Académique Documents
Professionnel Documents
Culture Documents
Design for
Constructability
National Steel
Bridge Alliance STEELBRIDGEDESIGNHANDBOOK
Disclaimer
All data, specifications, suggested practices, and drawings presented herein, are based on the best
available information and delineated in accordance with recognized professional engineering princi-
ples and practices, and are published for general and procedural information only. Procedures and
products, suggested or discussed, should not be used without first securing competent advice respect-
ing their suitability for any given application.
Publication of the material herein is not to be construed as a warranty on the part of the National Steel
Bridge Alliance - or that of any person named herein - that these data and suggested practices are suit-
able for any general or particular use, or of freedom from infringement on any patent or patents.
Further, any use of these data or suggested practices can only be made with the understanding that
the National Steel Bridge Alliance makes no warranty of any kind respecting such use and the user
assumes all liability arising therefrom.
Table of Contents
Introduction........................................................................................................1
General ..............................................................................................................1
Equipment ....................................................................................................1
Erection ........................................................................................................3
Site Considerations .......................................................................................7
STEELBRIDGEDESIGNHANDBOOK 13-1
Mobile Lattice Boom Crane Lattice Boom Crawler Crane Lattice Ringer Crane Tower Crane
where pick heights are high. Through the unfinished open terrain and where pick
use of telescoping hydraulic outriggers and heights are high (up to 400 feet). Typically,
self-assembly capabilities, the set-up and once assembled the crane is immobile due
tear down is quick compared to other to the track work used to support the mas-
crane types, generally one to two days for sive counterweights. A typical application
assembly of multiple trailer loads. In addi- would be the erection of a new bridge over
tion, the reach is versatile with 360 degree a wide river or bay where the crane could
rotational capability. be mounted onto a barge. By mounting
It should be noted that mobile lattice the crane on a barge, it becomes mobile
boom cranes and mobile hydraulic cranes increasing it versatility and ultimately mak-
cannot move once the pick is lifted. ing it more productive. The set-up and
tear-down is long and labor intensive due
Lattice boom crawler cranes are used for to the number of components that must
light-to medium-weight picks up to 300 be site-assembled to meet hauling
tons. These cranes are used where the site restrictions.
is typically unfinished terrain and where
pick heights are high (up to 400 feet). A Tower cranes are used for lightweight picks
typical application would be in the erection up to 20 tons. These cranes are used where
of a new bridge over a stream valley. These no mobility is required and excessive verti-
cranes come in a wide variety of sizes such cal heights must be overcome. A typical
that the appropriate crane can be used for application would be in the construction of
the given pick weight and height require- a tower for a suspension or cable stayed
ments. The set-up and tear-down is long bridge. These cranes come in a wide vari-
and labor intensive due to the number of ety of sizes to meet the need for a particu-
components that must be site-assembled lar height and reach. The setup and tear-
to meet hauling and site access restrictions. down are extremely long due to the assem-
Once assembled, the mobility and reach is bly process. Quite often, a separate foun-
versatile with 360 degree rotational capa- dation must be constructed to support the
bility. In addition, crawler cranes are able to base of the tower leg. Once in place the
travel with the load lifted. crane can be highly productive in deliver-
ing materials to the elevation required.
Lattice ringer cranes are used for heavy- Some models come with self jacking tower
weight picks up to 1,400 tons. These legs that allow the crane to adjust its
cranes are used where the site is typically height as construction progresses.
Along with these different crane types, var- ture and facilitate removal.
ious erection accessories are typically used Temporary pier brackets are often used in
to maximize the crane’s capabilities and the erection of river/water crossings to
function. Some of these accessories are increase the number of brace and reaction
described in the following paragraphs. points provided by the permanent pier.
Temporary Bent
Crane mats are series of timber or steel Pier brackets are typically comprised of a
members assembled in sections beneath series of steel members assembled into a
the crane to provide a level sound base to frame and temporarily attached to the face
support the crane during lifting opera- of the permanent pier. The configuration
tions. Most often large timbers are used, can vary greatly based on the geometry of
since they are widely available, inexpensive the permanent pier and the intended func-
and easily transported and assembled. If tion of the bracket. The brackets allow
existing ground conditions are poor (such individual members to be erected onto the
that proper support of the crane would be pier with the use of a single crane. The
marginal), the use of a more complex sys- erected member is attached to the perma-
tem of steel framing or other custom nent bearing and to the pier bracket for
designed site-cast crane pad could be stability during the erection of the remain-
implemented to span the poor soils. ing portion of the spans.
