Vous êtes sur la page 1sur 12

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/302947695

Transition of the Ernest Henry Mine from Open Pit to Underground Sub-Level
Cave

Conference Paper · May 2014

CITATIONS READS

2 197

3 authors, including:

Alex Campbell
Beck Engineering
15 PUBLICATIONS   13 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Full scale experiments to improve ore recovery in sublevel cave mines View project

All content following this page was uploaded by Alex Campbell on 28 May 2018.

The user has requested enhancement of the downloaded file.


Transition of the Ernest Henry Mine
from Open Pit to an Underground
Sublevel Cave
A T McGrath1, A D Campbell2 and J B Tucker3

ABSTRACT
Situated in north-west Queensland, Australia, the Ernest Henry Mine (EHM) has been producing
copper and gold since 1996. Owned and operated by Glencore Xstrata, ore is currently sourced
from a newly developed underground sublevel cave (SLC) mine below the old EHM open pit (the
pit). Ore feed to the concentrator is supplemented by satellite open pits comprising the Mount
Margaret operation.
The transition from open pit to a producing underground mine involved a complex extraction
sequence for the first two production sublevels on RL1650 and RL1625. Underground mining
during cave initiation was further complicated when south wall instability prevented completion
of the final open pit shell. The transition mining phase included mass firing of an inclined crown
pillar between the initial SLC void and the pit followed by a combination of transverse and
longitudinal SLC mining.
The inclined crown pillar mass firing was the first significant milestone in the extraction of the
transition ore block. Comprising approximately 890 000 t of in situ material; 70 000 m of drilling
was charged with 351 t of emulsion and 6026 electronic detonators to initiate the single mass firing.
The firing contained five direction changes over 19 seconds making it one of the largest and most
complex underground blasts ever conducted in Australia.
Risk management was integrated into every facet of the technical and operational planning
and execution of the transition mining phase, whilst maintaining daily mine construction and
production commitments. This paper provides a detailed overview of the transition objectives and
constraints, mining method selection, post mass blast outcomes and the journey ahead.

INTRODUCTION
The Ernest Henry Mine (EHM) is located approximately 38 km below the surface at RL1625 and measures 130 m wide (E–W)
north-east of Cloncurry in north-west Queensland, Australia by 100 m long (N–S).
(Figure 1). The mine is operated by Ernest Henry Mining Pty The EHM underground mine targets the orebody down
Ltd, a 100 per cent owned subsidiary of Glencore Xstrata. It
dip of the pit as depicted in Figures 2 and 3. The first cut
is situated in the Eastern Fold Belt of the Mount Isa Inlier.
in the decline was fired on 20 February 2008 at the RL1902
Operations comprise a producing underground sublevel cave
switch back in the north wall of the pit. Underground mine
(SLC) mine below the completed pit and a number of satellite
open pits forming the Mount Margaret operation, which are Ore Reserves currently measure 73 Mt at 0.97  per cent Cu
used to feed the EHM site concentrator. and 0.50 g/t Au. The first two production levels encircle
the pit at RL1650 and RL1625 to access a combination of
The orebody is hosted by strong and competent Proterozoic
rocks consisting of intermediate and felsic volcanics overlain transverse and longitudinal SLC mining, mass firing and
by a 50 m thick cover of sand, clay, shale and gravel units. uphole retreating. The conventional transverse SLC starts at
Pipe-like in appearance, the orebody dips at approximately RL1600, which is approximately 25 m below the pit base, and
45 degrees to the south and is as thick as it is wide. will extend to RL1200. In December 2011, the underground
The pit operated from late 1996 until November 2011. mine commenced production via decline trucking. Ramp up
During this period, the peak production rate was 11 Mt/a to a 6 Mt/a production rate via shaft hoisting will be realised
of copper gold ore. The final pit crest at RL2160 measures in 2014 following successful commissioning of the crushing,
1.49 km wide in the east–west (E–W) direction by 1.56 km conveying and hoisting systems. At these rates, current
long in the north–south (N–S) direction. The pit base is 535 m reserves will be exhausted by 2026.

1. MAusIMM, Senior Mining Engineer, Ernest Henry Mining Pty Ltd, PO Box 527, Cloncurry Qld 4824. Email: andrew.mcgrath@glencore.com.au
2. MAusIMM(CP), Senior Geotechnical Engineer, Ernest Henry Mining Pty Ltd, PO Box 527, Cloncurry Qld 4824. Email: alex.campbell@glencore.com.au
3. MAusIMM, Technical Manager – DynoConsult West, 223 Adelaide Terrace, Perth WA 6000. Email: john.tucker@dynonobel.com

12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014 297
A T MCGRATH, A D CAMPBELL AND J B TUCKER

FIG 1 – Ernest Henry Mine location within the north-west Queensland minerals province (Department of Employment, Economic Development and Innovation, 2009).

