TOTAL UNIT
NO URAIAN PEKERJAAN
(Rp)
I GEDUNG A
A GEDUNG A1 LT 1 ( INSTALASI RAWAT DARURAT ) 5,120,363,660
B GEDUNG A2LT 1 ( INSTALASI RAWAT JALAN) 3,533,335,560
C GEDUNG A3 LT 1 ( REKAM MEDIS, LABORAT DAN APOTIK ) 3,295,002,085
D GEDUNG A1 LT 2 ( OK / CENTRAL OPERASI ) 3,433,955,105
E GEDUNG A2 LT 2 ( INSTALASI RAWAT JALAN) 2,571,541,488
F GEDUNG A3 LT 2 ( ICU/ ICCU ) 1,946,401,353
G GEDUNG A3 LT 3 AUDITORIUM 2,081,198,030
II GEDUNG B
A GEDUNG B1 LT 1 ( PICCU DAN RADIOLOGI ) 10,066,287,477
III GEDUNG C
A GEDUNG C1, C2, C3 LT 1 17,866,320,924
B GEDUNG C1, C2, C3 LT 2 15,018,629,817
C GEDUNG PAVILIUN C4 LT 1 7,238,248,017
D GEDUNG PAVILIUN C4 LT 2 5,518,723,765
PPN 10 % 8,414,547,170
GRAND TOTAL 92,560,018,867
DIBULATKAN 92,560,018,000
TERBILANG
Seratus delapan Belas Miliyar Sembilan Ratus Lima Juta Lima Ratus Enam Puluh Tujuh Ribu Rupiah
Mengetahui Mengetahui
DIREKTUR RSUD DOLOPO KABUPATEN MADIUN
dr. Saifudin
Nip 19730102 2003 121 006
dr. Saifudin
Nip 19730102 2003 121 006
PROYEK : DED PERENCENAAN SARANA DAN PRASARANA
GEDUNG A1, A2, A3, B1, B2 , C1, C2,C3,DAN C4
PEKERJAAN: BQ REKAP PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
I PEKERJAAN ELEKTRIKAL
A Total Pekerjaan Genset - -
B Total Pekerjaan Panel 3 - -
C Total Pekerjaan Instalasi Kabel Feeder 3 - -
D Total Pekerjaan Instalasi Kabel Tray 6 - -
E Total Pekerjaan Instalasi Penerangan 4 - -
F Total Pekerjaan UPS 4 - -
G Total Pekerjaan Penangkal Petir Dan Grounding 9 - -
II PEKERJAAN ELEKTRONIK
A Total Pekerjaan Tata Suara 4 - -
B Total Pekerjaan Fire Alarm 4 - -
F PEKERJAAN UPS
1 UPS (IGBT Technology) 1 Set 0 -
Capacity : ….. Kva
Tegangan input/output : 380 V, 3 Phase, 50 Hz, power
factor ≥0,99 THD ≤3%by pass
Battery : Sealed Lead Acid
Back-up time : 30 menit
Panel
1 -
Penangkal petir jenis Elekro statis (Radius protection 125 m) 1 Set 0
2 Grounding penangkal petir incl. cable 2 ttk 0 -
3 Grounding panel incl. cable 2 ttk 0 -
4 Grounding Genset incl. cable 1 ttk 0 -
5 Grounding Trafo incl. cable 1 ttk 0 -
6 Grounding PABX 1 ttk 0 -
Total Pekerjaan Instalasi Penangkal Petir & Grounding -
1 Lantai 1 ZONA 1
Sound System terdiri dari :
Radio Tunner AM/FM 1 unit 0 0
CD/MP3 Player 1 unit 0 0
Autoreverse Cassete/Digital Sistem Audio 1 unit 0 0
Remote Microphone 1 unit 0 0
Mixer Frame c/w Module 1 unit 0 0
Chime Module 1 unit 0 0
Paging mic 1 unit 0 0
Power Amplifier 240 w 4 unit 0 0
Speaker Selector 16 Chanel 1 unit 0 0
Rak Kabinet + Blower, lengkap dengan monitor panel 1 unit 0 0
Ceiling Speaker 62 unit 0 0
TBSS 1 unit 0 0
Volume Control 20 unit 0 0
Instalasi Speaker 62 ttk 0 0
