as per ASTM

Project:Dhaka Metro Uttara RSS


Topic :Schedule for Field & Laboratory Test & report submission for Soil Investigation
Dec-18
Sl.No Description of works 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 Mobilization of team to the site
2 Boring Works including positioning, shifting of rigs
3 Bore‐log data submission(Field collected data)
4 Laboratory test and analysis
5 Test Pit and Electrical Resistivity Test
6 Preparation & Submission of soil report consulatnts
7 Cosultant approval/commets
8 Resubmisson & approval ( if required)

# Sensitivity: LNT Construction Internal Use


APPENDIX A :
CURRICULUM VITAE
1. Proposed Position : Geotechnical Engineer
2. Name of Firm : Prosoil Foundation Consultant

3. Name of Staff : Avijeet Kumar Ghosh

4. Date of Birth : 02 February 1994 Nationality: Bangladeshi

5. Education : Institution Degree year


University of Asia Pacific B. Sc. In Civil Engineering 2016

6. Membership in Professional : Associate Member, The Institution of Engineers, Bangladesh


Associations
7. Countries of Work : Bangladesh
Experience
8. Languages : Language Spoken Reading writing

English Good Good Good


Bangla Good Good Good
9. Employment Record :
Since June 2016 : To June 2017
Employer : Amin Design & Consultancy
Position Held : Assistant Engineer
Subsurface - Soil investigation for Ruppur Nuclear Power Plant Project.

Up to 25m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index were performed in the laboratory and
prepared soil test report. The shallow foundation designed by using the laboratory
test data.

Western Bangladesh Bridge Improvement Project.

Performed 50m-70m depth boring at the site. Disturbed and Undisturbed samples
collected from the holes. Grain size distribution and Hydrometer Analysis,
Atterberg Limit, Moisture Content, Specific Gravity, Unit Weight, Direct Shear
Test, Unconfined Compression Test, Consolidation Test, Other Physical &
Mechanical Properties were performed in the laboratory, prepared soil profile in
AutoCAD and soil test report.

Construction of Dual Gauge Double Rail Line and Conversion of existing


Rail Line into Dual Gauge between Akhaura and Laksam. (Bangladesh
Railway).

Up to 50m depth boring performed at the site. Disturbed and Undisturbed


samples collected from the holes. Grain size distribution and Hydrometer
Analysis, Atterberg Limit, Moisture Content, Specific Gravity, Unit Weight, Direct
Shear Test, Unconfined Compression Test, Consolidation Test, Other Physical &
Mechanical Properties were performed in the laboratory, prepared soil profile in
AutoCAD and soil test report.
Geotechnical Investigation of PC Capacity Expansion Project, KGF,
Chittagong. (Unilever Bangladesh Limited, Larsen & Toubro).

Up to 55m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index, Unconfined compression test for cohesive,
Consolidation test for cohesive soil, Specific gravity, Direct Shear test
(Consolidated drain test), (i) Chemical Analysis (test to be conducted) (i) PH,
(ii)Chlorides, (iii) Sulphates.

Proposed cycle way and walkway from Kolatoli to Laboni point.


(Bangladesh Army).

Up to 15m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index were performed in the laboratory and
prepared soil test report. The shallow foundation designed by using the laboratory
test data.

Subsurface-Soil investigation and foundation design for an Industrial


Building at Saver, Dhaka, Bangladesh. (Mutual Apparels Ltd. Project).

Up to 18m depth boring performed at the site. Natural moisture content, Unit
Weight of soil, Grain Size Analysis of soil by sieve and hydrometer analysis &
Specific gravity test, Plasticity Index were performed in the laboratory and
prepared soil test report. The shallow foundation designed by using the laboratory
test data.

Since July 2017 : To December 2017


Employer : LGED, Kalyan Samabay Samity, LKSS Engineering Unit.
Position Held : Assistant Engineer
terials (Soil, Aggregate, Cement)

to the projects from all over the


Bangladesh

Since January 2018 Till Now

Employer Prosoil Foundation Consultant

Position Held Geotechnical Engineer

Performed 50m depth boring in the river Bakhkhali and in the river bank. Disturbed
samples collected from the holes
the consultancy of NKDM Association
Up to 53m depth boring performed at site. Disturbed and undisturbed samples
collected from the holes.

