Vous êtes sur la page 1sur 5

A refinery’s journey to energy efficiency

Identifying a series of areas for improvement transformed the energy


performance of a refinery with a 60-year history

ZAFER KARATAS and SENA TURKOGLU


Tüpraş Batman Refinery

T
he city of Batman is at the units, its configuration is After the handover of Tüpraş
centre of a region of simple and its Nelson complex- Batman refinery from the
Turkey where 72% of ity index is 1.83. The refinery government to Koç Holding in
state crude production takes therefore runs as a bitumen 2006, several projects to
place. Located in the south east and cut-back production plant. improve energy efficiency and
of Turkey, Batman refinery is Intermediate products like environmental performance,
one of four refineries of straight run naphtha, kerosene, including many refinery
Turkish Petroleum Refineries gasoil and heavy gasoil are revamp projects, were
(Tüpraş). It was commissioned sent to another Tüpraş refinery, implemented.
in 1955 as the first refinery in Kirikkale, for further conver-
Turkey, with a crude oil sion and processing. Kirikkale’s Strategic planning and
processing capacity of 330 000 final products of gasoil and implementation
t/y. Following growing gasoline are then returned to Since the scale and complexity
demand in Turkey for crude oil Batman to meet demand in the of the refinery was known, it
and its refined products, city and its surrounding region. was not difficult to figure out
another crude processing unit Although the refinery was the gap between actual energy
was commissioned in 1972, originally situated far from any consumption and target
taking Batman refinery to its centres of population, it is now consumption based on a bench-
current processing capacity of surrounded by urban develop- mark case. Additionally,
1.1 million t/y. Besides Batman ment. In addition, since the preliminary calculations were
city itself, the refinery also has refinery is 60 years old, energy made in order to see the poten-
the advantage of being located efficiency was not considered tial for energy savings in the
near to other domestic sources an important target in its origi- refinery. These calculations
in the region, so it was nal design. For both of these covered topics such as energy
designed to process 15-22 API reasons, the refinery needs be savings in the heat exchanger
local crude. sensitive and ready to take network by setting a delta T
The refinery consists of the precautions to support the envi- approach; existing process
following processing units: two ronment, with due regard for furnace efficiencies and their
CDUs, a VDU, a naphtha split- emissions and human health. potential savings; comparison
ter, a straight run naphtha Revamping of old and ineffi- of steam production costs in
stripper and utilities, including cient equipment and systems is different boilers at different
wastewater treatment, a power another important issue that grades; and a comparison of
plant and a tank farm with an requires the refinery’s attention cogeneration, back pressure
oil heating system. Since it with regard to economic perfor- turbine and extractive condens-
does not have any upgrading mance and reliability. ing turbine efficiencies. After

www.digitalrefining.com/article/1001245 PTQ Q1 2016 1


Boiler and turbogenerator specifications tor. Additionally, new steam
tracing lines and steam traps
Boilers H-­501 H-­502 H-­503 H-­504 H-­508
were installed for heating the
Design capacity, tons/h 10.5 10.5 10.5 22.62 64 bitumen production lines.
Maximum working capacity, tons/h 5 5 5 15 64 Some of the existing blowing
Steam pressure, psig 420 420 420 420 620
Steam temperature, C 404 404 404 404 404 traps were replaced and other
Efficiency 50 50 50 78 88 leaking traps were repaired. In
Turbogenerators J-­503 J-­504 J-­506
Type Condensing Condensing Back pressure
parallel with AFI-2, implemen-
Design prod. capacity, Mwh 2.5 2.5 5.25 tation of AFI-3 was carried out.
Steam inlet pressure, psig 420 420 620
Efficiency, % (elec. energy prod/steam energy cons) 17 17 96
AFI-3: Review power and steam
generating strategies
Table 1 Specifications for the steam
boilers and turbogenerators in
identification of areas for ment system, including precoat the power plant are shown in
improvement (AFI) and their filters and activated carbon Table 1. Since the boiler tubes
potential savings, a series of filters, in order to remove oil underwent widespread retub-
actions was taken and project and recover flash steam in the ing and plugging in the past,
implementations were set in surface condenser. Moreover, their efficiencies and reliability
motion. instead of raw water, deminer- were low. Boiler H-504 did not
alised water was used in the have the capacity for required
AFI-1: Increase condensate system as a cooling utility. In electricity production, therefore
recovery this way, the temperature was two of boilers H-501, H-502,
Steam leaks were observed increased from 20°C to 67°C H-503 were run together with
everywhere in the plant. Most before the existing dearator in H-504 in order to supply steam
of the traps were leaking and the power plant, and steam demand for the turbogenerator
at many points in the steam consumption in the dearator and so sustain operational reli-
network there were no traps. A decreased by 55% as a ability. The most efficient
condensate return system was consequence. boiler, H-508, was run for
not operated. Estimations With the increased conden- process heating purposes at 13
based on some of the leaks sate recovery ratio, the barg and 250°C.
gave a loss of >100 kg/h each. utilisation capacity of the The situation for the
In order to enhance the overall demineralisation plant was turbogenerators was similar:
efficiency of the refinery and reduced to 50% of its base their efficiencies were very low
increase steam and condensate capacity, resulting in 10 540 and their electricity unit
recovery, a project team was Gcal/y of energy saving. production costs (depending
established with the support of on the load) were very high, in
all refinery staff. AFI-2: Reduce steam leaks and the region of 4-8 times that of
Within the scope of the consumption the grid, except for back pres-
project, 300 traps were replaced As AFI-1 indicates, prevention sure production. However, the
and many condensate collec- of steam leaks caused by back pressure turbogenerator
tors, 2000 metres of carbon instrumentation tracing lines was designed by taking into
steel pipe, 5000 metres of insu- vents, direct open heating consideration a thermo-cata-
lation material, a condensate vents and steam traps blowing lytic cracking unit that was
flash drum and a condensate to atmosphere was carried out dismantled in 2007, hence its
pump were installed. The main continuously between the years design capacity was too big
condensate collecting lines 2006-2011 across the site. In and this resulted in a case of
were divided into two compo- other words, instrumentation unbalance in steam-electricity
nents for clean and oily tracing line vents were production.
condensate. Oily condensate collected in a separate flash Since there were boiler tubes
was routed to a newly installed drum and the produced flash failures every 3-4 months, the
condensate recovery and treat- steam was used in the deara- first action for improvement

