Académique Documents
Professionnel Documents
Culture Documents
SUMMARY
This paper summarizes the studies carried out to set the control system parameters and evaluate the
dynamic performance of the ±800 kV, 4000 MW, Xingu to Estreito HVDC bipole associated to the
integration of Belo Monte hydro power plant.
The HVDC controller parameters have been optimized to meet the specified performance for a number
of AC system representations, operating conditions and fault locations. The off-line transient
simulation program PSCAD was used for the simulations with a very detailed and precise digital
model of the control and protection system of Bipole 1 and suitable network equivalents. The aim of
the study was to verify the stability and effectiveness of the designed control system and the dynamic
interactions between the HVDC system and the AC network, particularly on the aspects related to
power recovery after faults, commutation failure performance, voltage/frequency control and damping
of electromechanical oscillations. The multi-infeed dynamic interactions with other HVDC schemes
(Itaipu and Rio Madeira projects) were also assessed.
Dynamic Performance Tests (DPT) have been conducted to confirm the off-line simulation results and
verify the HVDC control hardware and software implementation. The DPT consists of a set of real-
time hardware-in-the-loop simulations using RTDS and a physical replica of the HVDC C&P
equipment. This paper discusses the results of both PSCAD and RTDS simulations.
The study concluded that a robust HVDC control system design was developed and that the specified
dynamic performance requirements will generally be met, even during severe contingencies in the
power system.
KEYWORDS
* Rua Real Grandeza, 219 – Sala E-110, Botafogo, Rio de Janeiro, RJ, Brazil
E-mail: cattan@furnas.com.br
SP94
1. Introduction
The Belo Monte hydroelectric generation complex is located in the state of Para in the north of Brazil
and has an installed capacity of approximately 11 GW (18 x 611 MW). Due to environmental
constraints related to the Amazon basis, it uses a run-of-river design with very small reservoirs.
Network planning studies indicated that the integration of Belo Monte into the Brazilian power system
would require a large reinforcement of the North-Southeast long distance transmission interconnection
to enable power transfer between sub-systems [1]. The chosen technical solution comprised two point-
to-point ±800 kV HVDC LCC bipoles, 4.000 MW each, connecting Xingu 500 kV substation (a few
km from Belo Monte) to two distinct point of connections in the southeast region. Each bipole was
offered by the national regulatory authority (ANEEL) as independent transmission concessions in
separated public auctions.
The development of the first bipole (Bipole 1) is under responsibility of the consortium Belo Monte
Transmissora de Energia (BMTE), a special purpose company formed by private and state-owned
utilities: State Grid Brazil Holding S.A. (51%), Furnas (24.5%) and Eletronorte (24.5%). The terminal
converter stations are supplied by SIEMENS. Bipole 1 started commercial operation in December
2017, connecting Xingu to Estreito 500 kV substation, in the south of Minas Gerais state, through a
bipolar overhead transmission line with a total length of 2.084 km. This is the first ±800 kV scheme in
Brazil and also the first HVDC scheme embedded in the Brazilian AC network, i.e. where the HVDC
system runs in parallel to the existing AC system. The second bipole (Bipole 2) is planned to begin
operation by the end of 2019 and will be connected to Terminal Rio 500 kV substation in the southeast
region, distant approximately 2400 km from Xingu. Bipole 2 is owned by a different owner, which
chose a different supplier to design, test and manufacturer the components, systems and equipment of
the converter stations. The near-future integration of the two bipoles in this multi-vendor/multi-owner
environment represents an additional challenge to the overall project.
This paper summarizes the studies carried out to set the control system parameters and evaluate the
dynamic performance of Bipole 1 against various types of disturbances, such as: step responses,
converter transformer energisation, AC system faults (single-phase and three-phase), loss of
generation units, AC filter switching, short-circuits within the converters and along the DC line,
converter misfiring, pole/bipole blocking, etc. A number of operating conditions and system models
were considered in the study.
The study was conducted with the off-line transient simulation program PSCAD [2] using a very
detailed and precise digital model of the C&P system of Bipole 1 and suitable network equivalents.
The aim of this study was to verify the stability and effectiveness of the designed control system and
the dynamic interactions between the HVDC system and the AC network, particularly on the aspects
related to power recovery after faults, commutation failure performance, voltage/frequency control
and damping of electromechanical oscillations. The multi-infeed dynamic interactions with other
HVDC schemes (Itaipu and Rio Madeira projects) were also assessed.
Dynamic Performance Tests (DPT) have been conducted as part of the Factory Acceptance Tests
(FAT) to confirm the off-line simulation results and verify the HVDC control hardware and software
implementation. The DPT consists of a set of real-time hardware-in-the-loop simulations using RTDS
[3] and a physical replica of the HVDC C&P equipment. This paper discusses the results of both
PSCAD and RTDS simulations.
1
SP94
Power
Terminal SCL (GVA) X/R LP (H) RP (Ω) RS (Ω)
Direction
X→E Minimum 18.3 10 0.03608 545.1 1.0201
X→E Intermediate 28.0 10 0.02358 356.26 0.6667
Xingu
E→X Minimum 15.3 10 0.043155 651.97 1.2202
E→X Intermediate 23.0 10 0.02871 433.7 0.8117
X→E Minimum 17.04 10 0.03875 585.4 1.096
X→E Intermediate 30.2 10 0.02186 330.3 0.6182
Estreito
E→X Minimum 17.9 10 0.03688 557.27 1.0429
E→X Intermediate 31.1 10 0.02123 320.75 0.6003
The load flow models have been used to study only AC and DC-side faults. The following sub-
sections briefly describe the network models and load flow scenarios used in each stage for the
Dynamic Performance Study (DPS). In both stages, detailed planning models (i.e. no vendor-specific
models) were used to represent the other HVDC schemes (Belo Monte Bipole 2, Itaipu and Rio
Madeira).
