ZUBARA GAS FIELD 

 
 

Development Plan 
 
 
 
 
 
 
 
 
 
 
Team members: 
Stefi Hooft van Huysduynen 
Menno de Nooij 
Payman Veisi Zadeh 
Niels Viezee 
Stef Vlaanderen 

 
Date: May 27, 2009 
 
 
 
 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Preface 
Gas N’ Roses is very proud to present this field development plan to you that is the best solution to develop concession 2 
of the Zubara Field. This final scenario is selected out of three scenarios. 
 
Part  A  explains  how  three  scenarios  are  created  and  which  scenario  is  chosen  for  the  final  development.  In  Chapter  1, 
some general information about the Zubara Field itself and characteristics of the gas and its pressure will be given. Also a 
global  risk  analysis  and  a  stakeholder  analysis  are  included  because  they  have  much  influence  on  how  Gas  N’  Roses 
decided to develop the three scenarios for this project. 
The method used to create three solutions is explained in Chapter 2. Chapter 3 gives information about all three scenarios. 
In  the  next  chapter,  4,  a  cost  analysis  of  all  three  scenarios  is  given.  On  basis  of  the  TECOP,  HSSE  and  cost  studies,  a 
proposal of the best scenario is given in Chapter 5, the last chapter of part A. 
 
Part B of the report is the final field development plan. Chapter 6 provides general information about the field layout and 
the value chain. Chapter 7 gives a thorough risk analysis consisting of an HSSE study and a TECOP risk identification. All 
technical specifications of the selected scenario such as the well plan, structures, topside and process plant are elaborated 
in Chapter 8. The costs of the total project and some sensitivity analyses are given in Chapter 9. And finally, in Chapter 10, 
a final conclusion is presented.  


Zubara Gas Field Development Plan, Concession 2  May 2009
           

Summary 
Gas N’ Roses is an engineering consultant in the field of oil and gas production which provides the client with a strategic 
plan concerning the development of gas or oil. The focus lays mainly on upstream production but we can also provide the 
client with downstream engineering solutions.  
 
The objective is to make a field development plan for the Zubara gas field northwest of Qatar. The field has a total GIIP of 
900 Tscf but for this project Gas N’ Roses will focus on concession 2, which has an area of 30,000 acres. The recoverable 
GIIP of concession 2 is 12.3 Tscf and the CIIP is 948.8 MMbbls. The distance to shore is 65 km and the water depth is 250 
m.  
 
Next to the technical information about this project other issues like the stakeholders and several risks are important. The 
most  important  stakeholders  which  come  out  of  the  stakeholder  analysis  are  the  Qatar  government,  Qatar  Petroleum, 
Shell and the gas and condensate consumers. Important risks in this project are the relations with surrounding countries. 
In the gas and oil branch, fluctuations in gas prices are a big issue and can have a large influence on the economical part of 
the development and continuity of the project.  
 
Risks concerning the specific field are the presence of sinkholes and the large amount of H2S. These issues will influence 
the  technical  aspects  of  the  project.  Because  of  the  high  H2S  production,  selling  this  product  could  be  also  economical 
attractive and profitable. 
 
The  kite  model  is  used  to  determine  different  scenarios.  The  scenarios  are  built  up  from  different  building  blocks  and 
finally rated with help of a Multi Criteria Analysis (MCA). The criteria are based on both Gas N’ Roses’ and Shells vision. 
Also  the  stakeholder  analysis  and  the  global  risk  analysis  are  taken  into  account.  Finally  three  different  scenarios  are 
gained  from  the  MCA.  The  first  scenario  is  a  jacket  structure  platform,  the  second  a semisubmersible  platform  and  the 
third scenario consists of only subsea units.  
 
The three scenarios are worked out as detailed as possible to compare them. The major criteria to compare these three 
scenarios  are  the  HSSE  Study,  TECOP  Risk  Analysis,  Cost  Analysis,  Execution,  and  the  First  Day  To  Gas.  After  this 
comparison,  a  sensitivity  analysis  is  used  to  be  certain  one  scenario  will  be  the  best  option.  In  all  cases  the  unmanned 
jacket structure seems to be the most feasible scenario.   
 
The second part of the report consists of the development plan of the selected scenario.  
The jacket platform is a proven technology with a relatively low CAPEX and OPEX. The CAPEX will be 2.7 billion USD, the 
OPEX, over a field life of 45 years, will be 5.5 billion USD. 
 
The  processes  will  be  controlled  and  monitored  at  an  onshore  facility  which  means  a  safer  work  area.  The  jacket  is 
accessible by helicopter for maintenance.  
 
The  production  topside  will  produce  1,500  MMscf/day  with  17  wells  (1  vertical,  10  horizontal  and  a  manifold  with  6 
deviated  wells).  Gas,  water,  condensates  and  impurities  will  be  separated  offshore.  The  gas  and  condensates  will  be 
evacuated  separately.  The  water  will  be  dumped  overboard  after  being  treated  and  the  CO2  will  be  re‐injected  into  an 
injection well. The H2S will not be separated offshore, but onshore in the LNG and GTL plants. 
 
Before  the  conversion  of  gas  to  any  product,  the  NPV  of  this  project  will  be  3,940  billion  USD  with  an  internal  rate  of 
return  of  42.  If  70  %  of  the  gas  is  delivered  to  the  Pearl  GTL  plant,  the  remaining  30  %  to  the  Q4  LNG  plant  and  the 
condensates to the Laffan Refinery which are all located in Ras Laffan.  


Zubara Gas Field Development Plan, Concession 2  May 2009
           
 

Table of Contents 
Preface.......................................................................................................................................................................................2 
Summary....................................................................................................................................................................................3 
Table of Contents ......................................................................................................................................................................4 
Abbreviations.............................................................................................................................................................................6 
Company Profile ........................................................................................................................................................................7 
Company background ...........................................................................................................................................................7 
Vision ....................................................................................................................................................................................7 
The Team ..............................................................................................................................................................................7 
Part A: General Information and Three Possible Scenarios.......................................................................................................8 
1.  Problem Definition...........................................................................................................................................................9 
1.1.  General Field Information ........................................................................................................................................9 
1.2.  Boundary Conditions................................................................................................................................................9 
1.3.  Stakeholders.............................................................................................................................................................9 
1.4.  General Risk Analysis..............................................................................................................................................10 
1.5.  Gas Characteristics and Metocean Data ................................................................................................................11 
1.5.1.  Gas Composition ...........................................................................................................................................11 
1.5.2.  Gas Pressure ..................................................................................................................................................11 
1.5.3.  Waves, Wind and Earthquakes......................................................................................................................12 
2.  Development of Scenarios .............................................................................................................................................13 
2.1.  Criteria and Weighting Factors ..............................................................................................................................13 
2.2.  Building Blocks .......................................................................................................................................................14 
2.3.  Multi Criteria Analysis ............................................................................................................................................15 
2.4.  Selected Three Scenarios .......................................................................................................................................16 
3.  Scenarios ........................................................................................................................................................................17 
3.1.  Scenario 1...............................................................................................................................................................17 
3.1.1.  General Layout ..............................................................................................................................................17 
3.1.2.  Wells and Subsea Arrangement ....................................................................................................................17 
3.1.3.  Topside ..........................................................................................................................................................18 
3.1.4.  Structure........................................................................................................................................................18 
3.1.5.  Costs ..............................................................................................................................................................19 
3.1.6.  HSSE Study.....................................................................................................................................................19 
3.2.  Scenario 2...............................................................................................................................................................20 
3.2.1.  General Layout ..............................................................................................................................................20 
3.2.2.  Wells and Subsea Arrangement ....................................................................................................................20 
3.2.3.  Drilling Schedule and Field Life......................................................................................................................21 
3.2.4.  Topside ..........................................................................................................................................................21 
3.2.5.  Structure........................................................................................................................................................22 
3.2.6.  Costs ..............................................................................................................................................................22 
3.2.7.  HSSE Study.....................................................................................................................................................22 
3.3.  Scenario 3...............................................................................................................................................................23 
3.3.1.  General Layout ..............................................................................................................................................23 
3.3.2.  Drilling Schedule and Field Life......................................................................................................................23 
3.3.3.  Multiphase Pipeline.......................................................................................................................................24 
3.3.4.  Costs ..............................................................................................................................................................24 
3.3.5.  HSSE Study.....................................................................................................................................................24 
4.  Cost Analysis ..................................................................................................................................................................25 
4.1.  Economical evaluation of three scenarios .............................................................................................................25 
4.2.  Sensitivity analysis of the three scenarios .............................................................................................................26 
5.  Selection of Final Scenario .............................................................................................................................................27 
Part B: Final Field Development Plan ......................................................................................................................................29 


Zubara Gas Field Development Plan, Concession 2  May 2009
           
6.  General Information.......................................................................................................................................................30 
6.1.  Layout.....................................................................................................................................................................30 
6.2.  Introduction of the Field Development Plan..........................................................................................................30 
6.3.  Value Chain ............................................................................................................................................................32 
6.3.1.  Re‐injecting of Carbon Dioxide......................................................................................................................32 
6.3.2.  Removal of Hydrogen Sulphide .....................................................................................................................34 
6.3.3.  Condensates ..................................................................................................................................................34 
6.3.4.  Destination of Gas .........................................................................................................................................35 
6.3.5.  Revenues .......................................................................................................................................................36 
7.  Risks ...............................................................................................................................................................................38 
7.1.  HSSE .......................................................................................................................................................................38 
7.2.  TECOP.....................................................................................................................................................................39 
8.  Technical Aspects...........................................................................................................................................................42 
8.1.  Well Layout ............................................................................................................................................................42 
8.1.1.  Drilling Schedule............................................................................................................................................43 
8.1.2.  Subsea Equipment.........................................................................................................................................44 
8.1.3.  Controls .........................................................................................................................................................47 
8.1.4.  IMR ................................................................................................................................................................48 
8.2.  Topside...................................................................................................................................................................49 
8.2.1.  Non‐processing modules...............................................................................................................................49 
8.2.2.  Process plant .................................................................................................................................................49 
8.3.  Structure ................................................................................................................................................................50 
8.3.1.  Jacket.............................................................................................................................................................50 
8.4.  Pipelines .................................................................................................................................................................52 
8.5.  Execution Plan........................................................................................................................................................53 
8.5.1.  Fabrication & Transportation ........................................................................................................................53 
8.5.2.  Installation.....................................................................................................................................................53 
8.5.3.  Decommissioning ..........................................................................................................................................54 
8.5.4.  Contracting ....................................................................................................................................................54 
8.5.5.  Schedule ........................................................................................................................................................55 
9.  Economical .....................................................................................................................................................................56 
9.1.  Costs.......................................................................................................................................................................56 
9.2.  Revenues................................................................................................................................................................56 
9.3.  Profit.......................................................................................................................................................................57 
9.4.  Economical sensitivity analysis ..............................................................................................................................58 
9.5.  Maximum exposure ...............................................................................................................................................60 
10.  Conclusion ..................................................................................................................................................................61 
Appendices ..............................................................................................................................................................................62 
Appendix I GIIP/ CIIP Calculations.......................................................................................................................................63 
Appendix II Building Blocks .................................................................................................................................................66 
Appendix III Calculation Production per Day and per Well.................................................................................................69 
Appendix IV Calculation of Dimensions of and Loads on Jacket.........................................................................................70 
Appendix V Calculation Semisubmersible...........................................................................................................................72 
Appendix VI.A HAZID Scenario 1.........................................................................................................................................73 
Appendix VI.B HAZID Scenario 2 .........................................................................................................................................75 
Appendix VI.C HAZID Scenario 3 .........................................................................................................................................77 
Appendix VII Calculation Production Deviated Wells Final Scenario..................................................................................78 
Appendix VIII H2S calculations............................................................................................................................................79 
Appendix IX Pipeline calculations .......................................................................................................................................80 


Zubara Gas Field Development Plan, Concession 2  May 2009
           
Abbreviations 
 
bbl  Barrels 
Btu  British Thermal Unit 
CAPEX  Capital Expenditure 
CIIP  Condensate Initially In Place 
FDTG  First Day To Gas 
FDU  Floating Drilling Unit 
FPSO  Floating, Production, Storage and Offloading unit 
GBS  Gravity Base Structure 
GIIP  Gas Initially In Place 
GTL  Gas To Liquid 
HAZID  Hazards Identification 
HSSE  Health, Safety, Sustainability, Environment 
HVAC  Heating, Ventilation, Air Conditioning 
IMR  Inspection, Maintenance and Repair 
IRR  Internal Rate of Return 
LAT  Lowest Astronomical Tide 
LNG  Liquefied Natural Gas 
LPG  Liquefied Petroleum Gas 
L.Q.  Living Quarters 
MRI  Maintenance Repair and Inspection 
NGO  Non‐Governmental Organization 
NPS  Net Present Value 
OPEX  Operational Expenditure 
ppm  Parts per million 
psi  Pounds per square inch 
PVT  Pressure, Volume and Temperature 
QG  Qatar Government 
QP  Qatar Petroleum 
ROV  Remotely Operated Vehicle 
Scf  Standard cubic feet 
SIMOPS  Simultaneous Operations 
TECOP  Technical, Economical, Commercial, Organizational, Political 
TLP  Tension Leg Platform 
VIR  Value to Investment Ratio 


Zubara Gas Field Development Plan, Concession 2  May 2009
           

Company Profile 
Gas N’ Roses is an engineering consultant in the field of oil and gas production. Our goal is to provide our clients with a 
strategic plan concerning the development of a gas or oil field in order for them to improve their E&P performance. From 
our  history  we  are  specialized  in  fields  offshore,  however  in  recent  years  we  have  successfully  completed  a  number  of 
onshore  projects.  Our  focus  lays  mainly  on  upstream  production  but  we  can  also  provide  the  client  with  downstream 
engineering solutions in most parts of the world. Gas N’ Roses is one of the world leaders when it comes to safety and 
creating a sustainable environment for our clients 

Company background 
Gas  N’  Roses  was  established  in  1975  as  a  spin‐off  company  from  the  Delft  University  of  Technology.  At  this  time,  the 
Dutch  government  was  looking  for  ways  to  become  less  dependent  on  oil  from  the  middle  east  and  in  particular  from 
OPEC after the first oil crisis of 1973. Gas N’ Roses received funding from the government for her first project, which was 
in cooperation with the Norwegian government, and successfully finished it in 1977. For Gas N’ Roses the project mainly 
involved  offshore  engineering  consult  with  respect  to  the  development  of  an  oilfield  in  the  North  Sea.  Gaining  more 
experience in following years after the energy crisis of 1979, Gas N’ Roses was later involved in projects in the Middle East 
and in the West Coast of Africa. The number of employees grew rapidly from 20 to 150 in a decade. By finding a good 
balance by recruiting experienced engineers as well as young, talented, innovative graduates, Gas N’ Roses was able to 
diversify  and  become  more  familiar  with  new  technologies  such  as  FPSOs  and  semisubmersibles.  With  gas  becoming 
increasingly profitable the company diverted its attention not only to oil field development, but also to the development 
of gas fields. 

Vision 
As the oil and gas industries are more and more of a controversial issue nowadays, Gas N’ Roses is very keen on protecting 
the  environment  but  also  on  providing  infrastructure  and  work  in  countries  where  the  project  is.  To  protect  the 
environment, not only will Gas N’ Roses find a way of installation with a minimal impact on the environment, also Gas N’ 
Roses  will  provide  a  strategy  for  decommissioning,  so  that  after  development  the  field  can  be  returned  as  ‘virginal’  as 
possible.  The  hiring  of  local  people  for  less  specialized  jobs  is  something  we  urge  our  clients  to  do,  in  order  for  these 
people to contribute to their society, as well as for the country to develop as a nation as a whole. 
 
To minimize hazards, a thorough risk analysis is made before the start of each project. In this analysis, technical risks, but 
also economic and political risks are assessed in order to provide the client with fair and truthful information on forehand. 
Gas  N’  Roses  is  in  particular  very  clear  about  possible  human  casualties:  we  cannot  accept  them.  By  selecting 
subcontractors  with  a  background  of  few  incidents,  we  are  proud  to  say  that  so  far  no  human  casualties  have  been 
reported in any of our projects. 

 The Team 
The team for this project is carefully selected from our available workforce. As a rule of thumb, Gas N’ Roses includes a 
senior engineer that has sufficient experience in all fields. The senior engineer for this project will be Payman Veisi Zadeh. 
His responsibilities within the team are such as the installation, decommissioning, the transport and the risk analysis. As 
mister Veisi Zadeh’s background lays in Iran and is familiar with this part of the world, he was selected for this project. 

Name  Function  Responsibilities 


Stefi Hooft van  Team leader and 
Huysduynen  reservoir engineer  Soil data, drilling, reservoir, time management 
Payman Veisi Zadeh  Senior engineer  Installation, decommissioning, transport, risk analysis 
Menno de Nooij  Mechanical engineer  Costs of project, pipelines, subsea 
Niels Viezee  Process engineer  Gas quality at surface, gas quality onshore, equipment 
Stef Vlaanderen  Offshore engineer  Structure, metocean, HSSE, contracting/political 


Zubara Gas Field Development Plan, Concession 2  May 2009
           

Part A: General Information and Three Possible Scenarios 


Zubara Gas Field Development Plan, Concession 2  May 2009
           

1. Problem Definition 

1.1. General Field Information 
The Zubara Field is a part of North Dome South Pars gas field, which is the 
biggest  known  gas  field  in  the  world.  It  is  located  offshore  northeast  of 
Qatar  and  partly  in  Iranian  territorial  waters,  see  Figure  1.1.  Besides  gas, 
the field also contains oil reservoirs near the border with Iran.  
Concession 
Concession 2 is located 65 km from shore and its  area is 36000 x 36000 ft 
which is ~29750 acre. The GIIP and CIIP of concession 2 can be found below 
in Table 1.1. 85 % of these are recoverable. For a calculation of these values, 
one is referred Appendix I.

Figure 1.1: Zubara Field and Concession 2 
Table 1.1: GIIP & CIIP 
Low Mid High
GIIP [Tscf] 7.38 14.48 24.27
CIIP [MMbbls] 590.50 1158.59 1941.41

Recoverable gas [Tscf] 6.27 12.31 20.63


Recoverable condensate [MMbbls] 501.93 984.80 1,650.20

1.2. Boundary Conditions 
This  project  consists  of  lots  of  aspects  which  can  all  be  worked  out  very  detailed.  Of  course  Gas  N’  Roses  cannot  be 
responsible for all phases of the field development. That is why some boundaries are stated: 
• The project contains all equipment the gas passes from the moment it is extracted out of the reservoir until it 
reaches the shore. This means onshore pipelines to the LNG and/or GTL plants are not a part of the project. 
• Also the export of the LNG/GTL from the plants to other countries will not be a part of this project. The thing we 
will provide is a number of countries where it can be transported to.  
• The commercialization is based on the Tax‐Royalty Contract. 
• Every solution provided by Gas N’ Roses does fit in Shell’s Business Principle. 
• Qatar has signed the Kyoto protocol and that is the reason why, in this project, CO2 emission will be minimized. 

1.3. Stakeholders 
During the field life many stakeholders, like governments, oil/gas companies and locals will be involved in this project and 
have to be well‐informed during all processes and perhaps brought together. Without the necessary permissions, great 
knowledge and experience of these stakeholders, this field cannot be developed. 
Below  in  Figure  1.2  and  Figure  1.3,  two  stakeholder  maps  are  shown:  an  interest  versus  influence  map  and  a  support 
versus influence map. 
    • Iran Government  • QP 
High  • Competitors  • NGOs 
• Subcontractors  • Shareholders 
• Employees  • Fishermen  • LNG consumer 
Interest 

Medium  • Local  • Pearl divers  • GTL consumer 


contractors   
  • Surrounding   
Low  countries 

 
Low  Medium  High 
 
Influence
Figure 1.2: Stakeholders Mapping: Interest versus Influence 


Zubara Gas Field Development Plan, Concession 2  May 2009
           
    • Subcontractors  • QP 
High  • NGOs 
• Shareholders 
Support 

• Employees  • Iran Government  • LNG consumer


Medium  • Local  • Competitors  • GTL consumer 
contractors   
  • Surrounding countries   
Low  • Fishermen 
• Pearl divers 
 
Low  Medium  High 

Influence

Figure 1.3: Stakeholders Mapping: Support versus Influence 

1.4. General Risk Analysis 
Before the development of possible scenarios commences, a global risk analysis is performed to investigate what aspects 
will mainly influence the development of the field. This global risks analysis contains a TECOP Risk Identification, Table 1.2, 
and an HSSE Study, Table 1.3. 
 
TECOP Risk identification 
For all Technical, Economical, Commercial, Organizational and Political aspects, risks are assigned.  
 
Table 1.2: General TECOP Risk Identification 
Technical  Economic  Commercial  Organizational  Politic 
Flow Assurance  Increase CAPEX  Problem on gas sale  Project manager  War in Middle East 
agreements, e.g. change in 
gas price 
Sinkholes  Increase OPEX  Main contract termination   International employees  Russia‐Iran‐Qatar gas 
cooperation 
Gas migration  Gas price changes  Change in contract with  Work done in different  Iran‐Qatar Government 
subcontractors  location  relations 
Subsea processing  Oil price changes  Gas demand  Operation by local people  Religious people (Muslims) 
Gas composition  Shareholders  Local regulation in  IMR locally  Terrorism attack 
contracts 
High content of H2S  Lack of budget        
Pressure drop in reservoir  World economic crisis       
Technical problem on GTL         
plant and/or LNG plant 
 
HSSE Study 
Of course not all risks can be grouped under technical, economical, commercial, organizational or political risks. Offshore, 
the most important issue is of course safety and that is the reason why an HSSE study is done before the development of 
scenarios. In this HSSE study most of the risks concerning Health, Safety, Sustainability and the Environment are assessed. 
 
Table 1.3: General HSSE Study 
Health  Safety  Sustainability  Environment 
Exposure to gasses  Fire  Degradation  of  structure  and  Leak (pipeline, process plant) 
equipment 
Falling from heights  Explosion  CO2  emission  during  transport  Destruction of sea life 
and fabrication 
Electric shocks  Accidents due to weather     
Falling into the sea  Falling objects     
  Training not sufficient     
  Failure of emergency equipment     
Using these two risks analyses, it is clear where the focus has to lay during the development of scenarios.  
When, at the end of this phase, the choice has to be made which scenario will be the final scenario, a much more detailed 
risk analysis will be performed. In this risk analysis, an HSSE Study will be done for all three possible scenarios. Based on 
these risk analyses and a cost calculation, the final scenario will be chosen. 

10 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
1.5. Gas Characteristics and Metocean Data  
1.5.1. Gas Composition 
The gas in the Zubara Field has a gravity of 0.81 relative to air and consists of the following components: 
 
Table 1.4: Gas Composition Zubara Field 
Component  Chemical Name  Percentage [%] 
Methane  CH4  77 
Ethane  C2H6  6.5 
Propane  C3H8  3 
Carbon Dioxide  CO2  1 
Hydrogen Sulphide  H2S  2.5  
Total  90 
 
The value of H2S in the reservoir differs between 1 and 5 %. The other 7.5 – 11.5 % of the gas consists of butane, pentane, 
etcetera and form the condensate part of the wet gas. When the gas composition of the Zubara Field is compared to a 
typical natural gas, it is clear that the H2S percentage of the Zubara Field is quite high. 
Because of the amount of H2S is high in the wet gas, the probability of sour corrosion is very high. Also because of the 
toxicity of H2S and the lack of heating value of CO2 natural gas being prepared for sales is required to contain no more 
than 5 ppm H2S and to have a heating value of no less than 920 to 980 Btu/scf. This means action has to be undertaken to 
prevent  corrosion  caused  by  the  H2S.  Using  a  pipe  material  that  doesn’t  corrode,  means  a  very  expensive  material  will 
have  to  be  used  to  prevent  corrosion.  This  means  the  total  costs  of  all  the  pipelines  will  become  unnecessarily  high. 
Corrosion allowance is also not an option for this gas composition, because the amount of corrosion will be too high to 
allow it because the pipeline will damage too much. There are already sulfur units in both the GTL and LNG plants present 
in  Qatar.  So  desulfurization  offshore  will  not  be  necessary  because  it  can  be  done  onshore  and  it  is  a  very  expensive 
procedure to perform offshore. Therefore, chemical injection is the solution for the high amount of H2S in all scenarios. To 
determine  the  amount  of  chemical  inhibitors,  a  sample  of  the  gas  is  taken  continuously  to  check  what  the  current 
percentage of H2S is. This is done to reduce costs because the chemicals are inhibited continuously and too much chemical 
inhibitor is a waste of money and not environmental friendly. 

1.5.2. Gas Pressure 
The  initial  pressure  in  the  reservoir  is  around  6000  psi.  The  temperature  at  reservoir  depth  is  127  °C.  As  the  reservoir 
produces,  formation  temperature  does  not  change,  but  pressure  decreases.  This  pressure  drop  will  decrease  the 
production because pressure and production are directly linked.  
When the production starts, the hydrocarbons that exist in pressurized formations will naturally rise up through the well 
to the surface. This is most commonly the case with natural gas. Since natural gas is lighter than air, once a conduit to the 
surface  is  opened,  the  pressurized  gas  will  rise  to  the  surface  with  little  or  no  interference.  This  is  most  common  for 
formations  containing  natural  gas  alone,  or  with  a  light  condensate.  In  these  scenarios,  once  the  christmas  tree  is 
installed,  the  natural  gas  will  flow  to  the  surface  on  its  own.  This  means  probably  no  water‐  or  gas‐injection  will  be 
necessary to keep the pressure high enough to prevent the gas from flowing out of the wells. 
 