FIG 3 – Isometric view of the Ernest Henry Mine orebody, pit and underground
mine looking north-west.

relatively high-grade ore, this material formed an inclined


crown pillar and barrier that prevented cave progression to
the south wall. Smaller transition blocks also existed in the
FIG 2 – Isometric view of the Ernest Henry Mine orebody, pit and underground western and eastern walls of the pit. A number of preliminary
mine looking north-north-east. concepts and design iterations were investigated for the safe
and efficient extraction of the transition ore. Options included:
This paper provides an insight into the complex and
unconventional design and operational methodologies for •• Modification of the final pit shell and in pit surface drilling
transition mining of the first two underground sublevels. and charging of transition ore blocks for underground
extraction. However, this option was discontinued due to
concerns about personnel and equipment access in close
EVOLUTION OF THE TRANSITION BLOCK
proximity to the south wall of the pit.
CONCEPT AND DESIGN SELECTION •• A combination of surface drilling to remove the ramp and
berms in the pit base and development of underground
Feasibility mine design access drives for the uphole drilling horizon. Initial
During the project feasibility stage, remaining unmined void would be created through the extraction of a
material between the pit and the initial SLC void was 40 m (W) × 40 m (L) × 40 m (H) open stope from RL1600
identified as ‘transition’ ore. Segregated into distinct zones, to RL1646 in the south-east SLC. This option was not
the majority of this ore was classified within the Southern selected due to previously stated south wall access
Transition Block (STB). Comprising approximately 2 Mt of concerns and stope stability.

298 12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014
TRANSITION OF THE ERNEST HENRY MINE FROM OPEN PIT TO AN UNDERGROUND SUBLEVEL CAVE

For all feasibility design iterations, the intention was to Selection of the transition block mining
cast fire multiple rings into the available pit void. This fired sequence
material would not be recovered but instead would contribute
By March 2012, a number of extraction options had been
to an ore blanket for air blast protection, prevention of early
investigated. A road map depicting major milestones in the
waste dilution and later extraction in the lower SLC levels.
transition phase, available options and the final selection is
presented in Figure 5.
Final open pit status and advanced
Due to the geometry and location of existing development
underground development and infrastructure on RL1650 and RL1625 levels and the
The south pit wall had a history of instability and failures due commencement of SLC production, reverse mining from
to intersecting faults and an aggressive wall angle. During north to south (ie working away from the open pit) was not
the final stages of open pit mining, geotechnical monitoring a considered option. An additional factor to this decision
and analysis identified potential impacts to underground was the expected production delay when changing the
workings. Consequently, the decision was made to leave some mining direction back to south to north on the third sublevel
material behind to confine dominant faults and structures (ie RL1600). Sequence 3 was selected for the open pit to
as risk mitigation to prevent premature south wall failure. underground transition because it:
Figure 4 shows the location of RL1646 and RL1625 ore blocks •• maximised stability
in relation to the RL1650 STB drilling access drives. •• minimised the number of mass firings and potential for
The 1646-212 pit blast was fired out of sequence causing mine development and infrastructure damage
lower sections of the south wall, including the ramp, to •• minimised the load on production drilling and charging
become unstable. A redesign of the remaining RL1646 and resources and enabled earlier recovery of ore tonnes
RL1625 pit benches to reduce the wall angle was required. •• minimised confinement issues associated with failed
To prevent additional instability in the pit wall and potential material from the south pit wall and achieved realistic
damage to underground access drives, the decision was made blast void by using a combination of free faces in the pit
to cancel 1625-220 and 1625-221 pit blasts. and underground
Changes to the final pit design and blast sequencing •• maximised contingency recovery options given the
significantly increased the volume of transition ore material dynamic nature of the south pit wall and transition pillar.
that remained for underground extraction. Compounding For extraction of the RL1650 Level STB, Option 4 was
the situation was the advanced completion of development selected because it:
on RL1650 and RL1625 levels, which restricted available •• provided the greatest volume and coverage of prefiring
alternatives. This development restricted conceptual drill ring void for the mass blast
design options and reduced the volume of material that could •• maintained void stability, south wall integrity and did
be effectively cast fired into the pit. As a result, the transition not break out into the overlying pit, which would have
mining methodology developed during the feasibility study resulted in lower mine level ventilation impacts due to
was no longer practical and required redesign. short-circuiting

FIG 4 – Section view of the final planned open pit shell relative to underground looking east (schematic not to scale).

12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014 299
A T MCGRATH, A D CAMPBELL AND J B TUCKER

FIG 5 – Road map of extraction options for the transition ore block (SLC = sublevel cave).