10. RESEARCH EXPERIENCE

ate on Self-Compacting Concrete: Rheological and Mechanical


ineer Ariful Hasnat, Assistant Professor, University of Asia Pacific.

Date: 30-04-18

[Signature] Day/Month/Year
Page 1 of

FORM 5A8 CURRICULUM VITAE (CV) OF PROPOSED PROFESSIONAL STAFF

1. Proposed Position : Geotechnical Engineer

2. Name of Firm : Prosoil Foundation Consultant

3 Name of Staff : Asaduzzaman Chowdhury


4 Date of Birth : 04 April 1995 Nationality: Bangladeshi

5. Education : Institution Degree Year


ISLAMIC UNIVERSITY OF B. Sc. In Civil Engineering 2017
TECHNOLOGY.

6. Other Trainings : Joydebpur BRT Depot, MRT project at Uttara.


Design training by McDonald Steel

8. Countries of Work Experience : Bangladesh


9. Languages : Language Speaking Reading Writing
English Excellent Excellent Excellent
Bengali Excellent Excellent Excellent
10. Employment Record :
From November 2017 : To Present
Employer : Prosoil Foundation
Positions held : Geo Technical Engineer
11. Detailed Tasks Assigned 12. Work Undertaken that Best Illustrates Capability to Handle the Tasks
Assigned
To carry out geotechnical study,
To supervise and coordinate sub- Name of assignment or project: Dhaka Mass Rapid Transit Development
soil investigations. Project Line-5.
Year: September 2017 to present.
Location: Bangladesh.
Client: Oriental Consultants Global Co., Ltd. et. al.
Main project features: Geotechnical survey
Positions held: Geo Technical Engineer.
Activities performed: Responsible for geotechnical survey investigation,
laboratory test and report preparation in connection with civil works

Name of assignment or project: Dhaka Mass Rapid Transit Development


Project Line-1.
Year: November 2017 to present.
Location: Bangladesh.
Client: Oriental Consultants Global Co., Ltd. et. al.
Main project features: Geotechnical survey
Positions held: Geo Technical Engineer.
Activities performed: Responsible for geotechnical survey investigation.

Name of assignment or project: Dhaka Mass Rapid Transit Development


Project Line-6.
Year: November 2017 to present.
Location: Bangladesh.
Client: Oriental Consultants Global Co., Ltd. et. al.
Main project features: Geotechnical survey
Positions held: Geo Technical Engineer.
Activities performed: Responsible for geotechnical survey investigation.

Asaduzzaman Chowdhury
Page 1 of

FORM 5A8 CURRICULUM VITAE (CV) OF PROPOSED PROFESSIONAL STAFF

1. Proposed Position : Geotechnical Engineer

2. Name of Firm : Prosoil Foundation Consultant

3 Name of Staff : Shaber Ahmed Hossain


4 Date of Birth : 01 January, 1994 Nationality: Bangladeshi

5. Education : Institution Degree Year


ISLAMIC UNIVERSITY OF B. Sc. In Civil Engineering 2017
TECHNOLOGY.

6. Other Trainings : Joydebpur BRT Depot, MRT project at Uttara.


Design training by McDonald Steel

8. Countries of Work Experience : Bangladesh


9. Languages : Language Speaking Reading Writing
English Excellent Excellent Excellent
Bengali Excellent Excellent Excellent
10. Employment Record :
From November 2017 : To Present
Employer : Prosoil Foundation
Positions held : Geo Technical Engineer
11. Detailed Tasks Assigned 12. Work Undertaken that Best Illustrates Capability to Handle the Tasks
Assigned
To carry out geotechnical study,
To supervise and coordinate sub- Name of assignment or project: Dhaka Mass Rapid Transit Development
soil investigations. Project Line-5.
Year: September 2017 to present.
Location: Bangladesh.
Client: Oriental Consultants Global Co., Ltd. et. al.
Main project features: Geotechnical survey
Positions held: Geo Technical Engineer.
Activities performed: Responsible for geotechnical survey investigation,
laboratory test and report preparation in connection with civil works