Temporary bents are often used in conjunc- Hydraulic jacks are often used in combina-
tion with cranes to aid in the erection tion with the temporary bents and pier
process. Standard scaffolding is widely brackets to allow for flexibility in vertical
available for use in creating these tempo- and horizontal location of the erected
rary supports. Each section of scaffolding is member. These jacks are readily available in
assembled into a geometric configuration a wide variety of sizes and capacities to
that can achieve the required elevation meet the requirements of each particular
and load carrying capacity needed for situation. Some other uses for hydraulic
each individual situation. Temporary bents jacks include longitudinally aligning a con-
are commonly used where it is necessary tinuous multi-span girder bridge with mul-
to provide support for a longer period of tiple fixed piers to ensure proper bearing/
time during complex erection and when pier alignment; aligning the ends of long
foundation conditions are favorable, due span continuous trusses and simple span
to shallow rock or good soil. Other arches to ensure proper fit-up for the clo-
instances where temporary bents are used sure members; and launching completed
include long-span bridge erection, and/or bridges into their final location as described
a situation where fit-up is to be at the “no in the erection section that follows.
load” condition and where site constraints
limit the placement of cranes. It is impor- Erection
tant to note that the temporary bent must The art of bridge erection has evolved over
be able to be lowered once erection is time to keep pace with technological
complete to transfer the load to the struc- advancements in machinery and accessories.
STEELBRIDGEDESIGNHANDBOOK 13-3
Even with today’s weight and capacity of the girder, the erec-
advanced computer tion crane could use either a single lift
controlled equipment, point located at the center of gravity of the
the most important member or two lift points centered about
aspect of bridge erec- the center of gravity utilizing a spreader
tion lies in the experi- beam. Based on the overall size and com-
ence of the personnel plexity associated with the bridge erection,
performing the work. the individual girder erection could incor-
Since the objective of porate the use of temporary bents, tempo-
I-Girder Erection Using a safely assembling the rary pier brackets or hold cranes to provide
Spreader Beam. structure into its stability to the member until a sufficient
required configuration number of girder lines are erected and con-
remains unchanged, nected via permanent cross frames or
the experience neces- diaphragms to form a stable system.
sary to achieve this Box girder erection is often accomplished
goal is paramount to using a pair of erection cranes working in
success. The following tandem during the lift. The cranes are typ-
paragraphs discuss dif- ically rigged with a spreader beam that
ferent rigging contains two beam clamps each. The beam
schemes that are tradi- clamps are attached to the top flanges of
tionally used in bridge the box girder near the ends of the mem-
Box Girder Erection Using
erection along with ber. Unlike I-girders, an individual box gird-
Two Crawler Cranes.
various methods of er may be stable once it is erected onto its
erection available for I- permanent supports, due to the internal
girder, box girder, bracing system.
truss, arch and cable
supported structures. An alternate girder erection method that
has been gaining popularity consists of
The rigging of a mem- launching the completely assembled
ber in preparation for bridge longitudinally across the permanent
erection can take on supports. This method of erection can be
many forms based on utilized for both I-girder and box girder
the size, weight, bridges. To accomplish a girder launch, the
I-Girder Bridge Launching. geometry and capaci- superstructure is assembled on a roller sys-
ty of the individual member as well as the tem behind one of the abutments in seg-
size, capacity and location of the erection ments of sufficient length to maintain sta-
crane. In its simplest form, rigging could bility during the launching. Once a seg-
consist of a single vertical sling hooked to ment is assembled, hydraulic jacks are used
the crane and attached to the member to move the structure across the abutment
with a beam clamp or through the use of a until it reaches the first pier support. After
wire rope sling around the member. In a the girders are properly aligned on the first
more complex form, rigging could consist pier, additional segments are assembled on
of a multi-point erection frame attached to the roller system behind the abutment and
the member with beam clamps or slings the hydraulic jacks advance the structure
and lifted using multiple cranes attached at until it reaches the next pier. This launching
different locations along the frame. With process is continued until the entire struc-
both rigging options, tag lines attached to ture rests on its permanent supports. This
the ends of the member are used for hand erection procedure requires minimal equip-
guidance to ensure safe placement. ment to perform, but the girders must be
I-girder erection is often accomplished using specifically designed both globally and
a single erection crane. Based on the size, locally to handle the large forces generated
STEELBRIDGEDESIGNHANDBOOK 13-5
installation until the end pier or mid-span is
reached. This procedure is repeated for
each tower of the bridge. When two adja-
cent cantilever ends are completed, the
closure pieces are installed and the erection
is finished. This erection method is com-
mon, since all of the erection forces are
resisted by permanent bridge components.