•• maximised stability and allowed for continued safe access internal slots for transition blast void. These uphole retreat
to the mass blast area via RL1650 level access drives rings were mined from south to north in ore drives (OD) 11,
•• achieved multiple firing fronts to reduce blast induced 17 and 23 on RL1650 as is shown in Figure 7. Selection of the
ground vibrations and resultant damage to surrounding internal slot locations was based on equidistant distribution
infrastructure and development of void for the RL1650 STB firing.
•• enabled greater primary recovery of ore from RL1650 as During the design of the internal slots, the following
opposed to waiting for the material to report through the assumptions were made:
cave at lower levels. •• all material north of the RL1650 West Access drive would
A zone of ore needed to be extracted from RL1650 prior report to the pit or would remain in situ, thus, not affecting
to initiation of the RL1650 STB mass firing. This ore block is available void for the remaining block
depicted in Figure 6. The first SLC production firing occurred •• void calculations did not include development within the
on 9 December 2011 at RL1650 Slot 7 in the south-west section internal slots due to leftover material from firings and an
of the cave. Within the initial production zone, approximately inability to remote bog
343 kt of ore was extracted from RL1650 via 32 m high uphole •• the two southernmost rings in each OD would see the
rings to a predetermined exclusion zone. This exclusion zone cave to the south as the free face.
preserved access to the RL1650 STB by ensuring:
Consequently, groups of ODs were organised into block
•• geotechnical stability of the pillar between RL1650 and the panels for void analysis. Based on geotechnical stability
south pit wall assessments of the slot crown and side walls, the ring draw
•• the rill pile from fired drawpoints did not extend into strategy was increased to 80 per cent or until the brow
intersections, thus restricting access. ‘cracked’ open. The lowest available void was 16 per cent for
A reduced draw strategy of 40 per cent was applied to RL1650 OD 21–29. The highest available void was 19 per cent
production rings within this initial zone to build up the ore for RL1650 OD 15–19. Final brows were closed and the rill pile
blanket for air blast control and to delay ore dilution in levels was sprayed with shotcrete to protect personnel and preserve
below. access.
When production ring extraction on RL1650 had reached The remaining material between the pit and the RL1650 STB
the exclusion zone, the decision was made to mine 25 m high was drilled, charged and fired in a single mass firing. This

FIG 6 – Isometric view of RL1650 sublevel cave mining to the exclusion zone FIG 7 – Isometric view of RL1650 internal slots for blast void
looking south-east. looking south-east.

300 12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014
TRANSITION OF THE ERNEST HENRY MINE FROM OPEN PIT TO AN UNDERGROUND SUBLEVEL CAVE

is represented in Figure 8. The east and west transition ore firing was completed in the central OD of the block to link the
blocks were extracted independently. Details of the extraction northern and southern transition zones. This firing assisted
of the RL1650 STB are discussed in greater detail later in this with the management of principle stress and resultant damage
paper. to the rock mass and ground control. A chevron retreat to the
After mining of the transition block on RL1650, the RL1625 west and east was achieved via a combination of SLC and
STB was scheduled for production. Based on Figure 5, multiple ring firings across RL1625 drive intersections. The
option 3 was selected. Previously detailed changes to the pit final mining sequence for the STB has been summarised in
mine design coupled with the anticipated heaving of broken Figure 10.
rock and resultant lack of free firing face from the RL1650
mass firing presented a transition block that was significantly RISK MANAGEMENT – DESIGN AND
larger and more confined than expected. Figure 9 provides an OPERATIONAL CONSTRAINTS FOR
isometric diagram of the block sequence and methodology. TRANSITION MINING TO DATE
As opposed to the mass firing approach that was employed Risk management was incorporated into every facet of the STB
for RL1650, RL1625 incorporated transverse and longitudinal design, preparation and extraction on RL1650 and RL1625. All
SLC retreat. Production commenced in the south-west section decisions were based on internally and externally reviewed
of the RL1625 cave during RL1650 production. As with designs and risk assessments. A significant portion of the risk
RL1650, the initial RL1625 STB production zone was retreated
from south to north to a predetermined exclusion zone. Ring
extraction then commenced from the open pit in the north
via a slot rise and modified SLC rings. An initial ‘cross over’

FIG 8 – Isometric view of RL1650 Southern Transition Block looking south-east FIG 9 – Isometric view of RL1625 sublevel cave (SLC) and Southern Transition
(SLC = sublevel cave). Block mining sequence looking east.

FIG 10 – Long section view and summary of the Southern Transition Block mining sequence looking east
(schematic not to scale; SLC = sublevel cave) of the Ernest Henry Mine.

