Vous êtes sur la page 1sur 7

120.

00% BAR CHAT & S-CURVE


Chart Title
PROYEK : PLTD CPO BELITUNG 5 MW
BOBOT 2016

ITEM NO. DESKRIPSI


APRIL MEI JUNI JULI AGT SEPT OKT NOV DES
%
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
I PERSIAPAN 100.00%
Soil Investigation+Land Clearing & Temporary Facility 0.19%
0.03% 0.03% 0.025% 0.025% 0.025% 0.05%
II. PERENCANAAN
1 Engineering - BD & DDE utk pek lokal 1.81%
0.29% 0.41% 0.41% 0.41% 0.29%

III. PELAKSANAAN (Including Procurement)


1 Engine, Transportation and Handling 46.64%
0.83% 0.83% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67% 1.67%
b Micellaneous hoist and trolleys, the contractor 0.28%
80.00%
to design to capacity based on the heaviest (2 ton) 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%

2 Mechanical & Piping *)


2.1. Fuel Oil System 6.35%
0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64% 0.64%
2.2 Lube Oil System 2.25%
0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28% 0.28%
2.3 Compressed Air System 1.26%
0.32% 0.32% 0.32% 0.32%
2.4 Cooling Water System 2.94%
60.00% 0.73% 0.73% 0.37% 0.37%
2.5 Water Treatment Plant 1.34%
0.67% 0.67%
2.6 Exhaust Gas System 2.80%
0.56% 0.56% 0.56% 0.56% 0.56%
2.7 Oily Water 0.49%
0.25% 0.25%
3 Electrical & Instrument
3.1 MV System 3.82%
0.64% 1.09% 2.09%
3.2 LV System 2.99%
40.00% 1.00% 1.00% 1.00%
3.3 DC System 0.92%
0.18% 0.18% 0.18% 0.18% 0.18%
3.4 Lighting 0.82%
0.21% 0.21% 0.21% 0.21%
3.5 Lightning Protection & Safety Earthing 1.81%
protection system 0.45% 0.45% 0.45% 0.45%
3.6 Internet & Data communication system 0.36%
0.18% 0.18%
3.7 CCTV & Security system 0.27%
20.00% 0.14% 0.14%
3.8 Cabling ( Incl. Tray, Conduit, Laying dan Connecting ) 1.25%
0.31% 0.31% 0.31% 0.16% 0.16%
4 Fire Fighting & Alarm system 3.33%
0.55% 0.55% 0.55% 0.55% 0.55% 0.55%
5 Civil Works and Structures 10.15%
0.30% 0.30% 0.30% 0.48% 0.48% 0.41% 0.41% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56% 0.48% 0.48% 0.48% 0.48% 0.48% 0.28% 0.28% 0.28% 0.28%
6 Erection & Commissioning 7.24%
0.80% 0.80% 0.80% 0.80% 0.80% 0.80% 0.80% 0.80% 0.20% 0.20% 0.20% 0.20%
IV. Others 0.70%
0.35% 0.35%
0.00%
0 100% 5 10 15 20 25 30 35 40
Total Budgeted Cost 0.00% 0.00% 0.29% 0.41% 1.27% 1.57% 2.28% 2.03% 2.21% 2.24% 1.67% 1.67% 3.61% 4.80% 4.84% 5.16% 4.42% 4.99% 5.22% 5.07% 6.07% 3.40% 3.90% 3.90% 3.23% 2.95% 2.75% 2.75% 3.31% 3.31% 2.43% 2.43% 4.53% 0.55%
Cumulative Planned Value (PV) 0.00% 0.00% 0.00% 0.29% 0.70% 1.97% 3.54% 5.82% 7.85% 10.07% 12.31% 13.97% 15.64% 19.25% 24.06% 28.90% 34.06% 38.48% 43.46% 48.68% 53.75% 59.82% 63.22% 67.13% 71.03% 74.26% 77.22% 79.97% 82.73% 86.04% 89.35% 91.78% 94.20% 98.73% 99%
Actual Cost and Earned Value 3.54% 12.31% 24.06% 43.46% 65.88% 79.87% 91.41%
30-May-16 3.54% 30-Jun-16 8.76% 30-Jul-16 11.75% 30-Aug-16 19.40% 22.42% 13.99%
BAR CHAT & S-CURVE
PROYEK : PLTD CPO BELITUNG 5 MW
BOBOT 2019

