Académique Documents
Professionnel Documents
Culture Documents
net/publication/292031320
CITATIONS READS
5 221
3 authors, including:
Goran Dukic
University of Zagreb
22 PUBLICATIONS 136 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Goran Dukic on 31 March 2016.
The paper aims at presenting the use of simulation methods in shipbuilding production process
design. The basic design procedure principle is described, the main elements of the designing spiral, flow
diagrams and interrelations between individual activities determined. The flow diagram indicates a point
in which the simulation results affect the design flow.
A simulation program package was used to create a shipbuilding production process model. An
example of possibilities and methods of presentation of the program package outputs is given, and the
advantages of using simulation methods in the shipbuilding production process are described in a conclusion.
© 2008 Journal of Mechanical Engineering. All rights reserved.
Keywords: shipbuilding, process design, simulation methods
huge disturbance in production. Nedess et al. [8] Interdependence of elements is complex, and their
emphasize, among other things, that due to the fact relations in the design stage are open in both ways
that required space is a resource for time-critical until the final solution has been found.
processes with restricted capacities on shipyards Simulation in the shipbuilding process
and other shipbuilding companies. The space design consists of a preparatory and executive
allocation has to be handled as one of the most process.
important tasks in production planning, and this The preparatory procedure includes
aspect was implemented in the simulation module calculation of necessary model element and
for space allocation within the Simulation Toolkit creation of the production process and final product
Shipbuilding (STS). They also highlight the need models.
for special simulation modules for shipbuilding Executive part of the simulation procedure
industry. Steinhauer and Meyer-König [9] present starts with the experiment scenario, which defines a
importance of simulation and STS in sub-assembly research purpose, input data and analyses
and assembly stage planning. parameters, such as the equipment efficiency or
experiment duration. The procedure continues with
1 SHIPBUILDING PROCESS DESIGN experiment with a model and analysis of output data,
which results in conclusions. If the conclusions have
A shipbuilding process design consists of determined that the research were to continue with
elements each of which has its appropriate a new experiment, the procedure is repeated, i.e. the
requirements and limitations. Elements of the changes are made in product analysis, production
shipbuilding process design are production concept, process and material flow. These changes affect the
product analysis, material flows, building production process and final product models, which
dynamics, arrangement of working areas, process initiate a new experiment. When all the options are
flexibility, management, logistics, human resources researched and final conclusion brought, the results
and investment. Their interrelation is complex, and are presented to responsible management, which
the ultimate solution is looked for in iteration of makes decisions on all the shipbuilding design
several steps [10]. Each next iteration step brings elements.
new solutions for the design elements, which affect
other design elements. The final result is a 2 AN EXAMPLE OF SIMULATION METHOD
compromise design of an overall shipbuilding USE IN SHIPBUILDING WORKSHOP
process, which does not offer the best solution for PRODUCTION PROCESS MANAGEMENT
each individual design element.
The shipbuilding process design procedure The simulation method use in management
may be expanded by application of simulation of production processes will be shown using an
program packages for modelling, visualisation and example of situation analysis for a shipbuilding
experimenting with a model, which enables workshop [11]. The data obtained from the shipyard
prediction and avoiding of adverse effects the will be used to build a simulation model of the
parameter changes have in a complex production shipbuilding workshop, define the production
process such as shipbuilding. program and carry out computer-supported
When the data obtained by analyses of experiments. Analysis of results of an individual
product, production process and material flow are experiment and comparison of results of a larger
used, the simulation procedure enables creation of number of experiments creates a database facilitating
production process and final product model. quality decision-making on the production process
Performing a large number of experiments with changes. Taylor ED software is used for modelling,
models in a short period of time will create a visualization and results analysis.
considerable database for quality and informed
decision-making on solutions for the production 2.1 Simulation Program Package Taylor ED
process.
Figure 1 shows a block diagram with Simulation software Taylor ED is object-
shipbuilding process design elements and their oriented program package for modeling,
interdependence achieved by two-way relations. visualization and analysis of the production
process. In the program package whole production element is defined by its geometry (sizes of
process and products of the workshop are created. equipment and devices), position in space and
A basic element of the simulation model is an atom. operating characteristics (speed of transport devices
The atom represents single machine, tool, and or fabrication duration on equipment). Figure 2
transport device, necessary areas like interim stores, presents a model layout.
semi-products and products of the workshop. There Cut lengths of plates, profiles and bars are
are 80 defined and created atoms in the program defined by their geometrical characteristics and
package. ship structure analysis. Through cutting machines
In the program package atoms are arranged possibilities, duration of cutting is determined for
on workshop layout. Their geometric characteristics each machine. Analysis of the cutting duration real
and functions are defined, as well. Relations values is basis for value distribution definition.
between atoms are defined to determine task Log-normal distribution is very close to real values
scheduling in the workshop. Connecting entry and and it is set in cutting machines atoms in the
exit channels of atoms define the routing - the flow simulation model.
