Target Price for Tower Foundation Work

Sr. No Description of Items UOM Final Rates Remark

Excavation of Earth-work including strutting, shoring and packing


cavities, if required, by close timbering. Backfilling with available
1 excavated earth in layers not exceeding 200mm with proper
compaction by achieving atleaest 95% modified Procter density &
disposal of surplus earth within 50 meter lead.

a All kinds of Soil Cu. M. 160


b Soft Rock Cu. M. 340
Hard Rock requiring Mannual/ Compressor operated Jack hammers Or
c requiring blasting through licensed Blaster with necessary Approval by Cu. M. 700
concerned Govt. Authority

Providing Pile Foundation including drilling, excluding RCC( M-20 or M-


2
15) & Reinforcement
a Below 350mm Dia RM 500
b 350mm - 500mm bore Dia RM 650

C Mobilization Charges subject to prior approval of Circle Head LS

3 Per Hr
Dewatering charges with 2HP Pump - (With prior approval) 100

Providing & Filling in plinth with Sand/ Mooram/ Good Earth/ Flyash as
directed by the TVI Project Manager under floors/ in tower base,
4 Cu. M. 300
including watering, ramming consolidating & dressing complete. (If
extra Soil required)

Providing & Laying of 100mm Size Boulder in layers with Compaction for
5 Soling. Thickness of the layer should not be more than 100 mm for Grade Cu. M. 1400
–I (45mm to 90mm) & 75mm for Grade –II (45mm to 63mm).

Providing & Laying in Position Cement Concrete of specified grade


6
including the cost of centring and shuttering & required curing:

1 : 4 : 8 (1 Cement : 4 Coarse Sand : 8 Graded Stone Aggregate 20mm


a Cu. M. 4000
Nominal Size)
1 : 5 : 10 (1 Cement : 5 Coarse Sand : 10 Graded Stone Aggregate 40mm
b Cu. M. 3500
Nominal size)

Providing & Laying in Position Reinforced Cement Concrete of specified


grade excluding the cost of centring and shuttering. The below prices
7
are including the Cube test report for 7 & 28 Days.
(# Curing for minimum 7 days is mandatory).

1 : 2 : 4 (1 Cement : 2 Coarse Sand : 4 Graded Stone Aggregate 20mm


a Cu. M. 5000
Nominal Size) - M15
1 : 1.5 : 3 (1 Cement : 1.5 Coarse Sand : 3 Graded Stone Aggregate
b Cu. M. 6000
20mm Nominal Size) - M20

Centering & Shuttering including strutting, propping etc. and removal of


8 Sq. M. 250
form for all type of works. - Only for RCC work.

Supply of Reinforcement for RCC work including straightening, cutting,


9 bending, placing in position and binding all complete Thermo- Kg 56
Mechanically Treated (TMT) bars.

Steel works in single or built up section, M.S. Grill Work, including


Fabrication, fixing, Grouting & Painting the same with Red Oxide primer
10 Kg 65
& then with 3-Coats of Synthetic Enamel Paint. (All the fabrications will
be as per approved Drawing) including supply and transportation.
Sr. No Description of Items UOM Final Rates Remark

Arranging & Fixing of template, anchor bolts / CIP etc. in position during
concreting as per drawing, true to alignment etc. complete as per the
11 Job 1500
direction of Enginer -in-charge. It also include the removal of templates
& supporting angles after 24 Hours of concreteing.

Transportation charges for shifting the Template & Foundation bolts / CIP
from TVIPL Ware house to Site / from other existing sites / site to ware
12
house. - (Not applicable in case of supply made by us Transporter at
specified site).

a upto 250 KM Job 3500


b above 250 KM Job 5000
13 Brick Work with bricks of class designation 75 in :
Cement Mortar 1 : 6 (1 Cement : 6 Coarse Sand) Cu. M. 4500
14 Half Brick Masonry with bricks of class designation 75 in :
Cement Mortar 1 : 4 (1 Cement : 4 Coarse Sand) Sq. M. 400
Stone Masonary: Random Rubble/ Coarsed Masonry with hard stone
15
including levelling up & pointing with
Cement mortar 1:6 (1 Cement : 6 coarse sand) Cu. M. 2300

Add for RCC work smooth finishing of the exposed surface with 6mm
16 Sq. M. 40
thick Cement Mortar 1 : 3 (1 Cement : 3 Fine Sand)

17 Cement Plaster - 12 to 15mm thick mix on the Brick wall :


a 1 : 6 (1 Cement : 6 Fine Sand) Sq. M. 140
b 1 : 4 (1 Cement : 2 Fine Sand + 2 Coarse Sand) Sq. M. 150

Finishing walls with Water proofing Cement Paint "Snowcem - Plus" of


M/s. Snowcem India Ltd.,or equivalent of required shade : New work
18 (Two or more coats applied @ 3.84 Kg/10 sqmts.) - White / Cement Grey Sq. M. 30
Color/ OR Oil Bond / Paiting with Synthetic enamel (Makes -
Berger/Shalimar/Asian/Nerolac (three or more coats)

Site cleaning from all Civil work related debris, removing the debris from
19 Job 1000
site premises and disposing it off Municipal limits. - For New Sites only

Demolishing & Dismentling including removal & cleaning of site and


20 removal of debris from site and dumping it to the nearest municipal
dumping land.
a Brick Work Cu. M. 100
b PCC Cu. M. 200
c RCC Cu. M. 400

Chipping the columns for exposing the reinforcement (if column


reinforcement is of not sufficient length concerned beam should also be
21 per coloumn 300
chipped and the reinforcement should be exposed) including cleaning
of site and removal of debris.

