Vous êtes sur la page 1sur 2

Equipment Losses Measurment

Downtime
Loading Time Availability=loading time - down time /
loading time
Setup

Downtime
Losses
Minor stops
Operating Time
Performance efficiency=theoretical cycle
time * processed amount time / operating
time

Reduced speed
Production
losses

Operating time

Defects in
process
Rate of quality = Processed amount -
Defect losses

defect amount/ amount processed

Actual Operating
times Yield

OEE= Availability * Performance Efficiency * Rate of Quality


Measure a machine center like a person

Total hour must accounted for


Down time
Setup time
From empty line- Time starts when setup begins. Time ends when first unit comes off last machine
From full line- Time start when last board clears last station. Time ends when first unit from next batch comes off last machine
Down time
Any time where bottleneck is starved for more than 5 minutes

Quality
Starts minus finishes devided by finishes (FTY)