12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014 301
A T MCGRATH, A D CAMPBELL AND J B TUCKER

was managed during the execution of the RL1650 STB mass and blast designs were devised to achieve controlled failure
firing. The following sections depict identified hazards and of the south pit wall.
implemented risk controls. The risk associated with seismic events and subsequent
rock mass damage extended to the immediate period after
Reactive ground the RL1650 STB mass firing. It was expected there would
Initial discovery of reactive ground occurred whilst mining be a short-term increase in levels of seismicity, which was
the pit in 2003. This classification of the EHM orebody was directly proportional to the size of the firing. A delayed mine
extended for the underground mine. A maximum 42 day re-entry based on observed seismicity levels (ie frequency
sleep time was recommended by the explosives manufacturer and magnitude) was enforced to ensure safety to personnel
for the tested and selected explosives product. Therefore, entering the underground mine. Post-firing seismicity was
a strict drilling and charging schedule was established to measured against a previously defined background level.
closely monitor and meet blasting deadlines. Background levels needed to be sustained for the six hour
time window to allow safe re-entry. As part of contingency
Ground conditions, air blast and seismicity planning, in the event that prefiring background levels were
Drilling and charging was conducted in deteriorating ground never realised, the Omori analysis method was to be used to
conditions on RL1650. As time progressed and the SLC void determine a new flat line trend in seismic behaviour.
was advanced closer to the nominated exclusion zones on
RL1650 and RL1625, a number of completed and uncharged Ground water and the wet season
drill holes could not be charged due to hole dislocation along The jointed rock mass coupled with proximity to the pit
rock mass structures. Consequently, drilling was scheduled resulted in a significant volume of ground water entering
as late as possible (ALAP) with immediate charging after an production drill holes in the STB. This had a detrimental effect
adequate 10 m buffer distance was established. on emulsion retention and detonator integrity, particularly
during the RL1650 STB mass firing. Controls included ALAP
In the lead up to the RL1650 STB mass firing, changes to
charging, blast hole sleeving, detonator testing and collar
prescribed ground control standards were made after a large
priming as a last resort. In the lead up period to the mass
seismic event resulted in multiple rock falls on RL1650 on
firing, a number of trials were conducted by the explosives
31 August 2012. The direct cause was fault slip along a large
manufacturer and EHM personnel to determine the correct
scale structure that was triggered by continued cave retreat
recipe.
and simultaneous firing of multiple production rings earlier
in the day. Remedial actions included: For the RL1650 STB mass firing, the approaching wet season
and expected water ingress into the pit and underground
•• reactive installation of mesh and split sets over existing workings posed an additional risk. Introduction of significant
fibrecrete and resin grouted bolts on RL1650 volumes of water into drill holes was identified as seriously
•• cable bolting of similar large scale structures compromising product retention and detonator integrity.
•• additional instrumentation and monitoring devices Furthermore, removal of the RL1650 STB effectively removed
including extensometers, SMART cable bolts, systematic the barrier between the pit and the underground thus
damage mapping and camera surveys of open holes allowing for a direct water conduit to lower mine levels. To
•• enforcement of production blasting rules including a manage flooding events, a number of prerequisite activities
limitation in the maximum number of production rings were simultaneously completed to provide sufficient post-
initiated during end of shift firings and the cessation of firing water storage and pumping capacity. These included:
adjacent OD ring firings. •• completion of a series of drain holes and pipe runs linking
Later proactive changes to preserve drive integrity included: the mine’s drainage system to its emergency storm water
•• pre-emptive installation of mesh and split sets over system
fibrecrete and resin grouted bolts on RL1625 and future •• completion of the emergency water storage stopes,
SLC drives for deformation support construction of a 6 m thick concrete plug, and pipe work
to the main pump station on RL1325
•• systematic mapping of all drive scale structures to
correlate with damage mapping observations •• excavation, installation and commissioning of the main
pump station on RL1325 and additional pump stations at
•• a change from square to semi-arched ore and slot drive
RL1600
profiles
•• construction and commissioning of four in-pit dewatering
•• use of decoupled perimeter blasting product to reduce rock
pump stations and rising mains for capture of storm water
mass damage from development blasting and improve
and its staged lifting to the surface storage dams.
drive profiles to enable compressive load transfer.
Prior to initiating the RL1650 STB mass firing, premature Blast vibrations, over-pressure and gases
failure of the south pit wall was identified as resulting in Damage caused by blast vibrations had the potential to
elevated air blast risk, additional rock mass and ground adversely impact underground drives and infrastructure
control damage and increased STB blast confinement. in close proximity to the RL1650 STB mass firing location.
Numerical modelling and geotechnical analysis was In particular, damage to the RL1625 Fan Chambers was
conducted to determine the optimal mining sequence and unacceptable due to the potential for drive shaft and bearing
exclusion zone to reduce the inclined crown pillar thickness misalignment to the fan units and the resultant mechanical
whilst maintaining a relatively stable south pit wall. For air damage sustained through continued operation (Campbell,
blast protection, cave draw points were kept closed with a Lilley and Henley, 2011). A number of horizontal and vertical
sufficient broken ore buffer established through the reduced near field (ie minimum distance of 10 m to a maximum distance
draw strategy for RL1650. Additional contingency STB blast of 90 m) blast vibration measurements were recorded by
void was created through the mining of the internal slots in Dyno Nobel and EHM personnel prior to the mass firing. This
RL1650 OD 11, 17 and 23. Consequently, block sequencing data was correlated with previous vibration data, including

