Plant: Nasulo

Date: 20-Apr-2018
Requirement: 80%
Speed Droop: 5%
Deadband Setting: 0.10 Hz
Capacity: 48.3 MW
Static Gain: 16.10 MW/Hz

Interval Schedule Events % Compliance C/NC Remarks


1 0 100.00% C
2 0 100.00% C
3 1 36.27% NC
4 1 37.26% NC
5 0 100.00% C
6 0 100.00% C
7 0 100.00% C
8 2 340.42% C
9 6 101.90% C
10 3 130.13% C
11 4 123.58% C
12 3 77.40% NC
13 3 95.05% C
14 3 113.26% C
15 4 127.53% C
16 2 0.00% NA
17 1 0.00% NA
18 2 0.00% NA
19 0 0.00% NA
20 0 100.00% C
21 0 100.00% C
22 2 107.43% C
23 5 53.47% NC
24 3 41.04% NC
Plant: Sogongon 1
Date: 20-Apr-2018
Requirement: 80%
Speed Droop: 5%
Deadband Setting: 0.10 Hz
Capacity: 20.0 MW
Static Gain: 6.67 MW/Hz

Interval Schedule Events % Compliance C/NC Remarks


1 0 0.00% NA
2 0 0.00% NA
3 1 0.00% NA
4 1 0.00% NA
5 0 0.00% NA
6 0 0.00% NA
7 0 0.00% NA
8 2 0.00% NA
9 6 0.00% NA
10 3 0.00% NA
11 4 0.00% NA
12 3 0.00% NA
13 3 0.00% NA
14 3 0.00% NA
15 4 0.00% NA
16 2 0.00% NA
17 1 0.00% NA
18 2 0.00% NA
19 0 0.00% NA
20 0 0.00% NA
21 0 0.00% NA
22 2 0.00% NA
23 5 0.00% NA
24 3 0.00% NA
Plant: Sogongon 2
Date: 20-Apr-2018
Requirement: 80%
Speed Droop: 5%
Deadband Setting: 0.10 Hz
Capacity: 20.0 MW
Static Gain: 6.67 MW/Hz

Interval Schedule Events % Compliance C/NC Remarks


1 0 0.00% NA
2 0 0.00% NA
3 1 0.00% NA
4 1 0.00% NA
5 0 0.00% NA
6 0 0.00% NA
7 0 0.00% NA
8 2 0.00% NA
9 6 0.00% NA
10 3 0.00% NA
11 4 0.00% NA
12 3 0.00% NA
13 3 0.00% NA
14 3 0.00% NA
15 4 0.00% NA
16 2 0.00% NA
17 1 0.00% NA
18 2 0.00% NA
19 0 0.00% NA
20 0 0.00% NA
21 0 0.00% NA
22 2 0.00% NA
23 5 0.00% NA
24 3 0.00% NA