2 PTQ Q1 2016 www.digitalrefining.com/article/1001245


Process steam saving

Crude processing, Weight average Process steam, Process steam, Steam reduction, Ton steam/ Saving,
tons/year boiler efficiency, % tons/year tons/h % ton crude %
2006 756000 82 264000 30 0.35
2011 946000 86 182000 21 31 0.19 45

Saving (based on reduction) Gcal/year 75149 =((264*(2939-89)/4.184))/0.82-((182*(2939-89)/4.184))/0.86


Saving (based on crude) Gcal/year 130264 =((((264*(2939-89)/4.184))/0.82)/756-(((182*(2939-89)/4.184))/0.86)/946)*946

Table 2

made was to improve the qual- ing diesel generator were consideration, a new process
ity of demineralised water in increased and, by taking the boiler operating at 30 t/h, 10
order to reduce failures, and to peak electricity demand of the barg and 93% thermal efficiency
increase the reliability and effi- refinery into account, one more was installed in 2012. The old
ciencies of the boilers. As a diesel generator was installed boilers, including H-508, were
result, the number of online in case of emergency and to switched off and mothballed. In
boilers was decreased subse- provide redundancy. The inef- this way, the refinery’s total
quently from four to one and ficient J-503/504 condensing steam demand was supplied
H-508 began to be employed turbogenerators, with just 17% only from the new boiler,
for both turbogeneration and operating efficiency (based on namely H-509. Since all of the
process heating by using the electricity produced per unit of boilers were high pressure boil-
existing let-down station. With fuel consumed in the boiler), ers they were integrated with
the combined effects of were stood by as redundant let-down stations in order to
AFI-1/2/3 in place, the result- items but received weekly reduce the operating pressure
ing process steam and energy maintenance, for instance lubri- to 10 barg process steam.
consumption figures are shown cation of rotors and bearings. However, boiler H-509 was
in Table 2. As a result, 53 000 Gcal/year of directly connected to a 10 barg
As a result, between 2006 energy saving was steam header without causing
and 2011, process steam accomplished. any energy loss in a let-down
consumption was reduced station. Comparing all of the
from 264 000 t/y to 182 000 AFI-4: Increase process boiler boilers with H-509, 56 000 Gcal/
t/y. This means that over a efficiency year of ‘potential’ energy saving
period of five years there was a As Table 1 shows, even though in process steam production
31% reduction in total process boiler H-508 had the highest was obtained with this
steam consumption, or a 45% efficiency compared with the measure.
saving in steam per tonne of other boilers, its reduced utilisa-
crude processed, resulting in tion capacity (one-third of AFI-5: Apply variable speed
75 000 Gcal/y of energy saving design capacity) due to imple- drive
based on total annual process mentation of these AFIs and Throughout the refinery, with
steam consumption, and utilisation of the other boilers the exception of the boiler’s air
130 000 Gcal/year of energy for any reason reduced overall fan and feed water pump,
saving based on tonnes of boiler house efficiency. there were no applications of
crude processed. Furthermore, with the switch- variable speed drives on rotat-
When it came to electricity ing off of the turbogenerators, ing equipment. Generally,
production, import from the the other boilers were switched equipment was running at 50
grid was maximised with mini- off too and this situation Hz and process control was
mal site production. Later, increased corrosion problems performed by mechanical
electricity production was and the number of tubes that equipment such as valves,
stopped completely for reasons had to be plugged in the boil- pressure control valves, level
of economy. Additionally, the ers. Therefore, by taking recent control valves, air dampers,
standby conditions of the exist- refinery steam demand into and so on. A pilot application