Only simple beam and winch erection
equipment attached to the cantilever ends
or deck mounted derricks are necessary to
lift the members into place.
Suspension bridge erection is performed by
using the permanent bridge members for
support of the partially completed super-
structure. After the main towers are con-
structed and the main suspension cables
Arch Erection using Stay are strung, the superstructure erection
nantly used to span deep canyons (true
begins at the tower.
Towers and Cables. arch) or wide bodies of water (tied arch).
One method of erecting the deck members
Another method of true arch erection that
follows the cantilever scheme where mem-
has been employed uses the canyon walls
bers are erected directly at the tower and
to support the arch as a cantilever. With
attached using temporary supports. After
this method the arch is erected from each
the first members are stabilized, additional
spring line simultaneously towards the
pieces are cantilevered from each end in an
crown. As each arch member is erected it is
alternating fashion until the location of the
“tied” back into the canyon wall using a
first permanent suspender is passed. At this
temporary connection. The tie member
point, the first set of suspenders is installed
can be part of the permanent structure (as
to connect the cantilevers to the main
shown below) or a temporary member/
cable. Alternating cantilever erection of
cable used solely for erection support.
members continues along with suspender
Once the arch is closed and erection com-
installation until the end pier or mid-span is
plete, the temporary tie members/connec-
reached. This procedure is repeated for
tions are removed and the arch is self sup-
each tower of the bridge. In addition to
porting.
erecting the pieces as balanced cantilevers
Cable stayed bridge erection is performed at each individual tower, the erection of the
utilizing a permanent tower to support all pieces at each tower along the length of
loads during the assembly of the super- the bridge must be considered relative to
structure. After the majority of the tower each other to maintain the shape of the
Arch Bridge Erection using
construction is completed, the first super- main suspension cables. This will prevent
the Floor System as a
structure segments are erected directly at large, unbalanced horizontal forces in the
Erection Tie to the Canyon the tower using temporary supports main suspension cables at the towers.
Wall. attached to the tower’s cross strut. After
A second method of erecting the deck
the first segment is stabilized, additional
members is to load the main cables in a
members are cantilevered from each end in
manner to try and mimic the final geome-
an alternating fashion until the location of
try of the cable. With this method individ-
the first permanent cable stay is passed. At
ual pieces are supported from the main
this point, the first set of stay cables is
cables at specific locations prior to con-
installed. Alternating cantilever erection of
necting any of the pieces to each other.
segments continues along with stay cable
STEELBRIDGEDESIGNHANDBOOK 13-7
increase, and consequently his overall cost Some general statements are provided say-
would go down. ing that investigations should be made for
Another important consideration deals handling, transportation and erection, but
with equipment and storage areas. If the no quantification is given. Some guidance
construction site has limited open areas is provided for the application of load fac-
within its boundaries, the contractor may tors for dead loads, dynamic effects
need to mobilize the same equipment (impact) and wind, but specific load com-
numerous times to and from the site as binations are not explicitly defined.
construction progresses. These multiple Construction loads that should be evaluat-
mobilization costs could make a longer ed during the design include deck form-
span or more complex structure more eco- work, overhang formwork and brackets,
nomical than a structure that is the most screed rail loads, walkways, handrails, con-
economical based on material cost alone. struction live loads, screed live loads, wind
During the design process the bridge loads on the structure and equipment, and
designer must be cognizant of the issues any other anticipated loads specific to the
that cause contractors to increase their cost particular bridge being designed. In addi-
without adding value. If the bridge design- tion, permanent loads, such as the weight
er properly addresses these potential con- of the uncured deck concrete, need to be
straints and adjusts his design to minimize considered in combination with the con-
or eliminate their impact, the most cost struction loads.
