@)ankazan as.
Caria and Eco Mini Wood Pellet
Boiler with Touch Panel
Installation, Operating and Maintenance Manualcleta nem oo se coumwoceme @antazan as.
CONTENTS
1- INTRODUCTION ....
2- WARNINGS AND CAUTIONS...
3- DECLARATION OF CONFORMITY...
4- WARRANTY INFORMATION ..
5- TECHNICAL INFORMATION...
5.1- General specifications
5.2- Operating principles...
5.3- Safety systems ...
6- CONTROL THE CHIMNEY;..
7- CONTROL THE VENTILATION OF THE BOILER ROOM; ..
8- CONTROL THE HYDROULIC INSTALLATION ;
9- PELLET SCREW FILLING + PELLET QUANTITY CALIBRATION + PARAMETER SETTINGS FOR
TOUCH PANELS
10- TOUCH SCREEN BOILER CONTROL PANEL ..
10.1- Menu Map
10.2- Setting the Parameters.
10.3- Night Time Module.
10.4- Starting the Boiler.
10.5- Alarms for Touch Screen..
10.6- Connecting your boiler to Interne!
10.7- Updating firmware
11- Caria T-LUX- ECO MINIT ELECTRICAL DIAGRAMS AND MODULE B CONNECTIO!
12- WARRANTY TERMS and CONDITIONSCARIA LUX and ECO MINI_COMMISIONING
1- INTRODUCTION
Thank you for selecting the Ankazan Caria wood pellet hot water boiler (the ‘boiler’; this manual must be read
carefully before using the boller for the first time so as to ensure its safe and correct use.
This manual comprises the information concerning the operation, use and maintenance of CARIA "CP" Model hot
water boilers with pellet burners. This manual alone is not sufficient for correct installation, operation and use,
installers, services and user must obey the rules specified in current EN + current Local norms, current EC directives
and current Local codes. This manual gives the supplementary information and precautions,
Keep this booklet near the appliance in a safe place in the boiler room for future reference.
Please read the manual very carefully, in order to be able to operate your boiler safely and with high efficiency for a
long period,
Due to the continuous development in the methods, design and the manufacturing, the contents of this document may
change at any time and without prior notice. Producer or distributor do not accept any responsibility for errors or
damage of any kind that might be attributed to this publication,
2- WARNINGS AND CAUTIONS
These safety guidelines should be read before operating the system, to avoid incorrect usage that might lead to
personal injury or damage to the system.
The boiler must be installed in accordance with the rules in force, only in a well ventilated and frost free space, indoor
but except the living areas.
All installation, first commissioning, assembly and maintenance, repair, replacement of components must be carried
out exclusively by a fully trained, professionally qualified service personnel and must conform with this manual and the
local codes and requirements of the authority having jurisdiction, or in the absence of such requirements, apply to the
EEC directives and European norms (EN),
After commissioning; the repair and maintenance work is under the responsibility of the user and must be done with a
qualified service.
If the boiler is not used for the purposes other than specified in this booklet and incorrect installation, commissioning
and use can cause a fire or explosion which may result property damage, personnel injury, of loss of life.
Boiler is designed for hot water operation only (max 80 °C) and the system pressure must be according to the limited
‘operating pressure specified on the boiler name plate (3 bar standard) . Heat transfer medium is water.
Boilers must be fired by fuels specified in this manual.
Boilers must be fired only by its original burner and screw feeder.
Recommendation: For long burner running times, in order to reduce the start-stop emissions and to reduce
maintenance costs, the boiler should be fitted with a buffer storage tank, thermo siphon buffer storage tank or
combination storage tank. In practice, buffer capacities between 40 and 75 litersikW have proven successful. Be sure
to take into account the country-specific requirements regarding buffer storage tanks. The operation of the system is
only permissible if it can be guaranteed that the boiler's nominal heat output can be reduced by 50% for a period of at
least 2 hours.
Use only those fuels recommended by us - wood pellets pursuant to EN 14961-2, Class A1+ A2 ( 6 mm). Only in
this way low-emission, economic, and trouble-free operation of your pellet heating system can be ensured. Non-
compliance will result in voiding of the guarantee
Your heating boiler is adjustable within an output range of 30% to 100% of the rated output. The units should be
operated if at all possible in the middle and upper output range (adjusted to the respective heat requirement), in order
to avold unnecessary emissions in low load operation
If technical changes are undertaken independently, we assume no liability for damages that may result thereof.