Vous êtes sur la page 1sur 3

POSORJA MULTIPURPOSE TERMINAL

TERMINAL WORKS

CONTRACTOR ENGINEER

CHINA HARBOUR CULLEN GRUMMITT & ROE

INSPECTION TEST REPORT


VIBRO-FLOTATION COMPACTION CONSTRUCTION

Doc No.
PMPT-ITP-010-01

REVISIONS RECORD
Rev. No. Date Issued by Approved by Description

01 06/04/2018 Yafeng Wang Shi Tianhua Inspection Test Plan


Doc. No.: PMPT-ITP-010-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1

Date: 06/04/2018
INSPECTION TEST REPORT
Page: 2 of 3
VIBROFLOTATION COMPACTION CONSTRUCTION

VIBROFLOTATION COMPACTION CONSTRUCTION

PERFORMANCE & INSPECTION TYPE OF INSPECTION/


SL NO ACTIVITY DESCRIPTION REFERENCE DOCUMENT ACCEPTANCE FRECUENCY FUNCTION SURVEILLANCE RECORD
PERFORMER CHECKER CHEC CGR FUNCTION
CRITERIA
CHEC CHEC
In accordance with Before start Planing Construction Method
1 Method Statement Employer´s Requirements Employer´s works engineering Manager H R Statement
A.10.11 Requirements
In accordance with Before start Environmental Construction Environmental
2 Enviromental Permit Employer´s Requirements Employer´s works Engineer Manager H R Permit
A.11.2.1 Requirements Certificate
In accordance with Before start Environmental Construction Access Permit
3 Access Permit Employer´s Requirements Employer´s works Engineer Manager H R Certificate
A.10.5.1 Requirements
In accordance with Before start Safety Incharge Construction Job Safety
4 Job Safety Analysis Employer´s Requirements Employer´s works Manager H R Analysis
A.10.11.1 Requirements
In accordance with Every vibro
5 Vibro-compaction pile depth D-132.003-301-06-011 / approved design compaction Site Engineer QA/QC H H ITP-CL09
D-132.003-301-06-012 bottom level pile Engineer

6 Capacity test ES-132.003-301-06-004 / not less than 160 kPa Every 5000 Lab Assistant QA/QC H H Test report
AASHTO T-222-78 m2 Engineer
Employer´s Requirements From 0 to -20m
7 Standard Penetration Test C.4.9.2 (depth): Every 5000 Lab Assistant QA/QC H H Test report
(SPT) ES-132.003-301-06-004 / 0 to 22 SPT N Value m2 Engineer
ASTM D1586
Note :
1) Strictly adhere with HSE plan for safe work enviroment.
2) Materials wich are not icluided in this ITP and need arises to use at site and same shall be added in ITP in later stage.
3) All items in wich cement is used shall be cured for minimun seven days.
LEGEND H = Hold Point W = Witness Inspection R = Review of Document S = Surveillance