Name of assignment or project: Dhaka Mass Rapid Transit Development


Project Line-1.
Year: November 2017 to present.
Location: Bangladesh.
Client: Oriental Consultants Global Co., Ltd. et. al.
Main project features: Geotechnical survey
Positions held: Geo Technical Engineer.
Activities performed: Responsible for geotechnical survey investigation.

Name of assignment or project: Dhaka Mass Rapid Transit Development


Project Line-6.
Year: November 2017 to present.
Location: Bangladesh.
Client: Oriental Consultants Global Co., Ltd. et. al.
Main project features: Geotechnical survey
Positions held: Geo Technical Engineer.
Activities performed: Responsible for geotechnical survey investigation.

Shaber Ahmed Hossain


LARSEN & TOUBRO LIMITED
CONTRACT No: CP-07: Procurement of E&M Systems
Description of request for approval : Method Statement for Soil Investigation
Document No: Revision no.: 001 Dated :
Clint Ref. No:
Our Ref. No:
Contract Ref. Volume/Title/Page/Clause: Volume 3/part/2/page no.:41/Cl 11.6
Reply To Comments
Drg / Doc CSD No.:
Sl. no. NKDM comments L&T's reply

You have to submitted the Method satetment for the soil


investigation for the following tests. Noted :- Please find attached the revised Method Statement
for Soil Investigation received from M/S Prosoil for your kind
a) Bore hole
review of approval.
b) Trial Pit
c) Plate Load Test
d) CBR Test
e) Earth resistity test.
However, the following may be included in method statement.

a) Working shifts per day ( 1shifts or 2 Shifts ) or no of working


hours per day
b) Workable days : Describe the holiays and non workable days
c) Capacity & model of equipment to be used.
d) Cycle time & work sequence for each test/work.
e) No. of workers per shifts. Attached in revised Metod Statement.
f) List of material to be described.
g) Name of Laboratory.

h) Time schedule from the start of work until submission of


results to be described with the time table
Marubeni-L&T JV
HAZARD IDENTIFICATION AND RISK ASSESSMENT
Region : DHAKA,BANGLADESH
Name of the Job Site : Contract CP07-Procurement of E&M systems for MRT Line-6 Ref: IM 6.1.2 A Rev 05
Name of the Main Activity : Geotechnical Activity – Soil Investigation, Trial Pits, Electrical Resistivity Test
Name of the project: : 132kV RSS with Cabling for Dhaka Metro CP-07 ( LE180882)

Routine/ Legal
Sl Non- Evaluation of After existing
Activity Hazards Consequences / Risk Require Existing Control Measures Additional Control Responsibility
No Routine / Hazard control measure
ments
Emergency
Situation Proba Seve Risk Proba Sever Risk
(R/NR/E) bility rity Level bility ity Level
H=Fx
A B C D E F G I J K L=JxK M
G
• Minor Injury to person
• First Aid Injury 1.Follow Kinetic method of lifting
• Improper posture
• Low Back ache, Neck, a) Proper posture while lifting Area Incharge,
during material handling,
R shoulder and body pain, • Yes 3 4 12 b) Training of personnel is required for manual material handling. 2 4 8 Site Engineer/
loading and unloading.
fatigue 2. Use of Safety Helmet, Safety steel toe Shoes, Cotton /leather hand Supervisor
gloves etc. while handling material manually.