2
SP94
Figure 3 – Simplified diagram of the Xingu-Estreito ±800 kV, 4000 MW HVDC Bipole
3
SP94
4
SP94
3. Performance requirements
The dynamic performance of the HVDC scheme should comply with the following performance
requirements defined in ANEEL’s Technical Annex [4]:
The performance requirements are applied for AC faults of normal duration (~100ms)
followed by a single circuit trip in the complete system (N-1 criteria);
The HVDC scheme should restore 90% of the pre-fault power within 220ms after fault
clearing, without further reduction in power;
Subsequent commutation failures after fault clearing are not allowed;
No inverter commutation failures are allowed for AC faults at the rectifier side;
The minimum AC voltage in the first power swing after clearing a fault on the AC side must
be greater than 0.8 pu;
In the event of a DC line fault, the control system must restore 90% of the pre-fault power
within 150ms, excluding arc and deionization time;
The susceptibility of commutation failures after filter switching or converter transformer
energisation must be minimised;
The time response for a 50% step change in the power order should be less than 150 ms;
The time response for a step change in the current order lower than the current margin (<10%)
should be less than 30 ms;
The time response for a 30% step change in the current order should be less than 70 ms;
The operation of the HVDC scheme must not harm the steady-state and transient performance
of other electrically close converters;
5
SP94
6
SP94
AC Filter Control:
o Harmonic Performance Control (HPC)
o AC Voltage Limitation Control (VLC)
o Reactive Power Control (RPC) – Q-control and U-control
o DC Current Limitation according to AC filter rating (CLIM)
In PSCAD, only the stability functions and the Current Balance Control are modelled in details. A
simplified functional model of the AC Filter Control is also provided to start-up the HVDC system
with an appropriate number of AC filters and to perform automatic filter switching in case of AC
under/overvoltage (VLC function).
7
SP94
In general, Pole Control functions are detailed represented in the PSCAD model using a proprietary
user library of functions that mimics the actual SIMATIC TDC processor structure/hierarchy and
sample times. The SIMATIC TDC measurement system including signal filtering and sampling is also
represented in details.
8
SP94
6. Study results
6.1. AC and DC system faults
The HVDC controller parameters have been optimized for a number of AC system representations,
operating conditions and fault locations. Different settings have been used for Xingu and Estreito
controllers, as well as for bipolar and monopolar operation. The controller parameters were initially
designed for the Concept Stage network models in PSCAD and verified in the Dynamic Performance
Tests (DPT) using RTDS and SIMATIC TDC control replicas. The dynamic behaviour of the HVDC
scheme was satisfactory and all specified performance requirements were fulfilled. Besides, no
adverse interactions with other HVDC projects have been observed.
The initial settings have been re-evaluated using the Detailed Stage network models in PSCAD. Some
controller parameters have been then adapted to avoid subsequent commutation failures and ensure a
fast and stable AC fault recovery, such as transient fault recovery logic, current error modulation,
firing angle limitation and PI-controller parameters.
For the 2018 scenarios, the great majority of test cases complied with the specified performance
requirements, including the recovery time of 220 ms after AC system faults. However, a final recovery
longer than 220 ms was observed for a few 3-phase fault cases. This is highly acceptable, since the
Detailed Stage network models represent a much more degraded system condition with very low
short-circuit level.
For the 2019 X→E scenario, where Bipole 2 is in operation, subsequent commutation failures during
recovery have been observed for a few 3-phase fault cases. These commutation failures have induced
commutation failures on Bipole 2, Itaipu and Rio Madeira HVDC schemes. However, the overall
system recovers without further consequences.
For the 2019 E→X scenario, Bipole 1 and 2 are feeding 2.500 MW into the AC system at Xingu
substation (total of 5.000 MW). This is a high power infeed for such a weak network. The overall
performance of the system will depend on the level of power infeed and on the number of machines
operating as synchronous condensers in Belo Monte (since it will determine the short-circuit level at
the converter busbar). With one synchronous condenser in operation, several fault cases led to multiple
commutation failures and complete shutdown of the HVDC systems. With three synchronous
condensers, some results were improved but AC faults in Xingu busbar followed by the trip of one
circuit of Xingu – Tucurui transmission line and some DC line faults still presented multiple
commutation failures and failed to recover. Additional tests showed that further optimization of
9
SP94
(a) Estreito 500 kV phase-to-ground voltages (b) Estreito firing angle and firing angle limits
(e) DC current and current references (f) DC voltage and voltage reference
Figure 6 – 1ph fault at Estreito inverter followed by trip of Estreito – Ribeirão Preto transmission line
10
SP94
11
SP94
BIBLIOGRAPHY DATA
Fernando Cattan Jusan received the B.Sc. degree in electrical engineering from
CEFET-RJ, Rio de Janeiro, Brazil, in 2003, and the M.Sc. degree in electrical
engineering from Federal University of Rio de Janeiro/COPPE, Rio de Janeiro, Brazil,
in 2007. Since 2004, he has been with Furnas Centrais Elétricas, Rio de Janeiro,
Brazil. He is currently a power system engineer of the Department of Electrical
Studies and Power System Operation. His main areas of interest are HVDC
transmission, FACTS devices, power system stability and control, small-signal
analysis and subsynchronous oscillations. He is a member of Study Committee B4 of Cigré (HVDC
and Power Electronics). He has large experience in the planning, design and operation of HVDC
schemes, with intensive involvement in the most important HVDC projects in Brazil, i.e. Itaipu, Rio
Madeira and Belo Monte, particularly in the following fields: main circuit design, AC and DC
harmonics and filtering, DC control and protection, modelling.
12