Académique Documents
Professionnel Documents
Culture Documents
com/pmp) » Study
Notes (https://www.deepfriedbrainproject.com/pmp/study-notes) » Total Float vs. Free Float in ...
When I was preparing for my PMP exam, I was very confused about the difference between Total
Float and Free Float in Critical Path Method (CPM). I understood Float
Float, but not the two types. So,
I did some research and nally made-up an example to understand the concepts myself. Today
I’m sharing the example that I prepared almost 2 years ago. I hope it will help in PMP
Certi cation aspirants on their exam.
Total Float is the amount of time that an activity can be delayed from its early start date without
delaying the project nish date. Free Float is the amount of time that an activity can be delayed
without delaying the early start date of any successor activity.
where ES = Early Start, EF = Early Finish, LS = Late Start, and LF = Late Finish
Let’s understand the concepts with the help of an example. Refer to the Network Diagram in the
gure rst. I’m assuming that you know how to work with a Network Diagram and how to
calculate ES, EF, LS, and LF for activities on a Network Diagram. Click on the gure to download
the network diagram as a PDF le.
Solution
The calculations are really simple.
For Activity F:
Total Float = LF of F – EF of F => 8 – 5 = 3
For Activity J:
Total Float = LF of J – EF of J => 8 – 3 = 5
Pro Tip
Free oat can only occur when two or more activities share a common successor, or in other
words, when activities converge on a Network Diagram. In our example, only activities F and J
can have Free Float.
In the next section, let’s address the question posted by Dr. PDG in the comments.
Total Float belongs to the project, whereas Free Float belongs to individual activities. If the
project is being done under a contract, it’s debatable whether Float belongs to the buyer or seller.
‘Float’ is a project resource. It should be used judiciously, mainly to cover the risks or other
unforeseen issues on the project.
While you are at it, also learn about Negative Float (http://tips.deepfriedbrainproject.com/2011/02/what-is-
negative- oat.html).
LEAVE A COMMENT
34 COMMENTS
Now that you have done a ne job clarifying the differences between Total and Free
Float, how would or could or should a professional project manager USE free and total
oat?
My real complaint with the PMP exam (and PMI's approach in general) lies with the fact
that while people may know the terminology and in some cases, may actually know how
to do various calculations, they haven't a clue as to how to effectively use this
information to manage projects.
BR,
Dr. PDG, in Boston
http://www.getpmcerti ed.com
Reply to Dr. PDG
Harwinder Singh
(https://www.blogger.com/pro le/17448550860024926123)
August 04, 2009 at 12:26 PM
Hi Dr. PDG,
Total Float belongs to the project, whereas Free Float belongs to individual
activities. If the project is being done under a contract, it's debatable whether
Float belongs to the buyer or seller.
Now I pass the ball to you. Please enlighten us more on this subject.
2. Regarding your point on the PMP certi cation, I think we are on the same
page. Nobody is claiming that PMI-certi ed PMs are "Super PMs". I see it
more as an academic quali cation (similar to a school or college degree).
Again, I have had this debate so many times in various forums and really tired
of it. There's no end to it ...
And although you are absolutely correct that oat is to cover or mititage risk, a
better or more complete answer would be that it shows you how much
exibility you have in terms of both time (spread between early and late date S
curve horizontally) and in terms of resources (the spread vertically between
the early data and late date S curves)
Very few people, unless they have been involved in litigation, truly understand
how to effectively use oat information to better manage their projects.
BR,
Dr. PDG, in Boston
http://www.getpmcerti ed.com
PS: For those really interested in this topic, be sure to download the many free
Recommended Practices (RP's) AACE offers. http://www.aacei.org/technical/rp.shtml .
Pay special attention to 29R-03 to learn about many of the games contractors play with
schedules.
And if you are interested in project controls/PMO as a career path, I urge you to move
beyond PMI's rather sophomoric credentials and challenge yourself to some very
di cult, albeit less well marketed credentials that AACE offers.
http://www.aacei.org/certi cation/
BR,
Dr. PDG, in Boston
http://www.getpmcerti ed.com
Nhlosenhle zwane
(https://www.blogger.com/pro le/06929859571323159492)
May 25, 2016 at 01:48 PM
Dear Dr PDG
MS
December 07, 2009 at 09:55 PM
confused OR student
Reply to MS
Anonymous
January 16, 2010 at 09:11 PM
I have a related question, which I m slightly confused about. Each of the books Rita,
Head rst and others have 2 different ways of drawing the network diagram..e.g Activity
A starts on Day 1 and has a duration of 5 then the ES of the activity A is 1 and the EF is
6....and Activity B which proceeds activity A has a duration of 8, then Activity B, then the
ES for B is 6 or 7 considering there is no lag between A and B.
Same way while calculating LF and LS some authors subtract a day by default others
don't...which is confusing...If you can kindly help with this, with an example that will be
very helpful.
In the end for calculating oat it doesn't make any difference as adding 1 and then
subtracting it correspondingly adjusts for the same.
What is the standard practice for this, can you please clarify?
Reply to Anonymous
Harwinder Singh
(https://www.blogger.com/pro le/17448550860024926123)
January 17, 2010 at 03:58 AM
@ Anonymous:
You are right. Different books follow different conventions. Whether you start
the rst activity at 0 or 1 is a matter of choice. Both methods will get you the
same answers. It doesn't make any difference when it comes to calculating
the duration of critical path, and oat values.
I prefer to follow the convention that which you nd in Rita's book, to calculate
the ES, EF, LS, LF, FF, TF.
The advantage with this convention is that you don't need to add/subtract
hours. The rst day starts at 0. If the rst activity's duration is 7 days, then its
ES = 0 and EF = ES + Duration = 0 + 7 = 7. The successor activity will have the
ES = EF of the predecessor activity (provided there's no lead or lag).
