applied loads during each stage of place-
the cross-frames connecting the two. In
ment. In Article 6.10.3.4 of the
doing this, the second half of the bridge
Specifications and its commentary explicit
would be erected and the deck placed up
direction is given regarding the type of cal-
to the centerline of the girder adjacent to
culations that must developed. An example
the half of the bridge carrying traffic. At this
of a typical deck placement sequence for a
point the cross-frames connecting the two
two-span continuous girder bridge would
independent structures into one would be
be as follows: First, place the concrete in
installed, and the closure deck placement
the positive moment portions of the spans
made. Many times the cross-frames con-
leaving a block-out at each end for installa-
nections are prepared only with shop
tion of the expansion devices (placement
drilled holes for connection to first half of
1). Note that all of the concrete in place-
the bridge. Once the cross-frames are erect-
ment 1 must remain plastic until the pour
ed and connected to the first half of the
is complete. Allow the concrete to cure for
bridge, the bolt holes for the connection to
a specified time or until a certain strength
the second half of the bridge are field
is obtained (this requirement is usually
drilled. Typically the holes in the cross
established by the owner). Second, place
frame members are used as a drill template
the concrete in the negative moment
to field drill the holes in the stiffener plate.
region over the pier up to the concrete pre-
Performing the work in this fashion allows
viously placed during Stage 1 (placement
for proper fit-up of the steel girders and
2). Finally, install the expansion devices at
reduces the amount of “locked-in” forces
each abutment and place concrete in the
carried by the cross-frames connecting
block-outs (placement 3), thus finishing
across construction stages.
the concrete deck placement. Construction
of the protective concrete barriers finishes
Stability
the deck.
Stability of the girders during erection
Half-width staged construction is typical for and subsequent construction stages is of

13-12 DESIGN FOR CONSTRUCTABILITY


Existing New

Second New Half


First New Half

Fully Connected New Bridge

primary importance to the designer since it tances. Instead, the spacing requirement Half-width Construction
is typically the driving factor in the selec- was removed to allow the designer flexibil- Staging.
tion of crossframe spacings, top flange ity in establishing reasonable equal spacing
width and lateral bracing requirements. for the crossframes (on the order of 20-30
The following paragraphs discuss stability feet) without the arbitrary maximum that
of girders and how it relates to cross- often results in an additional line of cross-
frames, lateral bracing, temporary bracing, frames simply to comply with the code.
uplift at supports, bearing selection, and Crossframe spacing is established to avoid
construction staging. flange buckling and limit the amount of
Crossframes are typically considered sec- lateral flange bending based on the pro-
ondary bracing members in girder bridges portions of the girder and geometric layout
(with the exception of highly skewed and of the bridge.
horizontally curved bridges) where the pri- The configuration of the individual mem-
mary function is to transmit wind forces bers that make up a crossframe can take on
from the bottom flange into the concrete various shapes depending on the ratio of
deck in the completed bridge and to pro- the girder spacing to depth. Typical cross-
vide bracing points for the girder flanges frame configurations are K-frames, X-
during construction (and in the final con- frames, solid bent plates, rolled sections,
figuration for bottom flanges in the nega- plate girders, inverted K-frames, and X-
tive moment regions). The Specifications frames with horizontal struts. For a more
eliminated the limits on maximum spacing detailed explanation of cross-frames and
for crossframes found in previous specifica- their practical uses, see Chapter 8.
tions. Instead, it is up to the designer to Once a cross-frame spacing and configura-
establish the spacing and properly design tion are determined, the girders lateral
the girders for the forces accordingly. By stresses must be checked for construction
removing the arbitrary 25 foot maximum loads and permanent wind loads to deter-
spacing requirement from the code, it was mine if the results are acceptable. If the lat-
not the intent of the code writers to have eral effects control the design of the
designers place cross-frames at large dis- flanges, the cross-frame spacing should