Condensate blockage 
The largest pressure drops occur near producing wells. When the pressure in a gas‐condensate reservoir decreases to a 
certain point, called the saturation pressure or dewpoint, a liquid phase 
rich  in  heavy  ends  drops  out  of  solution;  the  gas  phase  is  slightly 
depleted of heavy ends. A continued decrease in pressure increases the 
volume of the liquid phase up to a maximum amount; liquid volume then 
decreases.  This  behavior  can  be  displayed  in  a  pressure‐volume‐
temperature (PVT) diagram. 
Once  the  bottomhole  pressure  drops  below  the  dewpoint,  a  near‐well 
pressure  sink  forms  around  the  well.  As  gas  is  drawn  into  the  pressure 
sink,  liquid  drops  out.  After  a  brief  transient  period,  enough  liquid 
  accumulates  that  its  mobility  becomes  significant.  The  gas  and  liquid 
Figure 1.4: Phase Diagram Gas‐Condensate System  compete  for  flow  paths.  Condensate  blockage  is  a  result  of  the 

11 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
decreased gas mobility around a producing well below the dewpoint. Reservoir pressure dropping below the dewpoint has 
two main results: gas and condensate production decrease because of near‐well blockage, and the produced gas contains 
fewer valuable heavy ends because of dropout throughout the reservoir, where the condensate has insufficient mobility 
to flow towards the well.  
 
Solutions 
Hydraulic fracturing is the most common mitigation technology. This technique increases the effective contact area with a 
formation.  Production  can  be  improved  with  less  drawdown  in  the  formation.  However,  hydraulic  fracturing  does  not 
generate a conduit past a condensate saturation buildup area, at least not for long. Horizontal or inclined wells are also 
being  used  to  increase  contact  area  within  formations.  The  condensate  still  builds  up  around  these  longer  wells,  but  it 
takes  a  longer  time.  The  productivity  of  the  wells  remains  high  longer,  but  the  benefit  must  be  weighed  against  the 
increased well cost. Dry gas and solvent injections are able to mobilize some condensate, but the liquid saturation profile 
near a producing well reforms and the blockage effect returns. 
 
To prevent the production from becoming too low due to the decreasing pressure and due to condensate blocking, the 
reservoir pressure should not drop below a value of 4500 psi. This will be achieved by gas‐ or water‐injection later in the 
field life of the reservoir. To prevent condensate blocking, all three options mentioned above are kept in mind.  

1.5.3. Waves, Wind and Earthquakes 
Wave conditions 
Table 1.5: Wave Conditions Concession 2  For  maximum  load  calculations  on  a  fixed  or  floating  structure, 
extreme conditions must be taken into account. As can be seen 
  Unit  Value 
in  Table  1.5,  the  wave  conditions  are  not very  extreme and  will 
Water depth  [m]  250 
not cause many problems. 
Significant wave height  [m]  5.8 
 
Zero‐crossing wave period  [s]  11  Wind conditions 
Steady  current  speed  at  [m/s]  1.15  The  10  minute  wind  speed  is  26.2  m/s,  which  is  also  not  a 
mid depth  significant value. In the Zubara Field, shamals occur quite often. 
Storm surge  [m]  0.38  A shamal is a summer northwesterly wind blowing over Iraq and 
the Persian Gulf states, often strong during the day, but decreasing at night. This weather effect occurs anywhere from 
once to several times a year. The resulting wind typically creates large sandstorms. Shamals  normally last three to five 
days.  Since  the  resultant  dust  and  sandstorm  is  several  thousand  feet  deep,  travelling  by  air  and  ground  comes  to  a 
standstill. When they spread to nearby bodies of water, fishing and shipping becomes difficult. During these wind events, 
several Southwest Asia international airports have recorded winds as high as 49km/hour which can drive dust over large 
distances downwind. Shamals can have quite some impact on a floating platform. An unmanned jacket or subsea system 
will not be severely disrupted. 
 
Earthquakes 
For  extreme  load  calculations  it  is  also  important  to  know  that  the  seismic  activity  is  substantial  at  this  location.  The 
Persian Gulf is a marginal sea located next to the southern flanks of the Zagros Mountains between the Persian Plateau 
and Arabian Plate. Natural seismic activity around northern parts of the Persian Gulf is sometimes associated with great 
and  devastating  earthquakes.  These  earthquakes  seem  to  be  caused  by  the  convergent  movement  between  Arabia‐ 
Eurasia. The southern parts and the Persian Gulf itself are considered to be seismically quiet. Normally, one earthquake 
per 20 years occurs in this region, with a maximum magnitude of 6.5 on Richter scale. From historical data tsunami danger 
is limited. 

12 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

2. Development of Scenarios 
To determine what the best method is to develop concession 2 of the Zubara Field, the Kite‐
Orientation 
Model,  as  shown  in  Figure  2.1,  will  be  used.  This  means  that  first  several  scenarios  are 
composed  out  of  a  limited  number  of  building  blocks.  Then  all  scenarios  are  rated  using 
criteria and weighting factors. The best three scenarios are selected and further developed. 
Many scenarios  Before  several  scenarios  can  be  made,  it  is  necessary  that  the  criteria  have  been  identified. 
These criteria will be selected according to the vision of Gas N’ Roses and keeping in mind the 
values of Shell. Because these criteria are not all equally important, a weighting factor will be 
Three    scenarios  given to each criterion. What these criteria are will be discussed later in this chapter. 
 
After the selection of the criteria is done, an identification of the building blocks will be made. 
A  combination  of  these  building  blocks  will  make  up  the  whole  development  plan  of  one 
       FPDD  scenario to develop concession 2 of the Zubara Field. The building blocks will together form a 
possible field layout, from the extraction of gas, up to the moment the gas enters the facility 
 
Figure 2.1: Kite‐Model  onshore. By grading the scenarios and multiplying them by their weight factors, a ranking will 
be made between the scenarios.  

2.1. Criteria and Weighting Factors 
In order to make a selection of which scenarios are most feasible, three main criteria are selected. As a company that likes 
to profile itself as one that pursues sustainability and safety, HSSE is regarded as a very important criterion. The second 
main criterion is Economics. And the third criterion is Execution and contracting.  
 
These  three  main  criteria  are  subdivided  into  other  sub  criteria.  By  giving  the  main  criteria  a  weighting  factor,  with  a 
maximum of 18 points, an opinion of which criterion is most important can be made. The weighting factors of the main 
criteria  are  divided  over  the  sub  criteria.  For  each  scenario  a  grade  between  1  and  5  is  given  to  each  sub  criteria.  By 
grading each scenario by criteria, a final feasibility ranking of the scenarios can be made. 
The selection of these criteria and sub criteria, and their weighting factors is based on the experience of Gas N’ Roses. The 
top six scenarios will be considered as possible options for development of the field.  
 
The criteria matrix including the weights is shown in Table 2.2. Later on the criteria are explained. 
 
As  one  can  see,  CAPEX  and  OPEX  are  the  two  most  important  criteria  for  choosing  the  best  scenarios.  This  is  the  case 
because the whole project won’t be performed if it is not profitable, which completely depends on the CAPEX and OPEX.  
Gas N’ Roses believes HSSE and keeping all risks as low as practical (ALARP) are equally and extremely important. With a 
maximum of 18 point per main criterion, human safety, operation and environment are all graded six points. 
Execution and contracting is of course a main criterion, but not as important as economics and HSSE & risks. The way the 
project  will  be  installed  and decommissioned  is  very  important  for  Gas  N’  Roses  because  it  is  one  of  our  main  goals  to 
keep  the  environment the  same  after  the project  as  it  was  before  the development  of  the field  started.   Maintenance, 
supply and fabrication are considered less important than all other sub criteria. 

13 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

2.2. Building Blocks 
In order to create scenarios, five main building blocks are selected. These building blocks will be sufficient to create a field 
layout without going too much into detail yet. Other building blocks include risers, umbilicals, L.Q.’s and such but are not 
essential in creating a scenario. A brief introduction on the different building blocks is given below. More information and 
details can be found in Appendix II Building Blocks.  
 

  
Figure 2.2: Structure Options 
 
• Structure 
To keep open all scenario options, all possible structures have been considered, an artist impression of possible 
structure solutions is shown in Figure 2.2. These are the available structures to choose from. Also a combination 
of these structures is possible, something that has been proven to work in the past. 
• Process/topside 
The process of the gas, condensate and water mixture can be done onshore, offshore, subsea or a combination of 
these locations. These processes include mostly phase separation, pressure control and gas treatment in order to 
make a pipelineable product. The types of processes required together with the maximum production rate will 
influence the size of the deck/topside. 
• Subsea equipment  
To get the gas and condensates out of the reservoir, of course well casing and trees are necessary. How the wells 
are arranged can be done in several ways: wells connected to the platform individually, in clusters or in templates. 
• Drilling 
Drilling can be done in different ways depending on the subsea arrangement and the kind of structure. Methods 
considered are vertical, deviated and horizontal drilling. For each of these methods it is extremely important to 
know  where  exactly the  gas is  trapped.  This  can  be  estimated by  looking  at  the  bathymetry, fault  lines  and by 
surveying techniques.  
• Gas transportation 
For the transportation of the gas or gas/condensate mixture there are two ways of doing this: single phase flow 
or multiphase flow 

14 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

2.3. Multi Criteria Analysis 
After  making  the  selection  of  these  main  building  blocks  and  their  subdivisions,  13  scenarios  are  sketched  by  selecting 
compatible options from each main building block, see Table 2.1 below. These 13 scenarios are composed based on the 
knowledge and experience of Gas N’ Roses and are the result of a thorough brainstorming session. 
 
Table 2.1: All 13 Scenarios and their Building Blocks 
Structure Process Subsea Drilling GT

Template Manifold
Subsea equipment
Semi‐submersible
Compliant Tower

Cluster Manifold

Single phase
Multiphase
Horizontal
Individual

Deviated
Offshore
Onshore

Vertical
Subsea
Jacket

None
FPSO

Both
Spar
GBS

TLP

1
2
3
4
5 3X
6
7
8
9
10
11
12
13
 
After grading each sub criterion, the criteria matrix can be substituted, resulting in Table 2.2. The column ‘weighted sum’ 
is the multiplication of the grades for all criteria with their weighting factor, and results in the graph next to the table. 
 
Table 2.2: Grading of the Scenarios 
Economics HSSE & Risk Execution and contracting
Supply/Fabrication
Decommissioning

Weighted Sum 
Human safety

Maintenance
Environment

Installation
Operation
Scenario

CAPEX

OPEX

FdtG

0 50 100 150 200

1 5 4 2 2 1 4 3 3 4 5 155 1
2 5 3 4 2 2 3 2 2 3 3 142 2
3 1 4 4 4 2 1 1 2 2 1 110 3
4 2 4 4 4 2 2 2 2 2 2 130 4
5 4 4 2 4 1 2 2 1 3 4 133 5
6 5 4 2 2 1 2 3 1 4 3 133 6
7 5 4 2 2 2 4 2 3 4 4 154 7
8 3 4 5 2 2 2 2 2 3 3 133 8
9 1 4 4 3 3 4 3 4 3 2 148 9
10 1 4 1 3 1 4 3 4 2 1 120 10
11 1 5 4 2 3 2 1 4 2 2 125 11
12 3 5 3 2 2 4 3 4 2 2 151 12
13 2 3 5 5 5 4 1 5 3 3 171 13
Weighting factor 7 7 4 6 6 6 4 4 2 2
18 18 12

15 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Of course, also a sensitivity analysis on the weighting factors is performed, using the five different factor combinations as 
shown in Table 2.3. This results in Figure 2.3. As can be seen, the same scenarios are the best options. 
 
Table 2.3: Different Weighting Factors Combinations 
Total Total
Economics HSSE & Risk Execution and contracting weight  score rate

Supply/Fabrication
Decommissioning
Weight factor 

Human safety
combinations

Maintenance
Environment

Installation
Operation
CAPEX

OPEX

FdtG

Combination1 7 7 4 6 6 6 4 4 2 2 48 240 2.4


Combination2 7 7 4 7 7 7 4 4 4 4 55 275 2.75
Combination3 7 7 4 5 5 5 3 3 3 3 45 225 2.25
Combination4 7 7 5 6 6 6 3 3 3 3 49 245 2.45
Combination5 7 7 5 7 7 7 3 2 2 3 50 250 2.5

Sensitivity Analysis on Weight Factors

80
70 combination 1
60 combination 2
50
40 combination 3
30
20 combination 4
10 combination 5
0
Scenario

Scenario

Scenario

Scenario

Scenario

Scenario

Scenario

Scenario

Scenario

Scenario

Scenario

Scenario

Scenario
10

11

12

13
1

Figure 2.3: Result of Sensitivity Analysis 

2.4. Selected Three Scenarios 
The six best scenarios, scenario 1, 2, 7, 9, 12 and 13, were evaluated and most of them have very many similarities. That is 
why some scenarios were combined and eventually three final scenarios were selected: 
 
1. Jacket  scenario:  In  this  scenario,  a  jacket  will  be  used.  This  jacket  consists  of  a  process  plant  and  the  gas  is 
separated offshore from its condensates. There is no subsea equipment and the gas is transported to shore using 
two single‐phase pipelines. The platform could be unmanned.  
2. Semi submersible scenario: Now not a fixed structure, but a semisubmersible will produce the gas. As in scenario 
1, the gas is treated offshore and also transported in two single‐phase pipelines. Now there is subsea equipment, 
namely clustered wells around manifolds. 
3. Subsea scenario: This is the most innovative solution: everything is subsea. The gas is not separated offshore and 
transported to shore using one multiphase pipeline.  
The  scenarios  will  become  clearer  when  the  field  lay‐out  plan  is  discussed.  In  the  next  chapters  the  scenarios  will  be 
explained  into  more  detail  and  the  remaining  building  blocks  will  be  addressed.  When  this  is  done,  a  full  financial  and 
HSSE  analysis  will  be  made,  based  on  the  values  and  visions  of  Gas  N’  Roses,  for  each  scenario.  These  analyses  will  be 
compared so that advantages and disadvantages will become apparent.  

16 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

3. Scenarios 
3.1. Scenario 1 
3.1.1. General Layout 
In this scenario, a jacket will be used. Because the jacket has no heave motions, rigid risers and dry trees are used. This 
means no subsea arrangement is necessary.   
Figure  3.1  below  shows  a  side  view  and  a  top  view  of  this  scenario.  The  jacket  is  unmanned  and  that  is  why  all  IMR 
operations are performed by a subcontractor. 
 
Jacket 

Risers 

820
Export 
Pipelines 
 
 

7800 
Sinkhole 

800
Jacket 
CO2‐Injector 

1400 
 
     
Figure 3.1: Side View Structure and Top View Scenario 1  Figure 3.2: Cross Section Reservoir and Jacket with dimensions [ft] 

3.1.2. Wells and Subsea Arrangement 
Well plan 
In this scenario there is no subsea equipment like manifolds and templates. This means all wells will have to be drilled 
below the jacket. To get as much gas as possible out of the 
reservoir, several horizontal wells and only one vertical well will 
be drilled. The differences between vertical, deviated and 
horizontal wells are shown in Figure 3.3. 
A cross section of the reservoir, showing the wells, is given in 
Figure 3.2. The green well is the CO2‐injector. 
The maximum daily production is 1500 MMscf/day. The number 
of wells is based on this plateau production. For the calculation 
of the production per day and of the production of each type of 
well, one is referred to Appendix III. 
• Vertical well: A vertical well produces 85 MMcft/day.  
• Horizontal wells: The total production of all horizontal 
wells  is  1500  –  85  =  1415  MMscf/day.  The  production  Figure 3.3: Vertical, Deviated and Horizontal Wells 
per horizontal well is 153 MMscf/day. So the total number of horizontal wells necessary is 1415 / 153 = 10. 

17 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Drilling Schedule and Field Life 
All wells will be pre‐drilled using a drilling semisubmersible. When it is possible to keep a plateau production of nine years, 
a field life as shown in Figure 3.4 will be applicable to this scenario. Due to the pressure drop, the production will decline 
after the plateau period. Using CO2‐injection, the pressure will not drop too much and the production rate will always be 
above 10 % of the plateau production. 

Production Scenario 1
1600
Production [MMscf/day]

1400
1200
1000
800
600
400
200
0
0 2 3 5 7 8 10 12 13 15 17 18 20 22 23 25 27 28 30 32 33 35 37 38 40 42 43 45
Time [years]

Figure 3.4: Field Life Scenario 1 
 
As one can see in the graph in above, the total field life using scenario 1 will be 45 years. The area below this graph is 
equal to 85 % of the GIIP.  

3.1.3. Topside 
Gas N’ Roses will not install a drilling unit on this topside. 
Pre‐drilling has the advantage of earlier first gas. It should 
also  be  mentioned  that  a  drilling  derrick  is  a  relative 
expensive CAPEX, as it will not be used all the time.   Structure piles
 
Unmanned topside 
In this case, an unmanned production platform is chosen.  Risers, injection and 
product pipeline 
This reduces the chance of human harm on the platform. 
An unmanned platform does not have to stop production  Flare 
during  a  Shamal.  Because  no  people  are  needed  on  Storage 
the  platform,  the  needed  number  of  employees  is  low. 
Inhibitor 
This  has  its  advantages,  because  the  living  situation  for  Compressors 
employees in Ras Laffan is below standards. 
 It  is  proven  in  the  region  that  an  unmanned  platform  is  Life boats 
and rescue 
possible. 
Dehydration and 
40 m cleaning installation 
3.1.4. Structure 
The  weight  of  the  topside  will  be  around  9,000  mt.  To  L.Q. and 
estimate  the  further  dimensions  of  the  jacket  structure  Controls
assumptions  are  made  based  on  experience.  For  a  Separation 
calculation, one is referred to Appendix IV.  40 m installation
Because of the water depth, skirt piles will be used. Each     

of the legs will have 3 foundation piles, so for the whole  Figure 3.5: Side View and Top View Topside Jacket 
structure  12  foundation  piles  are  necessary.  Also  mud 
pads will be needed. The estimated diameter for the legs of the structure will be 3 meters. The total weight of the jacket 
will be 14,000 t. In the table below, Table 3.1, can be seen how the minimum height of the jacket structure is determined. 

18 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
The total height of the structure can also be seen in the adjoining picture. Lowest astronomical tide (LAT) is taken as 250 
m.  This  figure  also  shows  the  dimensions  at  the  bottom  of  the  structure.  The  size  of  the  structure  at  the  top  will  be 
30x30m. This will be enough to support the topside, which is estimated at dimensions of 50 x 50m.   
Air Gap [m]           1.50
Wave Crest [m]           2.90
Storm Surge [m]           0.38
Tide [m]           4.00

Total Deck Elevation Above LAT [m]            8.78


LAT [m]      250.00

Total Height Structure [m]        258.78


  Table 3.1: Minimum Deck Elevation 
Figure 3.6: Jacket Structure 
Dimensions 

3.1.5. Costs 
The CAPEX and OPEX for this scenario have been calculated using QUE$TOR. Some additional costs have been estimated 
and  manually  added,  such  as  onshore  expenditures,  as  they  are  not  featured  in  QUE$TOR.  When  the  scenarios  are 
compared, more financial information about the scenario will be given. 
CAPEX (Billion $) OPEX (Billion$) DRILLEX (Billion$) Decommissioning costs (Billion$)
Scenario 1 1.53 5.02 1.19 0.50

3.1.6. HSSE Study 
The hazard identification for this scenario is based on different areas/subjects such as the process plant, power generation, 
drilling, reservoir, L.Q.’s and geohazards. The hazard identification, HAZID, is classified and expressed in Appendix VI.A. 
Based  on  the  hazard  identification  table  and  probability  of  occurrence,  an  ALARP  table,  Table  3.2  for  this  scenario  is 
developed.  
 
Table 3.2: ALARP Table Scenario 1 
ALARP, As Low As Reasonably Practical, Scenario 1

● Condensate leakage ● Dropped object
● Gas leakage in process plant
Frequent

● Loss of electrical power ● Fire in power generation unit

● Gas leakage in power generation  ● Coral damage
Unfrequent ● Gas migration

● Flow assurance

● Corrosion due to H2S ● Gas leakage from risers ● Fire in process plant ● Politic issues

● Change in gas composition ● Sink hole ● Structure Failure ● Blow out


Unlikely ● Collapse of well ● Fatigue

● Deviation on Drilling ● Flare Failure ● Fault and Fractures ● Explosion in process plant

● Shallow water flow (SWF) ● Helicopter crash ● Landslide ● Terrorist Attack


Remote ● Active Faulting

Insignificant Minor Major Catastrophic


CONSEQUENCE
Intolerable Area

ALARP Area

Negligible Area
 

19 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
3.2. Scenario 2 
3.2.1. General Layout 
Scenario 2 consists of a semisubmersible without drilling equipment. To reach the wells with a Floating Drilling Unit (FDU) 
without moving the semisubmersible, the wells are arranged in clusters. The centers of these clusters are the manifolds 
that gather the production. This production is transported to the semisubmersible using flexible risers. At the semi, the 
production is separated into a gas and a condensate part.  An overview of scenario 2 is shown below in Figure 3.7. 
 
Semisubmersible   
Mooring Lines 

820 
Riser 

 
 

7800 
800
 
Sinkhole 

1400 
Semisubmersible 
Manifold 
Production Well  Figure  3.8:  Cross  Section  Reservoir  Scenario  2, 
Dimensions in Feet. 
CO2‐Injector 
Figure 3.7: Side View Structure and Top View Subsea Arrangement Scenario 2 

3.2.2. Wells and Subsea Arrangement 
The semisubmersible has no drilling equipment so all wells will have to be drilled using an FDU. When an MRI operation 
has to be performed on the wells, an FDU will have to be used to reach the well and do the workover actions. This means 
the semi cannot be located above a manifold because then the drilling unit cannot reach the wells. All wells will be vertical 
wells and arranged in clusters. 
 
Well Plan 
Because of the wells not having to be underneath the structure and the option to bundle the flows of the wells subsea, 
only vertical wells will be used in this scenario. Another reason to use only vertical wells is that the wells are located quite 
far apart from each other. This means the wells will not produce the gas in the production area of another well and each 
well will produce the maximum amount of gas.  
The  wells  are  arranged  in  clusters.  The  general  function  of  the  manifolds  is  to  gather  and  distribute  the  production 
through  an  arrangement  of  piping  and  valves.  The  wells  are  positioned  at  places  where  the  reservoir  is  closest  to  the 
seabed, so where the location of the gas is the least deep. The CO2‐injection wells will be drilled at the lowest locations of 
the reservoir because otherwise the gas that is still in the reservoir will get trapped. Figure 3.7 shows the arrangement of 
the  wells  and  manifolds  and  Figure  3.8  gives  a  cross‐section  of  the  reservoir  and  the  semisubmersible.  The  maximum 
production of a vertical well in this field is 85 MMscf/day. With a plateau production of 1500 MMscf/day, 1500 / 85 = 17 
wells are necessary.  

20 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
3.2.3. Drilling Schedule and Field Life 
This subsea arrangement of this scenario consists of four manifolds and 17 satellite, vertical wells. 
 
A semisubmersible has too many and heavy motions for using dry trees. This means flexible risers and subsea trees will 
have to be installed. There are two types of trees: Horizontal and conventional trees. Horizontal trees will be used in this 
scenario because these trees have all their valves and chokes outside of the tree which leads to easier IMR actions. 
The  manifolds  will  contain  valves  and  chokes  to  control  the  production  flows  from  the  wells.  Besides  the  chokes  and 
valves,  the  manifolds  also  consist  of  control  modules  to  control  the  chokes  and  valves  and  of  instrumentation.  The 
instrumentation is for the pressure, temperature and H2S readings on the commingled production. The information about 
the  H2S  content  will  be  used  to  determine  the  amount  of  chemicals  that  will  have  to  be  injected  into  the  wells.  The 
chemicals will be injected where the flows of the satellite wells commingle at the manifold. This means an umbilical has to 
connect the semisubmersible with the manifold that provides the control fluids and chemicals.  
 
Drilling one vertical well will take two months. So the total installation period will take 34 months. Figure 3.9 below shows 
the ideal production profile of this scenario 

Production [MMscf/day]
Production Scenario 2
1600
1400
1200
1000
800
600
400
200
0
0 2 3 5 7 8 10 12 13 15 17 18 20 22 23 25 27 28 30 32 33 35 37 38 40 42 43 45
Time [years]

Figure 3.9: Field Life Scenario 2 

3.2.4. Topside 
For scenario 2 a semisubmersible is used to create a floating production platform. The assumed weight of the topside for 
his semisubmersible is around 15.000 mt. The size of the deck is approximately 70 x 90 m. This should be enough room for 
all the equipment and to let the floaters be large enough to carry the load.  The two figures below, Figure 3.10 and Figure 
3.11 show a top and side view of the topside. 
Flare boom  
 
Living Quarters   
and Controls   
 
  Inhibitor injection
 
  Compressors 
 
  Life boats
Floater    
  Dehydration and 
  cleaning installation
 
Condensate and gas    Separation 
flowlines     installation 
 
Risers, injection  pipeline   
and umbilicals    
  Figure 3.11: Top View Topside Semisubmersible 
Figure 3.10: Side View Topside Semisubmersible 

21 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Accommodation  
This unit is also very well engineered to make this facility as safe as possible during emergency situations. For example at 
the vicinity of this unit, several equipment, like life boats and the helicopter deck, are located which will be necessary to 
leave the platform safely. Fire and blast protection is needed to protect the people and other equipment. Also, the L.Q. 
should contain HVAC (heating, ventilation and air condition). It would be wise to place a blast wall in front of the L.Q. to 
minimize potential injuries or even casualties. 