of the products through production process in a Basic areas are material stockyard and
simulation model. Function of the atom is operation shipbuilding workshop. Plates and profiles are
that has to be done. It could be set, for example, as arranged on the material stockyard, which is
duration of machine operation or speed, load and equipped with a portal crane. Portal crane transports
unload time of transport device. a material on the prefabrication line. After that
plates and profiles are going to the shipbuilding
2.2 Shipbuilding Workshop Simulation Model workshop.
The shipbuilding workshop consists of 5
The simulation program package models the naves. The first nave is used for profile cutting on
production program with elements that represent a robotised line, which consists of a line for the
equipment, devices and transport devices. Each profile edge cleaning and a robot station for plasma
cutting. Profiles are transported in the nave with 2.4 Experiments with Model
bridge crane, roller conveyors and transverse chain
transport device. The modelling process is followed by
The second nave is used for disposal of tools launching of an experiment. The visualisation
and as an auxiliary area off the main material flow. module used to monitor the experiment progress
Being less important, this area is not modelled in is started at the same time. It enables monitoring
the program package. of what is happening with material, semi-products,
The third nave is used for shaping of earlier equipment, devices and transport devices in any
cut plates. The plates are shaped in press, and part of the process.
transported in the nave with bridge crane and The paper describes two experiments with
trolley. models. Having in mind complexity of the analysis,
In the forth nave, the profiles are bent on monitoring of process and results analysis will be
bending machines and transported with bridge limited to the profiles and plates cutting processes.
crane and trolley. The efficiency of equipment, devices and transport
The plates are cut in the fifth nave. Three devices, situation at the interim store and quantity
cutting machines are used, one for plasma and two of fabricated material are monitored.
for gas cutting (Numorex and Corta). The plates The first experiment monitors and evaluates
are transported with bridge crane and trolley. situation in the basic simulation model for the
shipbuilding workshop. Based on the analysis
2.3 Production Program results, the changes and improvements are
Fig. 3. Mass percentages of plates, profiles and Fig. 5. Profiles cutting robot status during the
bars in total quantity of material first experiment
Fig. 6. Status of cutting machines and plate edge preparation bench during the first experiment
proposed to be included in the new simulation 8641 profiles and bars. Hence, the machine is not
model. sufficiently busy and it could fabricate an additional
The second experiment monitors effects of quantity of profiles and bars.
the proposed changes on situation in the nave in In plates cutting workshop (nave 5), all the
which the profiles and plates are cut. The proposed cutting machines and the bench on which semi-
improvements are estimated by comparison of automatic cutting machines are used to prepare the
obtained results. plate edges for welding were monitored. For the
Since an experiment with the simulation experiment, 30% plates were planned to be
model in the program package is running forwarded after machine cutting to the benches for
continually and permanently, the experiment edge preparation for welding. Number of fabricated
duration needs to be limited. The experiment plates, profiles and bars are in Table 1. During the
duration is set at 1920 hours, i.e. according to the experiment, 6403 plates were fabricated at the
number of working days and effective working cutting machines. Figure 6 shows status of
hours, at six months work in a shipyard. machines and bench during the experiment. It is
noticed that machines are blocked for quite a long
2.4.1 The First Experiment with Model time, which means that the plate is fabricated and
waiting for transportation. The transportation in the
Figure 4 shows distribution of material workshop is done with a bridge crane, which is
according to its fabrication site in the first expected to perform numerous tasks. It is also
experiment. Plates are commonly cut by plasma noticed that in the interim store, near the edge
cutting machine because of its cutting speed. Profiles preparation bench, a large quantity of material piles
are cut by robot, and bars are usually cut by hand. up and that it needs to be released of storage load.
During the experiment, profiles and bars Verification of the simulation model is
cutting robot operation was monitored, and the performed and the model behaves with
robot status is presented in Figure 5. The machine expectations. Validation of the model is established
was busy 52% and idle 48% of time, and it cuts for 6 months period by comparison of experiments
results and real number of worked elements. material according to the working place is shown
Simulation model expresses real situation in the in Figure 7.
shipyard workshop very well. During the experiment, same as in the
According to the analysis results, the previous experiment, operation of equipment,
process improvements are proposed which are to devices and transport devices, and quantities of
be incorporated into the new simulation model and material fabricated in the profiles and plates cutting
new experiment. workshops was monitored.
The proposals include: Figure 8 shows the profiles cutting robot
- Increase in profiles cutting machine efficiency status. The machine was busy 90% of time and it
by delivery of a larger quantity of bars for cut 14756 profiles and bars, which is an increase
fabrication. In new experiment, the robot is fed of 38% and 70% respectively compared to the first
with 60% bars compared to 22% from the first experiment.
experiment. Number of fabricated plates, profiles and
- Moving the plate edge prepared for welding to bars is given in Table 2. The machines fabricated
one of oxygen cutting machines so that number 7248 plates, which is 13% more compared to the
of plates that go to the edge preparation bench previous experiment. Cutting machines status is
is reduced from 30% to 25%. shown in Figure 9. Blocked status was reduced by
- Fitting the plate-cutting workshop with a new 25%, and efficiency increased because the crane
bridge crane to share the transportation load load was reduced and transportation became more
with the existing crane. efficient.
