Construction Site Measurement Sheet (CSM)

RA Bill No. RA-01

Measurement Date 30-12-2016

Project Name ReNew Akshay Urja Pvt Ltd

Installation Site Location 100 MW Mahbubnagar site


Vendor/Contractor Name

Type of Work £Supply þServices


PO/Work Order No. 430000381 Date :04.01.2017

Work Description Storm Water Drain Construction

Target work completion/Delivery Date

Sl. No. Work Description UOM Total Qty Billed Qty Balance Qty

Storm Water Drain Construction including


1 Rmt 33561 846.3 32714.7
Trapezidal and U Drain
2

10

For ReNeW For ReNeW For ReNeW For Vendor/Contractor


Site Incharge Site Quality Approved By CPM
M/s.
Name : Name : Name : Site In-charge

Date : Date : Date : Name :

Date :