Sub Total Lantai 1 0
2 Lantai 2
Ceiling Speaker 53 unit 0 0
TBSS 1 unit 0 0
Volume Control 43 unit 0 0
Instalasi Speaker 53 ttk 0 0
Sub Total Lantai 2 0
3 Testing Commisioning 1 ls 0 0
1 Lantai 1
MCFA 30 Zone, Anounciator (c/w battery & rectifier) 1 set 0 0
Photoelectric Smoke Detector 18 unit 0 0
ROR Heat Detector 40 unit 0 0
Intalasi Fire Alarm 58 ttk 0 0
Instalasi Fire Fighting Telephone 1 ttk 0 0
TBFA 1 unit 0 0
Sub Total Lantai 1 0
2 Lantai 2
Photoelectric Smoke Detector 15 unit 0 0
ROR Heat Detector 38 unit 0 0
Intalasi Fire Alarm 53 ttk 0 0
Instalasi Fire Fighting Telephone 2 ttk 0 0
TBFA 1 unit 0 0
Sub Total Lantai 2 0
3 Testing Commisioning 1 ls 0 0
C Pekerjaan Telephone
1 Lantai 1
PABX 16 Line-80 Extension, c/w Bateray NiCad+rectifier 1 set 0 0
MDFT 120 pair 1 set 0 0
Komputer set Pentium core i3 1 unit 0 0
Printer 1 unit 0 0
NO URAIAN PEKERJAAN VOL SAT HRG. SAT TOTAL
(Rp) (Rp)
Operator consule 1 unit 0 0
Billing System 1 set 0 0
Kabinet Rack 1 set 0 0
Hand set Digital 1 unit 0 0
Telephone hand set 18 unit 0 0
Telephone outlet 18 unit 0 0
TBT 20 pair 1 unit 0 0
Instalasi Telephone 18 ttk 0 0
Sub Total Lantai 1 0
2 Lantai 2
Telephone outlet 12 unit 0 0
Telephone hand set 12 unit 0 0
TBT 20 pair 1 unit 0 0
Instalasi Telephone 12 ttk 0 0
Sub Total Lantai 2 0
D. Pekerjaan MATV
1 Lantai 1
TV outlet 4 unit 0 0
TBTV 1 unit 0 0
Instalasi TV Outlet 4 ttk 0 0
Sub Total Lantai1 0
2 Lantai 2
TV outlet 4 unit 0 0
TBTV 1 unit 0 0
Instalasi TV Outlet 4 ttk 0 0
Sub Total Lantai 2 0
E. Pekerjaan CCTV
Video manage 12 ch. 4.00 unit 0 0
Digital Video Recorder 4.00 unit 0 0
Monitor 29" Color 4.00 unit 0 0
Keyboard Controller Digital 4.00 unit 0 0
NO URAIAN PEKERJAAN VOL SAT HRG. SAT TOTAL
(Rp) (Rp)
Video Tape Recorder 1.00 unit 0 0
UPS 4 kVA 1.00 unit 0 0
Sub Total Peralatan Utama 0
1 Lantai 1
Camera colour Dome 1/3 inch 15 unit 0 0
Instalasi CCTV 15 ttk 0 0
Sub Total Lantai 1 0
2 Lantai 2
Camera colour Dome 1/3 inch 17 unit 0 0
Instalasi CCTV 17 ttk 0 0
Sub Total Lantai 2 0
1 Lantai 1
Hub Switch 10 Port ex 1 unit 0 0
Outlet Komputer Modular Jack 45 (1 Hole) 12 unit 0 0
Instalasi 12 ttk 0 0
Sub Total Lantai 1 0
2 Lantai 2
Hub Switch 12 Port ex 1 unit 0 0
Outlet Komputer Modular Jack 45 (1 Hole) 15 unit 0 0
Instalasi 15 ttk 0 0
Sub Total Lantai 2 0
LANTAI - 1
1 AIR CONDITIONING INCL.INSTALASI & STOP KONTAK
- Capacity : 7000 Btuh, Split Wall type 5 Set - -
- Capacity : 9900 btuh, Splitwall type 5 Set - -
- Capacity : 12600 btuh, Split wall type 2 Set - -
- Capacity : 16000 btuh, Ceiling Mounted Duct type 1 Set - -
3 Instalasi
