Vous êtes sur la page 1sur 14

BILL OF QUANTITY

Project CP Trishal Project 11/30/2018


Quotation: Kasetphand Industry Co.,Ltd Building BOILER BUILDING Total 4 Sheet
Owner CHAROEN POKPHAND
Unit Price Total Unit Price
No. Description of work Quantity Unit (Material+Labo Direct Cost Overhead (4%)
Material Labour ur)
A CIVIL WORK
Conducting survey work for layout of structures in/c road &
1
pavement in accordance with design and drawings.
54.11 Sqm - 38.67 38.67 2,092.28 83.69
- - - - -
Earth work including giving layout with the help of total
station excavation in foundattion trenches of any kinds of soils
including leveling, ramming and preparing the base, bailing out
water and shoring if necessary, providing centre line and bench
2 mark pillars, removing the spoils etc. to a lead not exceeding - - - - -
60m. checking the levels and keeping the earth by stacking at a
safe distace from the trench, providing necessary tools and
plants all complete as per specification and direction of the
Engineer-in-charge.
a) Up to 2.40m depth and 60 m lead. 131.64 cum - 274.16 274.16 36,090.23 1,443.61
- - - - -
Earth filling in foundation trenches and plinth in 150 mm
layer with earth available within 90 m of the building site,
3
watering, leveling and consolidating each layer up to finished
131.64 cum - 176.58 176.58 23,244.53 929.78
level etc. all complete as per direction of the engineer-in-charge.

- - - - -
Sand filling in foundation trenches and plinth in 150 mm
layer with sand of FM.0.80 in/c watering, leveling and
4 consolidation each layer up to finished level, compacted up to 44.97 cum 634.25 206.38 840.63 37,804.67 1,512.19
98% by mechanical device etc all complete as per design,
drawing and direction of the Engineer-in-charge .
- - - - -
(1:3:6) mass concrete in foundation or floor with cement
sand (FM 1.2) and picked jhama chips including breaking chips,
5 screening, mixing, laying, compacting to levels and curing for at 3.49 cum 4,852.11 970.42 5,822.53 20,335.01 813.40
least 7 days etc. all complete.as per specification and direction
of the Engineer-in-charge.
BILL OF QUANTITY
Project CP Trishal Project 11/30/2018
Quotation: Kasetphand Industry Co.,Ltd Building BOILER BUILDING Total 4 Sheet
Owner CHAROEN POKPHAND
Unit Price Total Unit Price
No. Description of work Quantity Unit (Material+Labo Direct Cost Overhead (4%)
Material Labour ur)
- - - - -
Laying double layer polythene sheet weighing 1.00kg per 6.5
6 sqm under soling of floor and grade beam etc all complete as 46.57 sqm 27.79 17.27 45.06 2,098.28 83.93
per direction of EIC
- - - - -
125 mm brick work with 1st class bricks in cement sand (F.M.
1.2) mortar (1 : 4) in super structure in/c filling the interstices
with mortar, raking out joints, cleaning and socking the bricks at
7
least for 24 hours before use and washing of sand, necessary
7.40 sqm 874.30 264.17 1,138.47 8,424.68 336.99
scaffolding, curing at least for 7 days etc. all complete. as
perspecification and direction of the engineer-in-charge.

- - - - -

Reinforced cement concrete works(1:1.5:3)/ (1:2:4) of


specified compressive strength, f'c 19 Mpa/21Mpa at 28 days
on standard cylinder with cement conforming to BDS 232 &
ASTM standards, best quality sand [50% quantity of best local
sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand
8 of equivalent F.M. 2.5] and 20 mm down well graded stone - - - - -
chips placing in position, making shutter water-tight properly,
placing reinforcement in position; mixing with mixer machine,
casting in forms, compacting by vibrator machine and curing at
least for 28 days, removing centering-shuttering all complete as
per specification and direction of the engineer-in-charge.

