Académique Documents
Professionnel Documents
Culture Documents
net/publication/267606689
Challenges About Testing, Welding and NDT of CRA Pipelines in Brazilian Pre-
Salt
CITATIONS READS
2 840
8 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Manfred Ronald Richter on 12 January 2016.
OMAE2012-83461
ABSTRACT final girth weld by AUT. However, AUT solutions are normally
Some new pre-salt fields at Santos Basin in Brazil are more efficient in laminated & extruded materials than in weld
located in water depths as deep as 2200m and about 300 km overlaid ones. Additionally, the ECA methodology for both girth
away from the coast. There is variable level of contaminants in welds and weld overlay has complexities that are not usually
the produced fluid, mainly CO2, that affects the material addressed in a regular ECA for carbon steel pipelines (e.g.
selection of the infield flowlines and risers. Based on these internal misalignment of girth welds in risers has stringent
constraints, Petrobras has selected UNS N06625 clad or lined requirements because of its effects on fatigue performance and,
steel linepipes to develop the first fields in Pre-Salt area and consequently, the ECA girth weld criteria). Also CRA clad/lined
also the module 3 of Roncador a post-salt field in Campos pipelines and risers qualification program may include additional
Basin. Several challenges have arisen during design, testing when compared with usual carbon steel welding
construction and installation of these facilities related to qualification process (namely pitting and intergranular corrosion;
pipeline welding procedures, NDT inspection and Engineering full scale fatigue; spooling trials of lined linepipes; segment
Critical Assessment (ECA). Firstly weld overmatching testing for ECA and others). Finally, the contribution of clad/lined
condition may not be fully achieved due to differences in layer in pipeline design strength is also discussed. This work
mechanical properties between UNS 06625 and API X65, and presents challenges PETROBRAS has faced at design and
concern increases when reel-lay installation method is chosen. construction phases of on-going Guará and Lula-NE pre-salt
Another welding issue is the maximum interpass temperature of fields and Roncador Field Projects, as well as the solutions
nickel alloys (which DNV and PETROBRAS standards limit in proposed by the project team in order to overcome the issues
100ºC) and this impacts pipeline installation productivity. raised during project execution.
Thirdly, back purging characteristics and number of passes
protected with purging gases affects the possibility of root INTRODUCTION
oxidation. Also, the inspection of the weld overlay in the pipe
end of lined linepipes is other point of great concern. As defect So called “Brazilian pre-salt” is the offshore area close to the
sizing is mandatory for ECA, lined pipes have been designed Brazilian coast where hydrocarbon reservoirs exist below a
with a weld overlay length which allows the inspection of the geological salt layer. PETROBRAS has given enough data to