1. During the transportation of the materials by truck and trailer etc.,


Material handling avoid overloading
1 manually/ a) stores representative/ site supervisor to check loading before dispatch
Mechanically of truck.
b) Mark overhanging material with red flag/light.
• Injury to person Area Incharge,
• Fall of material c) Loaded vehicle to move at slow speed (15-20 KMPH)
R • Damage to property No 4 4 16 3 4 12 Site Engineer/
• Sharp Edges d) Trained person to tie-up load.
• LTA Supervisor
2. An authorized signalman should control all lifting operations at site·
3. Reversing procedure to be followed
4. Use of reverse horns
5. Use of cell phones to be restricted while in operation

1. Use standard & tested quality wire ropes & slings.


2. Use packing below the slings to avoid sling damage.
• Failure of wire ropes • Fatality
3. Use correct no. of dog clamps. Area Incharge,
• Snapping of wire • Major Accident 1. Ensure periodic
R/E Yes 4 5 20 4. Crane & its lifting tools/tackles should be inspected weekly basis. 3 4 12 Site Engineer/
• Crane movement/ • LTA inspection of boring rig.
5. Crane must be fit for deployment of work & reverse horn of crane Supervisor
reversing • Property Damage
should be working.
6. Personnel to be kept away from radius of operation of crane.
1. Inspect boom of crane once in a week for damages, cracks if any
2. Lift within SWL & follow approved lifting plan.
• Failure of boom
3. Ensure that the area is barricaded and personnel kept away
• Malfunctioning of crane
4. ASLI must be installed & ensure its use.
(overloading and
5. Ensure that brakes, limit switch, boom alarm, swing horn and over
or working beyond limits)
Tripod Rig Erection & hoist and safe load indicators are working properly.
• Miscommunication • Injury to Person Section Incharge,
Hydraulic machine a) Trained operator
between signalman NR/E • Property Damage Yes 4 4 16 3 4 12 Site Engineer/
2 installation b) Isolation of area
• Swing area of crane • Fatality Supervisor
(Erection with the help c) Preventive maintenance
when crane is in use
of crane & manually) 6. Operation should be carried out with authorized signalmen only.
• Fall of suspended load
a) Training of signalman
while crane is in
b) Isolation of area
operation.
c) Restriction of unauthorized person
7. Do not leave suspended load
Marubeni-L&T JV
HAZARD IDENTIFICATION AND RISK ASSESSMENT
Region : DHAKA,BANGLADESH
Name of the Job Site : Contract CP07-Procurement of E&M systems for MRT Line-6 Ref: IM 6.1.2 A Rev 05
Name of the Main Activity : Geotechnical Activity – Soil Investigation, Trial Pits, Electrical Resistivity Test
Name of the project: : 132kV RSS with Cabling for Dhaka Metro CP-07 ( LE180882)
Tripod Rig Erection &
Routine/ Legal
Sl Hydraulic machine Evaluation of After existing
Activity Hazards Non- Consequences / Risk Require Existing Control Measures Additional Control Responsibility
2
No installation Hazard control measure
Routine / ments
(Erection with the help
Emergency
of crane & manually)
Situation Proba Seve Risk Proba Sever Risk
(R/NR/E) bility rity Level bility ity Level
H=Fx
A B C D E F G I J K L=JxK M
G
1. Ensure cabin glass is not broken and rain water is not coming inside
the cabin.
• Adverse weather, rain,
2. Also ensure before starting cabins windows are clean. Section Incharge,
sun, storm etc.
• Injury a) Preventive maintenance Area Incharge
• Poor visibility and R Yes 2 5 10 1 5 5
• Major Accident b) Check equipment immediately after rain Site Engineer/
incorrect lifting
3. Ensure cleaning of glass and windows Supervisor
procedure.
4. Don't work in adverse weather condition
5. Training of operators in lifting procedures
Material handling
1 manually/ 1. All rotating parts of rig should be guarded
Mechanically 2. Pulley & wire ropes should be checked everyday & greased regularly.
Any damages found immediately replace the same.
• All rotating parts of rig 3. To be checked sufficient no of dog clamps with thimble are provided
• Failure of wire • Injury for wire ropes fixing. Section Incharge,
rope/pulley R • First Aid Yes 4 4 16 4. Shear legs of tripod should be damaged / cracked free. All steps of 3 4 12 Site Engineer/
• Failure of legs • LTA shear legs must be take workmen load. Supervisor
• Height work 5. At height work use full body double lanyard safety harness while
ascending & descending on legs of tripod.
6. Use all mandatory PPE at site.(Safety Helmet, Reflective vest, Safety
shoes/ Gum boots, safety harness, hand gloves etc.)