- Pipa Refrigerant incl. Isolasi 256 m - -
- Pipa Drain incl. Isolasi 250 m - -
- Instalasi Daya AC 13 Titik - -
SUB TOTAL LANTAI 1 -
LANTAI - 2
1 AIR CONDITIONING INCL.INSTALASI & STOP KONTAK
- Capacity : 7000 Btuh, Split Wall type 5 Set - -
- Capacity : 9900 btuh, Splitwall type 6 Set - -
- Capacity : 12600 btuh, Split wall type 3 Set - -
- Capacity : 16000 btuh, Ceiling Mounted Duct type 1 Set - -
3 Instalasi
- Pipa Refrigerant incl. Isolasi 384 m - -
- Pipa Drain incl. Isolasi 250 m - -
- Instalasi Daya AC 15 Titik - -
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL. SAT. SATUAN
Rp Rp
Interior
rear Walls Stainless Steel Hairline finished
side Walls Stainless Steel Hairline finished
front return panel Stainless Steel Hairline finished
door Stainless Steel Hairline finished
lighting Fluorescent light
entrance column Stainless Steel Hairline finished
flooring Luckstrong
kick plate Stainless Steel Hairline finished
Door sill Extruded Hard Aluminium
ventilation Exhaust fan
faceplate Stainless Steel Hairline finished
Entrance :
hoistway door Stainless Steel Hairline finished
jamb Stainless Steel Hairline finished
landing sill Extruded Hard Aluminium
Signal Semua lantai
Power Supply 380 volt, 3 phase, 50 hz
Lighting 220 volt, 1 phase, 50 hz
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL SAT
SATUAN
Rp Rp
4 Sentral Vaccum
Vaccum Pump (2 x 3,7 kW) 1 set - -
Sentral udara tekan
Terdiri dari : Regulator, Shut Down Valve
Blok Valve, Piping, Lead Copper Tube
-
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL SAT
SATUAN
Rp Rp
Pekerjaan Ruang OK
1 Medical Gas Wall Mounted Outlet Oxygen (O2), Push Type 9 unit 0 0
2 Medical Gas Wall Mounted Outlet Nitrous Oxide (N2O), Push Type 8 unit 0 0
3 Medical Gas Wall Mounted Outlet Compressed Air (C/A), Push Type 9 unit 0 0
4 Medical Gas Wall Mounted Outlet Vacuum (Vac), Push Type 9 unit 0 0
5 Medical Gas Ceiling Hose Outlet 4 Gases (O2, N2O, C/A, Vac ) 2 set 0 0
6 Wall Mounted Anaesthetic Gass Scavenging System (AGSS) 2 set 0 0
7 Zone Valve 4 Gases (O2, N2O, C/A, Vac) 1 set 0 0
8 Area Alarm 4 Gases (O2, N2O, C/A, Vac) 1 set 0 0
9 Zone Valve 3 Gases (O2, C/A, Vac) 1 set 0 0
10 Area Alarm 3 Gases (O2, C/A, Vac) 1 set 0 0
11 Copper Pipe, Seamless, ASTM B 88 Type L
dia. 3/8" 66 m 0 0
dia. 1/2" 109 m 0 0
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL SAT
SATUAN
Rp Rp
dia. 5/8" 169 m 0 0
dia. 3/4" 54 m 0 0
-
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL SAT
SATUAN
Rp Rp
114,000.00
22,750.00
8,312.50
787.50
6,000.00
18,000.00
22,107.33
22,107.33
21,406.47
235,471.13
Jumlah Harga
Rp.
