Académique Documents
Professionnel Documents
Culture Documents
A R T I C L E I N F O A B S T R A C T
Keywords: Drilling risers are the crucial connection of subsea wellhead and floating drilling vessel. Emergency Disconnect
Deepwater drilling riser (ED) is the most important protective measure to secure the risers and wellhead under extreme conditions. This
Emergency disconnect paper proposes a methodology for failure probability analysis of ED operations using Bayesian network (BN).
FT-ESD model The risk factors associated with ED operations and the potential consequences of ED failure were investigated. A
Bayesian network
systematic ED failure and consequence model was established through Fault Tree and Event Sequence Diagram
Failure probability analysis
(FT-ESD) analyses and then the FT-ESD model was mapped into BN. Critical root causes of ED failure were
inferred by probability updating, and the most probable accident evolution paths as well as the most probable
consequence evolution paths of ED failure were figured out. Moreover, the probability adaptation was performed
at regular intervals to estimate the probabilities of ED failure, and the occurrence probabilities of consequences
caused by ED failure. The practical application of the developed model was demonstrated through a case study.
The results showed that the probability variations of ED failure and corresponding consequences depended on
the states of critical basic events (BEs). Eventually, some active measures in drilling riser system design, drilling
operation, ED test and operation were proposed for mitigating the probability of ED failure.
∗
Corresponding author.
E-mail address: changyj1557@126.com (Y. Chang).
https://doi.org/10.1016/j.jlp.2017.11.005
Received 21 August 2017; Received in revised form 22 October 2017; Accepted 16 November 2017
Available online 22 November 2017
0950-4230/ © 2017 Elsevier Ltd. All rights reserved.
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
and insufficient. Therefore, it may be necessary to carry out a risk as- consists of inner and outer barrels where the relative motion (stroke) of
sessment based on multiple hazards which are represented in various these barrels can compensate for the length variations of riser column
forms such as probabilistic data, experts' opinions and linguistic re- with the motion of the drilling vessel. The LFJ and UFJ can improve the
presentations. The fuzzy set theory can be used to present subjective, mechanical performance for both ends of the riser column to avoid
vague, linguistic and imprecise data and information effectively. In the excessive bending moment and hence damage to the risers (Chang,
Fuzzy Fault Tree Analysis (FFTA), the probability values of components 2008).
will be characterized by fuzzy numbers. Using fuzzy set theory, fuzzy The subsea BOP/LMRP stack includes LMRP and BOP, which is
number in linguistic term can be transformed into fuzzy failure prob- usually equipped with two hydraulic connectors, namely, the LMRP
ability of BEs, and quantitative risk analysis of top events can be con- connector and wellhead connector. The LMRP connector is located in
ducted by FT method. Lavasani et al. (2011, 2015a, 2015b) applied the middle of two annular preventers, which is used to connect the
fuzzy set theory to evaluate the risk of leakage in abandoned oil and LMRP to the BOP, and the wellhead connector is used to connect BOP
natural-gas wells and Deethanizer failure in petrochemical plant op- and HPW (Cai et al., 2012a, 2012b). If ED is activated automatically or
erations. Ren et al. (2009) developed an offshore risk analysis method manually under extreme conditions, the LMRP will disconnect from
using a fuzzy BN where triangular fuzzy membership functions were BOP at the LMRP connector, and the riser column will be lifted up and
used to elicit expert judgments. Ferdous et al. (2009) proposed a suspended by the tensioners eventually after the disconnect is com-
methodology for computer aided FFTA. Chen et al. (2014) conducted pleted. If there is drill pipe in the drilling riser, the blind shear rams in
risk assessment of an oxygen-enhanced combustor using a structural BOP will cut through the pipe and seal the well before disconnect.
model based on the Failure Mode and Effects Analysis (FMEA) and
FFTA. Shi et al. (2014) performed FFTA for fire and explosion accidents 2.2. Reasons for emergency disconnect
for steel oil storage tanks.