302 12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014
TRANSITION OF THE ERNEST HENRY MINE FROM OPEN PIT TO AN UNDERGROUND SUBLEVEL CAVE

FIG 11 – Comparison of blast vibration results.

far field measurements conducted by Campbell, Lilley and (ie including in-pit dewatering pumps and substations at
Henley (2011). In Figure 11, it can be seen that based on the Sumps 1 to 4) was shielded with fly rock barriers.
distance and maximum instantaneous charge (MIC) weight Critical underground infrastructure in close proximity to the
of the mass firing, the RL1625 Fan Chamber (far field) and firing location included the RL1625 Fan Chambers housing the
RL1625 OD’s (near field) have scaled distances of 18 and 3, two 1.6 MW mixed flow exhaust fans, RL1650 substation and
respectively. Therefore, the maximum vibration level that was the main access decline. Containment of blast over-pressure
expected in the RL1625 Fan Chamber was less than 10 mm/s. was via construction of 500 mm thick firing bulkheads in
addition to the placement of blast protection bunds and
The risk of blast over-pressure and fly rock resulting from
shotcrete ribs in all underground accesses to the RL1650 STB
the RL1650 STB mass firing had to be controlled. Figure 12
mass firing. Fans were replaced with cover plates in fresh air
shows the straight line distances between the RL1650 STB, rises and all essential services and ducting were stripped.
pit shell and major surface infrastructure. A 500 m radius Although switched off during the blast, it was decided that
surface exclusion zone was established around the RL1650 the primary exhaust fans should be ‘windmilling’ to minimise
STB. Surface infrastructure that was unable to be moved the likelihood of bearing damage. The underground mobile
equipment fleet was removed from the mine for opportune
maintenance or parked in areas below RL1600 that were
identified as low risk for flooding and ground instability. A
truck, loader and telehandler were parked along the decline
between the RL1902 portal and RL1650 as a pre-emptive
measure for potential post-firing remedial works.
Due to the size of the RL1650 STB mass firing, a significant
volume and concentration of blast fumes was generated.
Whilst the majority of the fumes expelled into the pit, it
was decided that personnel would not re-enter the mine
for a minimum of 12 hours. Mine ventilation models and
simulations indicated that natural but restricted ventilation
would flow down the decline to RL1625. By sealing up the
RL1650 prior to firing, all efforts were made to contain the
blast gases to the area with minimal leakage into the rest of
the underground workings.

RL1650 MASS BLAST OVERVIEW, DESIGN AND


OPERATIONAL OUTCOMES
Overview
At 10.34 pm on 29 November 2012, a significant milestone
in the EHM transition mining phase was achieved when the
RL1650 STB mass firing was successfully initiated. In total,
FIG 12 – Plan view of RL1650 Southern Transition Block mass firing in relation 893 258 t of in situ material was remotely initiated from the
to surface mine infrastructure. surface. This material was unmined by the overlying pit and

12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014 303
A T MCGRATH, A D CAMPBELL AND J B TUCKER

formed the inclined crown pillar between the final pit shell unit was used as contingency for charging short and shallow
and the newly developed underground SLC mine. dumped 64 mm and 102 mm blast holes. In 41 days, 351 t of
The total block was accessed via conventional uphole and Titan 7000SX emulsion with a density of 1.0 g/cc was primed
with 6026 SmartShot detonators. Primers were vertically
horizontal drilling from RL1650. Atlas Copco Simba L6C and
offset by a minimum of 2 m between adjacent holes to reduce
Sandvik DL420-15C production drills were concurrently used
the risk of interaction. Primers were also located at least 1.5 m
to complete 66 810 m of 102 mm diameter blast hole drilling.
back from the toe of breakthrough holes. As a minimum,
Total redrills due to cleaning and reboring was approximately all holes were double primed as contingency for detonator
16 per cent. Due to rig dump constraints, 5646 m of acute failure and to ensure full charge column initiation. Figure 13
(ie horizontal to 45° dump angle) 64 mm diameter blast hole shows a charged drive within the RL1650 STB. The RL1650
drilling was performed by an Atlas Copco Cabletec LC rig. STB mass firing involved a multidirectional firing sequence
Charging commenced on 19 October 2013. Two Dyno Nobel making it one of the largest and most complex underground
Mobile Processing Units and additional charge up operators firings accomplished in Australia.
were deployed to site to assist with 24 hour blast hole Dyno Nobel and EHM staff developed a timing solution
preparation and charging. A mine development Dyno Miner that enabled use of available void within the 20 000 ms system

FIG 13 – RL1650 Southern Transition Block charged rings in ore drive 19.

