AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
Oracle Business Intelligence (BI) is a portfolio of technology and applications that provides the
industry's first integrated, end-to-end Enterprise Performance Management System, including BI
foundation and tools - integrated array of query, reporting, analysis, alerting, mobile analytics,
data integration and management, and desktop integration - as well as category-leading
financial performance management applications, operational BI applications, and data
warehousing.
3. Challenges of using BI
• Lot of entry needs to be done onto the Planning Tool.
• Every individual using the system , should have a good understanding on its working.
• Allocation of complex formulas is difficult.
• Dependent on client server for producing reports.
• Any changes to the reporting require IT support.
• Some of the resources that are not available on the system needs to be added.
• The Project ID needs to be aligned with the SAP name.
• Remote Connectivity.
3|Page
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
4. System Architecture
• Overview
• Schedule
• Milestone
• Resource
• Earned Value
• CPI/SPI
• Risk
4|Page
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
7. Overview Tab
7.1 Views by Project Phase
5|Page
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
7.4 The selection of various views is based upon allotment of Project and activity codes to the
Project.
In the above figure we see the various Project Codes assigned to the projects.
6|Page
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
7|Page
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
The columns mentioned above have been extracted from the following:
Status, Project Phase & Priority is assigned from the Project Codes.
The selection of Quarter can be done from the following drop down menu:
1. Original Duration: This column or field shows the originally planned duration of activities, while these
are planned. When we enter new activities in Primavera P6, we also enter their duration and that
duration is called Original Duration. This value may be changed (if needed) before execution starts.
2. Remaining Duration: This column/field shows duration of the activity yet to be completed. For
example Original Duration of the activity was 10 days. Now, 5 day work is completed. So, the remaining
duration for work is 5 days.
3. At Complete: This column/field shows how much duration will have been completed when the
activity will finish. Ideally, the duration you have planned for the activity should also be At Complete
duration. This will be possible if the work is managed properly so as to complete it in the same duration
which was planned. However, this is not always the case and activity duration is prolonged due to slow
work or non work, hence Original Duration doesn't remain valid in such a case, so we look at At
Complete value to know in how many days the activity will complete with current pace. At Complete
Duration is computed as Actual Duration + Remaining Duration. The At Complete Duration can be
viewed in the Status tab or in the column 'At Completion Duration'.
8|Page
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
8. Schedule Tab
9. Milestone Tab
The Milestone Tab indicates the performance of the milestone against the baseline date.
It also provides us an indication on the number of Milestones achieved and the targets missed.
9|Page
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
10 | P a g e
AMIT KUMAR SENAPATI PMP®
ORACLE BUSINESS INTELLIGENCE: DASHBOARD REPORTING
The CPI/SPI tab provides the CPI/SPI result of all the projects.
Here we can also check the Planned and Earned value cost.
12. Conclusion
If used Dashboard Reporting will tremendously reduce report development time and will
provide real time statistics of the health of the project.
It will also motivate the planners to streamline their deliverables on time and as per standards.