1. Tripod shear legs should keep on hard consolidated and level base.
2. All workmen should aware about risk & mitigation measures of rotary
• Loose Soil/ Uncompact parts & linear movement of wire ropes.
• Injury 1. Ensure soil strength &
soil 3. Use base plate/ Shear legs shoes below the legs of tripod. Section Incharge,
• First Aid shear leg's base plate with
• Topple of tripod rig R/NR No 4 4 16 4. Shear legs shoes should be pinned to prevent toppling over of shear 3 4 12 Site Engineer/
• LTA anchoring pins are locked
• Subside of tripod legs legs. Supervisor
• Fatal with soil.
• Fall of material 5. Wire rope should be tied properly at the chisel / bailer end.
5. Use always safety helmet in working area.
6. Unauthorized operation/entry should be strictly restricted.

1. Skilled, trained & authorized operator should be deployed.


• Unskilled / Section Incharge,
2. Unauthorized operation should be strictly restricted.
Boring, Sampling, Unauthorized operator NR • LTA Yes 4 4 16 3 4 12 Site Engineer/
3 3. Never allow helper as an operator for operating winch machine.
Testing • Loose Clothes • Fatal Supervisor
4. Never use loose clothes while working over tripod rig.
Marubeni-L&T JV
HAZARD IDENTIFICATION AND RISK ASSESSMENT
Region : DHAKA,BANGLADESH
Name of the Job Site : Contract CP07-Procurement of E&M systems for MRT Line-6 Ref: IM 6.1.2 A Rev 05
Name of the Main Activity : Geotechnical Activity – Soil Investigation, Trial Pits, Electrical Resistivity Test
Name of the project: : 132kV RSS with Cabling for Dhaka Metro CP-07 ( LE180882)

Routine/ Legal
Sl Non- Evaluation of After existing
Activity Hazards Consequences / Risk Require Existing Control Measures Additional Control Responsibility
No Routine / Hazard control measure
ments
Emergency
Situation Proba Seve Risk Proba Sever Risk
(R/NR/E) bility rity Level bility ity Level
Boring, Sampling,
3 H=Fx
Testing
A B C D E F G I J K L=JxK M
G

1. Bore casing should be atleast 30cm above the ground. bore hole
should be protected against fall of person inside.
2. All opening of bore should be covered by using bore caps or grating.
3. Working area should be barricaded & waring/ Danger sign boards to
• Bore opening be displayed.
• Fall of material 4. Strictly avoid other vehicle movements near the working zone.
• Fall of person in bored 5. All material/ equipment's should be stacked away from the bored pile. 1. Strictly ensure hard Section Incharge,
Material handling • LTA
pit R No 4 4 16 6. Hard barricade with Blinking light should be installed for identification 3 4 12 barricading of bore Site Engineer/
1 manually/ • Fatal
• Mud/ Slush/ water of hazard in night & provide adequate illumination for night work. opening area. Supervisor
Mechanically • Major accident
logging area 7. Use gumboots working near muddy/ slush area.
• Slip /Trip/ Fall 8. Dewatering should be done at working area if water logged area
exists.
9. Regular inspection of work area & tripod rig should be done by
concern engineer/ supervisor
10. Maintain good housekeeping near the working area.

