FOR
9078/13/02-02 - 400KV
FOR THE
Date 15.11.2018
Signature
Page 2 of 11
1
TABLE OF CONTENTS
8.0 INSPECTION.................................................................................................................. 9
10.0 RECORDS...................................................................................................................... 10
Page 3 of 11
1
1.0 PURPOSE
This Method statement details the procedure of installation & testing of Tower Earthing.
2.0 REFERENCES
BPC Technical Specification
Applicable codes & standards as per contract
Accepted Design Drawings
Baseline Risk Assessment
Approved Technical Data Sheet Approved PQP
Approved SHE Plan
EC Engineering Consultants
SC Subcontractor
Page 4 of 11
1
SHE File
The subcontractor shall be required to comply with all Project SHE aspects in line with the L&T
SHEQ policy, BPC Safety requirements, EIA and EMP recommendations and Project Quality
Plan. The subcontractor shall accede to the mandatory agreement as prescribed by L&T and the
following shall be submitted for review and approval prior to commencement of work;
Workmen cover/insurance
Employee competencies
Employee Identities
Employee medical certificates
Project Specific Induction
PPE issue
Risk Assessments & Hazard Identification shall be prepared including mitigation measures, and
responsibility for implementation. This shall be coordinated with site Safety In-charge and attach to
this method statement.
Hazard Identification, Risk Assessment plan showing activity, risk, mitigation measures,
responsibility are prepared to ensure safe working. Activity based HIRA plan is attached in this
method statement.
Before commencing any work, all permits shall be checked and ensured that they are valid until
completion of activity.
All works shall be referred to the Drawings and specifications.
All materials shall be approved, sampled, tested, & accepted (as applicable) by client prior to
incorporation to the work.
All staff and workmen shall wear Personnel Protective Equipment (PPE).
Toolbox talks shall be conducted every day before commencement of work.
All personnel shall be cautioned while working near live lines and other services.
Prior to commencement of activities/works, the entire area shall be barricaded.
Adequate sign boards shall be kept to forewarn all.
Accumulated debris shall be cleared from the work site on daily basis.
It will be ensured that all men working in high-level are wearing necessary safety harness complying
with the safety requirements and following precautionary measures on safety aspects.
All plant and equipment shall be calibrated and accompanied by the competent operators prior to
commencement of any works.
Page 5 of 11
1
Site Engineer
Quality Engineer
Quality Engineer shall review method statements and ensure all requirements are included.
Inspect the equipment for calibration.
Prepare & maintain inspection log and records.
Review Quality Control records and ensure correctness.
EHS Officer
Disseminate EHS requirements specific to the activities involved and facilitate implementation.
Facilitate for work specific Hazard / Aspect Identification, Risk / Impact Assessment. Ensure work is
carried out in safe manner by coordinating with site engineer, subcontractors etc
4.2 General
The L&T Team members are also responsible for monitoring the Subcontractor activities, Checking
and signing off of QITP (Quality inspection and Test Plan) for all activities as per the Earthing works.
Page 6 of 11
1
EC representative on site is to sign off the QITP’s of the completed works. The Sub Contractor shall
be responsible for ensuring his people are issued with PPE with proper issuing documentation and
complies with this working to this method statement.
The L&T Safety Officer/supervisor is responsible to check that the L&T personnel as well as the
Subcontractor have all safety precautions in place and that the personnel on site possess the
necessary and essential PPE (Compliance as per SHE plans)
6.0 METHOD STATEMENT / WORK METHOD (Ref: Botswana Power Corporation Specification for 400
KV single circuit overhead transmission line Letlhakane to Mawana Substation and associated works
item 24 “EARTHING COUNTERPOISE”)
Page 7 of 11
1
6.3 Earthing Testing (Ref: Botswana Power Corporation Specification for 420 kV single circuit overhead
transmission line Letlhakane to Mawana Substation and Associated Works item 46 “EARTHING OF
TOWERS”)
Measurement of the electrical resistance to earth of each tower before the earth conductor/s are
installed.
Where counterpoise is installed an electrical resistance reading to earth shall also be taken after the
counterpoise is installed.
The three-point method is the most thorough and reliable test method; used for measuring resistance
to earth of an installed grounding electrode.
With a four terminal tester, P1 and C1 terminals on the instrument are jumpered and connected to the
earth electrode under test while the C2 reference rod is driven into the earth straight out as far
from the electrode under test as possible. Potential reference P2 is then driven into the earth, at
a set number of points, roughly on a straight line between C1 and C2. Resistance readings are logged
for each P2 point.
Correct earth resistance is read from the curve for the distance that is roughly 62% of the total
Page 8 of 11
1
6.4 Backfilling
Excavated soil suitable for backfill will be returned to the excavation by backfilling with the subsoil first
and the top soil last.
The distribution of material shall be such that the compacted material will be homogenous to secure
the best practicable degree of compaction, impermeability, stability and no water deposition.
Material removed from the excavation, which is either not suitable or not required for backfill, shall be
spread evenly over or adjacent to the site.
FIRE 997
998
AMBULANCE
POLICE 999
Page 10 of 11
1
Malatswai 4639561
Dimajwe 4620346
9.0 RECORDS
Document TFR Checking report
Document Soil resistivity report
Page 11 of 11