198,999.60
35,750.00
13,062.50
1,237.50
6,000.00
18,000.00
22,107.33
22,107.33
31,726.43
348,990.69
Jumlah Harga
Rp.
277,007.90
39,000.00
14,250.00
1,350.00
6,000.00
18,000.00
22,107.33
22,107.33
39,982.26
439,804.82
Jumlah Harga
Rp.
(8)
85,500.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
15,371.47
169,086.13
Jumlah Harga
Rp.
215,582.90
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
28,379.76
312,177.32
Jumlah Harga
Rp.
554,015.80
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
62,223.05
684,453.51
Jumlah Harga
Rp.
219,800.00
22,400.00
13,300.00
18,480.00
18,480.00
10,360.00
1,400.00
2,800.00
36,000.00
22,107.33
22,107.33
38,723.47
236,643.41
Jumlah Harga
Rp.
(8)
85,500.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
15,371.47
169,086.13
Jumlah Harga
Rp.
(8)
185,250.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
25,346.47
278,811.13
Jumlah Harga
Rp.
(8)
242,250.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
31,046.47
341,511.13
Jumlah Harga
Rp.
(8)
270,750.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
33,896.47
372,861.13
Jumlah Harga
Rp.
(8)
299,250.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
36,746.47
404,211.13
Jumlah Harga
Rp.
(8)
327,750.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
39,596.47
435,561.13
Jumlah Harga
Rp.
(8)
356,250.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
42,446.47
466,911.13
Jumlah Harga
Rp.
(8)
413,250.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
48,146.47
529,611.13
Jumlah Harga
Rp.
281,916.10
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
35,013.08
385,143.84
Jumlah Harga
Rp.
315,082.70
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
38,329.74
421,627.10
Jumlah Harga
Rp.
348,249.30
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
41,646.40
458,110.36
Jumlah Harga
Rp.
381,415.90
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
44,963.06
494,593.62
Jumlah Harga
Rp.
414,582.50
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
48,279.72
531,076.88
Jumlah Harga
Rp.
480,915.70
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
54,913.04
604,043.40
Jumlah Harga
Rp.
547,248.90
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
61,546.36
677,009.92
Jumlah Harga
Rp.
605,290.45
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
67,350.51
740,855.63
Jumlah Harga
Rp.
671,623.65
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
73,983.83
813,822.15
Jumlah Harga
Rp.
362,241.10
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
43,045.58
473,501.34
Jumlah Harga
Rp.
404,857.70
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
47,307.24
520,379.60
Jumlah Harga
Rp.
447,474.30
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
51,568.90
567,257.86
Jumlah Harga
Rp.
490,090.90
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
55,830.56
614,136.12
Jumlah Harga
Rp.
532,707.50
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
60,092.22
661,014.38
Jumlah Harga
Rp.
617,940.70
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
68,615.54
754,770.90
Jumlah Harga
Rp.
703,173.90
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
77,138.86
848,527.42
Jumlah Harga
Rp.
777,752.95
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
84,596.76
930,564.38
Jumlah Harga
Rp.
862,986.15
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
93,120.08
1,024,320.90
Jumlah Harga
Rp.
(8)
85,500.00
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
15,371.47
169,086.13
Jumlah Harga
Rp.
215,582.90
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
28,379.76
312,177.32
Jumlah Harga
Rp.