www.digitalrefining.com/article/1001245 PTQ Q1 2016 3


of variable speed drives was options for a heat integration ing conditions. Finally, F-1201
carried out in the power plant network were identified using naphtha splitter furnace,
and track loading pump KBC SuperTarget software. designed in 1966, had a ther-
station, and it was decided that Then a TEMA data sheet was mal efficiency of 55%. In 2011,
the energy savings were high generated and equipment F-101 furnace was renewed
enough for further design was carried out. For the completely with a thermal
development. base case, in Plant 100 CDU efficiency of 88%. The saving is
Therefore, the implementa- there was no desalter/feed 23 000 Gcal/y.
tion of variable speed drives water effluent exchanger, and With projects ongoing for the
was widened to include other before the desalter there was F-1101 and F-1201 furnaces,
process rotating equipment. only one steam/crude 35 000 Gcal/year of additional
This resulted not only in elec- exchanger and one pumpa- energy savings will be
trical energy savings; it also round exchanger. In Plant 1100 achieved in 2017.
provided enhanced process CDU, the arrangement was the
control. The result of introduc- same except for two additional AFI-8: Recover overhead gas
ing variable speed drives, bitumen/crude exchangers from the condenser
together with some of the posi- before the desalter. Naphtha splitter and CDU
tive gains from applying other Nevertheless, SuperTarget’s overhead gases were connected
AFIs in the refinery, was a calculations showed substantial directly to the flare line. In
reduction in electricity savings potential in Plant 1100. other words, although there
consumption by 25% (based on Within the scope of the was a fuel gas system for
tonnes of crude processed) in project, in Plant 100 two consumption in the furnace,
the period 2007-2011, equiva- exchangers (crude/kero, the condenser top pressure
lent to 4300 Gcal/y of energy crude/diesel) were installed control valves were open to
savings. before the desalter, as well as flare in order to control pres-
one desalter effluent water/ sure in the distillation columns.
AFI-6: Heat integration in water exchanger. In plant 1100, By applying pressure split
process units two exchangers (crude/kero, control systems in the condens-
In the 1960s, energy conserva- crude/diesel) were installed ers, all condenser fuel gases
tion was a relatively low-level before the desalter, along with were routed to the fuel gas
economic issue. Therefore, two exchangers (crude/bitu- system, although the flare
decisions on development in men, crude/diesel) and one connection remained active in
the refinery mostly depended desalter effluent water/water case of emergency. With this
on investment cost rather than exchanger after the desalter. implementation, 35 000 Gcal/y
energy efficiency. In a 60-year- The outcome was 44 850 was saved.
old refinery it was easy to see Gcal/y of energy savings.
that the preheat trains of the Nevertheless, there is some Conclusion
crude units were extremely margin left for site-wide heat Tüpraş Batman refinery was
poor with regard to heat recov- integration. Therefore, the plan designed between 1950 and
ery and heat integration. In is to apply heat integration in 1970 when energy conservation
other words, there were a lot of the other process units as well was a relatively simple issue.
run-down coolers utilising as in the CDUs. However, the areas for
cooling water. Although Plant improvement described here
1100 CDU, installed in 1972, AFI-7: Revamp of the process have been implemented
was better than Plant 100, furnaces successfully between 2006 to
installed in 1954, with respect F-101 crude furnace was the present. The refinery now
to heat integration, there was designed in 1954 with a ther- has an energy intensity index
still a lot to do to improve the mal efficiency of 50-55%, while of 77. As well as these AFIs,
situation by means of heat F-1101 crude furnace was many quick-win enhancement
integration. designed in 1972 with a ther- projects have been imple-
After a test run in the CDUs, mal efficiency of 60-65%, mented to raise the site’s
the energy gap and the best depending on process operat- performance in technology,

4 PTQ Q1 2016 www.digitalrefining.com/article/1001245


energy efficiency, environment, paid to performance. Therefore, Sena Turkoglu is a Process Chief Engineer
health, reliability, recycling, it is vital to make periodic in the production department of Tüpraş
greenhouse gas emissions, audits of the overall system Batman refinery, Turkey. Her refining
hydrocarbon losses and safety. and to research opportunities experience includes R&D in refining,
energy management and hydrocarbon
In parallel with the substantial for improvement, keep refinery
loss prevention. She holds a BS in
energy savings obtained from staff up to date about develop-
chemical engineering from Hacettepe
implementation of these ments, and increase their University Ankara, Turkey.
projects, other gains to note awareness of the systems for Email: sena.turkoglu@tupras.com.tr
include reductions in CO2 which they are responsible.
emissions and raw water utili-
sation to 50 % and 70% Zafer Karatas is a Process Superintendent
respectively per tonne of crude in the production department of Tüpraş
processed. Batman refinery, Turkey. His refining LINKS
experience includes R&D in refining,
In refining, some areas for
process engineering in CDUs,VDUs,
savings are volatile – for More articles from the following
utilities, and energy and environment
instance steam consumption, categories:
management. He holds a BS in chemical
condensate recovery, heat insu- Energy Efficiency and Energy
engineering from Middle East Technical
lation and water consumption Management
University, Ankara, Turkey.
Thermal Technology
– unless constant attention is Email: zafer.karatas@tupras.com.tr

www.digitalrefining.com/article/1001245 PTQ Q1 2016 5

Vous aimerez peut-être aussi