- - - - -
a) Footings (use stone chips wth ratio 1:1.5:3) 17.70 cum 10,360.00 1,551.71 11,911.71 210,861.09 8,434.44
- - - - -
b Column (use stone chips wth ratio 1:1.5:3) 10.75 cum 10,360.00 1,551.71 11,911.71 128,038.08 5,121.52
- - - - -
c) Foundation Beam (use stone chips wth ratio 1:1.5:3) 3.83 cum 10,360.00 1,551.71 11,911.71 45,607.75 1,824.31
BILL OF QUANTITY
Project CP Trishal Project 11/30/2018
Quotation: Kasetphand Industry Co.,Ltd Building BOILER BUILDING Total 4 Sheet
Owner CHAROEN POKPHAND
Unit Price Total Unit Price
No. Description of work Quantity Unit (Material+Labo Direct Cost Overhead (4%)
Material Labour ur)
- - - - -
d) Beam (use stone chips wth ratio 1:2:4) 13.20 cum 10,360.00 1,551.71 11,911.71 157,293.60 6,291.74
- - - - -
e) Water tank slab (use stone chips wth ratio 1:2:4) 4.98 cum 10,360.00 1,943.04 12,303.04 61,237.90 2,449.52
- - - - -
f) Water tank RCC wall (use stone chips wth ratio 1:2:4) 19.77 cum 10,360.00 1,951.71 12,311.71 243,383.14 9,735.33
- - - - -
Supplying, fabrication and fixing to details of M.S
deformed bar reinforcement of required size and length for all
types of RCC work in/c straightening the rod, removing rusts,
cleaning, cutting, hooking, bending, binding with 22 B.W.G. GI
9
wire, placing the bars in position, in/c lapping, spacing and
- - - - -
securing them in position by concrete blocks, metal chairs, etc.
complete as per specifications, drawings and direction of the E-
I-C.
60 grade deformed bar with minimum fy = 415 Mpa, ultimate
strength 620 Mpa
9.45 Ton 59,000.00 8,733.80 67,733.80 639,885.05 25,595.40
- - - - -
Minimum 12 mm thick cement sand (F.M. 1.2) plaster
(1:4) having with fresh cement(conforming to BDS 232) to wall
outer surface, finishing the corner and edges in/c washing of
10
sand cleaning the surface, scaffolding and curing at least for 7
83.21 sqm 131.20 166.70 297.90 24,789.13 991.57
days, all complete in all respect as per drawing and direction of
the Plant Manager.
- - - - -
BILL OF QUANTITY
Project CP Trishal Project 11/30/2018
Quotation: Kasetphand Industry Co.,Ltd Building BOILER BUILDING Total 4 Sheet
Owner CHAROEN POKPHAND
Unit Price Total Unit Price
No. Description of work Quantity Unit (Material+Labo Direct Cost Overhead (4%)
Material Labour ur)
Minimum 12 mm thick cement sand (F.M. 1.2) plaster with
neat cement finishing to plinth wall (1:5) with cement
(conforming to BDS 232) up to 150 mm below ground level with
11
neat cement finishing in/c washing of sand, finishing the edges
165.88 sqm 131.20 166.70 297.90 49,414.49 1,976.58
and corners and curing at least for 7 days, all complete in all
respect as per drawing and direction of the engineer-in-charge.

- - - - -
Supply & Works of Wheather coat on out side wall of
approved quality and colour delivered from authorized local
agent of the manufacturer in a sealed container, made from
water based powder mixed with water (1:1), applying first coat,
curing the same after six hours for 24 hours, second coat
12
applied and curing the same for 7 (seven) days etc, taking care
- - - - -
and cleaning the surface fully from grease, oily substances, old
paints, lime wash, fungus, algae etc., sand papering the surface
before applying 1st and 2nd coat, complete as per direction of
the engineer-in-charge.
i) Berger: Durocem 83.21 sqm 154.77 91.20 245.97 20,468.20 818.73
- - - - -
Supplying fitting & fixing 600mm dia CI manhole cover as
13
per drawing & direction of the Engineer in charge.
2.00 no's 5,527.50 552.75 6,080.25 12,160.50 486.42
- - -
Total A. 1,723,228.60 68,929.14