554,015.80
-
-
-
6,000.00
18,000.00
22,107.33
22,107.33
62,223.05
684,453.51
ANALISA HARGA SATUAN MEKANIKAL
2 Pompa Booster
Kapasitas : 3x100 LPM, Head : 15 M set 1.00 48,155,000.00 48,155,000.00
Alat bantu ls 1.00 96,310.00 96,310.00
Upah Pasang
- Tkg. Pasang Pipa Hari 0.50 50,000.00 25,000.00
- Kpl. Tkg. Pasang Pipa Hari 0.60 55,000.00 33,000.00
- Mandor / Pengawas Hari 0.60 58,000.00 34,800.00
Jumlah 48,344,110.00
HSPK 48,344,110.00
4 Gate valve 10 Kg
Diameter 80 mm Buah 1.00 1,352,875.00 1,352,875.00
Alat bantu ls 1.00 40,586.25 40,586.25
Upah Pasang
- Tkg. Pasang Pipa Hari 0.30 50,000.00 15,000.00
- Kpl. Tkg. Pasang Pipa Hari 0.30 55,000.00 16,500.00
- Mandor / Pengawas Hari 0.20 58,000.00 11,600.00
Jumlah 1,436,561.25
HSPK 1,436,561.25
5 Gate valve 10 Kg
Diameter 65 mm Buah 1.00 1,087,125.00 1,087,125.00
Alat bantu ls 1.00 32,613.75 32,613.75
Upah Pasang
- Tkg. Pasang Pipa Hari 0.20 50,000.00 10,000.00
- Kpl. Tkg. Pasang Pipa Hari 0.20 55,000.00 11,000.00
- Mandor / Pengawas Hari 0.15 58,000.00 8,700.00
Jumlah 1,149,438.75
HSPK 1,149,438.75
6 Flexible Joint
Diameter 80 mm Buah 1.00 312,000.00 312,000.00
Alat bantu ls 1.00 9,360.00 9,360.00
Upah Pasang
- Tkg. Pasang Pipa Hari 0.20 50,000.00 10,000.00
- Kpl. Tkg. Pasang Pipa Hari 0.20 55,000.00 11,000.00
- Mandor / Pengawas Hari 0.15 58,000.00 8,700.00
Jumlah 351,060.00
HSPK 351,060.00
7 Flexible Joint
Diameter 65 mm Buah 1.00 292,560.00 292,560.00
Alat bantu ls 1.00 8,776.80 8,776.80
Upah Pasang
- Tkg. Pasang Pipa Hari 0.20 50,000.00 10,000.00
- Kpl. Tkg. Pasang Pipa Hari 0.20 55,000.00 11,000.00
- Mandor / Pengawas Hari 0.15 58,000.00 8,700.00
Jumlah 331,036.80
HSPK 331,036.80
8 Check Valve
Diameter 65 mm Buah 1.00 1,170,000.00 1,170,000.00
Alat bantu ls 1.00 35,100.00 35,100.00
Upah Pasang
- Tkg. Pasang Pipa Hari 0.20 50,000.00 10,000.00
- Kpl. Tkg. Pasang Pipa Hari 0.20 55,000.00 11,000.00
- Mandor / Pengawas Hari 0.15 58,000.00 8,700.00
Jumlah 1,234,800.00
HSPK 1,234,800.00
9 Butterfly Valve
Diameter 300 mm Buah 1.00 2,400,000.00 2,400,000.00
Alat bantu ls 1.00 72,000.00 72,000.00
Upah Pasang
- Tkg. Pasang Pipa Hari 0.20 50,000.00 10,000.00
- Kpl. Tkg. Pasang Pipa Hari 0.20 55,000.00 11,000.00
- Mandor / Pengawas Hari 0.15 58,000.00 8,700.00
Jumlah 2,501,700.00
HSPK 2,501,700.00
74 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.100 CFM / WALL TYPE unit 1.00 275,000.00 275,000.00
Alat bantu ls 1.00 11,000.00 11,000.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 315,600.00
HSPK 315,600.00
75 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.100 CFM / WALL TYPE unit 1.00 275,000.00 275,000.00
Alat bantu ls 1.00 11,000.00 11,000.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 315,600.00
HSPK 315,600.00