In practical operational conditions, various factors, e.g. human, Generally, There are four reasons for the ED of the drilling riser
design, operation, time, equipment and control are all able to cause the system that include drift-off, drive-off, storms and internal solitary
failure of ED which could cause disastrous consequences in deepwater waves.
drilling. However, studies for ED operations of deepwater drilling riser
from risk perspective can only be found sporadically in literature. Thus, 2.2.1. Drift-off
it is necessary to conduct a comprehensive study to address the failure Drift-off is an event normally caused by loss of power, malfunction
probability analysis of ED operations for the actual engineering re- in the power system, engine breakdown, or mechanical and human
quirements. errors. When the DP system can no longer hold the position, the in-
The objective of this paper is to propose a failure probability ana- creasing offset of the drilling vessel due to wind, wave and current will
lysis methodology for ED operations of deepwater drilling risers, which cause large horizontal force and bending moment to the subsea well-
could be used to assess the probabilities of ED failure and different head by drilling riser system, and the ED must be activated to avoid
failure consequences. In this research, a FT-ESD model was developed possible accident. If the ED operations can't be completed successfully
to present a systematic accident scenario and accident evolution process in 60 s at most, it may damage the wellhead or break the riser joints.
caused by ED failure. A BN model was mapped from the developed FT- Once the integrity of the well is damaged, the blowout accident will
ESD model to identify the critical events, analyze the most probable occur inevitably. According to the existing literature, it has been stated
paths for ED failure and the most probable paths of the consequences that the occurrence probability of drift-off event is 2 × 10−3 per year
resulting from ED failure by updating the prior probability of BEs. The (Olsen, 2001).
BN model also aimed to investigate the failure probability of ED by Establishing alert offsets for the ED of the vessel-connected riser
introducing new critical BEs. Finally, some suggestions and measures system through drift-off analysis is used to determine the point of dis-
for ED operations are proposed to reduce the probability of failure ac- connect. Generally, the alert offsets settings are as follows: green re-
cident. gion-drilling normally; yellow region-stop drilling and make the pre-
The paper is structured as follows: Section 2 introduces the process, paration for ED while the riser is in the “connected non-drilling mode”;
analyzes the reasons of ED, and investigates the mechanism of factors red region-the ED is initiated automatically (it can also be initiated
influencing the ED operations. In Section 3, the failure probability manually in advance) and must be completed before reaching the blue
analysis methodology for ED operations of deepwater drilling riser is region; blue region-the suspended riser column is in survival mode (Ju
proposed. Section 4 identifies the hazards and analyzes the accident et al., 2012).
evolution process of ED failure by FT and ESD. Section 5 is a case study
regarding the application of BN in quantitative failure probability 2.2.2. Drive-off
analysis of deepwater drilling riser ED operations. Finally, the conclu- A drive-off is much the same as a drift-off, but it comes from a
sions are presented in Section 6. malfunction in the DP system causing the rig to drive off from its lo-
cation. This is a very critical event due to the higher velocity of the
2. Background vessel, and it provides a short available time to activate the ED before
the horizontal offset gets too large. The occurrence probability of drive-
2.1. Deepwater drilling riser system off event is 1.6 × 10−5 per DP hour (Ambrose et al., 2001a, 2001b).
Deepwater drilling conductor is the first layer of casing installed 2.2.3. Storm
during the well construction in deepwater drilling, which is generally Generally, the MODU will disconnect from the BOP before a storm is
jetted into the formation without well cementing. After jetting the fully developed which is called “planned disconnect”. However, if the
conductor with low pressure wellhead (LPW), completing the installa- storm is larger than predicted or if an anticipated rapidly-developing
tion of the casing surface tubular with high pressure wellhead (HPW) seastate happens, an unplanned ED would be needed to secure the
and cementing, drilling operation is followed by deployment of riser drilling risers and wellhead.
system and LMRP/BOP by making up the riser joints.