STEELBRIDGEDESIGNHANDBOOK 13-13
probably be reduced provide stability during the construction of
to allow for a balance the bridge. For example, many owners per-
between the vertical mit the use of temporary external cross-
and lateral bending frames between boxes during the con-
effects. One rule of struction of steel tub girder bridges. The
thumb commonly advantages of using temporary cross-
used is to limit the lat- frames are that: (1) the aesthetics of the
eral flange bending bridge, when viewed from below, are max-
stresses to around imized with the completed bridge having
0.5Fy. clean, unobstructed lines; (2) the details of
Temporary Top Flange Lateral bracing is typically used in longer the members are simplified, since they do
span structures where the lateral flange not need to meet long-term fatigue and
Stiffening Truss.
bending stresses and/or lateral deflection maintenance criteria; and (3) the flexibility
cannot be effectively controlled by flange given to the contractor regarding erection
width and cross-frame spacing. The need methods is also maximized. There are also
for lateral bracing may often be dictated by some drawbacks to the use of temporary
the client. One owner requires designs that cross-frames: (1) the members can be diffi-
do not use lateral bracing for spans under cult to remove, since crane access is limit-
200 feet, allows it to be investigated for ed due to the concrete deck being in place;
spans between 200 and 300 feet, and (2) the contractor must remobilize equip-
requires it on spans over 300 feet. The ment and personnel to remove the mem-
bracing usually consists of WT sections and bers long after their role on the project is
is normally connected directly to either complete; and (3) if the bridge is redecked
girder flange. The lateral bracing creates a in the future, the temporary cross-frames
truss system between adjacent girders with must be reinstalled. The advantages and
the girder flanges acting as the chords, and disadvantages of using temporary bracing
the bracing members and cross-frames act- in a situation such as this must be thor-
ing as the diagonals and “verticals”, oughly investigated before the decision is
respectively. The optimum location (top or made to incorporate its use.
bottom flange) and configuration of the Another situation where temporary bracing
bracing has been debated for years and no could be used is in the erection of long
explicit conclusions have been determined. span I-girder bridges. An example would
The only definitive observation that can be be the use of a temporary stiffening truss
made is that lateral bracing dramatically attached to the top flange of a single I-
increases the lateral stiffness of the bridge girder to stabilize it until a second line of
regardless of location and configuration. girders is erected and attached with cross-
Often the largest drawback in the use of frames to form a stable system. In this
lateral bracing is the need to design the instance, the use of the temporary truss
bracing connections for vertical girder allows the contractor flexibility in the use of
bending effects. Frequently, the designer the erection equipment to perform girder
will utilize the bracing for final wind and picks without the need for addition hold
construction effects and allow the connec- cranes. One drawback to this scenario is
tions to “slip” for vertical capacity determi- the cost associated with fabricating and
nation. This is accomplished through the assembling the truss. Again, the benefit of
use of oversized holes in the slip critical needing fewer cranes needs to be weighed
connection design. For additional informa- against the cost of the additional material.
tion on lateral bracing considerations, see Uplift at support locations can lead to design
Chapter 8. issues during the construction stages as
Temporary bracing is sometimes utilized to well as in the final configuration of the