22 Tower Erection
a Tower Erection without Painting- Angular/Tubular - GBT MT 5000
b Tower Erection without Painting- Angular/Tubular - RTT MT 5500

Painting of Tower, Including one coats of approved primer & Two coat
23
of synthetic enamel paint of ICI/Berger make as per relevant IS Code

a Top 5 or 6 Meter (for 50 Meter Tower) L.S 1000


b Top 15 or 18 Meter (for 60 Meter Tower) L.S 2200
Providing & Fixing on unplasticised Rigid P.V.C rain water pipes
24 Mtr 100
110mm/moulded fittings/with all accessories.

Clearing of Jungle including uprooting of rank vegitation, grass, brush


25 wood & disposal of these upto a distance of 50m outside the periphery LS 1000
of the area cleared. (As per the instructions of Site-in-charge).
Sr. No Description of Items UOM Final Rates Remark

Head Loading - (Not Applicable for the case, where leading charges
26
already Claimed)
a Upto G + 2 LS 2500
b Upto G + 3 LS 3000
c Above G + 3 LS 3500

Leading Charges for Mannual / Animal transportation of construction


27 material (More than 100 Mtr) in case of congested / Typical Areas for RTT LS 4000
Sites. (Maximum upto 4000 INR, subject to Prior Approval)

28 If water is not Available on Site and tanker is arranged by Vendor Per Site 1000

Galavanised Barbed Wire Fencing with angle iron post placed at


required distance embedded in cement concrete blocks, , last put one
end post and corner post shall be strutted on both sides and end post
on one side only and provided with horizontal lines and two diagonals
29 interwoven with horizontal wires, of barbed wire 9.38 kg per 100 m RM 14
(minimum) between the two posts fitted and fixed with G.I. staples, turn
buckles etc. complete. (Cost of posts struts, earth work and concrete
work to be paid for separately) :- Payment to be made per metre cost
of total length of barbed wire used.

Drilling of 20mm holes in the column portion of Roof of 4" Depth (Min),
Blowing of air to expel the dust and fixing of 16mm dia rods by filling the
30 holes with Lockfix (HILTI ) Chemical compound RE500/(Excluding the No's 500
steel Cost, which has to be billed as per Sr No 11) - For RTT sites only.
Only for HITLI makes and depth upto 400mm.

Rock Anchorage by Fixing of 20mm dowel bars by drilling 30mm holes


upto depth recommeded by designer in Hard Rock & using Lokfix S /
31 other recommended compounds ready to use groute, Cost is including RM 600
Drilling & Lokfix material cost(Excluding the steel Cost, which has to be
billed as per Sr No 11) - For GBT Sites only.

Welding of rods at the junction of Columns and Beams including


32 transportation of machine, Material(Welding rods) and Labour charges. - LS 1000
Only for RTT Sites
33 Grouting of HCT vertical Support.

Pedastal for vertical support of dimension 650 x 350 x 300 (LxBxH) with
a 1:2:4 concrete including excavation/ chipping, shuttering, plastering No's 300
and painting with Snowcem.

Disposal of Excavated Soil/Hard/Soft rock from the site and Disposing off
34 Cu. M. 100
the Muncipal limits

Penalty for delay will be levied if Civil vendor is unable to complete the
site within 5 days of mutual agreed timeline. Civil Work completion time
35 Per Day Per Site
is taken from the date of site allotment till completion of foundation.
Waiver of penalty shall be a sole decision of Company.

Night working Charges for city sites where work to be executed in strictly
36 Nos 5000
in nights with approval of SCM head only

Security of site maximum one month for 24x7 for sites where theftprone
37 area and work to be executed in night subject to prior approval of per site 7000
circle head and HO SCM

Trail Pit for checking the feasiblity of site construction due to heavy
38 Nos 3500
utilities of for GBM and approval SCM head is required for this
Sr. No Description of Items UOM Final Rates Remark

Using of RMC pump where RMC mahcine is unable to go/narrow street


39 and high rise building/location constraints and subject to one time use per site 5000
only at site

Supply an dinstallation of 110mm(4.25”dia) PVC pipe with flow bearing


40 per meter 150
pressure (KG/CM )of 4KG of standard makes with ISI mark

41 Supply and Installation of HDPE Duct(40/33) mm per meter 85

Payment Terms:
95% Payment within 2-3 Week on completion of site and certified by EIC
1

2 Balance 5% after 3 month

Other Terms:
1 Site location will be in UPE
Detailed site layout and drawing will be provide on site allocation
2