ITEM NO. DESKRIPSI


JANUARI FEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
A PEKERJAAN PERSIAPAN 48
A.1 IJIN PEMBANGUNAN 48
A.2 MOBILISASI DAN DEMOBILISASI PERALATAN DAN KESELAMATAN KERJA 48
A.3 PERBERSIHAN LAHAN 48
A.4 PENGUKURAN LAPANGAN ( MARKING ) 48
A.5 ADMINISTRASI PROYEK 48
A.6 LISTRIK DAN AIR KERJA 48

B PEKERJAAN STRUKTUR
B.1 PONDASI
B.1.1 PEK. GALIAN 2
B.1.2 PEK. PEMANCANGAN PONDASI 4
B.1.3 PEK. URUGAN 3

B.2 PEKERJAAN STRUKTUR LANTAI 1 (SATU)


B.2.1 PEK. SLOOF
BETON 1
BEKISTING 2
BESI 1
B.2.2 PEK. PLAT LANTAI
BETON 1
BEKISTING 2
BESI 1
B.2.3 PEK. KOLOM
BETON 1
BEKISTING 2
BESI 1
B.2.4 PEK. TANGGA
BETON 2
BEKISTING 1
BESI 1
B.3 PEKERJAAN STRUKTUR LANTAI 2 ( DUA )
B.3.1 PEK. BALOK
BETON 1
BEKISTING 1
BESI 1
B.3.2 PEK. PLAT LANTAI
BETON 1
BEKISTING 2
BESI 1
B.3.3 PEK. KOLOM
BETON 1
BEKISTING 1
BESI 1
B.3.4 PEK. TANGGA
BETON 1
BEKISTING 1
BESI 1
B.4 PEKERJAAN STRUKTUR LANTAI TYPIKAL (LANTAI 3-6)
B.4.1 PEK. BALOK
BETON 1
BEKISTING 1
BESI 1
B.4.2 PEK. PLAT LANTAI
BETON 1
BEKISTING 2
BESI 1
B.4.3 PEK. KOLOM
BETON 1
BEKISTING 1
BESI 1
B.4.4 PEK. TANGGA
BETON 1
BEKISTING 1
BESI 1
B. 5 PEKERJAAN LANTAI ATAP
B.5.1 PEK. BALOK
BETON 1
BEKISTING 1
BESI 1
B.5.2 PEK. PLAT LANTAI
BETON 1
BEKISTING 1
BESI 1
B.5.3 PEK. RANGKA ATAP
PEK. KUDA KUDA BAJA 1
PEK. GORDING BAJA 1
PEK. RANGKA BAJA RINGAN 1

C PEKERJAAN ARSITEKTUR
C. 1 PEKERJAAN DINDING
C.1.1 PEK. PASANGAN DINDING 11
C.1.2 PEK. PLESTER
C.1.3 PEK. ACI 8
C.1.4 PEK. KOLOM DAN BALOK PRAKTIS
C.1.5 PEK. DINDING PARTISI 6
C.2 PEKERJAAN KUSEN PINTU JENDELA 6
C.2.1 PEK. KUSEN PINTU 6
C.2.2 PEK. KUSEN JENDELA 6
C. 3 PEKERJAAN LANTAI
C.3.1 PEK. PASANGAN KERAMIK LANTAI
C.3.2 PEK. PASANGAN PLINT LANTAI
C.3.3 PEK. PASANGAN KERAMIK DINDING
C.3.4 PEK. WATERPROOFING
C. 4 PEKERJAAN PLAFON
C.4.1 PEK. RANGKA PLAFON
C.4.2 PEK. LIST PLAFON
C. 5 PEKERJAAN PENGECATAN
C.5.1 PEK. PENGECATAN DINDING
C.5.2 PEK. PENGECATAN PLAFON DAN LANGIT LANGIT
PEK. CAT PLAFON
PEK. CAT LIST PLAFON
C.5.3 PEK. FINISHING KUSEN DAN DAUN PINTU JENDELA
PEK. FINISHING KUSEN DAN DAN DAUN PINTU
PEK. FINISHING KUSEN DAN DAUN JENDELA
C. 6 PEKERJAAN PENUTUP ATAP
C.6.1 PEK. PEMASANGAN GENTENG 1
C.6.2 PEK. NOK ATAP 1
C.6.3 PEK. TALANG AIR 1
C. 7 PEKERJAAN SANITARY
C. 8 LAIN - LAIN
C.7.1 PEK. RALLING
C.7.2 PEK. CERMIN