3.2.5. Structure 
To determine the dimensions, estimations are done. These estimations are done based on a semisubmersible with two 
floaters  and  six  columns.  An  impression  of  how  the  semisubmersible  could  look  like  is  given  in  Figure  3.12  and  the 
dimensions are given in Table 3.3. 
 
 
Floaters Columns Deck
number 2 [‐] number  6 [‐] area 6300 [m2]
length 110 [m] height 20 [m] length 90 [m]
width 16 [m] length 10 [m] width 70 [m]
depth 8 [m] width 10 [m] depth 7 [m]  
 
Figure 3.12: Impression of the  Table 3.3: Dimensions of the Semisubmersible 
Semisubmersible (Atlantis Platform)    
The calculations are given in Appendix V and show that a semisubmersible with the given dimensions is sufficient for the 
dimensions of our topside.  

3.2.6. Costs 
CAPEX (Billion $) OPEX (Billion$) DRILLEX (Billion$) Decommissioning costs (Billion$)
Scenario 2 2.47 6.04 1.19 0.40

3.2.7. HSSE Study 
As with scenario 1, the HAZID table is shown in Appendix VI.B. The ALARP table is shown in Table 3.4 below: 
Table 3.4: ALARP Table Scenario 2 
ALARP, As Low As Reasonably Practical, Scenario 2

● Condensate leakage ● Dropped object
● Gas leakage in process plant
Frequent

● Loss of electrical power ● Fire in power generation unit

● Gas leakage in power generation  ● Coral damage
PROBABILITY

Unfrequent ● Gas migration

● Flow assurance

● Corrosion due to H2S ● Fire inside LQ ● Fire in process plant ● Politic issues

● Change in gas composition ● Sinkholes ● Fire and explosion around LQ ● Blow out


Unlikely ● Collapse of well ● Fatigue
● Gas leakage from risers ● Semi‐submersible instability

● Shallow water flow (SWF) ● Flare Failure ● Fault and Fractures ● Explosion in process plant

● Helicopter crash ● Landslide ● Blocked escape routes


Remote ● Loss of mooring line ● Active Faulting

● Terrorist Attack

Insignificant Minor Major Catastrophic


CONSEQUENCE
Intolerable Area

ALARP Area

Negligible Area

22 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

3.3. Scenario 3 
3.3.1. General Layout 
In scenario 3, all equipment is subsea, as can be seen in Figure 3.13. The only treatment done offshore is the injection of 
chemical  inhibitors  downhole.  The  fluids  and  gases  produced  are  immediately  transported  to  shore  without  treatment 
and separation. Because there is no separation of the flow subsea, the CO2 cannot be separated offshore and cannot be 
re‐injected. That is why in this scenario, water‐injection wells will be drilled in the future if the pressure drops too much.  
Because  of  the  field  not  having  a  floating  or  fixed 
support  structure,  the  wells  itself  should  be  very  well 
                              protected  against  dropped  objects  because  IMR 
 
operations are difficult to perform. This means the best 
option is a template subsea arrangement. 
To determine the size of the templates, the number of 
wells will have to be determined first.  
In  this  scenario,  only  deviated  wells  will  be  drilled. 
Compared  to  the  deviated  well  at  another  location  in 
the  field,  this  well  will  produce  120  MMscf  per  day.  
With  a  peak  production  of  1500  MMscf/day,  13 
deviated wells will be necessary.  
The  best  solution  is  to  build  four  templates  all 
containing  four  well  slots.  Because  the  wells  are  very 
  close  together  in  such  a  template,  placing  all  wells  in 
 
Production Well  one  our  two  templates  will  not  be  very  wise  because 
Test Well  the wells will produce from a relatively small area, even 
CO2‐Injector 
CO2  Separator 
though the wells are a bit curved and reach out of the 
  area  a  vertical  well  can  reach.  These  templates  will 
contain three or four production wells and one test well. 
  The  four  templates  are  located  at  the  highest  location 
Figure  3.13:    Side  View  Structure  and  Top  View  Subsea  Arrangement 
Scenario 3 
of  the  reservoir  as  can  be  seen  in  Figure  3.13.  On  the 
main pipeline, an umbilical is connected that carries the 
hydraulics  and  electrics  for  control  of  the  four  templates.  This  umbilical  also  transports  the  chemicals  for  the  chemical 
injection from shore to the subsea templates. 

3.3.2. Drilling Schedule and Field Life 
The drilling will be done by an FDU once the templates are installed. Drilling one deviated well will take three months per 
well. Drilling 13 deviated wells will take 39 months and the production profile as shown in Figure 3.14 will be applicable to 
scenario 3. 

Production [MMscf/day]
Production Scenario 3
1800
1600
1400
1200
1000
800
600
400
200
0
0 2 3 5 7 8 10 12 13 15 17 18 20 22 23 25 27 28 30 32 33 35 37 38 40 42 43 45
Time [years]
 
Figure 3.14: Field Life Scenario 3 

23 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
3.3.3. Multiphase Pipeline 
Evacuating the gas untreated, leads to quite some complications. 
There are some issues related to the design, installation, operation and 
maintenance  of  a  multiphase  pipeline  that  should  be  taken  into 
account.  Even  though  multiphase  flow  is  more  complex  than  single 
phase  flow,  there  are  several  reference  projects  where  multiphase 
pipeline are used, like in Ireland, Norway and also the Persian Gulf.  
Hydrate  formation  is  one  of  the  main  issues  regarding  to  the 
multiphase  flow  assurance.  According  to  Figure  3.15  the  risk  of 
hydrates  is  moderate.  This  could  be  more  important,  especially  in 
winter and during shut down or start up. Injection of chemical inhibitor, 
MEG, will be done continuously to prevent hydrate formation. A special 
shut  down  and  start  up  procedure  should  be  made  and  performed  Figure 3.15: Typical Hydrates Curve 
correctly to avoid this risk. These procedures change from time to time due to the variation of temperature, pressure, flow 
composition, etcetera. 
Table 3.5: Multiphase Pipeline Specifications 
Items  Unit  Value 
Corrosion is another important issue in this pipeline. Based on the gas 
Pipe diameter  inch  42  composition,  H2S  corrosion  can  be  a  major  problem  especially  when 
Pipe length  m  63000  the H2S content is up to 5%.  In this case, chemical inhibitor injector is 
Input pressure  Barg  125  the way that will protect the pipeline against corrosion.  
Output pressure  Barg  90  A slug catcher unit is needed for phase separation onshore. There is a 
Wall thickness  mm  20 
Flow rate, gas  MMscf/day  1650 
slug catcher unit in both the LNG and GTL plant and their capacities are 
enough  to  deliver  and  separate  the  Zubara  Field’s  gas  production.  
  Flow rate, Condensate  bbls/day  132000 
Therefore, there is no need to build a new slug catcher for this field. 
The multiphase pipeline calculations can be found in Appendix IX and its specifications are listed in Table 3.5 

3.3.4. Costs 
CAPEX (Billion $) OPEX (Billion$) DRILLEX (Billion$) Decommissioning costs (Billion$)
Scenario 3 2.05 6.09 1.07 0.30

3.3.5. HSSE Study 
As with the two previous scenarios, the ALARP, Table 3.6, and HAZID, Appendix VI.C, are given below. 
Table 3.6: ALARP Table Scenario 3 
ALARP, As Low As Reasonably Practical, Scenario 3

● Condensate leakage ● Gas leakage in process plant

Frequent

● Gas migration ● Coral damage ● Dropped object


● Flow assurance ● Fishery / pearl industry
PROBABILITY

Unfrequent

● Corrosion due to H2S ● Collapse of well ● Fatigue ● Politic issues


● Change in gas composition ● Sinkholes ● Loss of umbilical ● Blow out
Unlikely

● Shallow water flow (SWF) ● Fault and Fractures ● Active Faulting

● Landslide ● Terrorist Attack
Remote

Insignificant Minor Major Catastrophic


CONSEQUENCE
Intolerable Area

ALARP Area

Negligible Area
 

24 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
4. Cost Analysis 
4.1. Economical evaluation of three scenarios  
The following inputs based on calculations done by QUE$TOR are used for financial calculations, see Table 4.1.  
Table 4.1: Costs of the three scenarios 
CAPEX (Billion $) OPEX (Billion$) Drillex (Billion$) Decommissioning costs (Billion$) Total costs (Billion$) 1st day to gas
Scenario 1 1.53 5.02 1.19 0.50 8.24 5 years
Scenario 2 2.47 6.04 1.19 0.40 10.10 5 years
Scenario 3 2.05 6.09 1.07 0.30 9.51 5 years  
 
Using this input the cash flows are calculated and showed graphically in Figure 4.1. 
  The cash flows are based on a number of base 
Cash flows of 3 different scenarios variables.  A  base  discount  rate  of  12%  is 
Scenario 1 Scenario 2 Scenario 3
chosen. The profit of each scenario is the same 
for each as the production profiles have exactly 
5000
the same aspects: 10 years plateau production, 
4000
45  years  field  life  and  a  plateau  production  of 
3000 1,500  MMscf/day.  Also  the  same  gas  (4.5 
$/MMBTU) and condensate price (0.8 x 60$ per 
NPV (Million$)

2000

1000 barrel  =  $48  per  barrel)  has  been  applied  to 


0 each scenario.  
0 10 20 30 40 50 60
‐1000  
‐2000 Apart  from  the  yearly  cash  flows,  the  net 
‐3000 present  value  (NPV),  internal  rate  of  return 
Time (years) (IRR)  and  the  value  to  investment  ratio  (VIR) 
  can be calculated, listed in Table 4.2 below.  
Figure 4.1: Annual Cash Flows of Three Different  Scenarios 
 
Table 4.2: NPV, IRR and VIR of 3 Scenarios  The  differences  in  these  results  are  accounted  for  by 
NPV (Million$) IRR VIR the  difference  in  expenditures,  CAPEX  because  it 
Scenario 1 3,941 42% 1.95 influences  the  amount  of  invested  money  and  the 
Scenario 2 3,870 37% 1.46
effect  of  OPEX  depends  on  the  amount  and  which 
Scenario 3 3,935 38% 1.71
amount  is  spent  at  what  time.  Revenues  are  almost 
identical in each scenario and will therefore not influence the NPV, IRR and VIR much.  
The  first  scenario  scores  highest  in  each  category.  The  CAPEX  is  low,  mainly  due  to  the  fact  that  it  is  a  conservative 
development plan and therefore no expensive equipment is needed. The CAPEX in scenario 2 is high because of the use of 
a lot of expensive subsea equipment just like in scenario 3. This high CAPEX of scenario 2 can be seen in Table 4.1. The 
lowest  trough  in  year  4  indicates  a  high  CAPEX.  Scenario  3  also  makes  use  of  expensive  subsea  equipment  such  as 
submerged pumps to evacuate the multi phase flow to shore and the costs of the slug catcher are substantial. 
 The OPEX in scenario 1 is also lowest. Although all three scenarios are unmanned, scenario 2 and 3 make use of more 
expensive subsea equipment which also brings a higher OPEX than a conventional well. Additionally, scenario 3 has a high 
CAPEX of three scenarios Cumulative cashflows of 3 different scenarios

Scenario 1 Scenario 2 Scenario 3 Scenario 1 Scenario 2 Scenario 3

1600 5000

1400 4000
1200
3000
1000
2000
MM$

NPV ($)

800
1000
600
0
400 2 3 4 5 6 7
‐1000
200
‐2000
0
1 2 3 4 5 6 7 8 9 10 ‐3000
Years Time (years)
   
Figure 4.2: CAPEX of the Three Scenarios  Figure 4.3: Cumulative Cash Flows of Three Scenarios 

25 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
OPEX because of the onshore use of the slug catcher.  
Decommissioning costs are highest in scenario 1 which can also be seen in Table 4.1 from the trough in year 48 and 50. 
The reason for this is the following: The Semisubmersible in scenario 2 can easily be disconnected and moved away. The 
jacket in scenario 1 will be more difficult to decommission. The costs for the subsea/pipeline decommissioning are similar 
in all three scenarios.  
A factor that has a large influence on the NPV is the time and amount of money that is spent. If the amount can be as low 
and spread out as much as possible and as late as possible, the NPV, IRR and VIR will improve. This is the reason scenario 1 
scores high compared to the other two scenarios. Two graphs below are given of the expenditure of the CAPEX and the 
NPVs in the first years for the three scenarios, see Figure 4.2 and Figure 4.3. The graphs are directly linked to each other. 
The high CAPEX in year 3 in scenario 2 generates the highest negative cash flow in this year, which can be seen in Figure 
4.3. 

4.2. Sensitivity analysis of the three scenarios 
In order to estimate how sensitive a scenario is to a change in a variable, a sensitivity analysis is made. In this analysis, the 
NPV, IRR and VIR are calculated. Variables that have been changed are given a low, mid and high value. Listed below are 
the variables and their low, mid and high values respectively. 
• Condensate price   (32, 48, 64 $/bbl) 
• Gas price     (4, 4.5, 5 $/MMBTU) 
• Discount rate     (14, 12, 10 %) 
There are more variables that can be given a low, mid and high value. These will be considered in the sensitivity analysis of 
the final selected scenario.  
Values for NPVs are given in Table 4.3: 
 
Table 4.3: The NPVs  One  can  conclude  that  the  NPV  of 
NPV
scenario 1 is least sensitive to a change in 
Low (USD Billion) Mid (USD Billion) High (USD Billion) Difference
1 $                    3,149 $                    3,941 $                     4,732 $      1,583
condensate  price,  gas  price  and  discount 
Consensate price 
2 $                    3,014 $                    3,840 $                     4,665 $      1,651 rate.  Scenario  2  and  3  are  both  equally 
(32,48,64 $/bbl)
3 $                    3,110 $                    3,935 $                     4,761 $      1,651 sensitive. 
1 $                    3,622 $                    3,941 $                     4,259 $         637 Values for IRRs are given in Table 4.4: 
Gas price                  (4, 
2 $                    3,507 $                    3,840 $                     4,172 $         665
4.5, 5 $/MMBTU)
3 $                    3,603 $                    3,935 $                     4,267 $         665
A  change  in  condensate  price  has  the 
1 $                    3,225 $                    3,941 $                     4,841 $      1,616 same result on the IRR for each scenario. 
Discount ratio     (14, 
12, 10 %)
2 $                    3,079 $                    3,840 $                     4,805 $      1,727 A  change  in  gas  price  has  a  very  limited 
3 $                    3,173 $                    3,935 $                     4,902 $      1,728 effect  on  the  IRR,  both  scenario  1  and  2 
Table 4.4: The IRRs 
are least sensitive to a change in gas price. 
IRR
Low Mid High Difference A change in discount rate has no effect on 
1 37% 42% 46% 9% the IRR. 
Consensate price 
(32,48,64 $/bbl)
2 32% 37% 41% 9%  
3 34% 38% 43% 9% Values for VIRs are given in Table 4.5. 
1 40% 42% 43% 3%
Gas price               (4, 
2 35% 37% 38% 3%
 
4.5, 5 $/MMBTU) The  sensitivity  of  the  VIR  is  lowest  for 
3 36% 38% 40% 4%
Discount ratio     (14, 
1 42% 42% 42% 0% scenario 2 if a change in condensate price, 
2 37% 37% 37% 0% gas  price  and  the  discount  rate  occurs. 
12, 10 %)
3 38% 38% 38% 0%
Scenario 1 is most affected by a change in 
Table 4.5: The VIRs 
VIR
discount rate.  
Low Mid High Difference
1 1.56 1.95 2.34 $        0.78
Consensate price 
2 1.14 1.46 1.77 $        0.63
(32,48,64 $/bbl)
3 1.35 1.71 2.07 $        0.72
1 1.79 1.95 2.11 $        0.32
Gas price               (4, 
2 1.33 1.46 1.58 $        0.25
4.5, 5 $/MMBTU)
3 1.57 1.71 1.86 $        0.29
1 1.67 1.95 2.29 $        0.62
Discount ratio     (14, 
2 1.23 1.46 1.73 $        0.50
12, 10 %)
3 1.45 1.71 2.03 $        0.58

26 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

5. Selection of Final Scenario 
A  jacket,  a  semi‐submersible  and  a  subsea  system  are  the  concepts  which  have  been  considered  as  field  development 
scenarios for the  Zubara gas  field.  The  major  criteria  to compare these three  scenarios  are  the  HSSE  Study,  TECOP  Risk 
Analysis, Cost Analysis, Execution, and the First Day to Gas.  
 
HSSE  
The HAZID for all scenarios are listed in Appendix VI. According to these tables, major hazards for scenario 1 are: politic 
issues, explosions in the process plant, active faults and blowouts. Losses of mooring lines, semisubmersible instability and 
dropped object have more impact on scenario 2. Finally, in scenario 3 dropped objects, loss of umbilicals and problems 
due to fishery activities are more important issues. 
TECOP 
The main issues and related drivers are listed in Table 1.2. Although some issues are the same for all scenarios, there are 
some particular items for only specific scenarios. For instance, the budgeting problem is more important for the scenario 
which has high CAPEX. Also, subcontractors and local contractors will be satisfied with scenario 1 rather than others. 
Costs Analysis 
One  of  the  most  important  parameters  to  evaluate  the  scenarios  is  the  financial  criterion.  The  cost  analysis  for  all 
scenarios  is  done  including  CAPEX,  OPEX,  Royalty,  Tax,  and  NPV.  QUE$TOR  is  the  program  which  is  used  for  the  cost 
analysis.  The results of the cost analysis are summarized in Chapter 4 and are significant parameters for comparing the 
scenarios economically.  
Execution 
Fabrication,  supply  of  equipment  and  materials,  transportation,  installation,  decommissioning  and  contracting  are  the 
issues that have been considered as execution criteria to compare the scenarios. 
First Day to Gas 
The FDTG plays a main role for the financial analysis. It means the time it takes before a project can start making money.  
 
Advantages and disadvantages 
Based on the scenario specifications the comparison table is made. Table 5.1 shows advantages and disadvantages of each 
scenario. 
 
Table 5.1: Advantages and Disadvantages of the Three Scenarios 

  Advantages  Disadvantages 
• Low CAPEX  • Risk on launching 
• Low OPEX  • Fatigue 
• Dry trees  • Political issues, Iran 
Scenario 1  • Easy maintenance  • One drilling center 
(Jacket)  • Local fabrication  • Modular topside installation 
• Proven system in field area  • Short time to first gas 
• Less sensitive to delay   
• Less CO2 emission 
• Easier abandonment  • High CAPEX 
• Easier installation  • High OPEX 
Scenario 2  • Low sensitivity to geohazards  • More impact by Shamal wind 
(Semisubmersible)  • Less CO2 emission  • Longer time to fabricate 
  • Wet trees 
• No local experience to fabricate 
• No offshore separation process  • Need to Slug ‐ Catcher unit onshore 
• More flexible for well pattern  • Power supply  
• Less political problem by Iran  • High installation costs 
Scenario 3 
• Short time to first gas  • High Maintenance costs 
(Subsea) 
  • Limitation on Subcontractors for 
fabrication, supply and IMR 
• New technology in field area 
 

27 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Comparison 
The major items for scenarios comparison are listed in Table 5.2. Each criterion is evaluated by poor, medium, good and 
excellent.  
 
Table 5.2: Scenarios Comparison 
  Scenario 1 (Jacket)  Scenario 2 (Semisubmersible)  Scenario 3 (Subsea) 
CAPEX  Excellent  Medium  Good 
OPEX  Excellent  Medium  Medium 
Impact on Environment  Medium  Good  Good 
Impact on people Health  Good  Medium  Excellent 
Safety  Good  Medium  Excellent 
Security  Medium  Good  Excellent 
Easy Fabrication / Supply  Excellent  Good  Medium 
Easy Transportation / Installation  Medium  Good  Medium 
Stakeholders satisfaction  Good  Medium  Medium 
Easy Maintenance  Good  Medium  Medium 
Future development sensitivity  Medium  Good  Good 
Technology availability  Good  Medium  Poor 
Contracting plan flexibility  Good  Medium  Poor 
Time to first gas  Medium  excellent  Good 
Decommissioning  Medium  Good  Medium 
 
Scenario Ranking 
Based on the advantages and disadvantages and also on the qualify comparison of the three scenarios, a table of scenario 
ranking is made. In Table 5.3different weighting factors and scores are assigned for criteria and scenarios respectively. The 
weighting factor for each criterion varies from 1 to 5 and scenario scoring varies form 1 to 4. Therefore, the maximum 
score of each scenario can be 100. 
Table 5.3: Scenario Ranking  Sensitivity Analysis 
Criteria  Weight  Scenario 1  Scenario 2  Scenario 3  A  sensitivity  analysis  on 
(Jacket)  (Semisubmersible)  (Subsea)  weighting factors is done to 
CAPEX  5  4  2  3  consider  the  effect  of  this 
OPEX  5  4  2  3  variable  on  the  selecting  of 
NPV  5  4  2  3  a  scenario.  The  results  are 
HSSE  4  3  2  4  shown  in  Figure  5.1.  If  the 
Time to first gas  2  2  4  3  weight  of  financial  criteria 
Contracting  1  4  3  2  such  CAPEX  and  /or  OPEX 
Fabrication / installation  2  4  4  3  changes,  scenario  1  still  will 
Decommissioning  1  2  3  2  be  the  best  option  versus 
TOTAL  25  90  60  77 
each  combination  of 
  weighting factors (Table 5.4).  
Table 5.4: Weight Factor Combinations 
Sensitivity Analysis on Weighting Factors Weight factor  Weight factor  Weight factor 
Criteria 
100 combination 1  combination 2 combination 3
90 89
90 87 CAPEX  5  4  3 
77 78 78
80 OPEX  5  4  3 
70
60
64 NPV  5  4  3 
60
HSSE  4  4  4 
50 44
Time to first gas  2  2  2 
40
Contracting  1  1  1 
30
Fabrication/Installation 2  2  2 
20

10
Decommissioning  1  1  1 
0
Scenario 1 Scenario 2 Scenario 3

weight factor combination 1 weight factor combination  2 weight factor combination 3


 
Figure 5.1: Sensitivity Analysis on Weighting Factors 

28 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Part B: Final Field Development Plan  

29 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

6. General Information 
6.1. Layout  
Figure 6.1 below shows the layout of the total field development plan. As can be seen, a jacket structure without drilling 
equipment will be used. Besides the wells located underneath the jacket, also a manifold with six wells shall be installed. 
The  gas  is  separated  offshore  at  the  topside,  the  CO2  is  reinjected  using  the  CO2  injection  well  and  the  gas  and 
condensates are evacuated to shore in two separate pipelines. 

 
Figure 6.1: Total Layout Final Field Development Plan 

6.2. Introduction of the Field Development Plan 
Based  on  the  scenario  comparison  given  in  Chapter  5,  the  jacket  concept  is  selected  as  the  best  option  to  develop 
concession  2  of  the  Zubara  gas  field.  The  field  development  plan  is  elaborated  in  the  following  chapters.  The  general 
layout  of  the  field  development,  shown  above  in  Figure  6.1,  and  the  value  chain  show  the  overall  impression  of  the 
development  plan.  After  performing  basic  studies,  technical  aspects  of  the  field  are  designed.  These  technical  aspects 
include  the  well  layout,  the  jacket  structure,  the  topside  and  the  pipelines.  Fabrication,  transportation,  installation, 
decommissioning  and  contracting  are  considered  in  the  execution  plan.  The  field  development  plan  schedule  is  made 
based  on  all  these  categories.  Finally,  a  cost  analysis  for  this  plan  is  performed  by  use  of  the  QUE$TOR  software.  The 
sensitivity analysis of the cost study shows that when changing the variables, the financial impact on the project can be 
large.  
This  development concept  consists  of  a  jacket,  an  unmanned  topside, two  drilling centers,  subsea manifolding  and two 
single phase pipelines. 70 % of the raw gas will be delivered to the Pearl GTL plant and the rest of it to the Q4 LNG plant. 
The produced condensate will be delivered to the Laffan Condensate refinery. The main drilling centre which is located 
under the jacket includes one vertical well and ten horizontal wells. To keep the plateau production time longer than the 
plateau duration of an individual well, a second drilling centre is provided. It contains six deviated wells. A subsea cluster 
and  manifold  system  is  used  for  this  drilling  centre.  There  is  also  one  vertical  well  for  CO2  injection,  and  another  CO2 
injector can be drilled later in the field life. If the pressure still drops too much, a water injection well can be drilled. All 
wells  are  pre‐drilled  by  using  a  semisubmersible  drilling  rig.  The  unmanned  platform  will  separate  the  liquid  and  gas 
offshore  and  there  is  a  water  treatment  module  to  clean  the  produced  water.  After  the  cleaning,  the  water  can  be 
discharged into the sea. This water can also be used for possible water injection in the future.  
The jacket and topside will be fabricated near the field, namely in Dubai. The launching method is used to install the jacket. 
The foundation consists of skirt piles, that will be driven by an underwater hammer. An integrated topside will be installed 
by a float over system. ROVs and supply vessels will be used to install the subsea systems and S‐lay is the method for the 
pipe laying. The decommissioning method of each part of equipment is taken into account during the design steps.  
All general specifications of the development plan of concession 2 of the Zubara Field are summarized in Table 6.1. 
 

