BAR BENDING SHEDULE

a a
b c b b
Type A
a c
Type D Type E
b a c a
Type B Type F
a c
b b
Type C a c
Type G

Cut Length Dia Unit Wt. Total Wt


S.No. Element Position Type a b c Nos.
mm mm Kg/m Kg
1 Raft Slab Bottom A 900 50 50 1000 14 10 0.62 8.64
2 Column Vertical G 1080 250 100 1430 8 16 1.58 18.08
3 TIES Transverse D 270 270 160 1240 6 8 0.40 3.14
Transverse D 196 196 160 942.44 6 8 0.40 2.38
Total 32.24
5% Extra for Wastage= 0.12
Total Steel For 4 PIT = 129.43
RCC
S.No. Element L B H Unit Nos. Qnty.
1 Raft Slab 1.00 1.00 0.18 Cum 1.00 0.18
2 Columns 0.35 0.35 1.03 Cum 1.00 0.13
TOTAL For 4 PIT 1.20

PCC RAFT 1.20 1.20 0.08 Cum 1.00 0.11


Total PCC for 4 PIT= 0.43

Excavation 1.20 1.20 1.275 Cum 1.00 1.84


Total Excavation for 4 PIT= 7.34