D PEKERJAAN LAHAN PARKIR ( HALAMAN )


D.1 PEKERJAAN PEMBERSIHAN LAHAN
D.2 PEKERJAAN URUGAN DAN GALIAN TANAH UNTUK JALAN
D.3 PEKERJAAN PEMADATAN JALAN
D.4 PEKERJAAN SIRTU
D.5 PEKERJAAN PENGASPALAN JALAN
D.6 PEKERJAAN KANSTIN
D.7 PEKERJAAN MARKA JALAN
D.8 PEKERJAAN PEMBUATAN TAMAN

E PEKERJAAN MEP
E. 1 PEKERJAAN MEKANIKAL
E.1.1 PEKERJAAN POMPA TRANSFER
INSTALASI POMPA TRANSFER
INSTALASI RADAR POMPA
E.1.2 PEKERJAAN POMPA DISTRIBUSI
INSTALASI POMPA TRANSFER
E.1.3 PEKERJAAN INSTALASI LIFT
PENGADAAN UNIT
PERIJINAN
INSTALASI UNIT
E.1.4 PEKERJAAN PANELING LISTRIK
PEK. PANEL LISTRIK
PEK. PANEL POMPA
PEK. PANEL LIFT
PEK. PANEL DATA
PEK. PANEL TELEPON

E. 2 PEKERJAAN ELEKTRIKAL
E.2.1 PEKERJAAN LAMPU / TITIK NYALA DAN STOP KONTAK
PEK. INSTALASI TITIK NYALA LAMPU
PEK. INSTALASI SAKLAR
PEK. INSTALASI STOP KONTAK
PEK. INSTAL LAMPU DAN ALMATURE
PEK. INSTAL SAKLAR
PEK. INSTAL STOP KONTAK
E.2.2 PEKERJAAN INSTALASI TELEPON
PERALATAN UTAMA
- PABX
- UNIT TELEPON
PEK. INSTALASI KABEL TELEPON
PEK. INSTALASI OUTLET DATA
E.2.3 PEKERJAAN DATA
PEK. INSTALASI KABEL DATA
PEK. INSTALASI OUTLET DATA
E.2.2 PEKERJAAN PENTANAHAN ( GROUNDING )
ARUS KUAT
ARUS LEMAH
E.2.3 PEKERJAAN PENANGKAL PETIR

E. 3 PEKERJAAN PLUMBING
E.3.1 PEK. INSTALASI AIR HUJAN
INSTALASI PEMIPAAN
PEMBUATAN RESAPAN
E.3.2 PEK. INSTALASI AIR BEKAS DAN KOTOR, VENT
INSTALASI PEMIPAAN
PEK. SEPTICKTANK
PEMBUATAN RESAPAN
E.3.3 PEK. INSTALASI AIR BERSIH
INSTALASI PEMIPAAN
PEK. GWT
PEK. WATER TORN
154
Total Budgeted Cost 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Cumulative Planned Value (PV) 0 0.00% 0.00% 0.00% 0.00% 0.00% #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Actual Cost and Earned Value #REF! 65.88%
30-May-16 30-Jun-16 #REF! 30-Jul-16 30-Aug-16 #REF!
PEMBANGUNAN PERPUSTAKAAN DAN KARYA UNIVERSITAS PANCASILA