FIG 14 – Plan view of RL1650 Southern Transition Block firing directions.

304 12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014
TRANSITION OF THE ERNEST HENRY MINE FROM OPEN PIT TO AN UNDERGROUND SUBLEVEL CAVE

limit. Figure 14 is a plan view representation of the firing and level accesses for blast fumes, observed the satisfactory
progression and the free face seen by each block of rings. In condition of the main underground exhaust fans at the
Figure 14, the arrows indicate the direction of free face seen by RL1625 Fan Chambers and electrical switch room and checked
the fired ring and the circled letters are firing block reference ground conditions in the closest drives to the RL1650 STB.
points. In devising the timing solution, single hole firing An engineering inspection of RL1650 identified a number
was successfully achieved to reduce blast induced ground of detonators in the West Access and adjacent ODs that had
vibrations. Over the entire blast duration, an MIC of 272.5 kg failed to initiate either due to hole cut-offs or disconnection
was designed to occur at 7880 ms. The first hole was designed from the shot in the lead up to firing. These detonators were
to be fired in RL1650 Southern Transition Drive (STD) 01 at repaired, reconnected and successfully refired following the
2100 ms. All rings within the RL1650 STB access drives were RL1650 STB mass firing.
designed to be fired within 9665 ms (ie Block A) with 4 ms and Auditing and reconciliation of the final detonator counts
10 ms inter-hole delays between 64 mm and 102 mm holes, was undertaken off-site via downloading of the bench boxes.
respectively. A 5 ms offset was used between each adjacent The initial download was provided to EHM on 10 December
drive. 2012. Final reconciliation was received in February 2013. Both
Rings within the RL1650 West Access and OD 17 used a sets of results indicated a significant variance in the actual
combination of open pit and RL1650 OD 17 internal slot void number of detonators fired versus plan. For the four bench
as the designated ‘cross over’ point for firings (ie Block B). boxes, a total of 6531 detonators were planned in the initial
The first two panels of rings in RL1650 OD 13–15 (Block C1) design. Due to deteriorating ground conditions and hole
and OD 19–21 (Block C2) sequentially fired into the southern loading issues, 6026 detonators were actually loaded into the
SLC and adjacent internal slot voids. Application of 5 ms available blast holes.
offsets between panels saw completion of this firing phase On 9 February 2013, three significant seismic events ranging
at 13 690 ms using 10 ms inter-hole and 20 ms inter-ring from 1.0 ML to 1.8 ML occurred following the firing of
delays. Retreat was designed along the RL1650 West and East RL1625 OD 08. Further analysis of the RL1650 STB mass firing
Accesses using created void in RL1650 STD 01–05, OD 13–15 detonator variance and interpretation of unfired and adjoining
and OD 19–21 (Blocks D1, E1, D2 and E2). Rings were blocks, which were fired under non-ideal conditions, indicated
progressively retreated in a ‘centre out’ approach by initially the presence of remnant pillars above the RL1650 STB. As the
using the southern SLC void and internal slots in RL1650 RL1625 OD rings were retreated to the north, these remnant
OD 11 and 23. Initiation of the final holes in the RL1650 east pillars were undercut resulting in destabilisation, failure and
and west was achieved at 17 755 ms (Block E2) and 19 000 ms vertical stress loading on remaining pillars. Figure 15 shows a
(Block E1), respectively.
section view schematic of the STB and remnant pillars.
Mass blast performance The stress redistribution depicted in Figure 15 resulted in
Blast initiation occurred from the surface via wireless rock mass and ground control damage along the RL1625 and
communication link to the bench boxes. With an original plan RL1650. The immediate response involved isolation of RL1625,
to fire at 8.00 am, the mine was fully cleared of personnel pillar analysis and level damage mapping. A detailed ground
and non-essential underground equipment by 6.00 am. control rehabilitation plan was developed and scheduled to
Throughout the day, failed attempts were made to initiate the achieve the most efficient re-access back into affected areas.
firing resulting in multiple re-entries to address issues within Following the seismic events, a number of holes had to be
the shot. The primary reason for these failed attempts was a redrilled and charged. A methodical approach was adopted
poor communication link between the base station and four to charge, fire and bog RL1625 OD rings that were found to be
bench boxes via a repeater. Successful initiation was achieved undercutting the remnant pillars. Strict post-firing mine and
by removing the repeater and establishing an alternative level re-entry protocols were enforced to minimise personnel
direct line of sight firing location. exposure to seismic events. Omori graphs and flat line trends
were analysed to determine appropriate isolation times for
Blast vibration measurements and seismic analysis were
the duration of pillar undercutting.
conducted during the RL1650 STB mass firing. The measured
vibration level in RL1625 OD 14, which was 25 m below the Prior to the RL1650 STB mass firing, the Hydraulic Radius
fired block, was 138 mm/sec. The measured vibration level in (HR) was 12 m. The baseline condition of the south pit wall
the RL1625 Fan Chamber was 1.17 mm/sec. A comparison of may be seen in Figure 16. Following the mass firing, the HR
the actual and predicted results may be observed in Figure 11. reached 28 m. Seismic activity and modelled displacement
In the first 24 and 36 hours following the blast, there were
1065 and 1180 seismic events recorded, respectively. The
largest seismic event was 0.3 ML. In all, blast vibrations were
in line with predictions and seismicity consisted of many
small events due to the tensile failure mechanism and low
energy release during rock breakage in the cave back.
The immediate post-firing effects were not assessed until
12 hours later when the mine was re-entered at 10.34 am
on 30 November 2012. Following the blast, seismic activity
rapidly decreased allowing for earlier than expected re-entry
into both ‘low risk’ and ‘high risk’ areas. A preselected team
consisting of two mining superintendents, an electrician,
pumping technician, ventilation and geotechnical engineers
were briefed and completed a pretask risk assessment prior
to being deployed underground. In order of mine priority, FIG 15 – Section view of RL1650 Southern Transition Block and remnant pillars
the team re-entered from the portal and cleared the decline looking east (schematic not to scale).

