RIVERSIDE DEVELOPMENT PILING WORK

AMOUNT
ITEM DESCRIPTION UNIT QTY RATE
RM

PILING WORKS

Notes:-

The contractor’s attention is drawn to boulders, hard


and soft rocks, etc. being present on site. He is
advised to probe for the presence of obstructions at
the position of the piles and remove all obstructions
before commencing the piling works. No additional
payments or extension of time will be allowed for
obstructions encountered during operations. Drive of
testing of piles shall be deemed to include the
provision of all pile testing equipment on site and
dismantling and removing the same on completion of
piling works

PILING EQUIPMENT

Allow for the provision of all necessary equipment


plant, piling frames, and tools an for their
transportation to the site handling, assembling
dismantling and removal off the site after completion
of the piling operations
Item 1 50,000.00 50,000.00

Allow for moving and handling equipment plant, etc.


about the site as often and wherever necessary for the
whole operations including all idling time, etc. Item 1 25,000.00 25,000.00

PILING RECORDS

Allow for the submission records of the installation of


all piles in triplicate dult signed by the contractor's
professional Engineer and deliver to the S.O. as the
work proceeds
Item 1 2,500.00 2,500.00

TESTING

Provide all necessary equipments, hydraulic jack,


defection gauges, kentledge, temporary staging, etc.
and test on initial test pile to a vertical load test of
twice allowable bearing capacity including all extra
costs in setting out and driving one pile before
commencement of the main piling work. No 1 1,500.00 1,500.00

Ditto and test a subsequent pile No 1 1,500.00 1,500.00

Pile Dynamic Analysis (PDA) Test No 2 1,000.00 2,000.00

To Collection RM 82,500.00

Page 2/1
RIVERSIDE DEVELOPMENT PILING WORK

AMOUNT
ITEM DESCRIPTION UNIT QTY RATE
RM

PILING WORK (CONT'D)

PAYABLE LENGTH

The installation of approved piles shall be measured


from toe level to existing ground level and paid for in
linear metre. No additional payment will be made for
cut off lengths or extra lengths added to the head of
the pile to suit the contractor’s method of working.

Rates to Include

All labour and materials for the complete pile inclusive


of wasteage.
-
Remove all cut off pile from the site.

The removal of all obstructions encountered including


disposal off site.

All driving through rocks, weathered rock, boulders


and the like.

Re-driving of heaved piles.

Replacement of incorrectly driven piles.

Replacement of defective/damaged piles and piles


failed under test.

Normal Wet Weather delays.

Standing time for equipment and labour for whatever


reasons.

Driving in cluster or singly.

Dolly and / or shoes including rock shoes.

Setting out pile points.

As-built drawings of all piled positions.

To Collection RM -

Page 1/2
RIVERSIDE DEVELOPMENT PILING WORK
AMOUNT
ITEM DESCRIPTION UNIT QTY RATE
RM

PILING WORKS (CONT'D)

THE FOLLOWING IN PRECAST REINFORCED


CONCRETE PILES AS DESCRIBED:-

Supply and deliver and unload on site 150mm x


150mm precast reinforced concrete piles as described
6.00m long as initial piles with and including all
reinforcement, moulds, lifting hooks and plates,
bands and all necessary 10mm thick fillet welding
No 83 173.40 14,392.20

Ditto 9.00m long as extension piles ditto No 129 260.10 33,552.90

Ditto 3.00m long as extension piles ditto No -

Handle, transport, and pitch vertical approved initial/


extension prescast square piles in 9m length. No 129 100.00 12,900.00

Handle, transport, and pitch vertical approved initial/


extension prescast square piles in 3m length. No -

Drive only approved precast concrete square piles to


final set required (to maximum 50m depth) m 1660 10.00 16,600.00

Labour and material for jointing 150mm x 150mm


precast reinforced concrete piles by butt weld as
described along the cirumferential groove of mild
steel and plates of the piles. No 83 15.00 1,245.00

Cut off 150mm x 150mm precast reinforced concrete


piles to required level and dispose of suplus length off
site and preparing pile head to receive pile cap as
described and in accordance to manufacturer's details
No 83 48.70 4,042.10

To Collection RM 82,732.20

Page 2/3
RIVERSIDE DEVELOPMENT PILING WORK
AMOUNT
ITEM DESCRIPTION UNIT QTY RATE
RM

COLLECTION

Page 2/1 82,500.00

Page 2/2 -

Page 2/3 82,732.20

SITE CLEARANCE AND EARTHWORK RM 165,232.20

Page 2/4