The main components of the riser column include BOP/LMRP stack, 2.2.4. Internal solitary waves
lower flex joint (LFJ), slick and buoyancy riser joints, telescopic joint Internal solitary waves are the nonlinear large amplitude waves
(TJ) and upper flex joint (UFJ). The top end of the riser column is existing in the oceanic pycnocline (Cai et al., 2012a, 2012b). A large
connected to the drilling vessel through the tension system. The TJ number of measurements and remote-sensing observations have shown
43
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
that internal solitary waves happen frequently and exist widely in the Table 1
South China Sea, which have been a fundamental environmental factor Categories and symbols of events (Swaminathan and Smidts, 1999).
that must be taken into account in designing the ocean engineering
Category Symbol Annotation
facilities (Huang, 2013). On 6 April, 2014, when NAIHAI-8 drilling
platform was drilling normally in Liuhua oilfield in the South China Initial event Beginning event of the ESD
Sea, the internal solitary waves pushed the vessel 137 m away from its
original position, and almost reached the red alert offset, causing da- Comment event Providing information of the development
mage to the ropes of the tensioners. of event sequence
Termination event An end state of the ESD
A fuzzy set takes values from the interval [0,1] and is characterized
by a membership function m(x), which represents the relationship
among different elements. Fuzzy sets are defined for specific linguistic
variables, which can be calculated by triangular fuzzy numbers (TFNs)
or trapezoidal fuzzy numbers (ZFNs). The TFNs are denoted by a triplet
(a1, a2 and a3) and the ZFNs are denoted by a triplet (a1, a2 and a3)
and a quadruple (a1, a2, a3 and a4) and can be defined as follows
(Kumar and Yadav, 2012; Chen et al., 2014):
⎧ 0; x ≤ a1
Fig. 1. Output OR gate representing multiple mutually exclusive outcomes.
⎪ (x − a1)/(a2 − a1); a1 ≤ x ≤ a2
μ (x ) =
⎨ (a3 − x )/(a3 − a2); a2 ≤ x ≤ a3
⎪ 0; x ≥ a3 i.e., Output AND gate, Input AND gate, Output OR gate and Input OR
⎩ (1)
gate. These gates can be used to represent various situations like con-
0; x ≤ a1 current processes, synchronization processes, multiple mutually ex-
⎧
⎪ (x − a1)/(a2 − a1); a1 ≤ x ≤ a2 clusive outcomes. Especially, for the Output OR gates, since the out-
⎪ comes are mutually exclusive, only one of the many possible outcomes
μ (x ) = 1; a2 ≤ x ≤ a3
⎨ will occur. Fig. 1 shows an example of an Output OR gate. After the
⎪ (a 4 − x )/(a 4 − a3 ); a3 ≤ x ≤ a4
⎪ 0; x ≥ a4 occurrence of Event 1, there are three possible scenarios. If P2, P3 and
⎩ (2)
P4 are the probabilities of occurrence of the three events respectively,
then their summation is equal to 1.
3.2. ESD Pr is a set of process parameters, which reflect the states of the
system. For example, the abovementioned occurrence probabilities of
ESD is a graphical method for visualizing the sequence of related the three events are the process parameters, which will influence the
events. As an effective risk assessment method, ESD has been used in evolution of the accident and eventually the probabilities of the ter-
many different fields (Zhou et al., 2016). The first ESD framework was mination events (end states).
proposed for risk modeling by NASA in the Cassini space program, and
since then it has been employed widely by different researchers (Luo
and Hu, 2013). Wu (2005) built an ESD model for the driving pump of a 3.3. Bayesian networks
spaceship cooling circuit with an initiating event ‘‘power failure’’, and
analyzed the related accidents. Zhou et al. (2016) applied ESD to BN is a graphical inference probabilistic method widely applied in
evaluate emergency response actions during fire-induced domino ef- risk analysis and fault diagnosis (Cai et al., 2014, 2016). It consists of
fects. To assess the ED failure probability in the present study, ESD was nodes, arcs and conditional probability tables which represents a set of
defined based on the work of Swaminathan and Smidts (1999). random variables and the conditional dependencies among them. Due
to its flexible structure and probabilistic reasoning engine, BN is a
ESD=(E, Cd, G, Pr) (3) promising method for risk analysis of large and complex systems.