12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014 305
A T MCGRATH, A D CAMPBELL AND J B TUCKER

FIG 18 – South facing photo of the south pit wall on 25 June 2013
FIG 16 – South facing photo of the south pit wall on 22 April 2012 (hydraulic radius = 34 m).
(hydraulic radius = 12 m).
•• successful initiation of the RL1650 STB mass firing within
the allowable sleep time limit and prior to damaging
seasonal rainfalls and significant south wall failure in the
pit
•• no immediate post blast damage to the rock mass
and ground control on RL1650, RL1625 and RL1600
underground access drives and excavations
•• air blast and concussion successfully controlled by firing
bulkheads and protection bunds on RL1650; blast gases
were contained on RL1650
•• the design MIC of 272.5 kg achieved through single hole
firings, which minimised blast vibrations; the entire
RL1650 STB mass firing achieved within firing system
time limits (ie 20 000 ms)
•• no blast damage incurred to mine infrastructure including
the 1.6 MW exhaust fans on RL1625 and the in-pit
dewatering pump stations
•• seismic activity successfully monitored and tracked as a
FIG 17 – South facing photo of the south pit wall on 30 November 2012 means of determining safe re-entry following the RL1650
(hydraulic radius = 28 m). STB mass firing; the mine fully re-entered within 16 hours
of firing, which was ahead of expectations
demonstrated that the cave hanging wall had begun to yield
•• the performance of primary ground support and
(see Figure 17). However, a progressive stage of caving
reinforcement during the extraction of the RL1625 STB,
expected with a predicted HR of 34 m (Campbell, 2013) had not
yet been reached. The continued retreat of RL1625 OD rings, which was based on stress redistribution and resultant
undercutting of RL1650 STB and the subsequent increase in deformation.
the HR resulted in significant south wall movement in the pit In retrospect, areas that could have been improved are
in late May 2013. From 2 June 2013 until 25 June 2013, there stated as follows:
were a number of large and staggered toppling failures up •• selection of a dedicated team of personnel to manage the
to RL1900 that were influenced by the relatively strong rock project who were separate from daily operational roles
mass and presence of Fault 2 parallel structures. These events and requirements
aligned with earlier predictions. A photo of the south pit wall •• commencing the detailed planning phase earlier so that
showing the cave propagation is shown in Figure 18. drill ring and horizontal development design align with
the finalised blasting concept; RL1650 development was
KEY LESSONS AND RECOMMENDATIONS completed and ring design had started prior to selection
The intention of this paper is to document the lessons that have of the final blasting methodology
been learnt during the transition mining phase. Should the •• earlier prioritisation of charging activities to minimise
need to conduct a similar size or orientated block extraction detonator and product sleep time
arise in the future, it is hoped that the following points will be •• in the lead up to the RL1650 STB mass firing,
taken into consideration. Particular emphasis is given to the conducting actual production ring firings using wireless
RL1650 STB mass firing. communication link between the bench boxes and base
Positive outcomes included: station via the repeater; ideally, this could have been
•• the coordinated and team-based approach between completed at the proposed surface firing position and may
personnel from different disciplines, backgrounds and have allowed for errors and shortcomings to be resolved
organisations in advance