A PEKERJAAN PERSIAPAN
A.1 IJIN PEMBANGUNAN
A.2 MOBILISASI DAN DEMOBILISASI PERALATAN DAN KESELAMATAN KERJA
A.3 PERBERSIHAN LAHAN
A.4 PENGUKURAN LAPANGAN ( MARKING )
A.5 ADMINISTRASI PROYEK
A.6 LISTRIK DAN AIR KERJA

B PEKERJAAN STRUKTUR
B.1 PONDASI
B.1.1 PEK. GALIAN
B.1.2 PEK. PEMANCANGAN PONDASI
B.1.3 PEK. URUGAN
B.2 PEKERJAAN STRUKTUR LANTAI 1 (SATU)
B.2.1 PEK. SLOOF
2.1.1 BETON
2.1.2 BEKISTING
2.1.3 BESI
B.2.2 PEK. PLAT LANTAI
2.2.1 BETON
2.2.2 BEKISTING
2.2.3 BESI
B.2.3 PEK. KOLOM
2.3.1 BETON
2.3.2 BEKISTING
2.3.3 BESI
B.2.4 PEK. TANGGA
2.4.1 BETON
2.4.2 BEKISTING
2.4.3 BESI
B.4 PEKERJAAN STRUKTUR LANTAI 2 ( DUA )
B.4.1 PEK. BALOK
4.1.1 BETON
4.1.2 BEKISTING
4.1.3 BESI
B.4.2 PEK. PLAT LANTAI
4.2.1 BETON
4.2.2 BEKISTING
4.2.3 BESI
B.4.3 PEK. KOLOM
4.3.1 BETON
4.3.2 BEKISTING
4.3.3 BESI
B.4.4 PEK. TANGGA
4.4.1 BETON
4.4.2 BEKISTING
4.4.3 BESI
B.4 PEKERJAAN STRUKTUR LANTAI TYPIKAL (LANTAI 3-6)
B.4.1 PEK. BALOK
4.1.1 BETON
4.1.2 BEKISTING
4.1.3 BESI
B.4.2 PEK. PLAT LANTAI
4.2.1 BETON
4.2.2 BEKISTING
4.2.3 BESI
B.4.3 PEK. KOLOM
4.3.1 BETON
4.3.2 BEKISTING
4.3.3 BESI
B.4.4 PEK. TANGGA
4.4.1 BETON
4.4.2 BEKISTING
4.4.3 BESI
B.4 PEKERJAAN LANTAI ATAP
B.4.1 PEK. BALOK
4.4.1 BETON
4.4.2 BEKISTING
4.4.3 BESI
B.4.2 PEK. PLAT LANTAI
4.2.1 BETON
4.2.2 BEKISTING
4.2.3 BESI
B.4.3 PEK. RANGKA ATAP
4.3.1 PEK. KUDA KUDA BAJA
PEK. GORDING BAJA
PEK. RANGKA BAJA RINGAN
C PEKERJAAN ARSITEKTUR
C.1 PEKERJAAN DINDING
C.1.1 PEK. PASANGAN DINDING
C.1.2 PEK. PLESTER
C.1.3 PEK. ACI
C.1.4 PEK. KOLOM DAN BALOK PRAKTIS
C.1.5 PEK. DINDING PARTISI
C.2 PEKERJAAN KUSEN PINTU JENDELA
C.2.1 PEK. KUSEN PINTU
C.2.2 PEK. KUSEN JENDELA
C.3 PEKERJAAN LANTAI
C.3.1 PEK. PASANGAN KERAMIK LANTAI
C.3.2 PEK. PASANGAN PLINT LANTAI
C.3.3 PEK. PASANGAN KERAMIK DINDING
C.3.4 PEK. WATERPROOFING
C.4 PEKERJAAN PLAFON
C.4.1 PEK. RANGKA PLAFON
C.4.2 PEK. LIST PLAFON
C.5 PEKERJAAN PENGECATAN
C.5.1 PEK. PENGECATAN DINDING
C.5.2 PEK. PENGECATAN PLAFON DAN LANGIT LANGIT
5.2.1 PEK. CAT PLAFON
5.2.2 PEK. CAT LIST PLAFON
