Académique Documents
Professionnel Documents
Culture Documents
Document
GETABEC
Third Party Contractor
Reference Document/Drawings/ Standard Production QA/QC
Item Area of activity Quality control activity Acceptance Criteria
Code
Point
Point
Point
Point
Signature Date Signature Date Signature Date Signature Date
1 Specification Verity that all relevant document have been received Client order and requisition
5 Welding Procedure & Qualification Verify to meet Code & specification Drawing for construction EN 15614-1
6 Welder & Qualification Verify to meet Code & specification WPS EN 287-1
7 Pre-fabrication
7.1 Shell
7.1.1 1) Material Material identification check Material identification record EN 12953-4:2002 - 5.2
7.1.3 3) Cutting & beveling Visual & Edge preparation check Drawing for con., WPS EN 12953-4:2002 - 5.15
7.1.4 4) Fit-up plate to plate a) Dimension check Drawing for con., WPS As Drawing
(alignment,gap,cleanliness inspection)
7.1.7 7) Cold Rolling & fit-up a) roundness & dimension check Drawing for con. EN 12953-4:2002 - 5.15
(alignment,gap,cleanliness inspection)
(alignment,gap,cleanliness inspection)
7.2.1 1) Material Material identification check Material identification record EN 12953-4:2002 - 5.2
7.2.3 3) Cutting & beveling Visual & Edge preparation check Drawing for con., WPS EN 12953-4:2002 - 5.15
(alignment,gap,cleanliness inspection)
7.3.1 1) Material Material identification check Material identification record EN 12953-4:2002 - 5.2
7.3.3 3) Cutting & beveling Edge preparation check Drawing for con., WPS EN 12953-4:2002 - 5.15
(alignment,gap,cleanliness inspection)
(alignment,gap,cleanliness inspection)
7.3.2 2) Tube Expansion a) Visual and Dimension Check As Drawing for construction As Drawing
7.3.2 3)Seal Welding a) Review WPS, welder certificates and visual Weld map,welding&NDESchedule EN 15614,287
7.4.1 1) Material Material identification check Material identification record EN 12953-4:2002 - 5.2
7.4.3 3) Cutting & beveling Edge preparation check Drawing for con., WPS EN 12953-4:2002 - 5.15
(alignment,gap,cleanliness inspection)
7.5 Nozzle
7.5.3 3) Cutting & grinding Edge preparation check Drawing for con., WPS EN 12953-4:2002 - 5.15
7.5.4 4) Fit-up flange to neck & weld a) Dimension check Drawing for con., WPS As drawing
Document
GETABEC
Third Party Contractor
Reference Document/Drawings/ Standard Production QA/QC
Item Area of activity Quality control activity Acceptance Criteria
Code
Point
Point
Point
Point
Signature Date Signature Date Signature Date Signature Date
a) Final dimension check Drawing for con., WPS,Weldmap EN 15614,287,EN 12952-6:2001 -10.1
8 Finishing (for internals & externals) b) Final weld inspection Final dimension check reports EN 15614,287,EN 12952-6:2001 - 10.1
9 Pressure Test
f) Reviewed and approve pressure test report Pressure Test Reports EN 12952-6:2001 - 10.2
g) Drain out of all water from inside Project Spec. Project Spec.