Revisi: 00
Attendance: Wimba W, Heryono, Archie, Andi Permana, Sarwi, Krisheri
Date: August 10 2017
No Description TIFICO FAJAR PAPER Gap Action Plan Due Date PIC
1 Coal Quality
1. Ash Content Max 5% Max 8% 3%
2. Sulfur Content Max 0.5% Max 1.2% 0.7%
Mr. Archie will make special tool list for check quality
depth of different of coal, also for tool coal sampling facility need to - Archie, Andi
3. Sampling Equipment Hydraulic bor sampler Manual
sampling point discuss in next meeting
possiblity of
4. Sample Container Use “Tupperware” as container Plastic cover as container
spilled coal
1. Building with roof and wall 1. Building with roof and wall
2 Coal Yard -
open open
b. For roof shower material list will be finish on August August 10, Archie, Andi,
10 2017 2017 Krisheri
Team
4. There is no sprinkler 4. There is no sprinkler - Make plan to install, still wait proposal from contractor
5. Hydrant available 5. Hydrant available -
6. APAR Available 6. APAR Available -
fire alarm and
7. Fire alarm and panic button 7. Fire alarm and panic button panic button August 17,
Material list will be finish on August 14 2017 Archie, Andi
available not available facility not 2017
available
8. Dust is put into Silo, transfer 8. Dust is put into Sil, transfer
Fly ash can be
area closed by curtain and area open and not operation Install spray shower and cover ducting target finish on August 28,
prevented out Archie, Andi
operation shower when fly ash shower when fly ash loading in August 28 2017 2017
Silo area
loading in truck truck