C.5.3 PEK. FINISHING KUSEN DAN DAUN PINTU JENDELA
5.3.1 PEK. FINISHING KUSEN DAN DAN DAUN PINTU
5.3.2 PEK. FINISHING KUSEN DAN DAUN JENDELA
C.6 PEKERJAAN PENUTUP ATAP
C.6.1 PEK. PEMASANGAN GENTENG
C.6.2 PEK. NOK ATAP
C.6.3 PEK. TALANG AIR
C.7 PEKERJAAN SANITARY
C.8 LAIN - LAIN
C.7.1 PEK. RALLING
C.7.2 PEK. CERMIN
D PEKERJAAN LAHAN PARKIR ( HALAMAN )
D.1 PEKERJAAN PEMBERSIHAN LAHAN
D.2 PEKERJAAN URUGAN DAN GALIAN TANAH UNTUK JALAN
D.3 PEKERJAAN PEMADATAN JALAN
D.4 PEKERJAAN SIRTU
D.5 PEKERJAAN PENGASPALAN JALAN
D.6 PEKERJAAN KANSTIN
D.7 PEKERJAAN MARKA JALAN
D.8 PEKERJAAN PEMBUATAN TAMAN
E PEKERJAAN MEP
E.1 PEKERJAAN MEKANIKAL
E.1.1 PEKERJAAN POMPA TRANSFER
1.1.1 INSTALASI POMPA TRANSFER
1.1.2 INSTALASI RADAR POMPA
E.1.2 PEKERJAAN POMPA DISTRIBUSI
1.2.1 INSTALASI POMPA TRANSFER
E.1.3 PEKERJAAN INSTALASI LIFT
1.3.1 PENGADAAN UNIT
1.3.2 PERIJINAN
1.3.3 INSTALASI UNIT
E.1.4 PEKERJAAN PANELING LISTRIK
1.4.1 PEK. PANEL LISTRIK
1.4.2 PEK. PANEL POMPA
1.4.3 PEK. PANEL LIFT
1.4.4 PEK. PANEL DATA
1.4.5 PEK. PANEL TELEPON
E.2 PEKERJAAN ELEKTRIKAL
E.2.1 PEKERJAAN LAMPU / TITIK NYALA DAN STOP KONTAK
2.1.1 PEK. INSTALASI TITIK NYALA LAMPU
2.1.2 PEK. INSTALASI SAKLAR
2.1.3 PEK. INSTALASI STOP KONTAK
2.1.4 PEK. INSTAL LAMPU DAN ALMATURE
2.1.5 PEK. INSTAL SAKLAR
2.1.6 PEK. INSTAL STOP KONTAK
E.2.2 PEKERJAAN INSTALASI TELEPON
2.2.1 PERALATAN UTAMA
- PABX
- UNIT TELEPON
2.2.2 PEK. INSTALASI KABEL TELEPON
2.2.3 PEK. INSTALASI OUTLET DATA
E.2.3 PEKERJAAN DATA
2.3.1 PEK. INSTALASI KABEL DATA
2.3.2 PEK. INSTALASI OUTLET DATA
E.2.2 PEKERJAAN PENTANAHAN ( GROUNDING )
2.2.1 ARUS KUAT
2.2.2 ARUS LEMAH
E.2.3 PEKERJAAN PENANGKAL PETIR
E.3 PEKERJAAN PLUMBING
E.3.1 PEK. INSTALASI AIR HUJAN
3.1 INSTALASI PEMIPAAN
3.2 PEMBUATAN RESAPAN
E.3.2 PEK. INSTALASI AIR BEKAS DAN KOTOR, VENT
3.2.1 INSTALASI PEMIPAAN
3.2.2 PEK. SEPTICKTANK
3.2.3 PEMBUATAN RESAPAN
E.3.3 PEK. INSTALASI AIR BERSIH
3.3.1 INSTALASI PEMIPAAN
3.3.2 PEK. GWT
3.3.3 PEK. WATER TORN

Vous aimerez peut-être aussi