30 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Table 6.1: Zubara Field Development Plan Specifications 
General 
Location  Persian Gulf, North of Qatar 
Area  30,000 Acres 
Water depth  250 m 
Distance to shore  63 km 
Total gas  14.5 Tscf 
Total condensate  1159 MMbbls 
Recovery factor  85% 
Gas destinations  70% Pearl GTL plant, 30% Q4 LNG plant 
Condensate destination  Laffan Condensate Refinery 
Technical 
Field life  45 years 
Peak plateau: gas  1500 MMscf/day 
Peak plateau: condensate  120,000 bbls/day 
Jacket height  259 m 
Jacket weight  14,000 tonnes 
Topside weight  9,000 tonnes 
Piles weight  1,400 tonnes 
Production wells  1 vertical, 10 horizontal, 6 deviated 
CO2 injection wells  1 vertical 
Possible water injection wells  2 vertical 
Subsea system  6 cluster, 1 manifold 
Gas pipeline length  63 km 
Gas pipeline diameter  32 inches 
Condensate pipeline length  63 km 
Condensate pipeline diameter  16 inches 
Execution 
Jacket installation method  Launching 
Integrated topside installation method  Float over 
Pipe laying method  S‐ lay 
Subsea system installation  ROV 
Drilling  Pre‐drilling by semisubmersible rig 
Well completion  Via Platform and semisubmersible rig 
First gas time  2014, first quarter 
Financial 
CAPEX  2.7 Billion USD 
OPEX  5.5 Billion USD 
Total Revenue  91.8 Billion USD 
Royalty  20% 
Tax  75% 
VIR at 12% discount rate  1.95 
NPV at 12% discount rate  3.9 Billion USD 
UTC at 12% discount rate  4.4 USD/bbls 
IRR  42% 

31 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
6.3. Value Chain 
The gas that is extracted from the reservoir travels a long way in which its composition changes tremendously. Below in 
Figure 6.2 an overview is displayed how the natural gas is transformed into GTL. 
 
Subsea 

Re‐injected 
CO2‐
Gas wells  into reservoir  CO2  injectors 
Raw gas 

Jacket 

  Water  Treatment Unit
Clean
   water 
Membrane skid CO2
Separators  Condensates 
Dumped
Gas  overboard 

Condensates

Gas pipeline  Condensate pipeline


Condensates
Onshore  Gas  Gas 
Sold to refinery
LNG plant  GTL plant  in Qatar 
LNG  GTL 
products  Sold to China
Sulfur
Sold to:  Sold to: 
Thailand  India and Qatar. 

 
Figure 6.2: Processes of Transportation and Separation 
In the following paragraphs, the final destinations of CO2, H2S, the condensates and the gas are elaborated.  

6.3.1. Re‐injecting of Carbon Dioxide 
Qatar has signed the Kyoto Protocol. The intent of this Protocol is: ‘stabilization of greenhouse gas (CO2, CH4, N2O, SF6, 
HFCs  and  PFCs)  concentrations  in  the  atmosphere  at  a  level  that  would  prevent  dangerous  anthropogenic  interference 
with the climate system’.
Table 6.2: CO2 Emissions of Leading Oil and Gas Producing Countries 

32 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Qatar is already producing the most CO2 per capita, as shown in Table 6.2, and is not fulfilling the Kyoto requirements. It 
costs a lot of money when no solution is found for achieving a lower CO2 emission and of course it is not good for the 
image of Qatar. That’s why Qatar is very busy looking for solutions to reduce its CO2 emissions. Nowadays, most of the 
acid gas, which is gas containing CO2, H2S, etcetera, is injected in Ras Laffan itself as can be seen in the picture below, see 
Figure 6.3..  

Dolphin 
Laffan  
Refinery 
Shell GTL Qatargas

Ras Gas
ORYX 
Acid Gas Injectors GTL 

Camp
 
Figure 6.3: Location of Gas Injection in Ras Laffan 

The CO2 content of the gas in the Zubara Field has an average of 0.75 %. With a total amount of 12.3 Tscf of natural gas 
being produced, a volume of 92 MMscf of CO2 will be produced during the development of concession 2 of the Zubara 
Field. 
This field will probably need water‐ or gas‐injection to maintain a high enough pressure for two reasons: 
• To prevent condensate blocking  
• To keep the project profitable because the production is high enough.  
These two reasons are explained in Chapter 1.5.2. 
An option to combine the CO2 problem and the pressure problem is to inject CO2 in the reservoir. 
Reservoir  simulation  and  laboratory  studies  have  suggested  that  injecting  carbon  dioxide  into  mature  natural  gas 
reservoirs for carbon sequestration with enhanced gas recovery (CSEGR) is technically feasible. Reservoir simulations show 
that  the  high  density  of  carbon  dioxide  can  be  exploited  to  favor  displacement  of  methane  with  limited  gas  mixing  by 
injecting carbon dioxide in low regions of a reservoir while producing from higher regions in the reservoir. 
In water‐drive reservoirs where the potential additional CH4 recovery potential is much higher, CO2 injection will maintain 
reservoir  pressure  that  will  tend  to  keep  water  out  of  the  reservoir.  If  CO2  breakthrough  to  production  wells  occurs, 
separation of CO2 from CH4 can be carried out as a gas processing step with reinjection of the captured CO2. 
 
Of course several extra processing units should be located on the topside. 
These processing units separate the CO2 from the gas and pressurize it to 
allow  it  to  flow  to  the  gas‐injection  wells.  For  the  separation,  membrane 
skids will be used. A typical example of such a membrane skid is shown in 
Figure  6.4.  Membrane  technology  can  be  seen  as  a  promising,  upcoming 
technology for effective CO2 removal from natural gas.  
If  the  CO2  produced  by  the  concession  itself  is  not  enough  to  keep  the 
pressure  high,  additional  CO2  produced  by  other  platforms  can  be 
transported to the CO2 injectors in this concession. 
 
 
Figure 6.4: Offshore CO2 Separator 

33 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
6.3.2. Removal of Hydrogen Sulphide 
As  explained  in  Chapter  1.5,  the  hydrogen  sulphide  is toxic  in  relatively  low concentrations  and  causes  corrosion  in the 
process plants and pipelines. 
Therefore, chemical inhibitors are injected into the wells to prevent the process plants and pipelines from being damaged. 
The  H2S  is  still  very  toxic  to  human  beings  so  a  leakage  should  be  prevented  at  any  time  and  a  lot  of  H2S  detection 
equipment should be present at the topside.  
The gas and the inhibitors are not completely treated offshore. At the topside only condensates and water are separated 
from the natural gas. When the gas reaches the shore, it is transported to the GTL plant via onshore pipelines. 
In the GTL plant the raw gas is treated and the acid gas goes to the sulfur unit. In this sulfur unit, the hydrogen sulphide is 
converted into elemental sulfur and water by the following chemical reaction: 2H2S + O2 → S2 + 2H2O. 
The total value chain from natural gas to GTL, including the sulfur unit, is shown below in Figure 6.5. 
 

 
Figure 6.5: Value Chain: from Natural Gas to GTL 
 
This  by‐product  of  the  gas  recovery, elemental  sulfur,  is  becoming  an  important phenomenon  to  the  financial  books of 
many corporations.  
Currently, the sulfur market is increasing at a slow pace particularly over the last couple of years to a current price of $64 
USD/MT  FOB  Vancouver.  In  order  for  organizations  to  be  profitable,  logistical  costs,  long‐term  contracts  and  planning 
need to be assessed or result in losses as some companies are currently experiencing. 
The sulfur created in the sulfur unit in the GTL plant is stored by means of blocking or forming the element into small, solid 
pastilles  where  it  can  be  retailed  to  markets  such  as  the  United  States,  China  and  Africa.  Shell  Canada,  a  leader  in  the 
sulfur  market,  has  devised  a  number  of  methods  to  earn  an  annual  profit.  Its  strategy  was  to  penetrate  the  Chinese 
market  in  2001  whereby  it  is  now  one  of  the  largest  exporters  of  sulfur.  Second,  Shell  has  implemented  a  number  of 
alternative  sulfur  products  such  as  fertilizer,  enhanced  asphalt,  concrete  and  other  viable  products  that  utilize  the  by‐
product. The sulfur produced in this project of Shell, will have the same purposes. 

6.3.3. Condensates 
The Condensate Gas Ratio (CGR) in Concession 2 is 80 bbls/MMSCF. With a plateau production of 1500 MMscf/day, the 
maximum daily production of condensates will be 120,000 barrels. The destination of these condensates will be the Laffan 
Refinery. The Laffan Refinery Company’s plant is one of the largest condensate refineries in the world, with a processing 
capacity  of  146,000  barrels  per  stream  day.  Probably,  its  capacity  will  be  doubled  in  2012.  This  means  when  the  gas  is 
being  produced  from  the  Zubara Field,  all condensates  can be  sold  to Laffan  Refinery.  The condensates  will  be  sold  for 
approximately 80% of the crude oil price of that moment. 

34 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
6.3.4. Destination of Gas 
In order to make a decision into what products the gas will be made, it is important to look at the plateau production, 
which is 1,500 MMscf/day and the existing infrastructure in Qatar. There are 4 LNG plants owned by Qatargas, and there 
is one GTL plant. Shell is owner for 30% of the GTL plant and for 49% of the Qatargas 4 refinery which makes LNG. CNG is 
something common in the area and is used in countries like Iran, but Qatar doesn’t hold a CNG plant at the moment. In 
Table 6.3 below one can read the maximum capacities of the plants. 
This means there are two options: The gas can be converted to either GTL or LNG.  
The choice of a 70% GTL and a 30% LNG conversion is made. This choice is complex and depends on different variables.  
• LNG is a gas and will mostly be used to create electricity. It is a proven technology; therefore quite an accurate 
estimation  of  a  profit  can  be  made.  There  are  many  destinations 
thinkable  for  LNG.  Also,  the  price  of  gas  doesn’t  fluctuate  much,  so  Table 6.3: plateau production of several plants
again a good estimation of income can be made.   Plateau production
• GTL has a different destination than gas. It will mostly be used in the  MMscf/d
transportation sector. Also costs are lower to export GTL than for LNG,  Qatargas 1 1,600
and  no  regasification  facility  is  needed.  These  are  the  main  reasons  Qatargas 2 2,600
that  the  value  of  GTL  is  115%  of  the  value  of  crude  oil.  The  price  for  Qatargas 3 1,300
GTL will depend strongly on a fluctuating oil price. The future of GTL is  Qatargas 4 1,300
less  sure  than  for  LNG,  therefore  the  profit  analysis  will  be  less  GTL Plant 1,600  
accurate.  
The reason for the choice of two different products is made in order to spread the risks, such as changing demand of a 
product in the future. Another reason for the choice of more conversion of gas into GTL than into LNG, has to do with the 
fact that Shell has invested a large sum of money in the GTL plant in Qatar and is looking forward to the return of this 
investment. 
 
Destination of LNG 
As  mentioned  above,  LNG  and  GTL  have  different  destinies:  transport  versus  creation  of  electricity.  Therefore,  the 
countries buying the products are also different. A typical LNG client: 
• Has  a  surplus  in  energy  consumption.  A  reason  could  be  that  it  is  a  growing  economy  and  is  not  capable  of 
producing this extra need themselves. 
• Is  interested  in  a  long  term  contract, therefore  for  Qatar  it  is  advised  to  sell  it  to  a  country  which  is  politically 
stable. 
• Is not too far away from Qatar, unless the transportation costs can be paid for by the client. 
 
A country that is a potential buyer of LNG could be Thailand. Thailand has signed the Kyoto Protocol but has had a rapid 
rising  in  CO2  emissions  in  the  last 15 years,  see  Figure  6.6.  Thailand  has  experienced a  rapid growth  and  has  an energy 
deficit as can be seen in Figure 6.7 Also Thailand is not located very far away from Qatar.  

 
Figure 6.6: CO2 Emission from Thailand (source: http://www.wikipedia.org)  Figure 6.7: Thailand's Oil Production and Consumption (source: EIA) 
 

35 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Destination of GTL 
GTL products are more valuable and make more profit for the producer than LNG products. It is also less dependent on 
the customer’s demand and gas sale agreement than with LNG. The capacity of the Pearl Plant is big enough to process all 
production gas of concession 2 of the Zubara field. Shell has gained unparalleled technical knowledge and expertise in GTL 
production and marketing and has demonstrated that GTL technology is safe, efficient, reliable and profitable. 
A country interested in buying GTL: 
• Needs to lower CO2 emission, especially in its cities. A country that is not meeting the Kyoto protocol goals could 
be an option. 
• Is a little more daring than other countries, as the future for GTL is less certain. 
 
Possible buyers could be India and Qatar.  
According to a study done be “The Economist”, India is a country in which people are concerned by global warming, see 
Figure 6.8. Although this study was done in 2006, it can be assumed this concern has not dropped significantly because 
the amount of CO2 emissions has risen considerably, see Figure 6.9. India has many highly polluted cities in which an 
environment friendly product such as GTL could improve the air quality considerably. At last, India is not located far away 
from Qatar, and therefore transportation costs will not make it unprofitable. 
 

   
Figure 6.8: Percentage of People Concerned about Global Warming  Figure 6.9: Cumulative Percent Change in CO2 Emissions  
(Source: www.instituteforenergyresearch.org) 
The reason Qatar is nominated as well is mostly due to the amount of CO2 emission see Table 6.2. If Qatar wants to meet 
the  Kyoto  Protocol  requirements,  something  fundamental  has  to  change.  Since  the  GTL  plant  is  located  in  Qatar  itself, 
Qatar can acquire GTL relatively cheap. 

6.3.5. Revenues  
The financial calculations for the project presented later in the report, are based on the boundary conditions mentioned in 
Chapter  1.2.  These  state  that  the  objective  is  to  deliver  the  gas  to  a  gas  treatment  plant  onshore.  However,  a  quick 
estimation of the revenue received after conversion of the gas could give a feel of the potential of the development of the 
field. If it is decided to convert 70% of the gas into GTL and 30% into LNG, and to sell the condensate and extracted H2S 
the following potential revenue is calculated. GTL revenue:  70% ⋅ 12.3 Tscf = 8.6 Tscf . 
The  capacity  of  the  GTL  plant  is  1.6Bcf  which  yields  140,000  bbls  of  GTL  each  day.  The  ratio  therefore  is 
140,000
=87.5bbls/MMscf . 
1,600
 
8.6 TCF will be converted to 753.4 million barrels of GTL throughout the project lifetime. One barrel of GTL has the price of 
115% of crude oil. If the oil price is 60$ per barrel, a barrel of GTL will cost $69. Total revenue of GTL will be 753.4 x $69= 
51.9 $ Billion. LNG revenue:  30% ⋅ 12.3 Tscf = 3.7 Tscf  
Since  1  MMscf=1,000  MMBTU  and  1  MMBTU=8  $  the  revenue  of  the  GTL  is  calculated  as  follows: 
3.7 ⋅ 1,000,000 ⋅ 1000 = 3,690,000MMBTU
 
8$
3,690,000MMBTU ⋅ = 29.5 $ Billion
MMBTU

36 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
 
Condensate revenue:  
The  total  amount  of  condensate  that  will  be  produced  is  roughly  984  MMbbls  based  on  the  Condensate/Oil  ratio.  If  a 
barrel of condensate can be sold for 80% the oil price of $60, the total revenue of condensate is 47.2 $ Billion. H2S revenue: 
The amount of H2S that can be extracted is calculated in Appendix VIII. Based on a conservative concentration of 2% of H2S 
and a price of 300$/tonne, this comes out to be: 
2.7 $ Billion 
 
Total total revenue of 131.3 Billion dollar can be made. It should be noted however that the CAPEX and OPEX onshore and 
offshore are not taken into account. Therefore this number should not be mistaken with total profit. 
 
Item Revenue ($ Billion)
Revenue from GTL 51.9
Revenue from LNG 29.5
Revenue from Condensate 47.2
Revenue from H2S 2.7
total 131.3  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

37 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

7. Risks 
In this chapter, the HSSE and TECOP risks analyses will be elaborated. 

7.1. HSSE 
The  hazard  identification  is  determined  based  on  different  areas/subjects  such  as  the  process  plant,  power  generation, 
drilling, reservoir and geohazards. The hazard identification, HAZID, is classified and expressed in Table 7.1. As this table 
shows, for each issue potential causes and risk reducing measurement methods are considered. Then, consequences and 
following up are given according to risk mitigation strategy.  
 
Table 7.1: Summary of HAZID Table 

Area/Subject  Hazard  Potential Causes  Risk Reduction  Potential  Follow up/Action 


Measures  Consequences 

Process  Explosion  Ignition of gas leak  Ignition source  Explosion load  Design for explosion scenarios. 


plant/deck  control, electrical  inside process plant. 
equipment in  External explosion 
Plant  load on LQ. 
Process  Flare failure  Fire in area close to     Flare boom may tip  Evaluate the passive fire protection of 
plant/deck  flare boom  over  lower part of flare  
Power  Gas leak from fuel     Gas detection  Gas may ignite. It    
generation  / gas supply in  system  will result in a small 
open air  local fire 
Drilling   Fault and  Tectonic structure  Geology and  Cause severe  Drilling through these hazards should 
fractures  seismic study  drilling problems  be avoided if possible, or if relocation 
is not an option, appropriate 
mitigating measures taken. 
Helideck  Helicopter crash  Unfavorable     Injuries, fatalities,  Location of helideck must fulfill all 
location of  damage to topside  regulations for helideck. 
helideck. Difficult  and Jacket 
weather conditions 
Reservoir/well  Sinkholes  Geology structures  Geology  study  Loss of the well,  Change the drilling location or use 
sever problem for  deviated drilling to avoid the 
drilling  hazardous area 
Risers/pipeline  Corrosion due to  H2S in gas  Measurement H2S  Corrosion in  Use suitable material for pipeline, 
H2S  composition  content, use  pipeline  inhibitor injection, offshore 
suitable material  desulfurization 
for pipeline, 
inhibitor injection 
Geohazard  Coral damage  Environment   Field investigation  Problem for  Change the pipeline path 
pipeline and risers 
Other hazards  Politic issues  Political issues  Be aware about  May cancel the  Negotiation with Qatar government  
politic issues,  project  and  other countries which have 
good relation  influence on project 
with government  
 
ALARP 
Based  on  the  hazard  identification  table  and  probability  of  occurrence,  an  ALARP  table,  Table  7.2  is  provided.  As  it  is 
mentioned in this table, there are some risks in the ALARP area which need more attention. 

38 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Table 7.2: ALARP Table 
  ALARP, As Low As Reasonably Practical  

● Condensate leakage  ● Dropped object       
● Gas leakage in process 
plant 
Frequent 

● Loss of electrical  ● Fire in power              
power  generation unit 
● Gas leakage in power  ● Coral damage 
Unfrequent 
generation 
● Gas migration 
● Flow assurance 
● Corrosion due to H2S  ● Gas leakage from  ● Fire in process plant  ● Politic issues 
● Change in gas  risers  ● Structure Failure  ● Blowout 
composition  ● Sinkholes  ● Fatigue 
Unlikely  ● Collapse of well 

● Deviation on Drilling  ● Flare Failure  ● Fault and Fractures  ● Explosion in process 


● Shallow water flow  ● Helicopter crash  ● Landslide  plant 
(SWF)  ● Earthquake  ● Terrorist Attack 
Remote    ● Active Faulting 
 

  Insignificant  Minor  Major  Catastrophic 

  Consequence 

        
Intolerable Area 
   ALARP Area       

   Negligible Area       
 

7.2. TECOP 

TECOP is the method which is used to evaluate the risks. According to 
this  method,  different  kinds  of  issues  for  the  risk  assessment  are 
considered, namely Technical, Economical, Commercial, Organizational, 
and Political risks. These risk categories are illustrated in Figure 7.1. 
  
The major issues for this field are listed in Table 7.3. 
The issues which have more influence on the project are categorized as 
opportunity and / or threat, Table 7.4. The Opportunity & Threat Grid 
provides a framework for examining the uncertainties and risks as well 
as the opportunities associated with the project. The tool highlights and 
ranks uncertainties and risks according to their impact on the value of 
the  opportunity  and  on  Gas  N’  Roses’  ability  to  influence  and  /  or 
 
Figure 7.1: Risks Categories based on TECOP  control the impact of the uncertainty or risk. 
 

39 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Table 7.3: TECOP Risk Identification 
Technical  Economic  Commercial  Organizational  Politic 
Flow Assurance  Increase CAPEX  Problem on Gas sale  Project management  War in Middle East 
agreements, e.g. change  team 
in gas price 
Sink Hole  Increase OPEX  Main contract  International employees  Russia‐Iran‐Qatar gas 
termination   cooperation 
Gas migration  Gas price changes  Change in contract with  Work done in different  Iran‐Qatar Government 
subcontractors  location  relations 
Variation of  GIIP  / CIIP  Oil price changes  Gas demand  Operation by local   Media, TV 
people 
Gas composition  Less interest for  Local regulation in  IMR locally  Terrorism attack 
shareholders  contracts 
H2S high content  Lack of Budget   GTL Products market  Local subcontractors  Competitors 
Pressure drop in  World economic crisis  LNG market  Limited suppliers for  Iran government 
reservoir  special technologies 
Technical problem on  By products sales  Condensate market  Interaction between  NGOs 
GTL plant and/or LNG  installation activities 
plant 
 
Risks mitigation 
As  shown  in  Table  7.4,  some  of  the  issues  can  be  both  an  opportunity  and  a  threat.  There  are  also  risks  that  have  an 
impact on the project as an opportunity or threat only. Some of these points are described below.  
• Technical 
Reservoir uncertainties have a high impact on the project. For instance, reservoir pressure drop can make more water and 
then the wells can be blocked, as mentioned in Chapter 1.5.2. In this case, the production rate will decrease extremely. 
Besides, gas pressure should be increased to keep the availability of delivering the gas by pipeline. Water injection is the 
option  to  maintain  the  reservoir  pressure.  GIIP  and  CIIP  also  have  an  impact  on  the  production  facilities,  pipeline, 
production life, etc.  If the GIIP and CIIP increases, extra equipments / trains, and longer production profile can be things 
to deal with. Therefore, reservoir characteristics should be monitored continuously.  
High content of H2S can be a serious problem. Chemical inhibitor injection, use of suitable steel, and a desulfurization unit 
can be taken into account to prevent this problem. Nevertheless, sulfur sale as a byproduct can make valuable benefit for 
the project. 
CO2  is  the  other  technical  issue  that  acts  as  both  an  opportunity  and  a  threat.  Carbon  dioxide  emission  is  a  significant 
environmental problem. CO2 injection is an option to get rid off of it. However, it is also possible to sell it to neighbor oil 
field for gas injection and maintain their reservoir pressure. 
• Economic 
Gas price is the main issue regarding to economical risks. If it increases, more revenue will be available. On the other hand, 
if the gas price falls, the revenue will decrease significantly.  
Oil price fluctuation is a key issue in the oil and gas industry. There are several parameters that have influence on the oil 
price. The point is that most of these parameters are out of Shell’s control. Therefore, it can be a serious threat if the price 
falls. Oil price variation can also have influence on other costs of the project like material, transport, equipments, etc. GTL 
product prices usually are based on the oil price.  
By product sales, is a suitable option to increase the revenue of the project. Sulfur and carbon dioxide are two of these 
products. Essential requirements to the process, such as a desulfurization unit, should be taken into account. 
• Commercial 
Gas sale agreements are usually based on long term conditions. In case there are some changes in the agreement terms, 
several  problems  can  occur  that  have  their  influence  on  revenue,  production,  etc.  For  instance,  the  client  may  tend  to 
decrease the gas price in the agreement because of gas market variation, government instability, and/or politic issues. 
The LNG market, GTL market and Condensate market are the major objectives of this project. Thus, variations of these 
markets  have  significant  impact  on  the  project  directly.  Long  term  agreements  are  an  important  method  to  secure  the 
project objectives.  
• Organizational 
A well organized project management team affects on maintain the project in right direction. On the other hand, lack of 
project management is a serious threat for the field development. 

40 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Local subcontractors can help the project to keep it less expensive especially to fabricate the jacket and topside. Moreover, 
engaging  the  local  subcontractors not  only spreads the  risks  but  also  satisfy  the  local  stakeholders.  The disadvantage  is 
they usually need more training and supervision.  
• Political 
Political issues in the oil and gas industry are one of the main key parameters. Middle‐East and Persian Gulf especially, is a 
very  complicated  political  area.  Therefore,  working  in  this  area  needs  more  attention  to  this  category.  The  relation 
between  Iran  and  Qatar  is  the  most  important  one.  Although,  nowadays  this  relation  seems  good,  everything  can  be 
changed easily due to the next president election in Iran and pressure on the Qatar government by the USA.  
To avoid most of the political issues, having a good relation with the Qatari government and being aware of political news 
is essential. 