13-14 DESIGN FOR CONSTRUCTABILITY


bridge. Typical girder bridges are propor- cific permanent bearing type used, the
tioned to ensure that uplift does not occur type of substructure, the bridge type, the
at the support locations in the final config- size of the bridge, etc. Many times a typi-
uration. Uplift is usually only a concern cal girder bridge is outfitted with blocking
when dealing with bridges that contain around the bearing to provide the neces-
sharply skewed supports, tight horizontal sary support or, if necessary, a system of
curvature, or incorporate complex bridge temporary cables is used to anchor the
types. If a bridge configuration results in girder to the substructure unit. To ensure
uplift, a traditional design solution is to proper fit-up, a survey of the horizontal
attach the bridge to the substructure unit and vertical alignment of the bearings
using a tension link. Although this should be made prior to erection.
approach has been used successfully for Construction staging must be evaluated by
decades, it usually incorporates a fatigue- the designer to ensure stability of the
sensitive detail into the bridge. As a result, bridge during all phases of the initial deck
owners now typically require the designer placement sequence, the conditions antici-
to resist uplift effects through the use of pated for the proposed future redecking
additional permanent dead load. This can scheme, and every stage associated with
be successfully accomplished by incorpo- half-width construction. For example, some
rating full-depth concrete diaphragms over owners require five girder lines when four
the support location or, if necessary, by would suffice, specifically to accommodate
placing permanent counterweights (usual- future redecking schemes. As previously
ly a large volume of concrete) at the sup- mentioned, Article 6.10.3.4 of the
port in question. During the construction Specifications describes the explicit method
of the bridge, uplift can occur at various of performing these design checks.
stages of the erection process depending
on the methods being used. In these situa- Fit-up
tions, the uplift can be resisted through the Fit-up of the steel bridge members is a crit-
use of temporary counterweights posi- ical component in the overall success of a
tioned over the support or temporary project. The designer must be able to
cables anchored into the foundations. clearly convey to the fabricator and erector
Temporary counterweights are commonly the intent of the design as it relates to bolt-
used when bridges are erected using the ing and pinning, camber, bolted field
“cantilever method” as previously splices, and differential deflections. The use
described. of oversize holes to facilitate fit-up is not
Bearing selection is normally based on the recommended. In the following para-
final bridge configuration and the needs graphs some important aspects relating to
associated with intended long term per- these topics are discussed.
formance of the bridge. Quite often the Bolting and pinning of connections requires
result is a single line of fixed bearings in the that proper procedures be followed.
bridge with the remainder of the bearings NCHRP Synthesis 345, “Steel Bridge
being either free (unrestrained in all direc- Erection Practices” recommends that the
tions) or guided (normally restrained in the procedures might contain the following:
transverse direction). During erection of
• Initial pinning and bolting should consist
the bridge, such an arrangement can cre-
of filling the holes in the connections
ate complications since the permanent
with 25% pins and 25% bolts and the
support locations are normally used to pro-
bolts at least snug tightened before
vide stability. Therefore, the permanent
releasing the crane and having the adja-
bearings are often augmented to provide
cent girders erected.
the necessary fixity during erection. The
type of modification depends on the spe- • After the cranes are released, the balance

STEELBRIDGEDESIGNHANDBOOK 13-15
of the holes in the connections should be locations may need to be designed and
filled with snug-tight bolts. incorporated into the design drawings. It
• Final tightening of the bolts to installa- should be noted in the design drawings
tion tension should not start until a con- that field splice locations can be eliminated
tinuous line or at least adjacent spans by the contractor. This will allow the con-
have been erected and the vertical and tractor to tailor the field piece size and
horizontal alignment has been verified. number of splice locations to his/her erec-
tion scheme, thus minimizing the cost of
• Pins should not be removed from the the bridge.
connection until after the previous step
has been accomplished. Differential defections between adjacent
girder lines can result from severe skew,
These recommendations are for typical horizontal curvature, staged construction,
bridges, for large or complex structures or extreme load imbalance. Many of the
the number of bolts and pins required issues associated with differential deflec-
need to be determined by design for each tions result from lack of communication
connection. among the designer, fabricator and erector.
Cambers are values prescribed by the One way to describe the effect of differen-
bridge type, member size, and geometry tial deflection is through the example of a
for each particular structure. The cambers severely skewed bridge: A two-span multi-
are derived by the designer to ensure that girder bridge has a skew angle of 70
the bridge achieves its final design geome- degrees between the center line of sup-
try after all dead loads are applied. A more ports and a line normal to the bridge cen-
detailed explanation of cambers for girder terline. With a skew angle this severe, the
bridges is provided in Chapter 8. For other intermediate cross-frames would be
larger bridge types the cambers can have a detailed perpendicular to the girder webs.
dramatic effect on the overall behavior of Therefore, one end of a particular cross-
the bridge. For example, arch bridges must frame may be located at the 0.4L point of
be properly cambered to ensure that the Girder 1 and the other end at the 0.5L
axis of the arch closely conforms to the point of Girder 2, where L is the span
dead load thrust line, since this is a stan- length. A comparison of the dead load
dard assumption in the design of the arch deflections at these two locations would
members. If the cambers are incorrect, sig- show that Girder 2 deflects much more
nificant vertical bending will be generated than Girder 1. If the cross-frames are not
in the arch rib due to the dead load, sub- properly detailed to account for the differ-
jecting the bridge to loads that were not ential deflection between Girders 1 and 2,
accounted for in the design. See Article the erector may not be able to properly
6.7.2 of the Specifications for camber install the member.
requirements.
If the girders’ webs are detailed to be verti-
Bolted field splices on girder bridges are cal under full dead load, then the girders
located to separate the individual girders must be erected with a predetermined
into manageable pieces in terms of both twist (out-of-plumbness) such that when
size and weight. See Chapter 8 for a gener- the erection is complete and all dead loads
al discussion regarding splice locations and are applied (deck, barriers, etc) the differ-
hauling considerations. The designer ential deflection between cross-frame ends
should also be cognizant of member piece will “roll” the girder into its final vertical
weights, since other concerns such as site position. For this condition, the designer
access could limit the maximum member must clearly state on the drawings that the
size. If member size is limited for concerns intent is to detail and fabricate the mem-
other than hauling, additional field splice bers such that the webs will be vertical in