effective bridge solution will be realized. Construction equipment loads can be esti-
mated based on bridge construction meth-
DESIGN ods typically used by contractors in the
CONSIDERATIONS region. Construction equipment could
consist of power screeds used for concrete
Various factors must be evaluated by the
deck placement, work bridges used to sup-
bridge designer to ensure the con-
port personnel performing deck placement
structability of the bridge. In the following
activities, bridge-mounted erection sys-
paragraphs, basic design topics dealing
tems (used more often in large, specialized
with construction loads, deck placement,
bridge construction), bridge-supported
stability, and member fit-up are discussed
concrete delivery systems, etc. The antici-
as they relate to construction of the bridge.
pated equipment loads should be deter-
In addition, a brief overview of erection
mined for each individual bridge based on
engineering and erection drawings is pro-
bridge type, member size, site location,
vided. All assumptions made during the
etc. For example, a typical I-girder bridge
design relating to construction loads and
would usually be subjected to only screed
construction methods should be docu-
and work bridge loads.
mented on the drawings for the contractor
to use in developing his/her detailed con- Wind loads during construction can be one
struction plans. of the most critical aspects to evaluate for
conventional girder bridges, since the con-
Construction Loads crete deck is typically used to transmit
The AASHTO LRFD Bridge Design these force effects back to the support loca-
Specifications (Specifications)(2) do not com- tions. Until the deck is placed and cured,
pletely address the loadings that should be the individual girders must be capable of
considered during construction of steel transmitting these loads back to the sup-
bridges. Requirements for deck placement ports through lateral flange bending. If the
sequences and overhang deck brackets are girders are not capable of resisting the
supplied, but other conditions are not. wind loads on their own, a permanent
STEELBRIDGEDESIGNHANDBOOK 13-9
ing these combina- bridge is being loaded with the majority of
tions, engineering its dead load while only discrete bracing
judgment must be stabilizes the most vulnerable top compres-
exercised to ensure sion flange components. The following
that the maximum paragraphs describe typical interior deck
feasible forces are forming, standard overhang bracket sys-
being evaluated. tems, deck finishing machines (screeds),
Some sample load deck pouring sequences, and considera-
combinations are: tions for half-width construction.
SIP Forms Attached to a Top
γp(DC+DW) + 1.5(CEL+CLL) for STR I Deck forming between interior girders typi-
Flange in a Tension Region.
Where: cally consists of corrugated metal stay-in-
place (SIP) members attached to the top
- γp is the load factor for dead load 0.9 flange of the girders. The SIP forms are sup-
min and 1.25 max (see Chapter 9 for ported by angles attached to the edges of
a detailed explanation). the girders’ top flange using a strapping
- DC includes all dead load associated detail spanning the flange (in tension and
with the bridge members and all form stress reversal areas) or by a direct weld to
work, attachments, deck, etc. the flange (in compression areas). The SIP
- DW includes all utilities. forms are usually attached to the angles
using self tapping screws. Typical SIP forms
- CEL includes all construction equip- can be used with girder spacings up to
ment loads such as screeds, etc. approximately 14 feet. SIP forms are avail-
- CLL is the construction live load. able in a wide variety of types and sizes to
γp(DC+DW) + 1.5(CEL) + 1.4(WS) for STR III meet the individual needs associated with
each bridge. There are numerous suppliers
Where: of the products, making them widely avail-
- WS is the wind on the exposed height able for use. For additional information
of the structure including all forming. about SIP forms, see the Steel Deck
γp(DC+DW) + 1.5(CEL) + 1.35(CLL) + Institute website at www.sdi.org.
0.4(WS) +1.0(WCEL) for STR V As an alternative to SIP forms, traditional
Where: removable formwork can be utilized
between the flanges of the interior girders.