76 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.150 CFM / WALL TYPE unit 1.00 275,000.00 275,000.00
Alat bantu ls 1.00 11,000.00 11,000.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 315,600.00
HSPK 315,600.00
77 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.150-160 CFM / WALL T unit 1.00 275,000.00 275,000.00
Alat bantu ls 1.00 11,000.00 11,000.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 315,600.00
HSPK 315,600.00
78 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.500/ WALL TYPE unit 1.00 790,000.00 790,000.00
Alat bantu ls 1.00 32,390.00 32,390.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 851,990.00
HSPK 851,990.00
79 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.550-600 CFM/INLINE unit 1.00 1,650,000.00 1,650,000.00
Alat bantu ls 1.00 67,650.00 67,650.00
Tenaga Kerja :
Mandor Oh 0.26 58,000.00 15,080.00
Tukang AC Oh 0.26 50,000.00 13,000.00
Pembantu tukang AC Oh 0.28 40,000.00 11,200.00
Jumlah 1,756,930.00
HSPK 1,756,930.00
80 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.250 CFM / WALL TYPE unit 1.00 327,000.00 327,000.00
Alat bantu ls 1.00 13,080.00 13,080.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 369,680.00
HSPK 369,680.00
81 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.1600 CFM / INLINE FA unit 1.00 3,410,000.00 3,410,000.00
Alat bantu ls 1.00 139,810.00 139,810.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 3,579,410.00
HSPK 3,579,410.00
82 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.250 CFM / INLINE FAN unit 1.00 1,000,000.00 1,000,000.00
Alat bantu ls 1.00 49,000.00 49,000.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 1,078,600.00
HSPK 1,078,600.00
83 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.3500 CFM / INLINE FA unit 1.00 5,500,000.00 5,500,000.00
Alat bantu ls 1.00 275,000.00 275,000.00
Tenaga Kerja :
Mandor Oh 0.20 58,000.00 11,600.00
Tukang AC Oh 0.21 50,000.00 10,500.00
Pembantu tukang AC Oh 0.21 40,000.00 8,400.00
Jumlah 5,805,500.00
HSPK 5,805,500.00
84 EXHAUST FAN
Bahan :
EXHAUST Fan Kap.400 CFM / WALL TYPE unit 1.00 704,000.00 704,000.00
Alat bantu ls 1.00 28,160.00 28,160.00
Tenaga Kerja :
Mandor Oh 0.19 58,000.00 11,020.00
Tukang AC Oh 0.20 50,000.00 10,000.00
Pembantu tukang AC Oh 0.20 40,000.00 8,000.00
Jumlah 761,180.00
HSPK 761,180.00
85 CEILING FAN
Bahan :
CEILING FAN Kap.1/200 CFM unit 1.00 357,900.00 357,900.00
Alat bantu ls 1.00 19,684.50 19,684.50
Tenaga Kerja :
Mandor Oh 0.15 58,000.00 8,700.00
Tukang AC Oh 0.15 50,000.00 7,500.00
Pembantu tukang AC Oh 0.15 40,000.00 6,000.00
Jumlah 399,784.50
HSPK 399,784.50
P - SDP-1
panel box 1 unit 2,500,000 2,500,000
MCCB 250 A 1 bh 1,707,600 1,707,600
MCCB 100 A 1 bh 1,584,900 1,584,900
MCCB 63 A 1 bh 649,965 649,965
MCCB 50 A 5 bh 649,965 3,249,825