Considering the conditional dependencies of variables, BN re-
where E refers to the events which implies any changes from one state
presents the joint probability distribution P (U) of variables U = {A1,
to another. Any observable physical phenomenon the analyst chooses to
…,An}, expressed as:
represent in an ESD would be considered as an event. These events
could be time-distributed events, demand-based events, non-quantifi-
able events, or end states. In the present work, events were divided into
P (Ai ) = ∑ P (U )
U / Ai (4)
three categories: (1) “Initial event”, being the beginning event of an
ESD, and starting the potential event sequence; (2)“Comment event”, where Pa (Ai ) is the parent set of variable Ai . Accordingly, the prob-
describing the development of an event sequence and (3)“Termination ability of Ai is calculated by:
event”, indicating the termination of the ESD. The symbols used to
represent such events and brief definitions are given in Table 1. P (Ai ) = ∑ P (U )
Cd indicates conditions which represent the rules controlling the U / Ai (5)
development of an event sequence into different branches. The event
sequence will develop in different directions depending on whether the where the summation is taken over all the variables except Ai . The main
conditions are satisfied or not. application of BN is in probability updating. BN takes advantage of
G represents the logic gates, indicating the logical relationships Bayes' theorem to update the prior probabilities of variables given new
among events. The basic gates are the AND gate and the OR gate, which observations, called evidence E, rendering the updated or posterior
can be further divided into four types according to event relationships, probabilities (Li et al., 2017):
44
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
45
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
46
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
Emergency
Disconnection
failure
Human Design
factors factors
X2 X5
(c) Sub-FT for design factors in ED failure
(b) Sub-FT for human factors in ED failure Disconnect
factors
Operation
factors
X22 Disconnect
moment
Longterm
Wellhead Cementing
service Normal Abnormal
X15 circumstances circumstances
X26 Storm
X23 X25
X16 x17 X18 X19 X20 X21
X24
Equipment Control
factors factors
Fluid Electric
control control
X29 X31
X30
Hydraulic X36 X37 X38 X40
(f) Sub-FT for equipment factors in ED failure X39
X32 X34
X33 X35
ESD are represented as top node, intermediate nodes, and the con- the ESD model. In the ESD mapping process in this study, the possible
sequence nodes in the equivalent BN, respectively. In the numerical events, the conditions controlling the development of an event se-
step, for each intermediate node as well as the consequence node, a CPT quence into different branches, logic relation for evolution of the ED
is assigned. CPTs are defined according to the process parameters Pr in failure accident and the occurrence probability, which represent the
47
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
Table 2 listed in Table 3 were invited to judge the fuzzy number and CPTs based
BEs of ED failure and their probabilities. on their experiences.
The expert elicitation is essentially a scientific methodology and is
Number Description of BEs Prior Posterior
probability probability often used in the study of rare events, and various elicitation methods
were examined for expert judgments. For the unknown prior prob-
X1 Poor company safety culture 7.45E-05 1.12E-04 ability of BEs of aforementioned human, design, operation, equipment,
X2 Poor training standards 5.07E-04 7.66E-04
time and control factors, the experts were asked to fill out five separate
X3 Unreasonable system and procedures 4.12E-04 6.75E-04
X4 Inadequate knowledge and skill 5.32E-04 8.71E-04 data sheets by linguistic terms, namely, occurrence possibility survey
X5 Distraction 4.09E-03 4.08E-03 tables of BEs. In the next step, using fuzzy set theory, the occurrence
X6 High work stress 5.07E-04 9.07E-04 possibility of BEs was transformed into fuzzy failure probability (prior
X7 Inadequate extremity rotation angles of 6.32E-05 1.46E-03 probability). The present work used the weighted averages of the five
UFJ
sets of data as the final input data. The weight of each event for the
X8 Inadequate extremity rotation angles of 7.43E-05 1.71E-03
LFJ experts was determined based on their qualifications and relevant ex-
X9 Midstroke of TJ is not configured 5.18E-04 1.50E-02 periences. The first and the second experts, who were acquainted with
X10 Inadequate bending capacity of HPW 7.28E-05 1.73E-03 human and equipment factors, had a higher weight for human and
X11 Inadequate bending capacity of LPW 6.83E-05 1.62E-03
equipment factors and a lower weight for control factors, whereas the
X12 Fabrication defects 9.40E-05 1.17E-03
X13 Unreasonable geometric parameters 7.88E-05 1.82E-03 third expert, who was acquainted with time and control factors, had a
X14 Inadequate yield strength of material 7.68E-05 1.77E-03 higher weight for time and control factors and a lower weight for design
X15 Inadequate overpull 1.32E-02 2.48E-01 factors. However, the experts were all acquainted with the ED of the
X16 Large stick-up 8.90E-04 2.09E-02 deepwater drilling riser system. With respect to the conditional prob-
X17 Large inclination angle of wellhead 1.32E-02 1.35E-01
ability tables of different factors, the five experts discussed and de-
X18 Poor cementing quality 9.54E-05 9.72E-03
X19 Inadequate top level of cement 8.33E-05 8.55E-03 termined the possible data based on their experiences.