13-16 DESIGN FOR CONSTRUCTABILITY


their full dead load position, and the erec- erector must develop a clear detailed pro-
tor needs to realize that the girders need to cedure for assembling the structure. Based
be erected with the predetermined twist. on a recent survey of bridge owners, very
For curved girders the key element in deal- few require the erector to develop a
ing with differential deflection is to provide detailed erection procedure. But such a for-
consistent detailing between all compo- mal procedure is a critical step in the con-
nents in the bridge. The Second Edition of struction of the bridge and should be man-
the AASHTO LRFD Bridge Construction dated. If the owner does not have standard
Specifications(7) states, “Unless otherwise requirements, the designer should develop
specified in the Contractor’s construction a contract provision requiring the erector
plan, fit-up shall be assumed to be per- to develop a plan for each specific project.
formed under the no-load condition”. The procedure must include detailed draw-
Therefore, unless the design drawings ings and written descriptions for each step
explicitly define a different condition, the necessary to complete the erection. In
fabricator and erector should construct the addition, complete calculations performed
bridge as though it is in the no-load condi- by a registered professional engineer must
tion. Good engineering judgment must be be developed for each stage of the process
used in determining the appropriate condi- to ensure that the permanent bridge mem-
tion to specify for each bridge. bers are not overstressed and stability is
maintained.
Bridges that are both curved and skewed
are beyond the scope of this document Provisions for erection procedures and
since this configuration is not currently erection drawings can be found in the
covered in the Specifications, and no rec- Second Edition of the AASHTO LRFD Bridge
ommendations are available. Additional Construction Specifications. In addition, the
research needs to be performed to support AASHTO/NSBA Steel Bridge Collaboration
current theories. Task Group 10 is developing a document
entitled “Steel Bridge Erection Guide
For additional information on differential Specification” that covers erection calcula-
deflections see Section 1.6 of the tions and drawings in greater detail.
“Guidelines for Design for Constructability”
document G12.1-2003 by the AASHTO/ The latest information for all of the
NSBA Steel Bridge Collaboration. Collaboration documents can be found on
the National Steel Bridge Alliance website
Erection Engineering and Drawings at www.steelbridges.org.
After award of the erection contract, the

REFERENCES
1. National Steel Bridge Alliance, Steel Bridge Design Handbook, Chapter 8 Stringer Bridges -
Making the Right Choices, 2007
2. AASHTO LRFD Bridge Design Specifications, Third Edition 2004.
3. ASCE/SEI 7-05; American Society of Civil Engineers, Minimum Design Loads for Buildings and
Other Structures, 2006.
4. AASHTO Guide Design Specification for Bridge Temporary Works, 1995
5. National Steel Bridge Alliance, Steel Bridge Design Handbook, Chapter 9 Loads and Load
Combinations, 2007
6. AASHTO Construction Handbook for Bridge Temporary Works, 1995
7. AASHTO LRFD Bridge Construction Specifications, Second Edition, 2004.

STEELBRIDGEDESIGNHANDBOOK 13-17

Vous aimerez peut-être aussi