In summary, pick the convention that you are more comfortable with, practice
it, and stick to it.
Harry, i was bit puzzled to use 0 or 1 to calculate the ES of the rst activity..
But after seeing your explanation, now i am clear on using 0 or 1. Thank you
However, I have seen calculations, where EF(x) will be 5 (1 through 5 = 5days). then
ES(x+1)=6 (not 5).
Both these methods will not make any difference to your CPM calculations as long as
you keep it constant throughout.
But, in ur PMI certi cation exam, this can make a difference because you have to
choose what PMI thinks is correct from the given options.
Reply to SOUMIT
De nitivamente son terminos que son necesarios comprender a fondo para darles la
aplicacion correcta en nuestros proyectos, agradezco mucho los comentarios y los
felicito... :D
Harwinder Singh
(https://www.blogger.com/pro le/17448550860024926123)
July 14, 2010 at 01:01 AM
Hello Williams,
I cannot read Spanish. So, I translated it to English for others' and my own
bene t. Here's what it translated to:
"They are de nitely terms that are necessary to fully understand them
correctly applied in our projects, I very much appreciate the comments and I
congratulate ... : D"
Rookie
September 14, 2010 at 01:41 PM
Continuing from Soumit's comments on 28 March, I'm sharing this link and a few
questions.
(link removed)
The Zero Method – all starts and nishes are at the end of a time period. In the Zero
Method, the start of an activity has the same number as the nish of the previous
activity on the critical path.
The One Method - all starts are at the beginning of a time period and all nishes are at
the end. In the One Method, the nish of a previous activity on the critical path, has 1
added to it to get the start of the next activity.
It seems that
- Rita Mulcahy uses the "zero method"
- Andy Crowe uses the "one method"
So 2 questions remain
1) Which one does PMI use? Any recent exam takers care to share your experience?
2) Are "zero method" and "one method" the o cial terms to describe these calculation
conventions?
Reply to Rookie
Anonymous
December 15, 2010 at 11:29 PM
Reply to Anonymous
Harwinder Singh
(https://www.blogger.com/pro le/17448550860024926123)
December 16, 2010 at 12:42 AM
Hello Anon.,
BR.
Anonymous
January 07, 2011 at 04:33 PM
Another excellent source of information on PMP is the PM Road Trip and in particular
the calculation for free oat as put forward by anon is correct:
FF = (ES of successor - ES of current - duration of current)
http://www.pmroadtrip.com/pdm_01.html
I prefer the "one menthod" as it is re ects the real world much better. I would never start
the rst activity on day zero as that doesn't make sense. You start on day 1 and if it
takes 5 full working days to complete (duration) then you would be working on it on
days 1, 2, 3, 4, and 5. Then the earliest you can start the next activity is day 6, not day 5!.
Reply to Anonymous
Shraddha
January 24, 2011 at 05:06 PM
Reply to Shraddha
Harwinder Singh
(https://www.blogger.com/pro le/17448550860024926123)
February 07, 2011 at 03:26 PM
Hello Shraddha,
I had to remove your post because it violates PMI's code of conduct. Try to
rephrase your question and post it again.
Thanks.
Anonymous
February 27, 2011 at 11:38 PM
which means
FF =(ES of Successor -(ES of current +Duration of current))
so it becomes
Reply to Anonymous
Anonymous
April 08, 2011 at 04:54 PM
Hi,
I have another question regarding identifying oat and utilizing it as a buffer/slack.
In case of leads and lags to N/W diagram, how should oat be identi ed? For example, it
might be required to wait for 2 days before Activity B starts after Activity A, say due to
planned maintainance. If we just go by oat calculation, this may be considered as a
buffer that can be utilized.
So how to really identify oad in case of leads and lags?
Reply to Anonymous
Reply to Muhmad
Harwinder,
I would like to know about Project oat ( Rita's book).As per my understanding there is
no oat for critical path activities.If this is correct.Does Project oat existis?.
Thanks
Ram
Reply to Ram
Anonymous
January 20, 2013 at 12:22 AM
Excellent job clarifying the concept. My students have had a lot of trouble understanding
this but now it crystal clear.
Thanks
Reply to Anonymous
Anonymous
April 20, 2013 at 09:47 AM
I CAN NOT UNDERSTAND HOW TO CALCULATE ACTIVITY DURATION IN CASE OF
RLLATION IS FF -2 OR FS +3 FOR EXAMPLE CAN YOU EXPLAIN PLEASE
Reply to Anonymous
Parsa Mahmoudzadeh
(https://www.blogger.com/pro le/10902819405395859870)
November 22, 2013 at 06:04 PM
HI, Harwinder,
I think you are right for the most part, let me elaborate a little bit more; Free Float
belongs to every activities done before the target activity we concern about. actually,
Independent Float is belong only to one activity itself.
Amit Ranjan
January 18, 2014 at 03:07 PM
I agree with Dr. PDG.... But, for this we should also favors that Project Planning Tools
supports, if all stake holders will have believe & directed only from PMO O ce
In my opinion....FLOAT is an asset of the project and NOT for the exclusive use/bene t
of the Contractor.
Anonymous
April 09, 2015 at 01:16 PM
Reply to Anonymous
Hamid Samadani
September 05, 2017 at 10:33 PM
perfect <3
zomuana
October 28, 2018 at 12:35 PM
Thank you very much for your clear and concise explanation especially with example..
Reply to zomuana
Richard
November 24, 2018 at 05:58 PM
It is helpful. But I need clari cation on where resounces can be used when allocation.
Reply to Richard