B STEEL WORK
BILL OF QUANTITY
Project CP Trishal Project 11/30/2018
Quotation: Kasetphand Industry Co.,Ltd Building BOILER BUILDING Total 4 Sheet
Owner CHAROEN POKPHAND
Unit Price Total Unit Price
No. Description of work Quantity Unit (Material+Labo Direct Cost Overhead (4%)
Material Labour ur)
Supply of Super structure Member Built up section
Column, Main Beam, Joist, Beam for stair, Base plate,
End plate, Connection plate, Cleat etc. by (M.S Plate.
1
ASTM-A570-50). Minimum yield strength-345 Mpa. All
8500.65 Kg 150.00 84.86 234.86 1,996,447.84 79,857.91
completed as per our design including one coat primer delivery
at site
- - - - -
Supply of Stainless Steel (S.S) plate by 6.0mm thick (S.S
2 Plate. ASTM-A570-50). Minimum yield strength-345 Mpa as per 4271.28 kg 1,492.43 574.86 2,067.29 8,829,947.75 353,197.91
design all complete delivery at site
- - - - -
Supply of Galvanized Anchor Bolt including nut & washer as
3
per design delivery at site
34.03 Kg
184.82 82.07 266.88 9,082.75 363.31
- - - - -
Supply of Angle Cross Bracing of 63x63x4mm by (M.S
Plate. ASTM-A570-50). Minimum yield strength-345 Mpa. All
4
completed as per our design including one coat primer delivery
1231.01 Kg 156.97 193,228.65 7,729.15
at site 120.74 36.22
- - - - -
Supply of Double Angle Clip by (M.S Plate. ASTM-A570-
5 50). Minimum yield strength-345 Mpa. All completed as per our 210.59 Kg 189.73 101.84 291.57 61,401.93 2,456.08
design including one coat primer delivery at site
- - - - -
Supplying, fitting and fixing of M.S. pipe all complete as per
6
design drawing and instruction of the Engineer in charge.
89.60 Rm 1,989.90 165.83 2,155.73 193,149.13 7,725.97
(75 mm dia M.S. pipe, Th=4mm) - - - - -
- - - - -
BILL OF QUANTITY
Project CP Trishal Project 11/30/2018
Quotation: Kasetphand Industry Co.,Ltd Building BOILER BUILDING Total 4 Sheet
Owner CHAROEN POKPHAND
Unit Price Total Unit Price
No. Description of work Quantity Unit (Material+Labo Direct Cost Overhead (4%)
Material Labour ur)
Supplying, fitting and fixing of MS pipe hand raiiling of
height 1000 mm, top of railling 2 mm thick 37.5 mm dia pipe, 2
mm thick 25 mm dia vertical post @ 300 mm c/c intermidiate 3
7
no's 2 mm thick 20 mm dia pipe, including welding and fixing
30.71 Rm 2,763.75 773.85 3,537.60 108,626.08 4,345.04
with floor beam & 3 coat anamel painting etc all complete as per
design drawing and instruction of the Engineer in charge.

- - - - -
Supplying, fitting and fixing Ladder, all complete as per
8
design drawing and instruction of the Engineer in charge.
20.00 Rm 10,557.53 1,105.50 11,663.03 233,260.50 9,330.42
- - - - -
Supplying and Painting work on steel surface by approved
9 color enamel paint by consultant ; Berger / Elite or equivalent 365.63 Sqm 154.77 91.20 245.97 89,936.24 3,597.45
Brand.
- - - - -
Supply of Nut bolt, Self Drilling screw including washer
10
delivery at site.
- - - - -
a) 16x75 mm Primary Connection bolt.(71 K) 322.00 Pcs 143.72 71.86 215.57 69,414.35 2,776.57
- - - - -
b) 12x35 mm Secondary Connection bolt. (25 kg) 621.00 Pcs 110.55 60.80 171.35 106,409.90 4,256.40
- - - - -
Erection of pre-engineered welded sheet , Column, Rafter,
purlin girt,and fitting & fixing charge of roof & wall sheeting in/c
11
Capping, Flashing, Gutter, Down pipe ,etc(basis on floor area)
167.00 Sqm - 2,054.10 2,054.10 343,034.70 13,721.39
per drawing all complete as per site in charge

Total B. 12,233,939.82 489,357.59

Grand Total (A+B) 13,957,168.41 558,286.74

Direct Cost Overhead (4%)