Table 7.4: Opportunity / Threat Grid 
  OPPORTUNITY
 
• Gas price  • Decrease CAPEX  • Project Management 
• Oil price  • Decrease OPEX  team 
• GIIP / CIIP  • Local subcontractors  High 
• GTL market   
• LNG market 

• Iran‐Qatar governments    • IMR locally 
relation  • Operation by local people 
• Gas demand  • Sub contractors contracts  Medium 
• By products sales 
 
  • International employees   

Low 
Impact 

• Russia‐Iran‐Qatar gas  • IMR locally  • Sub contractors contracts 


cooperation  • Special suppliers  • Flow assurance 
• High H2S  content 
• Sinkholes  Low 
• Iran‐Qatar governments 
relation 

• GTL plant problem  • Gas sales agreement   
• LNG plant problem  • Local low in contract 
• Gas composition  • Gas migration 
• Gas demand  • Lack of budget  Medium 
• Pressure drop 
• Economic crisis 

• Gas price  • Main contract  • Project Management 


• Oil price  termination  team 
• GIIP / CIIP  • Increase CAPEX   
• War in Middle East  • Increase OPEX  High 
• Terrorism   
• NGOs 
THREATS
 
Low  Medium  High 
 
Ability to Influence

41 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
8. Technical Aspects 
This chapter provides the information on all technical aspects of the Final Field Development Plan. First the well layout is 
given and it is explained what the production profile will be. Then the layout and weight of the topside and structure are 
elaborated in two separate subchapters. Another major aspect of the scenario is of course the pipelines that will transport 
the gas and condensates to shore. And at the end of this chapter, the way everything is fabricated and, at the end of the 
field life, decommissioned, is explained. 

8.1. Well Layout 
Figure 8.1 below shows the layout of the wells in the final field development plan.  

Figure 8.1: Well layout Reservoir Final Field Development Plan 
 
In this final field development plan, 10 horizontal wells and one vertical well will be drilled. 
Long‐radius  horizontal  wells  will  be  used  because  this  kind  of  well  is  used  for  achieving  large  horizontal  displacements 
from  platforms  or  drilling  pads  and  for  achieving  very  long  horizontal  sections,  to  more  than  6,000  ft.  In  this  case, 
horizontal wells with a length of 6000 ft will be used. The radius of these wells is ~4 degrees/ 100 ft. This means a total 
distance of 2250 feet is necessary to make a bend of 90 degrees. The reservoir depth is 7800 feet so that is more than 
enough to drill the horizontal wells. 
The capacity per foot of horizontal wells is not the same as for vertical wells. So the production is not directly related to 
the  length  of  the  horizontal  well.  Horizontal  wells  with  a  length  of  6000  ft  produce  of  course  quite  some  more  than 
vertical wells. This ratio is normally between 1.4 and 1.8. Because the horizontal wells are long and produce more than 
shorter horizontal wells, a factor of 1.7 times the productivity of vertical wells is used. 
The ten horizontal wells and one vertical well will be drilled before the jacket is installed. Once the jacket is installed, no 
extra  wells  can  be  drilled  anymore  under  the  jacket  because  the  jacket  does  not  consist  of  a  drilling  derrick  and  is 
unmanned. 
As can be seen in Chapter 3.1.2, a production profile of 45 years will be reached when the plateau production is ten years. 
But the maximum production of one well will only last for four years. Because all wells are predrilled and it is a waste of 
money to not use them immediately when the jacket is installed, all wells will start producing at the same moment once 
everything is placed and installed. So in this case, the plateau period will only be four years long and not all the gas will be 
produced in 45 years. 
This  means  that  during  the  production,  additional  wells  should  be  drilled.  Because  the  jacket  is  standing  in  the  way,  a 
manifold will be placed and satellite wells are drilled. The maximum jumper length nowadays is ±160 ft and this means the 
maximum  distance  between  the  satellite wells  and the manifold  is 160  ft.  Vertical wells  have  a  producing  area of  1000 
acres, which is 43560000 ft2. When these vertical wells are all placed around the manifold with a distance of 160 ft, the 
overlap would be too much. That is the reason why the satellite wells will be deviated wells. These deviated wells will still 
have  some  overlap  in  the  reservoir  and  will  not  produce  at  their  maximum  rate  of  120  MMscf/day.  As  can  be  seen  in 
Appendix III, the deviated, satellite wells will produce 85 MMscf/day.  

42 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Gas migrates to places where the pressure is the lowest and 
because the gas in the reservoir has a lower density than air 
and  water,  it  will  migrate  upwards.  This  means  most  of  the 
gas  will  accumulate  at  the  highest  point  of  the  reservoir. 
Nevertheless, the jacket will not be located above this point 
because it is not in the middle of the field. When the jacket is 
placed somewhat more to the south, the horizontal wells will 
reach  much  wider  area  in  the  concession.  The  jacket  is  not 
placed on a sinkhole and also the wells will not perforate the 
sinkholes,  as  can  be  seen  in  Figure  8.2.  One  pipeline  for  a 
CO2‐injector is located on a sinkhole but that is not a problem 
because  it  is  possible  to  place  surface  equipment  above  the  Sinkhole 
Jacket 
sinkholes.   CO2 Injector 
The gas that is present at locations that aren’t reached by the  Manifold 
Satellite 
horizontal  wells  will  still  be  produced.  This  will  happen  Well
because  the  gas  will  migrate  towards  the  wells  because  the  Figure 8.2: Top View Final Field Development Plan 
wells are located less deep and the pressure near the wells is 
lower  because  of  production.  When  this  natural  migration  will  not  occur  fast  enough,  the  injection  of  CO2  at  the  CO2‐
injector will help. The produced CO2 is separated at the jacket and reinjected into the reservoir using the CO2 injector well 
at the southern part of the concession. When the pressure still drops too much, an additional CO2 well can be drilled at 
the left corner of the field or even a water‐injector can be drilled. 
The additional deviated wells are located at the highest part of the reservoir and will produce the gas that has migrated 
towards this area. 

8.1.1. Drilling Schedule 
Three kinds of wells are used in this scenario: horizontal, vertical and deviated. 
Table 8.1: Drilling Time per Well  The drilling time of one well consists of the time of the drilling itself and four 
extra  days  for  completion.  Of  course  drilling  a  horizontal  well  will  take  a 
Well Type  Drilling Time [days]  longer time than a vertical well because it is more complicated and the well 
Vertical  64  itself is longer. This gives an overview of drilling times per type of well listed 
Deviated  94  in Table 8.1. 
Horizontal  109  The  drilling  schedule,  Figure  8.3  will  consist  of  two  phases.  Phase  one 
consists  of  the  drilling  and  completion  of  the  horizontal  wells,  vertical  well 
and CO2‐injector. After phase 1 has finished, production can start. When the plateau period of the wells is over after four 
years,  the  additional  cluster  wells  are  drilled.  To  keep  the  production  at  its  plateau  level  for  ten  years,  every  year  one 
deviated well will be completed. The drilling of the six additional wells will be done right after each other because hiring a 
drilling semi for only three to four months per year for six years is too expensive. To let the wells start producing one year 
after each other, the completion of a well will be done once per year. 
First Gas

Months
Type of well Start Finish 0 10 20 30 40 50 60 70 80 90 100 110 120
Horizontal well 1 0 4
Horizontal well 2 4 7
Horizontal well 3 7 11
Horizontal well 4 11 15
Horizontal well 5 15 18
Horizontal well 6
Horizontal well 7
Horizontal well 8
18
22
25
22
25
29
Phase 1
Horizontal well 9 29 33
Horizontal well 10 33 36
Vertical well 36 38
CO2 injector 38 41
Deviated well 1 98 101
Deviated well 2 101 104
Deviated well 3 104 107
Deviated well 4 107 110 Phase 2
Deviated well 5 110 113
Deviated well 6 113 116
Figure 8.3: Drilling Schedule Final Scenario 
 
The drilling and completion of the deviated wells can be grouped in some phases as shown in Figure 8.4. 

43 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
 
8  Phase 1: Drilling all the wells, as can be seen in Figure 8.3 this will take 3.5 

months per well times 6 wells = 21 months.  
1  6 
Phase  2:  Installation  of  the  manifold,  jumpers  and  pipeline  and  umbilical 

3  connecting the jacket and manifold. 

4  2  Phase 3 till 8: Placing of the horizontal trees on the pre‐drilled wells. This is 
5  called the completion of the wells and this will be done once per year. 
1   
1  According to this drilling and completion schedule, the following production 

profile as shown in Figure 8.5 will obtained: 
Figure 8.4: Drilling and Completion Phases   
 
Production 
Total Production
Pre‐drilled Wells
1600
Cluster Wells
1400

1200
Production [MMscf/day]

1000

800

600

400

200

0
0 5 10 15 20 25 30 35 40 45
Time [years]

Figure 8.5: Production Profile Final Scenario 

8.1.2. Subsea Equipment 
Well configuration 
The well completion is the same for vertical, deviated and horizontal wells. 
Completing a well consists of several steps: 
1. Installing the well casing 
a. Stove pipe: This 30” conductor casing has a length of 330 ft. 
b. Conductor casing: Has a diameter of 20” and a length of 1640 ft. 
c. Surface casing: to a depth of 3000 ft. 
d. Intermediate casing: to a depth of 7000 ft. 
e. Production casing: This casing runs to the target depth of 9200 ft. 
2. Completing the well. 
Production casing is run through the formation and the sides of this casing 
are perforated with tiny holes along the sides facing the formation. This 
type of well completion is called conventional perforated completion. 
3. Installing the wellhead.  
The wells will have a wellhead as is shown in   
Figure 8.7.  Figure 8.6: Well Casing 
4. Treating the formation. 
As explained in Chapter 1.5, the gas needs to be treated with a chemical inhibitor to prevent corrosion due to the 
large amount of H2S.  
These chemicals will be injected in the well itself to prevent corrosion in the wellhead and risers. This will be done 
by inserting chemical injection tubing into the production tubing, as can be seen in Figure 8.8. The chemicals that 
are  injected  passivate  steel  surfaces.  These  compounds  are  generally  mixtures  of  organic  amines.  Exact 
formulations are not always known, as the vendors are usually secretive about analyses.  
 

44 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
18 ¾” Wellhead 
housing 

Wellhead to 
casing

30” Conductor 

20” Casing 

13 3/8” Surface 
casing
9 5/8” Intermediate 
casing 

7” Production 
casing 

   
Figure 8.7: Wellhead  Figure 8.8:  Chemical Injection Tubing: Dual Completion 
 
Drilling the horizontal and deviated wells 
An assembly consists of the parts that make up the drill string that the rig lowers into the hole to 
drill the well. They include the following: 

• Mud Motor: The directional assembly consists of a "mud motor" which is a machine that 
contains a rotor and stator inside it which are turned by the force of the drilling fluid or 
"mud"  that  is  pumped  down  the  drill  pipe.  This  motor  turns  the  drill  bit  so  instead  of 
turning  the  entire  length  of  drill  pipe,  the  motor,  which  is  bent  at  a  certain  angle,  can 
remain in a fixed position drilling the hole in whatever direction the bend of the motor is 
aimed toward. An image of a mud motor is shown in Figure 8.9.   
Figure 8.9: Mud Motor 

• MWD Probe: A probe full of instruments is placed inside a nonmagnetic length of drill pipe just above the mud 
motor  to  show  the driller  on  the  surface which direction  he  is  drilling  in  and  at  what  angle  or  inclination he  is 
heading. This instrument is an MWD or "Measure While Drilling" probe. It typically consists of instruments that 
measure  inclination  utilizing  accelerometers  and  instruments  that  measure  azimuth  or  compass  heading  using 
magnetometers.  This  information  is  sent  via  a  series  of  pressure  pulses  in  the  column  of  drilling  fluid  flowing 
down to the bit from pumps on the surface.  At the surface a device called a transducer picks up these increases 
in pressure (similar to Morse code signals) and they are decoded by surface equipment in the MWD company’s 
mobile lab that is placed on deck of the offshore rig. This equipment is connected to a display on the rig floor 
where the driller can see which way the bent motor is sliding.  

The directional driller can then turn the entire length of drill pipe ever so 
slightly  in  the  direction  he  wants  the  well  to  go  and  the  motor  which  is 
being  turned  by  the  flow  of  drilling  mud  coming  down  the  drill  pipe 
causes the bit to chew away at the rock and drill ahead. MWD equipment 
can also be combined with sensors that record gamma rays given off from 
the  rock  formations  below,  instruments  that  measure  resistivity  and 
conductivity,  etc.  This  is  known  as  "logging  while  drilling"  or  LWD.  It 
enables  the  oil  company geologists  to  see  if  they  are  staying  in,  or have 
reached, the oil or gas bearing zones in real time instead of having to pull 
all  the  drill  pipe  out  of  the  hole  and  run  a  wireline  based  logging  tool 
  down the hole. An image of a drilling platform drilling a horizontal well is 
Figure 8.10: Horizontal Well from a Drilling Platform  shown in Figure 8.10. 

45 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Trees 
The horizontal and vertical wells will all have dry trees on the jacket itself. In contrary, the 
six  deviated  wells  drilled  later  in  the  field  life  will  be  controlled  using  wet  trees.  
Horizontal shallow water trees are used because the tubing hanger is installed within the 
treehead, and this means heavy workover, like tubing retrieval, can be achieved without 
the need to recover the tree system. A horizontal shallow water tree of Vetco is shown in 
Figure  8.11.  This  range  of  horizontal  trees  is  usually  deployed  on  guidelines  in  water 
depths up to 500m from an anchored semisubmersible drilling rig.  
 
  Figure 8.11: Horizontal Vetco Tree 
Jumpers 
The wells are located 160 feet from the manifold. To connect the trees and manifold, jumpers are used. Figure 8.12 shows 
the installation of a horizontal jumper connecting a manifold and a horizontal well. The jumpers are designed in such a 
way that they can resist the pressure of the gas coming out of the well. 

Figure 8.12: Horizontal Jumper 
 
Figure 8.13:   Reliance Project Subsea Layout 
 
Manifold 
To determine the right size for the manifold, a similar gas field development plan is analyzed. The Reliance Project, in the 
KG‐DWN‐98/1 (KG‐D6) field in India, produces 14 Bscf of natural gas with a forecasted daily production of 2800 MMscf/d. 
This daily production is achieved by using 18 wells. These 18 wells are clustered around three 6‐slot manifolds. Figure 8.18 
below shows the subsea layout of this project.  
Because  the  production  in  the  similar  project  is  twice  as  high  per  well  than  in  this 
Zubara  project,  the  size  and  weight  of  the  manifold  will  be  somewhat  smaller.  The 
manifolds in the Reliance Project have a weight of 225 t so 200 t for the manifold of 
the Zubara Project is a good estimation. 
A typical size for a 6‐slot manifold is 15 x 10 x 5 m. 
The manifold can have several options for its foundation: 
• Piles:  not  very  commonly  used  because  special  equipment  needed  during 
installation. 
• Mudmat: Used in hard to medium soil conditions. Large areas required, high 
slamming loads in splash zone 
• Suction  Pile:  robust  foundation  concept  from  soft  to  “ultra  soft”  soil 
conditions. Guide mast on suction pile interfaces centre column on manifold. 
Levelling  possible  by  adjustment  of  position  of  guide  cone.  Images  of  the 
guide mast and guide cone are shown in Figure 8.14.  
Because of its robustness, a suction pile will be used as foundation of the manifold.  
The soil in this area consists mainly of clay and sand and in the top 10 meters, it is not 
very strong. That is the reason why the suction pile will be relatively wide and not so 
long. The rules of thumb for determining the dimensions of a suction pile in clay are: 
L/d  =  3  to  6  and  d/t  =  100  to  250.  With  a  diameter  of  5  meter,  a  suction  pile  with  a   
length of 15 meters and a wall thickness of 35 mm will be obtained.  Figure 8.14: Suction Pile and Manifold  
 
 

46 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
8.1.3. Controls 
To control the manifold and wells a control system is necessary. This control system consists of equipment at the topside 
and components subsea: 
 
Topside  Hydraulic Power Unit 
  Methanol / chemical injection skids 
  Accepts platform ESD signals 
  Topside Umbilical Termination Unit 
Subsea  Umbilical Termination Assembly 
  Control Pod on Tree / Manifold 
  Readback of pressure / temperature / choke position / downhole data 
 
This equipment is connected to each other in the following way as displayed in Figure 8.15. 
 
Master Control 
Hydraulic  Station 
Power Unit  Computer/Power 
Supply 

Platform Junction  Chemical 
Box  Injection Unit 
Topside 
 
Umbilical 
Subsea 
Electrical/Hydraulic Power  Process Instrumentation
Subsea Umbilical  Communications  Subsea Control  Xmas Tree and 
Termination /  Module  Hydraulic Power Manifold 
Distribution 

Chemical Injection  Downhole

 
Figure 8.15: Control System 
 
The umbilical can be seen in Figure 8.16 and has the following three functions: 
 
1. Transportation of the chemicals that are injected downhole to prevent corrosion caused by the H2S. 
2. The  chokes  and  valves  on  the  trees  and  manifold  are  controlled  by  hydraulics.  These  hydraulics  are  flowing 
through the umbilical from the jacket to the manifold. 
3. Providing electric power to operate all the chokes and valves on the trees and manifold.  

47 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

 
Figure 8.16: Umbilical 

 
Figure 8.17:  Subsea Controle Unit 
The Subsea Control Unit (SCU) will be both hydraulic and electric. This design offers several advantages over conventional 
direct  hydraulic  control  systems,  including  instantaneous  hydraulic  venting  of  the  actuators,  increased  instrumentation 
capabilities, and ROV retrievability with down line. An image of such a SCU is shown in Figure 8.17. 
The manifold and six cluster wells including the jumpers and SCU is shown in Figure 8.18 below: 

 
Figure 8.18: Subsea Layout Final Scenario 

8.1.4. IMR 
Because of safety reasons and cost reduction, ROVs, as shown in Figure 8.19 will be used for 
all  IMR  operations  subsea  and  divers  are  never  used.  The  jacket  is  a  fixed  structure  so  dry 
trees are used instead of wet trees. This means workover operations on the dry trees of the 
horizontal and vertical wells can be done at the topside itself which makes IMR operations 
easier  and  much  less  expensive.  These  IMR  operations  should  be  planned  and  performed 
very  well  because  the  jacket  is  unmanned.  This  means  workover  operations  are  relatively 
expensive compared to a manned platform because first specialists will have to be arranged  Figure 8.19: Typical ROV 
and first brought to the platform, but that will be done by the subcontractor responsible for 
all IMR operations. 
Wellheads and casings deteriorate with age and if left unchecked, these processes will eventually cause structural failure. 
Structural  inspection  provides  a  means  of  detecting  damage  before  failure  occurs  and  is  thus  an  important  element  in 
failure prevention. Once per year an ROV will be used to inspect all the wells and risers. 
The deviated wells will need other IMR actions because their trees are wet. 
The chokes are the piece of subsea equipment that is most subject to wear. It is very likely that the subsea chokes will 
have to be replaced every two to three years. All satellite wells are connected to the manifold via jumpers. Nowadays, all 
templates and Christmas trees are designed in such a matter that an ROV can do all necessary actions. 

48 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
8.2. Topside 
This  unmanned  jacket  will  consist  of  non‐processing  modules  and  processing  modules.  In  8.2.1  the  non‐processing 
modules are explained and in 8.2.2 the process plant.

8.2.1. Non‐processing modules 
The platform should be accessible by helicopter for inspection and maintenance. These periodical inspections could take 
several  days  perhaps  weeks  and  therefore  the  platform  has  accommodation  for  the  crew  along  with  a  control  and 
communication centre. Control and monitoring of the installation will normally be carried out onshore. 
 
During hazards the personal must be able to escape the platform safe and quickly.  
A range of facilities are provided for the safe evacuation to the sea, primarily Totally Enclosed Motor Propelled Survival 
Crafts (TEMPSC). These are backed up by life rafts, survival suits, life jackets, smoke hoods, and lifebuoys which coupled 
with alternate means of escape, provide a large range of appliances. Beside this, more emergency equipment will be on 
deck like fire water installations, fire and blast walls. 
 
During emergency situations, fire and blasting are the main serious problems on the platform. To prevent these kinds of 
situations  different  measurements  have  been  taken.  First  of  all  monitoring  the  equipment  constantly,  failures  that  can 
cause  fire  or  blasting  will  be  noticed  soon  enough  so  measurements  could  be  taken  very  quickly.  Secondly  different 
hazardous  platform  areas  should  be  designed  separately  from  each  other  so  in  times  of  emergency  the  fire  or  blasting 
won’t spread like a chain reaction through the platform. And at last fire and blast walls will have their tasks to prevent that 
fire will spread over the decks. In case of fire, the common fire water installation can be used to put out the fire.

8.2.2. Process plant 
The main functions of the unmanned platform are: 
  ‐ Import of gas, condensates, water and impurities 
  ‐ Processing the gas, condensate, water and impurities 
  ‐ Injection of CO2 and chemicals 
  ‐ Evacuation of gas, condensate and impurities 
Metering  and  gas  quality  monitoring  is  performed  at  the  production  platform  constantly.  The  gas  flow,  pressure  and 
temperature will be monitored precisely which will give the most important information about the properties of the gas to 
know exactly what’s needed to be done to process the gas. 
The gas and condensate processing unit is illustrated in Figure 8.20. 
 
Incoming  raw gas, condensation 
and  water  will  be  separated  on 
deck and after this processed to 
make  a  pipeline  able  product. 
After the separation the gas will 
be  compressed.  The 
condensates  will  be  after 
processing  evacuated  to  shore 
as  well.  The  acid  gas  CO2  will 
also  be  separated  from  the  gas 
and re‐injected into the ground. 
 
Next  to  gas  and  condensates, 
water  will  be  produced, 
separated  and  after  cleaning  it 
carefully,  dumped  overboard. 
Later  in  the  field  life  this  water 
can be used for water injection. 
 
Figure 8.20: gas and condensate processing unit 

49 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
There will be no H2S separation on the platform which means that H2S will be evacuated from the platform together with 
the  inhibitor  to  prevent  corrosion.  Like  almost  every  production  platform,  this  platform  has  a  flare  structure  for  flaring 
excess gas.  
The power unit on the platform provides electric and hydraulic power. In cause of emergency or maintenance an extra 
generator provides the necessary power to control all the processes.  
With  the  QUE$TOR  program  the  weight  of  each  topside  equipment  of  the  platform  can  be  calculated  and  rough 
estimations are made. In Table 8.2 and Table 8.3 the weights of the units are listed. 
 
Table 8.2: Weight of Topside Equipment  Table 8.3: Total Topside Weight of the Scenario 
 

Equipment   (in tons) 
Fabrication details  (in tons) 
Manifolding  450 
Primary steel  2900 
Condensate separation  550 
Secondary steel  2600 
Gas processing  500 
Equipment  2300 
Gas compression  150 
Piping  800 
Gas injection  30 
Electrical  150 
Control and 
communications   10  Instruments  110 
Helideck   30  Others  140 
Utilities   300  Total Topside weight  9000 
Flare structure  80 
Power   100 
Others  100 
Total  topside  equipment 
weight   2300 

 
The  total  topside  weight  consist  of  all  the  steel  that  is  necessary,  equipment  for  separating  the  water,  gas  and 
condensates,  piping  to  connect  the  units  with  each  other,  electrical  units  and  finally  all  the  instruments  to  control  the 
different  units.  The  weights  of  the  non‐processing  units  are  included  as  well.  The  weight  of  the  equipment  is  more 
detailed in upper table. See Table 8.3 for the weights.  

8.3. Structure 
8.3.1. Jacket 
For a safe and reliable design the minimal height of the platform above sea level should be calculated. How this is done 
can be seen in Table 8.4 below. The different values are all taken for the maximum value in 100 years. The LAT is taken as 
250 m.  
 
Table 8.4: Deck Elevation 

Air Gap [m] 1.5


Wave Crest [m] 2.9
Storm Surge [m] 0.38
Tide [m] 4
+
Total Deck Elevation Above LAT [m] 8.78
LAT [m] 250
+
Total Height Structure [m] 258.78

50 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
The weight of the topside is 9000 mt as found in the previous part. For dimensions for the legs of the jacket a diameter of 
3 m with a D/t ratio of 40 is chosen, which results in steel thickness of 7.5 cm. These estimations are based on experience. 
To examine the dimensions of the legs of the structure, a buckling analysis is made. For this buckling analysis both topside 
weight and jacket weight are taken into account. For the jacket weight one third of the total weight is taken. Calculations 
can be found in Appendix IV.  
 
In the calculations, the legs of the jacket are taken as slender cylinders with the same diameter at top and bottom. For the 
final design, different diameters along the legs can be chosen. Also the D/t ratio could be varied. In this case the diameter 
at the top of the structure would be less, which would also have an impact on the load calculations

For a jacket structure there are different loads to take into account. The most important loads are given in Figure 8.21 and 
Table 8.5below. Calculations can be found in Appendix IV. 
Topside weight Table 8.5: Loads on Jacket 

Wind
Topside weight [mt] 9.00E+03
Topside load [kN] 8.83E+07

Jacket weight [mt] 1.40E+04


Wave & current 
Jacket load [kN] 1.37E+08
loading Jacket 
Buoyancy & 
Current load [kN] 3.02E+03
Weight
Wave load [kN] 2.16E+04
Wave + Current  [kN] 2.46E+04

Wind load [kN] 6.66E+02  

 
Figure 8.21: Loads on Jacket 
 
The load from the jacket weight is determined by the total amount of steel. To make sure not only the steel of the legs, 
but all the steel is covered, a multiplying factor of 2.5 is chosen. This means that the weight of 4 legs is multiplied by 2.5.  
For the wave and current loads the Morrison equation is used. This equation consists of an inertial and a drag force part. A 
detailed  calculation  can  be  found  in  Appendix  IV.  The  estimation  of  the  equivalent  diameter  for  the  whole  structure  is 
taken as 5 times the diameter of one leg. For the wave load the structure is divided in 5 parts to get a more accurate load. 
For the current load, one calculation is made.  
Wind load calculations are based on the drag force for the area of one side of the topside. The load is calculated for a 
single area of 20x50m.  
 