- WCEL is the wind on construction Removable formwork usually consists of
equipment (screeds, etc). plywood attached to timber supports or
If there are varying stages of structural con- prefabricated metal forms, either of which
figuration associated with the design, addi- would be held in position by blocking
tional construction load combinations down to the bottom flanges or hangers
should be evaluated to ensure that all per- attached to the top flanges. Although this
tinent conditions are checked. For exam- method of forming is more labor-intensive,
ple, if the girders behave as simply support- some owners require inspection access to
ed for self weight and continuous for all the underside of the concrete deck or are
other dead and construction loads, then concerned about consolidation of the con-
both conditions should be evaluated using crete in the SIP form valleys. To mitigate
the appropriate loadings and capacities. this concern some owners permit the
placement of Styrofoam strips in the val-
Deck Placement leys. This has an added benefit since it
Typically, the most critical stage in the con- lightens the deck dead load.
struction of girder bridges occurs during
Overhang brackets are typically used to sup-
placement of the concrete deck, since the
port deck forms in the area beyond the
HANGER
OVERHANG BRACKET
STEELBRIDGEDESIGNHANDBOOK 13-11
bridge replacement or rehabilitation proj-
ects where traffic must be maintained on
the bridge throughout all construction
stages. A simple example would be the
replacement of an existing bridge that car-
ries two 12-foot wide travel lanes, two 12-
foot wide outside shoulders, and a single
turning lane. The ideal condition would be
to maintain a single lane of traffic in each
direction on half of the existing bridge
while the other half is removed and
replaced. Once this first stage of construc-
Sample Deck Placement appropriately sized piece of equipment tion is complete, traffic would be trans-
Sequence. based on the width of the bridge and the ferred onto the new bridge while the
placement sequence developed for the remaining portion of the existing bridge is
design. With this information, actual removed and replaced. The difficulty asso-
weights can be readily obtained from local ciated with this procedure lies in the con-
equipment suppliers in the region of the nection of the first half of the new structure
bridge. to the second half; particularly how to place
the concrete deck in the connecting region.
A deck placement sequence must be devel-
One method of performing this work is to
oped by the designer to ensure that the
build most of the second half of the bridge
girders are capable of supporting the
independently from the first by omitting
applied loads during each stage of place-
the cross-frames connecting the two. In
ment. In Article 6.10.3.4 of the
doing this, the second half of the bridge
Specifications and its commentary explicit
would be erected and the deck placed up
direction is given regarding the type of cal-
to the centerline of the girder adjacent to
culations that must developed. An example
the half of the bridge carrying traffic. At this
of a typical deck placement sequence for a
point the cross-frames connecting the two
two-span continuous girder bridge would
independent structures into one would be
be as follows: First, place the concrete in
installed, and the closure deck placement
the positive moment portions of the spans
made. Many times the cross-frames con-
leaving a block-out at each end for installa-
nections are prepared only with shop
tion of the expansion devices (placement
drilled holes for connection to first half of
1). Note that all of the concrete in place-
the bridge. Once the cross-frames are erect-
ment 1 must remain plastic until the pour
ed and connected to the first half of the
is complete. Allow the concrete to cure for
bridge, the bolt holes for the connection to
a specified time or until a certain strength
the second half of the bridge are field
is obtained (this requirement is usually
drilled. Typically the holes in the cross
established by the owner). Second, place
frame members are used as a drill template
the concrete in the negative moment
to field drill the holes in the stiffener plate.
region over the pier up to the concrete pre-
Performing the work in this fashion allows
viously placed during Stage 1 (placement
for proper fit-up of the steel girders and
2). Finally, install the expansion devices at
reduces the amount of “locked-in” forces
each abutment and place concrete in the
carried by the cross-frames connecting
block-outs (placement 3), thus finishing
across construction stages.
the concrete deck placement. Construction
of the protective concrete barriers finishes
Stability
the deck.
Stability of the girders during erection
Half-width staged construction is typical for and subsequent construction stages is of
primary importance to the designer since it tances. Instead, the spacing requirement Half-width Construction
is typically the driving factor in the selec- was removed to allow the designer flexibil- Staging.
tion of crossframe spacings, top flange ity in establishing reasonable equal spacing
width and lateral bracing requirements. for the crossframes (on the order of 20-30
The following paragraphs discuss stability feet) without the arbitrary maximum that
of girders and how it relates to cross- often results in an additional line of cross-
frames, lateral bracing, temporary bracing, frames simply to comply with the code.