According to a simulation, suggested
2.4.2 The Second Experiment with Model improvements result with greater efficiency and
performance of the machines in the workshop.
Introduction of changes into the model Comparison of the data from table 1 and 2 shows
results in a new scenario of material input into the that greater quantity of material could be processed
shipbuilding workshop. New distribution of on the cutting machines. This is, very important
Fig. 7. Distribution of material according to the Fig. 8. Profiles cutting robot status during the
working site in the second experiment second experiment
Fig. 9. Status of cutting machines and plate edge preparation bench during the second experiment
for plasma cutting machine. It could cut about 20% tools, working areas, transport devices) and
more plates with better transport organization. products (plates, bars and profiles) was modeled
Improvements influence the quality of the material and analyzed by simulation.
flows. It is seen that there are not huge quantities Simulation model of the shipyard workshop
of material on work-in-process storage areas, which was verified and validated, ensuring the confidence
could cause problems with sorting and control. in suggested improvements of the technological
The effects of proposed changes in processes.
workshops for plates and profiles cutting are Experiments with model are used to analyse
positive, so it is necessary to make a technical and different technological solutions for a production
economic analysis that would estimate necessary process, and to anticipate situations in case of
investment and payback period. investment into new equipment or when alternative
production programs are considered which might
3 CONCLUSION affect particular stages in the production process.
Differently defined experiment scenaria include
Paper presents the usage of the simulation changes in model parameters, and carrying out of
methods in the shipbuilding production process a number of experiments in a short period of time
management. The entire workshop (machines, enables a broadly based research, resulting in a
database that makes it possible to evaluate status [2] •iljak, V. Simulation by computers. Zagreb:
of all the production process stages according to Školska knjiga, 1982. (in Croatian).
the criteria such as efficiency of equipment and [3] Medeiros, D.J., Traband, M., Tribble, A.,
devices, process duration or capacity of interim Lepro, R., Fast, K., Williams, D. Simulation
stores. The analysis conclusions are used for based design for shipyard manufacturing
efficient management and decision-making process process. Proceedings of the 2000 Winter
in a real system. Simulation Conference, Orlando, USA.
An advantage of simulation procedure use [4] Williams, D., Finke, D.A., Medeiros, D.J.,
in production process management is that it enables Traband, M.T. Discrete simulation
creation of a realistic model of the production development for a proposed shipyard steel
process and final product, and an approximation processing facility. Proceedings of the 2001
of situations encountered in a real production Winter Simulation Conference, Arlington,
system to be used in production process control USA.
and management. Complex production processes, [5] Kiran, A., Cetinkaya, T., Cabrera, J.
such shipbuilding, are too complicated to be Hierarchical modelling of a shipyard
resolved by mathematical analysis, and simulation integrated with an external scheduling
methods have proven better for analysis and application. Proceedings of the 2001 Winter
understanding of their behaviour. Their application Simulation Conference, Arlington, USA.
is possible in already defined production processes [6] McLean, C., Shao, G. Simulation of
as well as in those, which are in a design stage. shipbuilding operations. Proceedings of the
Application of the state-of-the-art program 2001 Winter Simulation Conference,
packages enables a more extensive use of simulation Arlington, USA.
procedures in production process control and [7] Dain, O., Ginsberg, M., Keenan, E., Pyle, J.,
management than before. This is certainly due to Smith, T., Stoneman, A., Pardoe, I. Stochastic
advancement in computer technology and capacities, shipyard simulation with SimYard.
primarily in their operation speed and graphic Proceedings of the 2006 Winter Simulation
software. Advancement in program packages Conference, Monterey, USA.
resulted in their being user-friendlier; the users need [8] Nedess, C., Friedewald, A., Wagner, L.,
not involve in programming, coding and testing of Hubler, M. Simulation of material flow
programs. Instead, they may focus on modelling, processes in the planning of production spaces
experiments with model and analysis of results. in shipbuilding. On-line: www.tudelft.nl.
An advantage the state-of-the-art program [9] Steinhauer, D., Meyer-König, S. Simulation
packages have is an option of 2D and 3D visualisation aided production planning in block assembly.
of production process model, which facilitates an On-line: www.tudelft.nl.
experiment monitoring, detection of errors in model [10] Sladoljev, ., Zaplatiæ,T., Ljubenkov,B. Some
creation and pinpointing of interruptions or possibilities of shipbuilding process
bottlenecks in the production process. management by simulation method. The Tenth
Congress of the International Maritime
4 REFERENCES Association of the Mediterranean, Crete,
Hellas, 13-17 May, 2002.
[1] Ljubenkov, B. Simulation in management of [11] Kuzmaniæ, M. Technological process of
the jack-up drilling rig building process, shipbuilding workshop, Graduation project.
Master Thesis. University of Zagreb, Faculty University of Zagreb, Faculty of Mechanical
of Mechanical Engineering and Naval Engineering and Naval Architecture, 2006. (in
Architecture, 2002. (in Croatian). Croatian).