Corrosion 
The field life is 45 years, so the structure should resist the environmental impact for 
this period. A steel structure in salt water is heavily exposed to corrosion, so this is a 
very important thing to take into account.  
To  protect  the  structure  against  this,  sacrificial  protection  is  used.  Aluminum  alloy 
anodes  will  be  used,  because  they  have  a  high  electrochemical  efficiency  and 
 
because they are light. Light parts are more easy, because they have to be replaced a 
Figure 8.22: Anodes on Jacket  number  of  times.  The  upper  part  of  the  structure,  at  the  sea  level  will  be  covered 
with a protective coating. An example of anodes is shown in Figure 8.22. 
 
 
 
 

51 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
8.4. Pipelines 
There are two single phase pipelines for gas and condensate.  One extra pipeline is provided to return the MEG (Mono 
Ethylene  Glycol)  from  onshore  plant  to  the  jacket.  The  reason  for  this  extra  piggy  back  on  the  pipeline  is  that  if  the 
required quantity of MEG as chemical inhibitor is quite high, then MEG recovery is a suitable option to decrease the costs. 
The  gas  and  condensate  pipelines  are  steel  pipes  with  concrete  protection  cover  layer.  MEG  pipeline  is  a  4  inch 
polypropylene pipe that will be bundle to the gas pipe, see Figure 8.23. 
The total offshore length of each pipeline is 63 km. The shore crossing is near Ras 
Laffan  port  that  is  an  industrial  area  and  it  is  close  to  the  Pearl  GTL  Plant,  LNG 
Plant  Q4  and  Laffan  condensate  refinery.  The  existing  onshore  pipelines  will  be 
used to transport the gas and condensates from the shore crossing point to their 
final destinations. As it is already mentioned, the gas delivery plan is 30% of raw 
gas  to  the  Pearl  GTL  plant,  70%  of  raw  gas  to  the  LNG  plant  Q4  and  100%  of 
condensate to the Laffan refinery. 
Calculation of pipelines is based on different conditions which are listed as below: 
1. 100% of peak production as maximum flow rate 
 
Figure 8.23: Piggy Back with MEG   2. 30% of peak production as minimum flow rate 
3. 50% of peak production as pigging time condition 
According to above mentioned conditions, some pipelines calculations are done. The results are summarized in Table 8.6. 
Details of the calculations are listed in Appendix IX. 
 
Table 8.6: Pipeline Characteristics 
  Gas pipeline    Condensate pipeline   
Item  Unit  Value  Unit  Value 
Maximum Flow rate  MMscf/d  1350  bbls/d  108000 
Maximum Flow rate  m3/s, standard condition  442  m3/s  0.2 
Pipe diameter  inch  36  inch  18 
Pipe length  m  63000  m  63000 
Input pressure  bar  125  bar  80 
Output pressure  bar  75  bar  34.4 
Flow velocity  m/s  1.6  m/s  1.2 
Wall thickness  mm  18  mm  10 
Pumping power  kW  1800  kW  1200 
 
Based  on  the  bathymetry,  geotechnical  data  and  the  shore  crossing  location,  the  pipeline  route  is  determined.  As  it  is 
shown in Figure 8.24, the pipeline won’t cross the concession 1 to avoid the steep slope and any interaction during the 
installation activities over there. Also, the pipeline reaches the shore location, Ras Laffan, by passing the area where the 
seabed  undulation  is  as  low  as  possible.  To  minimize  the  pressure  drop effects,  seabed  preparation is  performed.  Rock 
dumping is the best method to the prepare seabed for the pipelaying.  
 
 
 
‐  
 
 
 
 
 
 
 
 
 
 

Figure 8.24: Pipeline Route to Ras Laffan and in Concession 2 Itself

52 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
8.5. Execution Plan 
Fabrication,  transportation,  installation,  decommissioning  and  contracting  are  considered  as  execution  plan.  These 
categories have also impact on design of project. Therefore, interaction between design and execution should be kept in 
mind. According to design and execution specification, a time schedule for field development is provided.  

8.5.1. Fabrication & Transportation 
Fabrication methods and the transportation loads have significant influence on the design of the structures. Also, these 
issues play a main role in the project schedule. 
Fabrication  of  the  jacket  and  the  topside  is  possible  near  the  field,  for  instance  in  Dubai.  This  can  decrease  the  costs 
dramatically. In this case, transportation will be easier and less expensive than when the jacket and topside are fabricate 
far away. Some parts of the topside modules can only be fabricated outside the field area. After fabrication elsewhere, 
they are assembled in a fabrication yard to finally get integrated topside. Then, the topside will be transported to location 
by barge. 

8.5.2. Installation 
Jacket 
There are two methods for installation the jacket: lifting and launching. In this project, the total weight of the jacket is 
about 14,000 tonnes. For this weight, both lifting and launching is possible. Although existing lifting capacity is higher than 
14,000  tonnes,  there  are  just  a  few  contractors  who  can  lift  this  jacket.  To  decrease  dependency  on  these  companies, 
launch method is selected in this case. The Launch method sequences are shown in Figure 8.25. As a result, the design of 
the jacket will be affected by is installation method. The geometry of jacket, number of legs, transportation load and loads 
during launching are some of the effects of the installation on the design. 
 

Figure 8.25: Launch Method Sequences for the Installation of the Jacket, Samedan field, Mediterranean Sea 
 
Topside 
Lifting is the main method to install the topside. The topside weight 
and  the  capacity  of  the  lifting  vessel  play  the  biggest  roles  in  this 
system.  If  the  total  weight  is  higher  than  the  available  lifting 
capacity, topside should be built and transported in several modules. 
This  means  more  offshore  work  for  the  topside  installation. 
Otherwise,  it  is  possible  to  use  the  float  over  method  for  the 
topside  installation,  as  shown  in  Figure  8.26.  First,  all  topside 
facilities  are  built  at  an  onshore  yard.  Then,  the  topside  will  be 
installed almost as one module. In this case, the offshore activities 
for the topside installation are less than for lifting and installation of 
the  topside  in  separate  modules.  Consequently,  the  float  over 
method will be deployed for this project.  
   
Figure 8.26: Float Over Method to Install the Topside 
Soroush, South Pars field, Iran

53 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Risers 
The platform is a fixed structure, jacket; hence, steel rigid risers are used. The risers will be attached to jacket during the 
jacket fabrication. All the production risers, future risers and export line will be fabricated and connected to jacket before 
launching. A special piece will be needed to connect a vertical riser to a horizontal riser on the sea bed. There are extra 
risers on the jacket for future programs such as water injection wells. 
 
Pipelines 
The J‐lay method is more suitable for deeper water and is relatively more expensive in a water depth of 75 to 250 meters. 
The reel method is limited for pipe diameter less than 18 inches. Another limitation is fabrication of the required pipes 
that is usually done by a few companies.  
The S‐lay method meets all requirements in this field such as pipe diameter and the limited water depth near the coast. 
Therefore, S‐lay is used for the pipelaying in this case. 
Shore crossing is very important to connect the subsea and onshore pipeline. Pipe laying in shallow water and pulling the 
pipeline to shore are significant parameters in the pipelaying activities. 
 
Sea bed preparation 
According to bathymetry and seabed specifications, seabed preparation will be done before pipe laying. Rock dumping is 
the  common  technique  to  prepare  the  sea  bed  for  the  installation  of  the  pipeline.  Crossing  new  pipeline  and  existing 
pipeline needs more attention to avoid damage to the existing pipeline and new‐laid pipeline. 

8.5.3. Decommissioning 
Decommissioning of all structures and equipment is a part of the 
project lifecycle that should be taken into account. This can be a 
major criteria to design the structures.  
It  should  be  noted  that  decommissioning  methods  will  be 
improved in future, at the end of the field life: 50 years later. At 
that  time,  more  knowledge,  experience,  and  facilities  will  be 
available for removal of the structures.  
 
The  decommissioning  will,  probably,  be  done  in  the  following 
matter: 
• Jacket:  Split  in  several  parts  (underwater  cutting)  and 
then removed by a lifting vessel, as shown in Figure 8.27. 
• Topside:  removal in several modules by a lifting vessel 
• Pipelines:    Split    in  several  parts  (underwater  cutting) 
and then removed by a lifting vessel   
Figure 8.27: Removal of the Jacket by Cutting it in Several Parts 
• Subsea  system:  removal  of  all  subsea  equipment  by 
ROVs and lifting vessel 
• Wellhead:  removal of all production and injection wells by an FDU 

8.5.4. Contracting  
According to project specification, contract conditions, client visions, field area facilities and subcontractors availabilities, a 
contracting plan for major parts of the project is provided. This plan consists of 8 different packages as below: 
• Package 1:    Fabrication, transportation and installation of the jacket 
• Package 2:    Fabrication, transportation and installation of the topside 
• Package 3:             Drilling and completion 
• Package 4:   Supply of Subsea system  
• Package 5:  Subsea system installation 
• Package 6:   Sea bed preparation 
• Package 7:   Subsea pipelines and shore crossing 
• Package 8:  Onshore control and operating facilities 

54 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
8.5.5. Schedule 
Now,  the  field  development plan  is determined.  Based  on  this plan,  a  time  schedule  for  field  development  is provided, 
Table  8.7.  Each  task,  such  as  jacket,  consists  of  a  detailed  design,  material  supply,  fabrication,  transportation  and 
installation. As this table shows, the schedule consists of different phases of the project, from design till decommissioning. 
First gas is dated in the fifth year. To keep longer a plateau production, a second drilling phase will be started from the 8th 
year. The production profile will take 45 years. Then, abandonment will be done in years 51 and 52.   
 
Table 8.7: Field Development Time Schedule 
Time (year)
1 2 3 4 5 6 7 8 9 10 11 12 49 50 51 52

FEED study

Contracting

Jacket

Topside

Drilling, Phase I

Offshore pipelines
Onshore pipelines, 
Shore crossing

Commissioning

First Gas

Production, Operation

Drilling, Phase II

Subsea Systems

IMR

Decommissioning  
 
 
 
 
 
 
 
 
 

55 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

9. Economical 
9.1. Costs 
The cost estimation of the project has been done using the software programme QUE$TOR which is based on a database 
with existing projects. Some additional costs have been added such as onshore OPEX. In the following two tables, Table 
9.1 and Table 9.2, one can see what the main costs will be and how they are divided.  
The years in which the CAPEX and OPEX are spent is graphed in   
Figure 9.1. For most projects OPEX is spent after CAPEX, however since this development strategy has a second phase in 
which wells are drilled and subsea equipment, such as pumps, wellheads and risers, is needed after the first gas had been 
produced in phase 1, this is not the case.  
Table 9.1: The CAPEX 
CAPEX and OPEX
CAPEX Million $
CAPEX OPEX
Subsea equipment 98.62
Pipelines 352.73 1000.00

Topside 952.90 900.00

Structures 123.78 800.00

DRILLEX 1,190.00 700.00


Total 2,718.04   600.00
USD Million

  500.00

400.00
Table 9.2: The OPEX 
OPEX Million $ 300.00

Offshore 4,566.21 200.00

Onshore 454.38 100.00

Decommissioning 500.00 0.00


0 10 20 30 40 50
Total 5,520.59   Years
 
Figure 9.1: CAPEX and OPEX  
Due to the work over rate of four years, a peak can be seen every four years.  In year 8 the OPEX increases due to the 
installation of subsea equipment in phase 2. 

9.2. Revenues 
Total Revenues ($ MM)
The  revenues  have  been  calculated  and 
were  based  on  a  few  variables.  These  Total Revenues ($ MM)

variables are listed and explained below: 
• A  gas  price  of  4.5  $/MMBTU  is 
$5,000.0

$4,500.0
assumed,  this  is  also  the  base 
$4,000.0
estimate  of  the  gas  price.  The 
$3,500.0
low and high values are 4 and 5 
Total revenue ($ MM)

$3,000.0
$/MMBTU. 
$2,500.0
• A  condensate  price  of  80%  of  $2,000.0
the price of crude oil is selected.  $1,500.0
This  is  based  on  the  fact  that  $1,000.0
condensate has more limitations  $500.0
to  the  conversion  to  final  $0.0
products  than  crude  oil.  The  oil  0 10 20 30 40 50
Years
price  chosen  is  60$  per  barrel. 
 
Low  and  high estimates  are 40$  Figure 9.2: Total revenues 
and 80$ per barrel relatively.  
The  annual  production  of  gas  and  condensate  multiplied  by  their  prices  gives  the  annual  revenue.  This  revenue  of  the 
project before royalty and tax is graphed in Figure 9.2.  

56 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
9.3. Profit  Table 9.3: Economical Data 
The  NPV  and  cash  flows  calculated  for  scenario  1  are  based  on  the  input  Item value
described above and on the financial structure in Qatar:  NPV @12% (USD MM) $          3,940
• The  discount  rate  is  chosen  to  be  12%.  An  estimation  of  10%  is  a  VIR @12% 1.95
discount rate of projects of this size. An additional 2% is added for  UTC  @12% $            4.43
inflation.   IRR 42%  
• The payment of tax can and will be carried forward one year and is 
75%.  Table 9.4: key financial information 
• Depreciation is paid off in 5 years  Item $ Billion
• Royalty take is 20%.  Total Revenues $              91.78
  Total CAPEX $                2.72
With  the  CAPEX  and  OPEX  and  discount  rate  estimated,  and  the  legal  tax  Total OPEX $                5.52
system in Qatar known, a final conclusion to what the yearly cash flows will  Royalty $              18.36
be can be made. Under these conditions mentioned above, the NPV is $3.94  Total Depreciation $                2.63
billion and the IRR is 42%. The unit technical cost is 4.43$ per barrel and the  Tax $              49.33
Value  Investment Ratio (VIR)  is  1.95.  This  is  listed  in  Table  9.3.  In  Table  9.4  Pretax cashflow $              83.74
other key financial information is listed.   Post tax cash flow $              16.05
 
The graph below (Figure 9.3) shows financial results such as the cash flow for a discount rate of 0% and 12%, the post tax 
cash flow and the gas and condensate production per year.  

Post tax cash flow ($ MM) Cumulative cashflow 12% ($ MM)


cumulative cash flow ($ MM) Gas production field including condensate (MM scf)

$20,000.0 600,000.0

500,000.0
$15,000.0

400,000.0
$10,000.0
USD MM

MMscf

300,000.0
$5,000.0
200,000.0

$0.0
100,000.0
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52

-$5,000.0 0.0

year
 
Figure 9.3: Financial results 

In this figure one can also read off the pay‐out time of concession 2 by looking at the year the cumulative cash flow 
crosses the x‐axis, in this case this is after five years. It is quite unique that a project of this size has a breakeven point after 
one year of production. This has to do with the fact that in the first production year plateau production is reached, an 
therefore maximum revenue is generated, see   
Figure  9.2.  This  strategy  has  profitable  consequences  because 
Table 9.5: Tax and Royalty
money generated early has a high present value.   Item Percentage of revenue
  Royalty  20%
The project is based on a tax‐royalty contract. In Table 9.5 and  Total Capex  3%
Figure  9.4  below  show  this  distribution.  The  top  slice  of  the  Total Opex  6%
barrel is the profit the Shell Gas N’ Roses consortium generates;  Tax  54%
17%.  Post tax cash flow  17%  

57 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Profit based on royalty‐tax contract

Post tax cash flow ($ MM)

100% Tax ($ MM)
90%
80% Total Opex  ($ MM)
70%
60% Total Capex ($ MM)
50%
40% Royalty  ($ MM)
30%
20%
10%
0%
1

Figure 9.4: The distribution barrel 

9.4. Economical sensitivity analysis 
There  are  a  number  of  sensitivities  in  the  project  that  could  have  an  impact  on  the  financial  result.  By  altering  these 
variables a low mid and high estimation can be made. The variables are briefly listed below. Base variables are: 
• Error in calculation of recoverable gas and condensate 
• Discount rate: 12% 
• Oil price: 60$/barrel (condensate price of 0.8 x 60 = 48 $/barrel) 
• Gas price: 4.5$/MMBTU 
• OPEX and CAPEX: 100% of value calculated in QUE$STOR. 
• Carry forward of tax: 1 year 
 
In the following page(s) these variables are altered to a low and high estimation in order to create different profitability 
grids.  
 
The most serious error that can be made in the calculations is the one for the recoverable gas and condensate. The low 
estimate for recoverable gas was calculated to be 6.27 Tscf. This is done by multiplying the low estimate of the GIIP by the 
recovery factor of 85%. This gives a decrease in recoverable gas of 49%. For further calculations see appendix I. The low 
estimate for recoverable condensate is calculated the same way and yields 502 MMbbls. High estimates for recoverable 
gas and condensate are 20.6 Tscf (+133%) and 1650 MMbbls respectively. Results of this error are listed in the following 
Table 9.6.  
Table 9.6: Error in gas and condensates calculations 
 
Error in recoverable gas and condensate 
This error is serious as can be seen in Table 9.6. In a low 
calculations
case scenario, the NPV decreases with 2.6 billion dollars, 
Low Mid High
the IRR drops down 18%, and the VIR goes down to 0.68. 
However, a higher recovery of gas and condensate yields  NPV ($MM) 1,371 3,940 6,844
an increase in NPV of 2.9 billion dollars, 9% in IRR and the  IRR (%) 24% 42% 51%
VIR increases to 3.23.  VIR 0.68 1.95 3.23  
 
 
Discount rate  Table 9.7: Changes in discount rate
The  base  discount  rate  of  12%  is  chosen.  Low  and  high  Discount rate
rates are 10% and 14% respectively. Results are listed in  10% 12% 14%
the following table, see Table 9.7.   NPV ($MM) 4,839 3,940 3,224
  IRR (%) 42% 42% 42%
The  NPV  and  VIR  change  dramatically  whereas  the  VIR 2.29 1.95 1.67
internal rate of return stays unchanged. Figure 9.5 shows 
graphically what the cumulative NPVs are for discounts at different rates. Rates taken are 0% and 12%, 17% because this is 
based on 15%, (a maximum rate for a project of this size), plus 2% for inflation and 42% because this is the IRR. 

58 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Oil price 
Even though this is a gas field, the oil price is an  Cumulative NVP's at different discount rates

important variable. If the gas is converted to GTL,  Discount rate of 0% Discount rate of 12% Discount rate of 17% Discount rate of 42%

20000
the  price  of  oil  is  very  relevant  because  a  GTL 
price  of  115%  of  the  crude  oil  price  can  be 
assumed.  The  condensate  price  is  linked  also  15000

directly to the oil price by a multiplication factor 
of  0.8.  The  oil  price  is  a  variable  that  is  hard  to  10000

USD MM
predict.  In  the  last  3  years we  have  seen a  high 
price  of  147  $/barrel  and  a  low  price  of  33  5000

$/barrel.  It  is  therefore  very  important  to  know 


what the economical result will be if the oil price  0
0 10 20 30 40 50

is  low  or  high.  40  $/barrel  is  selected  as  a  low 
price, 80 $/barrel is selected as a high price, see  ‐5000
Years

Table 9.8.   
Figure 9.5: Cumulative NPVs at different discount rates 
 
It can be seen that an increase of 33% to 80 dollars per barrel means an increase of NPV of 800 million dollars. The current 
oil price is 60$ per barrel, therefore this price is used in other financial calculations, however a higher oil price is likely. 
This  has  to  do  with  a  relatively  fixed  supply  (most  Table 9.8: Changes in condensate price 
countries  produce  at  near  100%  capacity)  and  an  Condensate price
increasing  demand.  Some  OPEC  countries  such  as  32 $/barrel 48 $/barrel 64 $/barrel
Venezuela  are  dependent  on  an  oil  price  o  85$  per 
NPV ($MM) 3,149 3,940 4,732
barrel. An increasing oil price of one dollar per year over 
IRR (%) 37% 42% 46%
the next 50 years, i.e. 60$ per barrel in 2009, 110$ per 
VIR 1.56 1.95 2.34
barrel in 2059, simulates this scenario. In this case, the 
Table 9.9: The condensate price after increasing the oil price 
NPV comes out to be 4,327 $ MM, the IRR is then 43% 
Condensate price
and the VIR is 2.14 as can be seen in Table 9.9. 
incr. oil price of 1 
  48 $/barrel
USD/ year
Gas price 
The  gas  will  be  brought  to  the  plants  in  gas  phase,  NPV ($MM) 3,940 4,327
therefore  for  Gas  N’  Roses  and  for  Shell  a  good  IRR (%) 42% 43%
estimation  of  the  gas  price  is  essential.  Low,  mid  and  VIR 1.95 2.14  
Table 9.10: Changes in gas price 
high prices are 4, 4.5 and 5 $/MMBTU. 
  Gas price
The  differences  are  not  as  large  as  for  an  increase  in  4 $/MMBTU 4.5 $/MMBTU 5 $/MMBTU
condensate  price.  The  reason  for  this  is  that  the  gas  NPV ($MM) 3,628 3,940 4,259
price is fixed, and therefore a big change in price is not  IRR (%) 40% 42% 43%
expected. This is also the reason a scenario in which gas  VIR 1.79 1.95 2.1  
prices rise is not calculated.   Table 9.11: Increasing of CAPEX and OPEX 
  5% increase in CAPEX and OPEX
CAPEX and OPEX  100% 105%
The  cost  estimations  done  by  QUE$TOR  are  not  NPV ($MM) 3,940 3,875
necessarily  100%  correct  but  can  come  out  up  to  5%  IRR (%) 42% 40%
higher. If this is the case, the NPV, IRR and VIR come out.  VIR 1.95 1.82  
  Table 9.12: Financial results after carrying forward the taxes 
Carry forward tax  Carry forward tax payment
Carrying  forward  the  taxes  one  year,  makes  a  big  1  year 2 years
difference in the financial result. If an agreement can be  NPV ($MM) 3,940 4,944
made  with  Qatar  to  carry  forward  tax  one  more  year, 
IRR (%) 42% 49%
NPV and IRR will improve significantly as can be seen in 
VIR 1.95 2.44
the next table. 
 
From practice this is usually a very tough negotiation and will probably come at a price. 
 

59 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
9.5. Maximum exposure 
It is important to know what the maximum exposure for a project of this size is. This maximum exposure is based on a 
combination of the most negative variables: 
o Recoverable gas and condensate are actually 49% lower 
o Discount rate is 17% 
o Condensate price is 32 $/bbl 
o Gas price is 4 $/MMBTU 
o CAPEX and OPEX come out to be 5% more expensive 
 
The highest possible profit estimation is based on the following variables. 
o Recoverable gas and condensate are actually +133% higher 
o Discount rate is 0% 
o Condensate price is 64 $/bbl 
o Gas price is 5 $/MMBTU 
o CAPEX and OPEX come out to be as calculated 
  Table 9.13: Highest possible profit estimation 
The carrying forward of tax to 2 years is not included as  Low Mid High
in  practice  this  is  hardly  ever  achieved.  The  results  are  NPV ($MM) 149 3,940 8,573
listed in Table 9.13. 
IRR 19% 42% 58%
 
VIR 0.08 1.95 4.05
Even in this unlikely scenario of all variables to come out 
lowest, the project will be profitable.  
 
It is also important to know what the biggest  Highest investment costs for Low, Mid and High cases of NPV's

negative cash flow in a year could be in order  Mid High Low

to  estimate  if  this  project  can  actually  be  8000

financed.  If  a  cash  flow  in  one  year  is  lower 


than what the enterprising company has in its  6000

cash position in that year, this project cannot 
4000
be executed. Also the last possible break even 
USD MM

year is important information. The cumulative  2000

cash  flows  in  a  low  and  mid  scenario  are 


calculated.   0
3 3.5 4 4.5 5 5.5 6 6.5 7
The first few years of the projects are plotted 
‐2000
below, see Figure 9.6. 
  ‐4000

The  conclusion  can  be  made  that  the  Years

maximum  negative  cash  flow  in  any  Figure 9.6: Highest investment costs 


reasonable scenario thinkable, would be $2.5 
billion in the 4th year, generated by the most profitable (high) scenario. The reason for this has to do with the time value of 
money. The discount rate in this scenario is taken as 0%. This means expenditures are relatively more expensive. However 
this scenario has the soonest break‐even point after 4.5 years. The last possible break‐even point is in the least profitable 
scenario (low) and is after 6.5 years. 
 
 
 
 
 
 

60 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

10. Conclusion 
The solution to develop concession 2 of the Zubara gas field is an unmanned jacket. This production platform will produce 
1,500  MMscf  of  gas  per  day,  together  with  120,000  bbls  of  condensates  per  day.  The  gas  will  be  extracted  from  the 
reservoir by using ten horizontal, one vertical and six deviated wells. The horizontal and vertical wells are located beneath 
the jacket and the deviated wells are clustered around a subsea manifold. To produce 85 % of the GIIP of 14.5 Tscf of gas, 
the field will have a production life of 45 years. 
 
The platform is unmanned to minimize the risk of human casualties. Other, more field related risks are the presence a high 
amount of H2S in the gas and sinkholes in the soil. The risk of corrosion caused by the high amount of H2S is dealt with by 
downhole chemical injection and the presence of sinkholes is dealt with by avoiding them during drilling and installing the 
jacket. 
 
To  maintain  a  high  enough  pressure  in  the  reservoir  to  keep  the  production  going  and  to  prevent  condensate  blocking 
near the wells, the produced CO2 is reinjected into the reservoir. Another advantage of CO2 injection is that the field will 
not raise the CO2 emission of Qatar, which is already too high according to the Kyoto protocol. 
 
