1. Foundation Trench
a) Excavation of trench not more than 1m depth - N22,000
b) Excavation of Column Bases. - N4,000
N26,000
9. Parapet Headcourse
a) Twisted Iron Bars in Headcourse
i. 6 lengths of y12 mm at 2500/1 - N 15,000
ii. 3 lengths of y10 mm at 1500/1 - N 4, 500
iii. Iron Benders - N 6, 000
b) Carpenters - N10,000
c) Concrete in Headcourse
i. 6 bags of cement at 2550/1 - N 15,300
ii. Labourers - N 8, 000
d) 21m of Polysterine Fascia at 4400/m - N92,400
N151,200