Académique Documents
Professionnel Documents
Culture Documents
Over the last few decades, India has witnessed a steep rise in generation capacity.
With government’s efforts, even if half of the planned renewable capacity gets
installed by 2022, the generation would certainly match the nation’s requirement.
However, the key to this fulfillment will be to match generation capacity addition
with adequate power transmission and more importantly, intrastate transmission
and the sub-transmission network. This network must be made available to enable
the downstream to the load centers around densely populated urban areas of
important states and industrial areas.
Under the 13th five-year plan, high capacity transmission corridors comprising 765
kV AC and 800 kV High Voltage Direct Current (HVDC) system have been
planned to strengthen the national grid. It is estimated that 13,000 MW of HVDC
systems will be required for grid expansion, but with growing demand, this itself is
projected to grow to 15,000 MW under the 13th five-year plan. Most transmission
networks in India had been built to handle specific amount of power flow. With
increasing load, they’re ill-equipped for higher power flow, and now need up
gradation to better transmission capabilities.
o Using narrow base tower which has lower height, narrower base, as
well as lower weight as compared to a standard tower maintains the
tower footprint within the existing ROW requirements and saves
significant costs and time.
o For example, upgrading a line from 66KV to 132 KV requires ROW
to be increased from 18 m to 27 m. With compact towers, this
effective 33% reduction in ROW typically results in cost- savings of
up to Rs. 1cr/Km and saves a timeframe of 6 months to 1 year since
no additional ROW approval or forest clearance is required.
India is the third largest producer of electricity in Asia, and its generating capacity
is continuously growing. The distance between generating stations and load centers
is increasing day by day. Huge transfer of power from generating plants to load
centres at long distance will require significant line upgradation and adding
additional infrastructure will not be a feasible solution to go forward.
Access to power has the potential to change the lives of millions, by bringing
about a transformation in the local economy, and with it, the country as a whole.
The country wide power transmission upgradation, however, will require a co-
ordinated effort by government and various power transmission solution providers
to solve the toughest challenges of energy delivery.