Before  the  conversion  of  gas  to  any  product,  the  NPV  of  this  project  will  be  3,940  billion  USD  with  an  internal  rate  of 
return of 42%. In a worst case scenario, the maximum negative cash flow in a year will be $2.5 billion, but the project will 
still be profitable. 
 
If 70 % of the gas is delivered to the Pearl GTL plant, the remaining 30 % to the Q4 LNG plant and the condensates to the 
Laffan  Refinery,  all  located  in  Ras  Laffan.  The  total  pre‐tax  revenue  in  this  case  for  Shell  will  be  131.3  billion  dollars 
excluding CAPEX and OPEX.  

61 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Appendices 

62 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Appendix I 
GIIP/ CIIP Calculations 
 
Reservoir data: 
Reservoir depth:      8500‐9000 ft True Vertical Depth Subsea (TVDSS) 
Initial pressure:      6000 psia 
Reservoir thickness:     1300 – 1500 ft 
Temperature at reservoir depth:  260°F 
Permeability:       10 – 500 mD 
Porosity:       8 – 15 %, with an average of 10%. 
Gas saturation:       85 – 90 % 
Recovery factor:      85 % 
Gravity of the gas:     0.81 relative to air. 
H2S amount:       1 – 5 % 
Condensate – Gas Ratio (CGR):   65 bbls/MMscf. 
 
 
Formulas:  
 
 
 
 
6°  
 
 
N 1
  GIIP = GRV ⋅ ⋅ n ⋅ Sgas ⋅
  G Bg
 
CIIP = GIIP ⋅ CGR
 
GIIP =   Gas Initially In Place [Tscf] 
GRV =   Gross Rock Volume [m3] 
N/G =   The net to gross ratio: Thickness of productive (net) reservoir rock within the total (gross) reservoir thickness [‐] 
n =   Porosity [‐] 
Sgas =   Saturation of Gas 
Bg =   Volume of gas at reservoir temperature and pressure / Volume of gas at surface conditions.  
 

Low Mid High


GIIP [Tscf] 7.38 14.48 24.27
CIIP [MMbbls] 590.50 1158.59 1941.41

Recoverable gas [Tscf] 6.27 12.31 20.63


Recoverable condensate [MMbbls] 501.93 984.80 1,650.20   
Table 0.1: Final recoverable gas/ condensate 
 

63 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Low Mid High
Height layer [ft] 1300 1400 1500
Radius [ft] 20310 20310 20310
Base (big circle) [ft2] 1.296E+09 1.296E+09 1.296E+09
Base (small circle) [ft2] 1.947E+08 1.503E+08 1.116E+08
Top big cone [ft] 2.135E+03 2.135E+03 2.135E+03
Top small cone [ft] 8.275E+02 7.270E+02 6.264E+02
Big cone [ft3] 9.221E+11 9.221E+11 9.221E+11
Small cone [ft3] 5.372E+10 3.642E+10 2.330E+10

GRV [ft3] 8.684E+11 8.857E+11 8.988E+11

GRV [rcf] 8.684E+11 8.857E+11 8.988E+11


N/G [‐] 0.5 0.6 0.8
n [‐] 0.08 0.1 0.15
S_gas [‐] 0.85 0.875 0.9
Bg [rcf/scf] 0.004 0.004 0.004

GIIP  [scf] 7.381E+12 1.162E+13 2.427E+13


CIIP  [bbls] 4.798E+08 7.556E+08 1.577E+09

GIIP  [Tscf] 7.38 11.62 24.27


Recoverable gas [Tscf] 6.27 9.88 20.63
Recoverable condensate [MMbbls] 407.82 642.26 1,340.79  
Table 0.2: First estimation of GIIP/ CIIP 
 
The calculations on the gas field are based one the outer layer of a cone. The radius is chosen as 20310 ft, to get an equal 
base area for the circle, compared to the area of the real square area.  
 
The most uncertain parameters in this calculation are N/G ratio and porosity. To get a better estimation than the first mid 
estimation, these parameters are differed. The net to gross ratio is taken from 0.5 to 0.8, the porosity from .08 to 0.15. 
Both  parameters  were  differed  and  afterwards  combined,  as  can  be  seen  in  Table  0.3.  Figure  0.1  shows  a  chart  of  this 
table, for the gas recovery. The average outcomes are taken as the estimation for final mid GIPP and CIPP.  

Recovery Gas probability 

120%
100%
80%
Probability

60%
40%
20%
0%
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Recovery gas (Tscf)
 
Figure 0.1: Recovery Gas Probability 

64 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
N/G n GIIP [MMscf] REC. GAS [Tscf] REC.COND. [MMbbls]
0.5 0.08 7,749,735 6.6 428
0.5 0.09 8,718,452 7.4 482
0.5 0.1 9,687,169 8.2 535
0.5 0.11 10,655,886 9.1 589
0.5 0.12 11,624,603 9.9 642
0.5 0.13 12,593,319 10.7 696
0.5 0.14 13,562,036 11.5 749
0.5 0.15 14,530,753 12.4 803
0.55 0.08 8,524,709 7.2 471
0.55 0.09 9,590,297 8.2 530
0.55 0.1 10,655,886 9.1 589
0.55 0.11 11,721,474 10.0 648
0.55 0.12 12,787,063 10.9 706
0.55 0.13 13,852,651 11.8 765
0.55 0.14 14,918,240 12.7 824
0.55 0.15 15,983,828 13.6 883
0.6 0.08 9,299,682 7.9 514
0.6 0.09 10,462,142 8.9 578
0.6 0.1 11,624,603 9.9 642
0.6 0.11 12,787,063 10.9 706
0.6 0.12 13,949,523 11.9 771
0.6 0.13 15,111,983 12.8 835
0.6 0.14 16,274,444 13.8 899
0.6 0.15 17,436,904 14.8 963
0.65 0.08 10,074,656 8.6 557
0.65 0.09 11,333,987 9.6 626
0.65 0.1 12,593,319 10.7 696
0.65 0.11 13,852,651 11.8 765
0.65 0.12 15,111,983 12.8 835
0.65 0.13 16,371,315 13.9 905
0.65 0.14 17,630,647 15.0 974
0.65 0.15 18,889,979 16.1 1,044
0.7 0.08 10,849,629 9.2 599
0.7 0.09 12,205,833 10.4 674
0.7 0.1 13,562,036 11.5 749
0.7 0.11 14,918,240 12.7 824
0.7 0.12 16,274,444 13.8 899
0.7 0.13 17,630,647 15.0 974
0.7 0.14 18,986,851 16.1 1,049
0.7 0.15 20,343,054 17.3 1,124
0.75 0.08 11,624,603 9.9 642
0.75 0.09 13,077,678 11.1 723
0.75 0.1 14,530,753 12.4 803
0.75 0.11 15,983,828 13.6 883
0.75 0.12 17,436,904 14.8 963
0.75 0.13 18,889,979 16.1 1,044
0.75 0.14 20,343,054 17.3 1,124
0.75 0.15 21,796,130 18.5 1,204
0.8 0.08 12,399,576 10.5 685
0.8 0.09 13,949,523 11.9 771
0.8 0.1 15,499,470 13.2 856
0.8 0.11 17,049,417 14.5 942
0.8 0.12 18,599,364 15.8 1,028
0.8 0.13 20,149,311 17.1 1,113
0.8 0.14 21,699,258 18.4 1,199
0.8 0.15 23,249,205 19.8 1,285
AVERAGE: 14,482,317.3 12.3 800.1  
Table 0.3: Estimation recoverable gas/ condensate 

65 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Appendix II 
Building Blocks 
Structure 
The  structures  that  are  looked  at  will  briefly  be  explained  below.  They  are  listed  from  being  used  in  shallow  to  deeper 
water. 
• Jacket: 
A jacket, being bottom founded, is used in shallow water up to 300 m.  
Advantages are that jackets: can support large deck loads, can be constructed in sections and are able to support 
a  large  number  of  wells.  Disadvantages  are  there  are  high  initial  and  maintenance  costs  and  a  jacket  is  not 
reusable. 
A project specific advantage is that a fabrication contractor can easily be found in the Qatar area. 
• Gravity Base Structure (GBS): 
GBSs  are  constructed  of  steel  reinforced  concrete,  often  with  tanks  or  cells  which  can  be  used  to  control  the 
buoyancy of the finished GBS. When completed, GBSs are towed to their intended location and sunk.  
A project specific disadvantage is that GBSs need a high water depth for construction which is not available at the 
Qatar coast. A advantage is that there is enough concrete in the area to be able to construct this type of structure. 
• Compliant Tower:  
As well as a jacket, a tower is bottom founded but is used in deeper water, up to 900 meter. Because the water 
depth at concession 2 is only 250 meters, using a compliant tower may not be possible. 
• FPSO: 
An FPSO has different abilities than bottom founded structures. They are maneuverable and can be new built or 
made of a converted oil tanker, but they can also be leased. Advantages of FPSOs are that there is an earlier cash 
flow  because  they  are  faster  to  develop  than  fixed  platforms  and  they  retain  their  value  because  they  can  be 
relocated to other fields.  
As FPSOs have a lot of deck space this can be a solution if the oil or gas from the field needs to be processed and 
separated offshore. FPSOs can be used for storage of oil, and therefore it can be used in remote area so that no 
pipeline is needed. A project specific disadvantage is that much more gas than condensates are produced which 
makes storage of oil not so very important. 
• TLP: 
A  Tension  Leg  Platform  is  used  in  a  water  depth  of  up  to  1500  meters.  By  having  a  taut  mooring  system,  the 
heave is minimized and therefore it can make use of dry trees, making IMR operations easier. TLPs are relatively 
expensive, especially in shallower water.  
• Semi submersible: 
Semisubmersibles  are  also  floating  structures  and  can  be  used  in  very  deep  waters  and  they  can  be  equipped 
with a drilling derrick. Compared to other floating structures, semisubmersibles have higher transit speeds and 
large deck areas. They are also very stable, but not as stable as spars and TLPs. And because they don’t need to 
weathervane like FPSOs, they can support a large number of flexible risers. 
Disadvantages of semisubmersibles are the high initial and operational costs and the deck load being limited. The 
motions, whilst considerably smaller than those of a ship‐shaped structure, are too large to permit rigid risers. 
As  well  as  for  an  FPSO  and  a  TLP,  a  semisubmersible  has  the  advantage  of  not  being  bottom  founded.  This 
eliminates the problem of have to deal with weak soil conditions such as sinkholes. 
• Subsea production equipment: 
Subsea  equipment,  being  the  most  expensive  option,  can  be  used  up  to  2700  meters  water  depth.  The 
equipment however depends strongly on the water depth due to the surrounding pressure. Subsea equipment is 
quite  advanced  nowadays  making  it  possible  to  even  process  the  gas  or  oil  on  the  sea  bottom.  The  biggest 
advantage of using only subsea equipment is the fact that during operation no people are needed offshore. 
• A spar, SEVAN FPSO and a jack‐up structure are also options but are not considered too seriously. A spar in a field 
with a water depth of only 250 meters is unlikely to be economically feasible. A jack‐up is usually used for drilling 
or for the production of smaller fields for a shorter period of time and in shallower water. As a SEVAN is mostly 
used for oil storage, and only a limited amount of condensate is produced, a SEVAN is not likely to be used for the 
development of this concession. 

66 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Process/topside 
• Onshore: 
The  biggest  advantage  of  onshore  processing  that  there  is  lot  of  space  and  therefore  it  is  a  lot  cheaper  than 
offshore. A disadvantage of onshore treatment is that toxic gas could corrode the pipelines, therefore making the 
pipelines more expensive due to coating, inserting inhibitors offshore, etc. 
• Offshore: 
The advantage of offshore processing is that toxic components can be taken out of the gas before transporting it 
to  shore.  By  making  use  of  offshore  phase  separation,  the  destination  of  gas  and  condensate  can  differ.  The 
condensates can, for example, be transported to another platform in the neighborhood. This can be turned into 
an advantage. The biggest disadvantage of offshore processing is the cost and safety of the personnel. By taking 
toxic components out of the gas, corrosion of the pipelines can be reduced. 
• Subsea: 
Risks of hazards are reduced to a minimum because a collision with a ship is practically impossible and also the 
chance of human casualties is very small. However, subsea processing is expensive because all the treatment is 
being done on the bottom of the Gulf. 
 
Subsea equipment  
• Clustered manifold: 
When using manifolds, all wells are arranged around a manifold and connected to that manifold using jumpers. 
The manifold regulates the flow of all wells using chokes and valves. 
Advantages  of  this  clustered  manifold  arrangement  are  that  the  number  and  location  of  wells  is  flexible  and 
appraisal wells can be tied in. Also the access and IMR opportunity are good.  
Disadvantages are that the wells are not located closely together and not very well protected against dropped 
objects. 
• Template: 
Templates control, just as with clustered manifolds, the flow of all the wells. But the difference with a clustered 
manifold is that all wells are located inside the template. In this way the wells are very well protected and close 
together. 
Disadvantages  of  templates  are  the  complexity  due  to  number  of  components  and  contractor  interfaces,  the 
restricted  access  to  the  central  manifold  and  tree  faces  and  a  heavy  lift  vessel  being  required  for  both  the 
installation and decommissioning. 
• Individual: 
All  wells  are  individually  connected  to  the  structure  at  the  waterline.  This  requires  a  riser  per  well  which  can 
result in very much risers being connected to the structure. Also will it be very expensive to process and regulate 
the flow subsea because this means all wells will need chokes, valves and control modules with an umbilical per 
well. 
• None: 
All  wells  are  connected  to  the  structure  without  subsea  trees  and  processing.  This  option  is  only  available  for 
fixed structures, TLPs and spars because all other structures have too much heave motions. 
A disadvantage of no subsea control is that if something goes wrong, it goes wrong at the topside which can harm 
people.  
 

67 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Drilling 
• Vertical drilling: 
It is the cheapest option as no expensive directional drilling heads are needed. A serious disadvantage of vertical 
drilling is the limited length of reservoir that is reached per well, which will make a lot of wells necessary. A lot of 
wells means very big templates/manifolds or a lot of risers. 
• Deviated drilling 
Deviated drilling is drilling under an angle with the vertical. 
This method can be applied to increase the production of one well. A well at an angle will produce more as it has 
more length in the reservoir than with vertical drilling. For a large field, multiple drilling centers are needed in 
order to extract as much gas as possible. 
• Horizontal drilling 
Horizontal drilling had the disadvantage that the field depth cannot be too small. Since the maximum deviation 
angle is approximately 4 degrees per 100 feet, the minimum required depth will be: 
90 ⋅ 100 = 2250 ft. 
4
For  concession  2,  the  reservoir  depth  is  a  lot  deeper  than  2250  ft  so  horizontal  drilling  is  certainly  an  option. 
Horizontal  drilling  has  the  advantage  that  from  one  drilling  centre  a  much  wider  area,  than  using  only  vertical 
wells, can be reached. 
 
Gas transportation 
• Single phase flow: 
An advantage of single phase flow is that pressure, temperature, the effect of inhibitors and such, in single phase 
flow  are  better  controllable.  Also  by  choosing  for  single  phase  flow  the  gas  and  the  condensate  could  have 
different destinations. However, by using single phase flow, an offshore separation plant is needed, and possibly 
also two separate pipelines. 
• Multiphase flow: 
Only  one  pipeline  is  needed,  which  means  less  separation  equipment  is  necessary  offshore.  However  the 
pressure drop is substantially greater than with single phase flow, meaning that the pump capacity will need to 
be higher than for single phase flow. 

68 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Appendix III 
Calculation Production per Day and per Well 

Concession 2
Low Mid High BEST
Recoverable gas [Tscf]                6.27                9.88              20.63               12.31
Recoverable condensates [MMbbls]            501.93            790.47        1,650.20             984.80

Production per day during peak production years
Low Mid High BEST
GIIP [MMscf]             773.52          1,218.19        2,543.12        1,517.67
CIIP [bbls]        61,881.38        97,455.53    203,449.24    121,413.40

Total production per day [MMscf/day]                     1,500.00

Scenario 1 Kind of wells Total Production Number of wells Production per well


Horizontal                     1,415.00     9.826                               144.00
1 Vertical                           85.00             1 85

Scenario 2 Kind of wells Total Production Number of wells Production per well


Vertical                     1,500.00                             17                                  88.24

Scenario 3 Kind of wells Total Production Number of wells Production per well


Deviated                     1,500.00                             13                               120.00

Type of well Length Production


Vertical well 1400.0 85.0 according to nearby well log
Horizontal well 5000.0 144.5 1.7 * production vertical well
Deviated well (30°) 1616.6 120.0 according to nearby well log

69 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Appendix IV 
Calculation of Dimensions of and Loads on Jacket 
 
Dimensions 
Buckling analysis for Jacket Leg
Topside weight [mt] 9000
Jacket weight [mt] 1.40E+04
Height structure [m] 258.78
Number of legs [‐] 4
Diameter legs [m] 3
D/t legs [‐] 40
E steel [Pa] 2.10E+11
Density steel [kg/m3] 7.85E+03
K [‐] 0.5

Wall thickness [m] 0.075


r out [m] 1.5
r in [m] 1.425
I [m4] 7.38E‐01
Critical Force [N] 9.13E+07

Force Topside [N] 8.83E+07


Max Force Jacket [N] 4.58E+07
Max Force [N] 1.34E+08
Max Force on each leg [N] 3.35E+07

Calculations for weight of Jacket
Steel For 1 Leg [m3] 1.78E+02
Steel For 1 Leg [kg] 1.40E+06
Steel 4 Legs [mt] 5.60E+03
Total Steel Jacket [mt] 1.40E+04
 

Wind 
Rho [kg/m3] 1.293
Wind speed [m/s] 26.2
Area [m2] 1000
Drag coefficient [‐] 1.5

Fd [N] 665675.2
Fd [kN] 665.7  

70 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Waves 
Block 1 Block 2 Block 3 Block 4 Block 5 Total
Diameter of the (circular) member at point (x,y,z) D [m] 15.00 15.00 15.00 15.00 15.00
Significant Wave Height  Hs [m] 5.80 5.80 5.80 5.80 5.80
Zero‐crossing wave period Tz [s] 11.00 11.00 11.00 11.00 11.00
2π / T ω [rad/s] 0.57 0.57 0.57 0.57 0.57

1.56 * T^2 λ 188.76 188.76 188.76 188.76 188.76


2π / λ k [rad/s] 0.03 0.03 0.03 0.03 0.03

Location z [m] 0.00 ‐50.00 ‐100.00 ‐150.00 ‐200.00


water depth h [m] 50.00 50.00 50.00 50.00 50.00
mass density of water rho [kg/m3] 1025.00 1025.00 1025.00 1025.00 1025.00

Horizontal velocity component ω * H/2 * e^kz u(t) [m/s] 1.66 0.31 0.06 0.01 0.00


Horizontal acceleration component ω * u(t) u'(t) [m/s2] 0.95 0.18 0.03 0.01 0.00

Keulegan Carpenter Number  u(t) * T / D KC 1.21 0.23 0.04 0.01 0.00


Keulegan Carpenter Number  π * H/D KC [‐] 1.21 1.21 1.21 1.21 1.21
Roughness 1/1000 1/1000 1/1000 1/1000 1/1000

Inertia coefficient Cm [‐] 1.90 2.00 2.00 2.00 2.00


Drag coefficient Cd [‐] 1.20 1.20 1.20 1.20 1.20

inertial force per unit length at point (x,y,z)   π/4 * rho * Cm * D^2 * u'(t) dFi [N/m] 325628.37 64891.61 12285.09 2325.78 440.31


drag force per unit length at point (x,y,z) 1/2 * rho * Cd * D * u(t)|u(t)| dFd [N/m] 25312.60 907.23 32.52 1.17 0.04
Force per unit length of cylinder (N/m) dFi + dFd dFmax [N/m] 350940.97 65798.83 12317.61 2326.94 440.35
dFmax * h Fmax [kN] 17547.05 3289.94 615.88 116.35 22.02 21591.24  
 

Block 1
50 m
Block 2
50 m
Block 3
50 m
Block 4
50 m
Block 5
50 m

 
 
 
Current 
Diameter of the (circular) member at point (x,y,z) D [m] 15.00
Significant Wave Height  Hs [m] 5.80
water depth h [m] 250.00
mass density of water rho [kg/m3] 1025.00
Total velocity vector U [m/s] 1.15
Cone angle between U and cylinder axis k rad 1.47

Keulegan Carpenter Number  π * H/D KC [‐] 1.21


Roughness 1/1000
Drag coefficient Cd [‐] 1.20

Current force per unit length at point (x,y,z) 1/2 * rho * Cd * D * U^2*sin2(k) dFc [N/m] 12076.53


Fc [kN] 3019.13  

71 
OE4652 exercise EXAMPLE input orange g = 9.81 m/s2
Appendix V 

try/error blue sg water 1.025 t/m3


INPUTS result black

Floaters Columns Deck


number 2 number  6 area 6300 m2 min deck area 4000
length 110 m height 20 m length 90 m ok
width 16 m diameter 0m width 70.00 m 
depth 8m length 10 m depth 7 m
width 10 m airgap 12 m column draft 8
spec grav 2 kN/m3 spec grav 2 kN/m3 min airgap 12 m max draft 16
spacing 62 m spec grav 1.5 kN/m3
advies sp. 60.00 m Behaviour
Components unit mass/weightz cog ref for cog Tn heave 18 s
Calculation Semisubmersible 

drlling sys mt 0 6 upper deck Tc heave s


variable load mt 12000 4 upper deck Ca, added m 1
anchor pull kN 2000 0 floater deck GM min 0.5 m
transition GM min 0.1 m

Weights weight Buoyancy operational Stability at operational draft


kiloNewtons z COG moment tonnes weight z COB moment draft 16 m4 spacing  plus eigen
floaters 56320 4 225280 5741 283155.84 4 1132623.4 WL inertia 581600 m4 transverse is 576600 plus 5000
Zubara Gas Field Development Plan, Concession 2 

columns 24000 18 432000 2446 48265.2 12 579182.4 MB 17.645631


deck 66150 31.5 2083725 6743 0 BK 5.17
drilling sys 0 41 0 0 0 KG 22.27
variable load  117720 39 4591080 12000 0 GM 0.541 excl free surface
anchor pull 2000 8 16000 204 0 WL inertia 965000 m4 longitudinal, based on not extending beyond deck and 4 columns
ballast 65231 0.5 32615.52 6649 0 MB 29.277913
Total 331421 22.27 7380700.52 33784 331421.04 5.17 1711805.8 BK 5.17
Light disp 148470 volume 32960 m3 GM 12.17 excl free surface
mass 33784 tonnes Vol floaters 28160
Checks : ballast volume less than floater volume ok Awl 600 m2 28160
transverse GM over  0.5 m  ok Theave 21.03 sec w0 0.2988144
longitudinal GM over  0.5 m ok Tc FK 13.13 sec wc 0.4787049 kc 0.0233597
transition GM over  0.1 m ok Tc vSanten 19.85 sec wc 0.3166045 kc 0.010218 0.0119749 0.0103728 0.0118337 0.0105015 0.0117163
draft 16 m  Tc gemengd 19.01 sec wc 0.3305587 exp() 1.0417187 1.0490652 1.0423639 1.048473 1.0429007
0.0111738 0.0111032 0.0111676 0.0111089
Loading at transition Stability at transition 0.0111385 0.0111354 0.0111383
Disp 283155.84 4.0 1132623.36 Volume 28160 m3
floaters 56320 4 225280 WL inertia 581600 m4
columns 24000 18.0 432000 MB 20.653409
deck 66150 31.5 2083725 BK 4.00
drilling sys 0 41.0 0 KG 9.92
GM 14.73
variable load  0 39.0 0
anchor pull 0 8.0 0
ballast 136686 0.5 68342.92 13933.317

72 
May 2009
           
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Appendix VI.A 
HAZID Scenario 1 
Hazard Identification for Zubara Gas Field, Scenario 1
RISK REDUCING  POTENTIAL  RISK 
ID AREA/SUBJECT HAZARD POTENTIAL CAUSES FOLLOW UP/ACTION COMMENTS
MEASURES CONSEQUENCES CLASSIFICATION
A.1 A.process plant/deck Explosion Ignition of gas leak Ignition source control, electrical  Explosion load inside process  Design for explosion scenarios. Ensure that there will be  3
equipment in Plant plant. External explosion load  no activities in the 
on LQ. process plant that causes 
sparkes during normal 
operation.
A.2 A.process plant/deck Fire  Ignition of gas leak Fire detection. Deluge system Exposure of compact flange  Consider shut down and  3
which may rupture. blowdown philosophy of process 
area.

A.3 A.process plant/deck Dropped objects Failure during lifting  Procedure for maintanace of  This should be considered in  2


operations when doing  process plant and lifting  material handleing procedures
maintenance  activities

A.4 A.process plant/deck Crane operation above movement of crane protecting structure and lift  possibility to damage the pipe  protecting structure and lift  2


operation restrictions and vessels. Gas leak. operation restrictions to be 
evaluated.

A.5 A.process plant/deck Flare Failure Fire in area close to flare  flare boom may tip over Evalute the passive fire  3


boom protection of lower part of flare 

A.6 A.process plant/deck Condensate leak  from valves, flanges,etc reduce the number of valvec  3


and flanges/ control the flange 
and valves during operation 
continiousely

A.7 A.process plant/deck fire and explosion fire and explosion in  make distance between different  This may cause failure of  Extremely important to keep  3


different process modules modules/ keep distance  process plant process module away of LQ.
between deck and process 
modules elavation

A.8 A.process plant/deck gas leak gas leak from process  flammable gas clouds may  Fire and explosion scenarios  3


modules,valves,flanges occure. If ignited, fire and  have to be evaluated. 
explosion will occure.

