NAME: TAJORA, ALEX P.

BSCE 5

PROPOSED ONE STOREY RESIDENTIAL BUILDING

ACTIVITY DESCRIPTION IMMEDIATE DURATION MANPOWER


PREDECESSORS

(DAYS)
A SITE CLEARING -------- 2 3

B EXCAVATE A 5 4

C STEEL WORKS B 7 4

D INSTALLATION OF B,C 3 4
FORMS OF
SCAFFOLDINGS

E CONCRETE WORKS C,D 14 5

F MASONRY WORKS D,E 14 5

G ROOF FRAMING AND E 7 2


ROOFING

H REMOVAL OF E,F 2 3
SCAFFOLDING
I PLASTERING/FINISHING F 5 3

J CONSTRUCTION OF G,H,I 3 3
CEILING
K INSTALLATION OF F 2 2
DOORS AND WINDOWS
L TILE WORKS I 5 3

M PLUMBING WORKS I 3 2

N ELECTRICAL WORKS I 2 2

O PAINTING J,K,L,M,N 3 4

P SITE CLEANING O 2 2