uplift at supports, bearing selection, and Crossframe spacing is established to avoid
construction staging. flange buckling and limit the amount of
Crossframes are typically considered sec- lateral flange bending based on the pro-
ondary bracing members in girder bridges portions of the girder and geometric layout
(with the exception of highly skewed and of the bridge.
horizontally curved bridges) where the pri- The configuration of the individual mem-
mary function is to transmit wind forces bers that make up a crossframe can take on
from the bottom flange into the concrete various shapes depending on the ratio of
deck in the completed bridge and to pro- the girder spacing to depth. Typical cross-
vide bracing points for the girder flanges frame configurations are K-frames, X-
during construction (and in the final con- frames, solid bent plates, rolled sections,
figuration for bottom flanges in the nega- plate girders, inverted K-frames, and X-
tive moment regions). The Specifications frames with horizontal struts. For a more
eliminated the limits on maximum spacing detailed explanation of cross-frames and
for crossframes found in previous specifica- their practical uses, see Chapter 8.
tions. Instead, it is up to the designer to Once a cross-frame spacing and configura-
establish the spacing and properly design tion are determined, the girders lateral
the girders for the forces accordingly. By stresses must be checked for construction
removing the arbitrary 25 foot maximum loads and permanent wind loads to deter-
spacing requirement from the code, it was mine if the results are acceptable. If the lat-
not the intent of the code writers to have eral effects control the design of the
designers place cross-frames at large dis- flanges, the cross-frame spacing should
STEELBRIDGEDESIGNHANDBOOK 13-13
probably be reduced provide stability during the construction of
to allow for a balance the bridge. For example, many owners per-
between the vertical mit the use of temporary external cross-
and lateral bending frames between boxes during the con-
effects. One rule of struction of steel tub girder bridges. The
thumb commonly advantages of using temporary cross-
used is to limit the lat- frames are that: (1) the aesthetics of the
eral flange bending bridge, when viewed from below, are max-
stresses to around imized with the completed bridge having
0.5Fy. clean, unobstructed lines; (2) the details of
Temporary Top Flange Lateral bracing is typically used in longer the members are simplified, since they do
span structures where the lateral flange not need to meet long-term fatigue and
Stiffening Truss.
bending stresses and/or lateral deflection maintenance criteria; and (3) the flexibility
cannot be effectively controlled by flange given to the contractor regarding erection
width and cross-frame spacing. The need methods is also maximized. There are also
for lateral bracing may often be dictated by some drawbacks to the use of temporary
the client. One owner requires designs that cross-frames: (1) the members can be diffi-
do not use lateral bracing for spans under cult to remove, since crane access is limit-
200 feet, allows it to be investigated for ed due to the concrete deck being in place;
spans between 200 and 300 feet, and (2) the contractor must remobilize equip-
requires it on spans over 300 feet. The ment and personnel to remove the mem-
bracing usually consists of WT sections and bers long after their role on the project is
is normally connected directly to either complete; and (3) if the bridge is redecked
girder flange. The lateral bracing creates a in the future, the temporary cross-frames
truss system between adjacent girders with must be reinstalled. The advantages and
the girder flanges acting as the chords, and disadvantages of using temporary bracing
the bracing members and cross-frames act- in a situation such as this must be thor-
ing as the diagonals and “verticals”, oughly investigated before the decision is
respectively. The optimum location (top or made to incorporate its use.
bottom flange) and configuration of the Another situation where temporary bracing
bracing has been debated for years and no could be used is in the erection of long
explicit conclusions have been determined. span I-girder bridges. An example would
The only definitive observation that can be be the use of a temporary stiffening truss
made is that lateral bracing dramatically attached to the top flange of a single I-
increases the lateral stiffness of the bridge girder to stabilize it until a second line of
regardless of location and configuration. girders is erected and attached with cross-
Often the largest drawback in the use of frames to form a stable system. In this
lateral bracing is the need to design the instance, the use of the temporary truss
bracing connections for vertical girder allows the contractor flexibility in the use of
bending effects. Frequently, the designer the erection equipment to perform girder
will utilize the bracing for final wind and picks without the need for addition hold
construction effects and allow the connec- cranes. One drawback to this scenario is
tions to “slip” for vertical capacity determi- the cost associated with fabricating and
nation. This is accomplished through the assembling the truss. Again, the benefit of
use of oversized holes in the slip critical needing fewer cranes needs to be weighed
connection design. For additional informa- against the cost of the additional material.