A.9 A.process plant/deck loss of electrical power and  fire fire resistance and redundant  2


signal cables are planned to be used.

B.1 B.Power Generation gas leak flanges,valves pipe in pipe solution provided  Confirmed gas in  two separate engine  2


for fuel gas inside hull. Inert gas  HVAC/combusion air intake must  room
with gas detection installed in  lead to shut down.
room between two pipes.

B.2 B.Power Generation Gas leak from fuel Gas detection system gas may ignite.will result in a  2


 gas supply in open air small local fire

B.2 B.Power Generation fire in the generator fire in electrical total flooding fire extinguisher  Define emergency power  Important that the power  1


 equipment system consumers, and make sure that  source is available for the 
there are sufficient power supply  fire water pumps.
during emergency situations.

C.1 C.Drilling Unit Shallow water flow Sands  SWF sands can flow out of  Seismic data Analysis,   cause severe drilling problems Seismic data Analysis,   when pore pressure in  2


(SWF) the formation, into the  unconsolidated sands is 
borehole high enough to suspend 
the grains so that rock 
strength diminishes.

C.2 C.Drilling Unit Fault and fractures Techtonic structure Geology and seismic study cause severe drilling problems Drilling through these hazards  2


should be avoided if possible, or 
if relocation is not an option, 
appropriate mitigating measures 
taken.

73 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Hazard Identification for Zubara Gas Field, Scenario 1
RISK REDUCING  POTENTIAL  RISK 
ID AREA/SUBJECT HAZARD POTENTIAL CAUSES FOLLOW UP/ACTION COMMENTS
MEASURES CONSEQUENCES CLASSIFICATION
D.1 D.Helideck helicopter crash Unfavorable location of  Injuries,fatalities, damage to  location of helideck must fulfill all  3
helideck. Difficult weather  topside and Jacket regulations for helideck.
conditions

E.1 E.Reservoir/well  collapse of well wall Mud composition/pressure,  Control and adjust the mud  loss of the well, sever problem  Use deviated drilling 2


shallow water flow compsition  for drilling

E.2 E.Reservoir/well Sink hole geology structures geology  study loss of the well, sever problem  Change the drilling location or  2


for drilling use deviated drilling to avoid the 
hazrdous area

E.3 E.Reservoir/well Change in gas composition reservoir property measerment the gas  Different processing/ it may  Adjust the process procedure  2


composition continuously make problem for high H2S  according to gas composition, 
content/ Different production  define suitable scenarios based 
rate for gas and condensate on different gas composition 

E.4 E.Reservoir/well Gas migration reservoir property measerment the reservoir  decrease the recovery factor,  Adjust the production rate 2


property, Control the migration  problems for drilling
during drilling activities

F.1 F.Risers/pipeline Riser leak/rupture risers failure/  Inspection, suitable material  gas leakage , air /water  Inspection the risers 2


corrosion/fatigue selection, gas detection pollution, fire/ explosion

F.2 F.Risers/pipeline flow assuranse gas composition Measermentgas composition,  Blocked the risers, pipeline Start up/ shut down procedures,  2


insulation, pigging chemical inhibitor injection

F.3 F.Risers/pipeline Corrosion due to H2S H2S in gas composition Measerment H2S content, Use  Corrosion in pipeline Use suitable material for pipeline,  1


suitable material for pipeline,  inhibitor injection, offshore 
inhibitor injection desulfurization

G.1 G.GeoHazard Active Faulting Underground activities Geology and seismic study Problem for pipeline, Drilling  Change the drilling location, and  3


string,foundation pile, Jacket  pipeline path/ Calculate the 
due to earthquake probability of earthquake 

G.2 G.GeoHazard landslide Dredging, earthquake Field investigation Loss of pipeline, Jackect failure Change the location of  2


jacket,Change the pipeline path 

G.3 G.GeoHazard coral damage Environment  Field investigation Problem for pipeline and risers Change the pipeline path 1

H.1 H.Other Hazards Politic issues political issues Be aware about politic issues,  May cancel the project Negotiation with Qatar  4


good relation with government  government  and  other countries 
which have influence on project

H.2 H.Other Hazards terrorist attack political issues Be aware about politic issues,  may lead to severe  Negotiation with Qatar  3


good relation with government  consequence government , local group and 
international organizations

H.3 H.Other Hazards Fatigue Frequent load on structure  Condider fatigue problem in  structural Failure  Inspection to prevent fatigue  1


e.g. waves design, Inspection of structure  problem
especially connection

H.4 H.Other Hazards structural failur/equipment  Sever environment Define suitable specifications for  large load on deck, damage to  Check different design scenarion.  2


damage materials/ equipments in design  process module and  Select proper material/ 
documents piping/equipment on deck equipments

74 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Appendix VI.B 
HAZID Scenario 2 

Hazard Identification for Zubara Gas Field, Scenario 2


RISK REDUCING  POTENTIAL  RISK 
ID AREA/SUBJECT HAZARD POTENTIAL CAUSES FOLLOW UP/ACTION COMMENTS
MEASURES CONSEQUENCES CLASSIFICATION
A.process plant/deck Explosion Ignition of gas leak Ignition source control, electrical  Explosion load inside process  Design for explosion scenarios. Ensure that there will be  3
equipment in Plant plant. External explosion load  no activities in the 
on LQ. process plant that causes 
sparkes during normal 
A.1 operation.
A.process plant/deck Fire  Ignition of gas leak Fire detection. Deluge system Exposure of compact flange  Consider shut down and  3
which may rupture. blowdown philosophy of process 
area.

A.2
A.process plant/deck Dropped objects Failure during lifting  Procedure for maintanace of  This should be considered in  2
operations when doing  process plant and lifting  material handleing procedures
maintenance  activities

A.3
A.process plant/deck Crane operation above movement of crane protecting structure and lift  possibility to damage the pipe  protecting structure and lift  2
operation restrictions and vessels. Gas leak. operation restrictions to be 
evaluated.

A.4
A.process plant/deck Flare Failure Fire in area close to flare  flare boom may tip over Evalute the passive fire  3
boom protection of lower part of flare 

A.5
A.process plant/deck Condensate leak  from valves, flanges,etc reduce the number of valvec  3
and flanges/ control the flange 
and valves during operation 
continiousely
A.6
A.process plant/deck fire and explosion fire and explosion in  make distance between  This may cause failure of  Extremely important to keep  3
different process modules different modules/ keep  process plant process module away of LQ.
distance between deck and 
process modules elavation
A.7
A.process plant/deck gas leak gas leak from process  flammable gas clouds may  Fire and explosion scenarios  3
modules,valves,flanges occure. If ignited, fire and  have to be evaluated. 
explosion will occure.

A.8
A.process plant/deck loss of electrical power and  fire fire resistance and redundant  2
signal cables are planned to be used.

A.9
B.Power Generation gas leak flanges,valves pipe in pipe solution provided  Confirmed gas in  two separate engine  2
for fuel gas inside hull. Inert gas  HVAC/combusion air intake must  room
with gas detection installed in  lead to shut down.
room between two pipes.
B.1
B.Power Generation Gas leak from fuel Gas detection system gas may ignite.will result in a  2
 gas supply in open air small local fire

B.2
B.Power Generation fire in the generator fire in electrical total flooding fire extinguisher  Define emergency power  Important that the power  1
 equipment system consumers, and make sure that  source is available for the 
there are sufficient power supply  fire water pumps.
during emergency situations.
B.2
C.Drilling Unit Shallow water flow Sands  SWF sands can flow out of  Seismic data Analysis,   cause severe drilling problems Seismic data Analysis,   when pore pressure in  2
(SWF) the formation, into the  unconsolidated sands is 
borehole high enough to suspend 
the grains so that rock 
strength diminishes.
C.1
C.Drilling Unit Fault and fractures Techtonic structure Geology and seismic study cause severe drilling problems Drilling through these hazards  2
should be avoided if possible, or 
if relocation is not an option, 
appropriate mitigating measures 
C.2 taken.
D.LQ/Helideck helicopter crash Unfavorable location of  Injuries,fatalities, damage to  location of helideck must fulfill all  3
helideck. Difficult weather  topside and Jacket regulations for helideck.
conditions

D.1
D.LQ/Helideck Fire and explosion from other  for instance, fire and  fire wall and blast wall towards   exposure of sides of LQ.  exposing windows in control  identify the relevant  3
part of the installation explosion in the process  process plant and side wall room facing turret. scenarios that LQ shall 
plant or power generation  withstand. 
unit
D.2
D.LQ/Helideck fire and explosion insufficient temporary refuge Define the design requirements  3
of temporary safe refuge.

D.3
D.LQ/Helideck Fire inside LQ several reasons e.g.  injuries and fatalities Use non‐combustible materials  2
smoking, electrical problem as far as possible. 

D.4
E.Escape/Evacuation blocked escape routes smoke/radiation from fires alternative escape routes.  personnel entrapped,injuries  Make sure there is at least one  2
Protected escape routes. and fatalities. available escape route for all 
relevant scenarios.

E.1
E.Escape/Evacuation blocked longitudinal escape  smoke/radiation from fires alternative escape routes.  personnel entrapped,injuries  Make sure there is good  2
routes Protected escape routes. and fatalities. transverse escape routes 
between the longitudinal escape 
routes
E.2

75 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Hazard Identification for Zubara Gas Field, Scenario 2
RISK REDUCING  POTENTIAL  RISK 
ID AREA/SUBJECT HAZARD POTENTIAL CAUSES FOLLOW UP/ACTION COMMENTS
MEASURES CONSEQUENCES CLASSIFICATION
F.Reservoir/well  collapse of well wall Mud composition/pressure,  Control and adjust the mud  loss of the well, sever problem  Use deviated drilling 2
shallow water flow compsition  for drilling

F.1
F.Reservoir/well Sink hole geology structures geology  study loss of the well, sever problem  Change the drilling location or  2
for drilling use deviated drilling to avoid the 
hazrdous area

F.2
F.Reservoir/well Change in gas composition reservoir property measerment the gas  Different processing/ it may  Adjust the process procedure  2
composition continuously make problem for high H2S  according to gas composition, 
content/ Different production  define suitable scenarios based 
rate for gas and condensate on different gas composition 
F.3
F.Reservoir/well Gas migration reservoir property measerment the reservoir  decrease the recovery factor,  Adjust the production rate 2
property, Control the migration  problems for drilling
during drilling activities

F.4
G.Risers/pipeline Riser leak/rupture risers failure/  Inspection, suitable material  gas leakage , air /water  Inspection the risers 2
corrosion/fatigue selection, gas detection pollution, fire/ explosion

G.1
G.Risers/pipeline flow assuranse gas composition Measermentgas composition,  Blocked the risers, pipeline Start up/ shut down procedures,  2
insulation, pigging chemical inhibitor injection

G.2
G.Risers/pipeline Corrosion due to H2S H2S in gas composition Measerment H2S content, Use  Corrosion in pipeline Use suitable material for pipeline,  1
suitable material for pipeline,  inhibitor injection, offshore 
inhibitor injection desulfurization

G.3
H.GeoHazard Active Faulting Underground activities Geology and seismic study Problem for pipeline, Drilling  Change the drilling location, and  3
string,foundation pile, Jacket  pipeline path/ Calculate the 
due to earthquake probability of earthquake 

H.1
H.GeoHazard landslide Dredging, earthquake Field investigation Loss of pipeline Change the pipeline path  2

H.2
H.GeoHazard coral Environment  Field investigation Problem for pipeline and  Change the pipeline path 1
risers

H.3
I. Mooring Loss of Mooring line Sever weather condition,  measurment the movement of  Movement of the semi, risers  Redundancy in mooring lines,  1
earthquake semi failure define a scenario for loss of 
mooring line in design

I.1
I. Mooring Loss of anchors landslide control the mooring line force loss of connection of mooring  redundancy in mooring lines,  1
line define a scenario for loss of 
mooring line in design, install the 
new anchor
I.2
I. Mooring Fatigue in chain close to  fatigue Inspection loss the mooring line Use suitable method to  1
seabed installation mooring line i.e. S 
wave, inspection and pull up the 
mooring line a few meter every 4‐
I.3 5 years
J. Semi‐submersible ship collision supply ship,  ballast tanks as buffer damage of semi, instability Deside what kind of collision the  fulfill the collision loads. 1
 hull hull can resist. 

J.1
J. Semi‐submersible Fatigue in structural  Frequent load on structure  inspection structural instability Design based on fatigue, use  1
 hull connection e.g. waves suitable material for hazardoud 
part of structure

J.2
K. Subsea equipments Dropped objects Supply ship, During work  procedure for maintanace /  Loss of subsea equipments subsea equipment location and  2
over / maintenance unloading the equipments from  arrangement, Cover equipments 
supply ship with shelter structure

K.1
K. Subsea equipments hazard By fishery / pearl  fishery / pearl people protecting the area above  damage on subsea  protecting the area above subsea  2
industry and people  subsea equipments equipments systems

K.2
L. Other Hazards Politic issues political issues Be aware about politic issues,  May cancel the project Negotiation with Qatar  4
good relation with government  government  and  other countries 
which have influence on project

L.1
L. Other Hazards terrorist attack political issues Be aware about politic issues,  may lead to severe  Negotiation with Qatar  3
good relation with government  consequence government , local group and 
international organizations

L.2
L. Other Hazards structural failur/equipment  Sever environment Define suitable specifications for  large load on deck, damage to  Check different design scenarion.  2
damage materials/ equipments in design  process module and  Select proper material/ 
documents piping/equipment on deck equipments

L.3

76 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Appendix VI.C 
HAZID Scenario 3 
Hazard Identification for Zubara Gas Field, Scenario 3
RISK REDUCING  POTENTIAL  RISK 
ID AREA/SUBJECT HAZARD POTENTIAL CAUSES FOLLOW UP/ACTION COMMENTS
MEASURES CONSEQUENCES CLASSIFICATION
A. Drilling  Shallow water flow Sands  SWF sands can flow out of  Seismic data Analysis,   cause severe drilling problems Seismic data Analysis,   when pore pressure in  2
(SWF) the formation, into the  unconsolidated sands is 
borehole high enough to suspend 
the grains so that rock 
strength diminishes.
A.1
A. Drilling  Fault and fractures Techtonic structure Geology and seismic study cause severe drilling problems Drilling through these hazards  2
should be avoided if possible, or 
if relocation is not an option, 
appropriate mitigating measures 
A.2 taken.
B. Reservoir/well  collapse of well wall Mud composition/pressure,  Control and adjust the mud  loss of the well, sever problem  Use deviated drilling 2
shallow water flow compsition  for drilling

B.1
B. Reservoir/well Sink hole geology structures geology  study loss of the well, sever problem  Change the drilling location or  2
for drilling use deviated drilling to avoid the 
hazrdous area

B.2
B. Reservoir/well Change in gas composition reservoir property measerment the gas  Different processing/ it may  Adjust the process procedure  2
composition continuously make problem for high H2S  according to gas composition, 
content/ Different production  define suitable scenarios based 
rate for gas and condensate on different gas composition 
B.3
B. Reservoir/well Gas migration reservoir property measerment the reservoir  decrease the recovery factor,  Adjust the production rate 2
property, Control the migration  problems for drilling
during drilling activities

B.4
C. Risers/pipeline Riser leak/rupture risers failure/  Inspection, suitable material  gas leakage , air /water  Inspection the risers 2
corrosion/fatigue selection, gas detection pollution, fire/ explosion

C.1
C. Risers/pipeline flow assuranse gas composition Measermentgas composition,  Blocked the risers, pipeline Start up/ shut down procedures,  2
insulation, pigging chemical inhibitor injection

C.2
C. Risers/pipeline Corrosion due to H2S H2S in gas composition Measerment H2S content, Use  Corrosion in pipeline Use suitable material for pipeline,  1
suitable material for pipeline,  inhibitor injection, offshore 
inhibitor injection desulfurization

C.3
D.GeoHazard Active Faulting Underground activities Geology and seismic study Problem for pipeline, Drilling  Change the drilling location, and  3
string,foundation pile, Jacket  pipeline path/ Calculate the 
due to earthquake probability of earthquake 

D.1
D.GeoHazard landslide Dredging, earthquake Field investigation Loss of pipeline and subsea  Change the pipeline path  2
equipments

D.2
D.GeoHazard coral Environment  Field investigation Problem for pipeline and  Change the pipeline path 1
risers

D.3
E. Subsea equipments Dropped objects Supply ship, During work  procedure for maintanace /  Loss of subsea equipments subsea equipment location and  1
over / maintenance unloading the equipments from  arrangement, Cover equipments 
supply ship with shelter structure

E.1
E. Subsea equipments hazard By fishery / pearl  fishery / pearl people protecting the area above  damage on subsea  protecting the area above subsea  1
industry and people  subsea equipments equipments systems

E.2
E. Subsea equipments Loss of power / data, umbilical fishery / pearl people protecting the area above  stop the production protecting the area above subsea  1
subsea equipments systems

E.3
F. Other Hazards Politic issues political issues Be aware about politic issues,  May cancel the project Negotiation with Qatar  4
good relation with government  government  and  other countries 
which have influence on project

F.1
F. Other Hazards terrorist attack political issues Be aware about politic issues,  may lead to severe  Negotiation with Qatar  3
good relation with government  consequence government , local group and 
international organizations

F.2
F. Other Hazards structural failur/equipment  Sever environment Define suitable specifications for  large load on deck, damage to  Check different design scenarion.  2
damage materials/ equipments in design  process module and  Select proper material/ 
documents piping/equipment on deck equipments

F.3

77 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Appendix VII 
Calculation Production Deviated Wells Final Scenario 

Deviated wells
Production area 43560000 ft2 based on: 1000 acres
Production radius 3724 ft
Production diameter = Dwell 7447 ft
30°
Manifold 8000 ft
Distance well ‐ manifold at seabed 160 ft based on maximum jumper length Well 
Distance well ‐ manifold TVDSS = D 4779 ft D = tan(30°) ⋅ 8000 + 160 depth
Perimeter 30026 ft P = 2 ⋅π ⋅ R
Length per well 5004 ft Lwell = P / 6
Producing length per well 5255 ft Lp ,well = 1.05 ⋅ Lwell

Efficiency per well 0.71 η = Dwell / Lwell


Production per well 84.7 MMscf/day Q = η ⋅ Qdeviated = 0.65 ⋅ 120
4619 ft

Because of overlap 5 % extra 
production per well

78 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

scenario 1 2 3

amount of gas 1.23E+13 1.23E+13 1.23E+13 cf


35.314667 35.314667 35.314667 cf/m3
Appendix VIII 

gas 3.48297E+11 3.48297E+11 3.483E+11 m3


H2S 2 3 4 %
Amount of h2s 6965944207 10448916310 1.3932E+10 m3
H2S calculations 

density H2S 1.393 1.393 1.393 kg/m3


H2S 9703560280 14555340420 1.9407E+10 kg

1/3 van H2S 3234520093 4851780140 6469040187 kg


2/3 van H2S 6469040187 9703560280 1.2938E+10 kg

H2S 34 g/mol
O2 32 g/mol 8 H2S + 12 O2 _> 8 SO2 + 8 H2O
SO2 64 g/mol
H2O 18 g/mol 16 H2S + 8 SO2 _> 3 S8 + 16 H2O
S8 256 g/mol

first reaction ratio SO2/H2S 1.882352941


second reaction ratio S8/SO2 1.5

First reaction SO2 6088508411 9132762616 12177016822 kg


second reaction S8 9132762616 1.3699E+10 18265525233 kg
9132762.616 13699143.9 18265525.23 tons
Zubara Gas Field Development Plan, Concession 2 

2% 3% 4%
Amount of ton S8/12.3TCF 300 $ 2,739,828,784.92 $ 4,109,743,177.38 $ 5,479,657,569.84 $
22830000 ton 400 $ 3,653,105,046.56 $ 5,479,657,569.84 $ 7,306,210,093.12 $
12300000 MMscf 500 $ 4,566,381,308.20 $ 6,849,571,962.30 $ 9,132,762,616.40 $

79 
May 2009
           
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Appendix IX 
Pipeline calculations 
Part A: Gas pipeline calculation, single phase 

Pressure drop
Value Unit
Pout #NUM! Mpa
Pin 12.500Mpa
L 63000.000m
C 5.70E-10Mpa/K
f 0.016-
z 0.530-
Tabs 308.955K
rho 70.418kg/m^3
Q 540.773m^3/s
d 1.067m

Pipeline
Value Unit
Area 0.894m2
Diameter 42.000inch
Conversion factor inch to m 0.025m/inch
Production 1650.000MMscf/d
Conversion seconds per day 86400.000second/day
Cubic feet per second 19097.222ft^3/second
Conversion factor ft^3 to m^3 0.028m3/ft^3
Cubic meters per second, standard 540.773m^3/second
Compressed to 87 bar in pipeline 13.946m^3/second
Flow speed 15.602m/s

P, V, T in process plant and in pipeline


Value Unit
P1 1.000bar
P2 125.000bar
V1 1.000m3
V2 0.026m3
R 8.314J/mol K
T1 95.841K
T2 308.955K
k 1.320-

Density of air
Value Unit
Temperature 15.000Degrees Celsius
Density of air at 15 degrees 1.225kg/m3
81% of value of air 0.992kg/m3

80 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Rho
Gas % density Fraction Unit
Methane 0.77 6.67E-04 5.14E-04g/cm3
Ethane 0.065 1.25E-03 8.15E-05g/cm3
Propane 0.03 1.88E-03 5.64E-05g/cm3
CO2 0.075 1.84E-03 1.38E-04g/cm3
Other 0.06 1.41E-03 8.46E-05g/cm3
Average 1.75E-04g/cm3
Average 1.75E-01kg/m3

Reynolds number to determine value of f


Value Unit
V 15.602m/s
kinematic visc. 1.44E-05m2/s
dynamic viscosity 1.43E-05Pa*s
D 1.067m
Re 1.17E+06
f 1.60E-02
new
Value Unit
Q, gas flow rate, measured at
standard condition 46722796.890m3/day
f, frction factor 0.02[-]
Pb, base pressure 100.00kPa
Tb, base temprature 288.000K
P1, upstream pressure 1250.000kPa
P2, downstream pressure 650.000kPa
G, gas gravity (air=1.0) 0.810[-]
Tf, average gas flowing temperature 303.000K
L, pipe length 63.000Km
Le, equivalent pipe length 65.97Km
Z, gas compressibility factor at
the flowing temperature 0.53[-]
D, pipe diameter 1901.76mm
D, pipe diameter 74.87inch
F, transmission factor 15.81[-]
H2, end point elevation 265.00m
H1, start point elevation 0.00m
S, elevation adjustment parameter 0.09[-]
Flow velocity 4.91m/s
Area of pipe 2.84m2

Wall thickness 3.24E+01 mm


Pressure 1.25E+07 Pa
Yield strength 2.06E+08 Pa
Outer diameter 1.07E+00 m

81 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

82 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Part B: Condensate pipeline calculation, single phase 
 
 
Pressure drop
Value Unit
Pi 3.142
Pressure in pipeline (input) 80.000bar
L 63000.000m
f 0.038-
rho 709.000kg/m3
Q 0.199m^3/s
d 0.406m
h 265.000m
Pressure drop (friction) 4895386Pa
Pressure drop (elevation) 1843152Pa
Pressure drop (total) 6738537Pa
Pressure drop (total) 67.385bar
Pout, output pressure 12.615
 
Pipeline
Value Unit
Area 0.130m2
Diameter 16.000inch
Conversion factor inch to m 0.025m/inch
Production 107923.000bbls/d
Conversion seconds per day 86400.000second/day
Production per second 1.249bbls/second
Conversion factor bbls to m^3 0.159m3/bbls
Cubic meters per second 0.1986m^3/second
Flow speed 1.53109m/s

Rho
Condensate Value Unit
Density of condensate 2.70lbs/gal
Convert 0.45kg/lb
5.95kg/gal
Convert 3.79gal/liter
1.57kg/liter
kg/m3
709kg/m3

83 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Reynolds number to determine value of f


Value Unit
V 1.531m/s
kinematic visc. m2/s
dynamic viscosity 4.42E-05Pa*s
D 0.406m
Re 1.41E+04
relative roughness 7.38E-03
f 3.80E-02

Wall thickness
Value Unit
Pressure 8.00E+06Pa
Yield strength 2.06E+08Pa
Outer diameter 4.06E-01m
wall thickness 7.89E+00mm
wall thickness 1.00E+01mm

Pumping power
Value Unit
Q 0.20 m3/s
Difrencial pressure 6738.54 Kpa
pump eficiency 0.75
Pumping power 1784 KW

84 
Zubara Gas Field Development Plan, Concession 2  May 2009
           
Part C: Multiphase pipeline calculation 

Existing pipeline in Iran

Pressure drop calculation


Q 7.761m3/s
D 0.6096m
A 0.292m2
V 26.590m/s
g 9.810m/s2
L 8648.000m

Pressure drop calculation


Q 540.7731122 m3/s
D 1.0668 m
A 0.893831993 m2
V 605.0053213 m/s
g 9.81 m/s2
L 63000 m

Wall thickness 1.71E+01mm


Pressure 1.25E+07Pa
Yield strength 3.90E+08Pa
Outer diameter 1.07E+00m

85 
Zubara Gas Field Development Plan, Concession 2  May 2009
           

Pressure drop Multi-phase flow

14000000

12000000

10000000
Pressure drop (bar)

8000000

6000000

4000000

2000000

0
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Diam eter (inch)

86 