MCCB 40 A 5 bh 575,500 2,877,500
MCB 25 A 1 bh 590,875 590,875
aseesories & installasi 1 set 1,500,000 1,500,000
14,660,665
P - UPS
panel box 1 unit 1,000,000 1,000,000
MCCB 50 A 1 bh 649,965 649,965
MCB 25 A 2 bh 590,875 1,181,750
MCB 10 A 6 bh 65,500 393,000
aseesories & installasi 1 set 750,000 750,000
3,974,715
LP - L1
panel box 1 unit 1,000,000 1,000,000
MCCB 50 A 1 bh 649,965 649,965
MCB 6 A 27 bh 94,755 2,558,385
aseesories & installasi 1 set 1,000,000 1,000,000
5,208,350
PP - L1
panel box 1 unit 1,200,000 1,200,000
MCCB 50 A 1 bh 649,965 649,965
MCCB 40 A 1 bh 575,500 575,500
MCB 25A 2 bh 590,875 1,181,750
aseesories & installasi 1 set 1,000,000 1,000,000
4,607,215
PP -AC-L1
panel box 1 unit 1,000,000 1,000,000
MCCB 50 A 1 bh 649,965 649,965
MCB 3P 10 A 3 bh 223,500 670,500
MCB 10 A 23 bh 65,500 1,506,500
aseesories & installasi 1 set 1,000,000 1,000,000
4,826,965
LP - L2
panel box 1 unit 1,000,000 1,000,000
MCCB 50 A 1 bh 649,965 649,965
MCB 6 A 33 bh 94,755 3,126,915
aseesories & installasi 1 set 1,000,000 1,000,000
5,776,880
PP -AC-L2
panel box 1 unit 1,000,000 1,000,000
MCCB 50 A 1 bh 649,965 649,965
MCB 3P 10 A 3 bh 223,500 670,500
MCB 10 A 29 bh 65,500 1,899,500
aseesories & installasi 1 set 1,000,000 1,000,000
5,219,965
P - SDP-2
panel box 1 unit 2,500,000 2,500,000
MCCB 250 A 1 bh 1,707,600 1,707,600
MCCB 100 A 1 bh 1,584,900 1,584,900
MCCB 63 A 1 bh 649,965 649,965
MCCB 50 A 5 bh 649,965 3,249,825
MCCB 40 A 5 bh 575,500 2,877,500
MCB 25 A 1 bh 590,875 590,875
aseesories & installasi 1 set 1,500,000 1,500,000
14,660,665
PP -LIFT
panel box 1 unit 2,500,000 2,500,000
MCCB 80 A 1 bh 1,346,400 1,346,400
MCCB 63 A 3 bh 1,346,400 4,039,200
aseesories & installasi 1 set 1,000,000 1,000,000
8,885,600
HSPK 67,821,020
NURSE CALL
Master nurse station 1 unit 83,828,000
Central Control Unit 1 unit 8,471,700
Call Patien Station 1 unit 1,121,500
Bathroon pull cord 1 unit 344,250
hand held 1 unit 277,500
Speaker 1 unit 388,650
Lampu coridor 1 unit 233,150
emergency cancle 1 unit 1,421,200
Lantai 1
Master Control 1 bh 83,828,000 83,828,000
Call Patien centre 5 bh 1,121,500 5,607,500
hand held 7 bh 277,500 1,942,500
Lampu coridor 5 bh 233,150 1,165,750
emergency cancle 5 bh 1,421,200 7,106,000
Bathroon pull cord 5 bh 344,250 1,721,250
HSPK 101,371,000
Lantai 2
Master Control 2 bh 83,828,000 167,656,000
Call Patien centre 22 bh 1,121,500 24,673,000
hand held 66 bh 233,150 15,387,900
Lampu coridor 23 bh 344,250 7,917,750
emergency cancle 23 bh 233,150 5,362,450
Bathroon pull cord 19 bh 277,500 5,272,500
HSPK 226,269,600
KABEL
FRC 4(1X240) mm² m 1 1800000 1800000
Tenaga Kerja :
Mandor Oh 0.025 58,000.00 1450
Tukang listrik Oh 0.050 50,000.00 2500
Pembantu tukang listrik Oh 0.050 40,000.00 2000
HSPK 1805950
3840000
2304000
7200000
2700000