1. Ensure correct fire extinguishers are supplied and in good working


• LTA condition.
• Fire
NR • Fatal Yes 4 4 16 2. Ensure fire extinguishers are in date and fit for purpose 3 4 12
• Oil Spillage
• Property Damage 3. Maintain good housekeeping on daily basis.
• Environment incident 4. Use oil / diesel spillage kit for avoid any spillage.
Marubeni-L&T JV
HAZARD IDENTIFICATION AND RISK ASSESSMENT
Region : DHAKA,BANGLADESH
Name of the Job Site : Contract CP07-Procurement of E&M systems for MRT Line-6 Ref: IM 6.1.2 A Rev 05
Name of the Main Activity : Geotechnical Activity – Soil Investigation, Trial Pits, Electrical Resistivity Test
Name of the project: : 132kV RSS with Cabling for Dhaka Metro CP-07 ( LE180882)

Routine/ Legal
Sl Non- Evaluation of After existing
Activity Hazards Consequences / Risk Require Existing Control Measures Additional Control Responsibility
No Routine / Hazard control measure
ments
Emergency
Situation Proba Seve Risk Proba Sever Risk
(R/NR/E) bility rity Level bility ity Level
H=Fx
A B C D E F G I J K L=JxK M
G
1. Use only approved equipment and deploy competent operator.
2. Adhere to permit to work system
3. Inspect machine (Excavator) before starting the job.
4. If excavation is manually - all tool should be insulated & Make sure
absence of underground utilities.
5. Don't stack material at the edges of excavated pit. (atleast 2 m away
• Fall of person into pit
from the edge or depth of excavation whichever is more)
• Fall of heavy objects
6. Provide hard barricade with sign boards surrounding to the excavated
Material handling stone, boulder, soil etc. 1. For finding out
• Injury to person pit.
1 manually/ into pit underground utilities to
• Property Damage 7. As per soil type should be make benching & sloping.(Maintain angle of
Mechanically • Cave-in/ side wall be used earth penetrating Section Incharge,
• LTA repose as per classification of soil)
collapse R/NR Yes 3 4 12 2 4 8 radar (If exists) Site Engineer/
• Electric shock 8. Ensure safe access/ egress while working in pits & also ensure
• Working near 2. Ensure all tools shall be Supervisor
5 Trial Pit/ Excavation • Overhead powerlines • Electrocution emergency exit.
well insulated to prevent
• Drowning 9. Ensuring Vehicle/ Equipment are stopped far away from the edge of
• Defective Machinery electrical shock.
excavated area at least 2m or equal distance of depth of excavation
• Water accumulation in
whichever is more.
pit
10. Maintained safe clearance distance from live cables (As per
electricity rule)
11. Body earthing is providing for equipment for avoid induction.
12. Dewatering pump should be arranged for accumulated water
removal.
13. Pep-talk & training to be conducted to workmen on Excavation safety.
1. To be make an arrangement for water sprinkling against dust.
• Health related illness
• Dust 2. Ear plug/ ear muff are using.
R (Lungs Cancer) Yes 2 4 8 1 4 4 Site Engineer/
• Noise 3. Nose mask to be provided to workmen.
• NIHL Supervisor
1. Work area should be baricaded.
2. Use standard tools & use right tool for right job.
3. If vehicle movement is present, divert the trafic/ vehicle movement.
4. Be certain the circuit is deenergized and discharged before connecting
• Nearby Vehicle
resistant tester.
movement • Injury 1. Ensure standard tools
5. Do not apply power to a circuit while measuring resistance.
Electrical Resistivity • Bare conductor • LTA Section Incharge,
6 NR No 2 5 10 6. When you are finished using an measuring apparatus, switch it to the 1 5 5 & equipements are using
Test • Faulty apparatus • Electrocution Site Engineer/
OFF position. while conducting test.
• Loose connection • Electric shock Supervisor
7. Don't touch any lead/terminal of appratus when the testing starts.
• Damaged cables/wires
8. Trained & skilled person should have deployed for work.
9. Unauthorised entry to be restricted in work area.
10. Use all necessary PPE (Safety Helmet, Safety Shoes, Reflective
jackets, Rated electrical rubber hand gloves etc.)

_________________ _________________
PM / CM / Section Head EHSO
E=Elimination
S=Substitution AC=Administrative controls
EC=Engineering controls PPE=Personal Protective Equipment