tion on lateral bracing considerations, see Uplift at support locations can lead to design
Chapter 8. issues during the construction stages as
Temporary bracing is sometimes utilized to well as in the final configuration of the
STEELBRIDGEDESIGNHANDBOOK 13-15
of the holes in the connections should be locations may need to be designed and
filled with snug-tight bolts. incorporated into the design drawings. It
• Final tightening of the bolts to installa- should be noted in the design drawings
tion tension should not start until a con- that field splice locations can be eliminated
tinuous line or at least adjacent spans by the contractor. This will allow the con-
have been erected and the vertical and tractor to tailor the field piece size and
horizontal alignment has been verified. number of splice locations to his/her erec-
tion scheme, thus minimizing the cost of
• Pins should not be removed from the the bridge.
connection until after the previous step
has been accomplished. Differential defections between adjacent
girder lines can result from severe skew,
These recommendations are for typical horizontal curvature, staged construction,
bridges, for large or complex structures or extreme load imbalance. Many of the
the number of bolts and pins required issues associated with differential deflec-
need to be determined by design for each tions result from lack of communication
connection. among the designer, fabricator and erector.
Cambers are values prescribed by the One way to describe the effect of differen-
bridge type, member size, and geometry tial deflection is through the example of a
for each particular structure. The cambers severely skewed bridge: A two-span multi-
are derived by the designer to ensure that girder bridge has a skew angle of 70
the bridge achieves its final design geome- degrees between the center line of sup-
try after all dead loads are applied. A more ports and a line normal to the bridge cen-
detailed explanation of cambers for girder terline. With a skew angle this severe, the
bridges is provided in Chapter 8. For other intermediate cross-frames would be
larger bridge types the cambers can have a detailed perpendicular to the girder webs.
dramatic effect on the overall behavior of Therefore, one end of a particular cross-
the bridge. For example, arch bridges must frame may be located at the 0.4L point of
be properly cambered to ensure that the Girder 1 and the other end at the 0.5L
axis of the arch closely conforms to the point of Girder 2, where L is the span
dead load thrust line, since this is a stan- length. A comparison of the dead load
dard assumption in the design of the arch deflections at these two locations would
members. If the cambers are incorrect, sig- show that Girder 2 deflects much more
nificant vertical bending will be generated than Girder 1. If the cross-frames are not
in the arch rib due to the dead load, sub- properly detailed to account for the differ-
jecting the bridge to loads that were not ential deflection between Girders 1 and 2,
accounted for in the design. See Article the erector may not be able to properly
6.7.2 of the Specifications for camber install the member.
requirements.
If the girders’ webs are detailed to be verti-
Bolted field splices on girder bridges are cal under full dead load, then the girders
located to separate the individual girders must be erected with a predetermined
into manageable pieces in terms of both twist (out-of-plumbness) such that when
size and weight. See Chapter 8 for a gener- the erection is complete and all dead loads
al discussion regarding splice locations and are applied (deck, barriers, etc) the differ-
hauling considerations. The designer ential deflection between cross-frame ends
should also be cognizant of member piece will “roll” the girder into its final vertical
weights, since other concerns such as site position. For this condition, the designer
access could limit the maximum member must clearly state on the drawings that the
size. If member size is limited for concerns intent is to detail and fabricate the mem-
other than hauling, additional field splice bers such that the webs will be vertical in
REFERENCES
1. National Steel Bridge Alliance, Steel Bridge Design Handbook, Chapter 8 Stringer Bridges -
Making the Right Choices, 2007
2. AASHTO LRFD Bridge Design Specifications, Third Edition 2004.
3. ASCE/SEI 7-05; American Society of Civil Engineers, Minimum Design Loads for Buildings and
Other Structures, 2006.
4. AASHTO Guide Design Specification for Bridge Temporary Works, 1995
5. National Steel Bridge Alliance, Steel Bridge Design Handbook, Chapter 9 Loads and Load
Combinations, 2007
6. AASHTO Construction Handbook for Bridge Temporary Works, 1995
7. AASHTO LRFD Bridge Construction Specifications, Second Edition, 2004.
STEELBRIDGEDESIGNHANDBOOK 13-17