Vous êtes sur la page 1sur 4

Upgrading Power Transmission Lines To

Higher Voltage With Existing


Infrastructure | Sterlite Power
Due to increasing urbanization and industrial growth, energy consumption has
gone up in Tier I and Tier II cities in India. The rising population, along with the
government’s focus to provide uninterrupted electricity to all homes by 2019, is
projected to increase electricity consumption five to six times between 2014 and
2030.

Over the last few decades, India has witnessed a steep rise in generation capacity.
With government’s efforts, even if half of the planned renewable capacity gets
installed by 2022, the generation would certainly match the nation’s requirement.

Get More Detail at electrical power cable

However, the key to this fulfillment will be to match generation capacity addition
with adequate power transmission and more importantly, intrastate transmission
and the sub-transmission network. This network must be made available to enable
the downstream to the load centers around densely populated urban areas of
important states and industrial areas.

Under the 13th five-year plan, high capacity transmission corridors comprising 765
kV AC and 800 kV High Voltage Direct Current (HVDC) system have been
planned to strengthen the national grid. It is estimated that 13,000 MW of HVDC
systems will be required for grid expansion, but with growing demand, this itself is
projected to grow to 15,000 MW under the 13th five-year plan. Most transmission
networks in India had been built to handle specific amount of power flow. With
increasing load, they’re ill-equipped for higher power flow, and now need up
gradation to better transmission capabilities.

Get More Detail at power transmission in India

This transition traditionally requires building additional transmission capacity by


reinforcing the existing infrastructure, which is currently being done in the one or
more of the following ways:
Building additional circuits or towers

o Most of the current structures, however, aren’t designed to


accommodate additional circuits.

Constructing new parallel transmission lines

o However, rapid urbanization, escalating land costs and right-of-way


(ROW) challenges make this option prohibitively expensive. A right-
of-way, that involves permission for additional ground space, can take
several years to negotiate in addition to the time needed to upgrade to
higher voltage transmission. Additionally, approvals for adding lines
are difficult with today’s environmental concerns due to depreciating
forest and agriculture cover.

Get More Detail at aluminium conductor

Replacing existing conductors with conventional conductors of higher size

o This would require tower replacements because of the additional


structural loading and relative condition of the existing structures.
Thermal sag associated with the conventional conductors is a concern
too.

Uprating the existing transmission lines with reconductoring

o This method is a quick-fix arrangement and applicable to only short


stretches within the network to enable decongestioning.
o The method also leads to high losses in the stretches thereby creating
voltage drops and system imbalances which is why, a wide scale
adoption is not possible by transmission planners.

The challenge today is to reduce the footprint of transmission corridor upgradation


while increasing the transmission capacity multifold. Increased capacity without
the need to reinforce existing infrastructure translates to greater profitability and
lower transmission losses, therefore improving life-cycle costs compared with
conventional line upgradation projects that often overrun, thereby increasing costs.

Fortunately, it is possible to upgrade transmission lines and substations to higher


voltages without having to replace or reinforce the existing tower structures. The
upgradation challenges can be overcome with a modern cost-effective approach
that provides an ideal solution with respect to grid stability and widespread
adoption for getting up to 12 times the existing power throughput. Let’s understand
this approach in detail.

 Use of compact towers to maintain the same corridor footprint

o Using narrow base tower which has lower height, narrower base, as
well as lower weight as compared to a standard tower maintains the
tower footprint within the existing ROW requirements and saves
significant costs and time.
o For example, upgrading a line from 66KV to 132 KV requires ROW
to be increased from 18 m to 27 m. With compact towers, this
effective 33% reduction in ROW typically results in cost- savings of
up to Rs. 1cr/Km and saves a timeframe of 6 months to 1 year since
no additional ROW approval or forest clearance is required.

Get More Detail at transmission line company in india

 Lowering the corridor footprint by using monopoles and micropiles

o Monopoles (single poles) can mitigate space constraints related to


traditional poles that stand on 3-4 poles.
o Use of Micropiles reduce excavation effort and time as well as tower
foundation footprint (by 10-20%) and adds to tower stability.

 Replacing existing ACSR conductors with high performance HTLS


conductors

o HTLS (High Temperature-Low Sag) conductors can carry more


current per sq.mm than conventional ACSR (Aluminum Conductor-
Steel Reinforced) conductor.
o The power losses of the HTLS conductor are 20% to 25% lower as
compared with the conventional conductor.
o HTLS operate at much higher temperature ranges (150-2500C) than
ACSR (1000C), which increases the power transmission throughput to
almost twice the current capacity.
o Additionally, HTLS conductors have low thermal expansion in the
temperature range.
o The low sag feature also facilitates reduction in tower height, which
helps overcome ROW issues, as explained before.
 Use of Mobile Substations during upgradation for minimum shutdowns
o Usage of mobile substation at suitable strategic locations results in
zero/minimal shutdown during the time upgradation is being carried
out, thus resulting in higher grid reliability.

Sterlite Power is India’s leading integrated power transmission developer and


solutions provider, which has been able to demonstrate this approach that tackles
the key constraints of time, space and capital in voltage upgradation. Sterlite power
has carried out comprehensive feasibility studies for voltage upgradation across
numerous states in India and has proposed cost-effective solutions with the
approach mentioned above.

India is the third largest producer of electricity in Asia, and its generating capacity
is continuously growing. The distance between generating stations and load centers
is increasing day by day. Huge transfer of power from generating plants to load
centres at long distance will require significant line upgradation and adding
additional infrastructure will not be a feasible solution to go forward.

Access to power has the potential to change the lives of millions, by bringing
about a transformation in the local economy, and with it, the country as a whole.
The country wide power transmission upgradation, however, will require a co-
ordinated effort by government and various power transmission solution providers
to solve the toughest challenges of energy delivery.

For More Information Visit: www.sterlitepower.com

Vous aimerez peut-être aussi