BILL OF QUANTITY
Project CP Trishal Project 11/30/2018
Quotation: Kasetphand Industry Co.,Ltd Building BOILER BUILDING Total 4 Sheet
Owner CHAROEN POKPHAND
Unit Price Total Unit Price
No. Description of work Quantity Unit (Material+Labo Direct Cost Overhead (4%)
Material Labour ur) Direct Cost Overhead (4%)
Total cost Profit (10%) Sub Total VAT (6%) Grand Total

2,175.97 217.60 2,393.57 143.61 2,537.18


- - - - -

- - - - -

37,533.84 3,753.38 41,287.22 2,477.23 43,764.46


- - - - -

24,174.31 2,417.43 26,591.74 1,595.50 28,187.24

- - - - -

39,316.86 3,931.69 43,248.54 2,594.91 45,843.46

- - - - -

21,148.41 2,114.84 23,263.25 1,395.79 24,659.04


Total cost Profit (10%) Sub Total VAT (6%) Grand Total
- - - - -

2,182.21 218.22 2,400.43 144.03 2,544.45

- - - - -

8,761.67 876.17 9,637.83 578.27 10,216.10

- - - - -

- - - - -

- - - - -
219,295.53 21,929.55 241,225.08 14,473.50 255,698.59
- - - - -
133,159.60 13,315.96 146,475.56 8,788.53 155,264.09
- - - - -
47,432.06 4,743.21 52,175.26 3,130.52 55,305.78
Total cost Profit (10%) Sub Total VAT (6%) Grand Total
- - - - -
163,585.34 16,358.53 179,943.88 10,796.63 190,740.51
- - - - -
63,687.42 6,368.74 70,056.16 4,203.37 74,259.53
- - - - -
253,118.47 25,311.85 278,430.31 16,705.82 295,136.13
- - - - -

- - - - -

665,480.46 66,548.05 732,028.50 43,921.71 775,950.21


- - - - -

25,780.70 2,578.07 28,358.77 1,701.53 30,060.29

- - - - -
Total cost Profit (10%) Sub Total VAT (6%) Grand Total

51,391.07 5,139.11 56,530.17 3,391.81 59,921.98

- - - - -

- - - - -

21,286.93 2,128.69 23,415.62 1,404.94 24,820.56


- - - - -
12,646.92 1,264.69 13,911.61 834.70 14,746.31
- - - - -
1,792,157.74 179,215.77 1,971,373.51 118,282.41 2,089,655.92
Total cost Profit (10%) Sub Total VAT (6%) Grand Total

2,076,305.75 207,630.58 2,283,936.33 137,036.18 2,420,972.51

- - - - -

9,183,145.66 918,314.57 10,101,460.22 606,087.61 10,707,547.84

- - - - -
9,446.06 944.61 10,390.67 623.44 11,014.11
- - - - -

200,957.80 20,095.78 221,053.58 13,263.21 234,316.79

- - - - -

63,858.00 6,385.80 70,243.80 4,214.63 74,458.43

- - - - -
200,875.09 20,087.51 220,962.60 13,257.76 234,220.36
- - - - -
- - - - -
Total cost Profit (10%) Sub Total VAT (6%) Grand Total

112,971.13 11,297.11 124,268.24 7,456.09 131,724.33

- - - - -
242,590.92 24,259.09 266,850.01 16,011.00 282,861.01
- - - - -

93,533.69 9,353.37 102,887.06 6,173.22 109,060.28

- - - - -
- - - - -
72,190.92 7,219.09 79,410.01 4,764.60 84,174.61
- - - - -
110,666.30 11,066.63 121,732.93 7,303.98 129,036.90
- - - - -

356,756.09 35,675.61 392,431.70 23,545.90 415,977.60

12,723,297.41 1,272,329.74 13,995,627.15 839,737.63 14,835,364.78

14,515,455.15 1,451,545.52 15,967,000.67 958,020.04 16,925,020.71

Total cost Profit (10%) Sub Total VAT (6%) Grand Total
Total cost Profit (10%) Sub Total VAT (6%) Grand Total
Total cost Profit (10%) Sub Total VAT (6%) Grand Total

Vous aimerez peut-être aussi