306 12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014
TRANSITION OF THE ERNEST HENRY MINE FROM OPEN PIT TO AN UNDERGROUND SUBLEVEL CAVE

•• detonator checks by representatives from the contractor hanging wall) to greater than 160 per cent (ie deeper in the
and client prior to firing; prior understanding and formal mine and closer to the foot wall).
sign-off of significant deviation from the original plan
(eg what detonators were to be disconnected following CONCLUSIONS
failed firing attempts)
The transition of EHM from open pit to underground SLC
•• on-site bench box download and detonator reconciliation operation has been a challenging and complex undertaking.
to facilitate quicker turnaround for post-blast analysis and Site personnel have coordinated with a range of external
remediation parties to achieve the desired outcomes. The governing
•• pre-event testing of all dewatering infrastructure and factor to achieving the objectives has been meeting deadlines
fixtures associated with explosives sleep times, deteriorating ground
•• formalised project debrief with all key stakeholders. conditions and the looming threat of rainfall.
The RL1650 STB was one of the largest known firings
THE JOURNEY AHEAD conducted in an Australian underground metalliferous
At the time of writing, remaining transition ore blocks included mine. The blast was successfully initiated via wireless
the southern and western transition blocks on RL1625 and the communication link with all personnel and equipment
RL1650 Eastern Transition Block. Table 1 provides a summary removed from the immediate vicinity. No direct blast damage
of key features for these ore blocks. was sustained to surface or underground infrastructure. As a
result of this firing, a large section of the inclined crown pillar
between the pit and underground mine was fragmented
TABLE 1
and formed an ore blanket for air blast management and
Remaining transition ore blocks. prevention of early waste dilution.
Area Tonnes Mining method Status The extraction method was altered for RL1625 STB due to
confinement and completed level development. By applying
1625 Southern 336 kt Combination of transverse (in In progress until
lessons learnt from the RL1650 STB mass firing, this phase
Transition Block a north and south direction) September 2014
of transition mining has progressed according to plan.
and longitudinal sublevel cave
During the next year, the remaining transition ore blocks will
retreat
continue to be removed as supplementary and independent
1625 Western 624 kt Transverse sublevel cave retreat In progress until underground ore feed to the conventional transverse SLC
Transition Block from pit wall to the west November 2015 production.
1650 Eastern 458 kt Transverse sublevel cave retreat Producing from
Transition Block from pit wall to the east December 2013 ACKNOWLEDGEMENTS
until October 2014 The authors wish to acknowledge and thank Glencore
Xstrata and Dyno Nobel for supporting and approving the
publication of this paper. In addition, gratitude is expressed
To date, the after effects of the RL1650 STB mass firing
to the many mine site personnel and industry experts who
have been managed. The remnant pillars from unfired
have contributed towards the ongoing safe and efficient
regions have been handled through controlled undercutting.
extraction of the transition ore blocks.
Unfired Smartshot detonators from the RL1650 STB present
an ongoing hazard and will continue to be managed through
misfire management and secondary breakage protocols. Areas REFERENCES
of concern have been identified based on cave flow modelling Campbell, A, 2013. Cave management plan, internal document,
and the post blast analysis and interpretation. Ernest Henry Mine, pp 27–31.

Steady state caving should be realised from May 2015. This Campbell, A, Lilley, C and Henley, K, 2011. Prevention of blast
induced damage at EHM, in Proceedings EXPLO Conference 2011,
coincides with production of RL1600, RL1575 and RL1550
pp 1–14 (The Australasian Institute of Mining and Metallurgy:
transverse SLC retreats beneath the pit and the cessation of
Melbourne).
uphole retreating on RL1625. A total of 16 production levels
shall take the SLC down to RL1200. Each level will produce Department of Employment, Economic Development and
an average of 3.7 Mt. The draw strategy will range from Innovation, 2009. North West Queensland Mineral Province
[online]. Available from: <http://mines.industry.qld.gov.au/
40 per cent (ie for southern production rings close to the
assets/tenders/nwqmp_map_2.pdf> [Accessed: 1 October 2013].

12TH AUSIMM UNDERGROUND OPERATORS’ CONFERENCE / ADELAIDE, SA, 24–26 MARCH 2014 307

View publication stats

Vous aimerez peut-être aussi