X20 Formation of natural gas hydrate 8.96E-03 8.32E-02 The conditional dependencies among elements of BN were assigned
X21 Bonding force induced by corrosion 3.07E-04 3.12E-03 in CPT. The logical gate of FT and experience-based judgment were
X22 Unreasonable disconnect moment 1.89E-02 2.37E-01
used to determine CPTs in BN model. The logical gate of FT represents
X23 Strong wind 8.10E-03 1.09E-02
X24 Large wave 7.92E-03 1.07E-02.
deterministic relationship between primary events and intermediate
X25 High current 8.35E-03 1.13E-01 events. For example, if both X10 and X11 succeed, the wellhead would
X26 Internal solitary waves 8.55E-03 4.82E-02 fail inevitably. This relationship is described by a CPT in Table 4. Ac-
X27 Typhoon 2.30E-02 7.92E-02 tually, if both X10 and X11 succeed, the wellhead may not fail. How-
X28 Local rapidly-developing storm 8.29E-03 2.93E-02
ever, although X10 and X11 do not fail, the failure of wellhead is still
X29 Inadequate tensioner stroke extremity 5.07E-04 1.24E-02
X30 Inadequate TJ stroke extremity 5.06E-04 1.24E-02 possible. Such scenario can be modeled through an amending CPT
X31 Inadequate DP capacity and accuracy 4.52E-04 8.12E-03 shown in Table 5. The amending values in CPT were determined by
X32 Operation panel failure 1.46E-04 2.23E-03 expert judgments. Note that the computed results may be subjected to a
X33 Leakage of accumulator in BOP 9.88E-04 8.22E-03
margin of error because the input data were obtained from expert
X34 Actuator modules failure 9.55E-04 6.13E-03
X35 High unlock pressure in connector 4.52E-03 7.62E-02
judgments and reference reviews, resulting in some possible errors.
induced by leakage of corrosion The BN of ED failure was developed using graphical network in-
X36 Signal transmission failure 5.07E-04 9.23E-03 terface (GeNIe) software. Using the BN model of ED failure shown in
X37 Umbilical termination failure 5.33E-04 9.56E-03 Fig. 5, with the probabilities listed in Table 2, the probability of ED
X38 Two redundant SEMs failure 7.45E-05 1.82E-03
failure was estimated to be 4.91E-02, and the probabilities of three end
X39 Triple modular redundant PLCs failure 7.45E-05 1.82E-03
X40 Software failure 5.07E-04 3.24E-03 states were also calculated, which were 4.17E-3, 1.89E-2 and 2.37E-2
for blowout, sinking to the seabed and safe suspension by the vessel
respectively. It is worth noting that the blowout probability is far lower
process parameters, were all determined by expert judgments. than other consequences, as in no case could the weakest point of the
Because of the uncertainty and complexity, it is difficult to de- drilling riser system be located below LMRP, and it should be verified
termine the prior probabilities for BEs and conditional probability ta- by weak point analysis in design stage (Kavanagh et al., 2002). The
bles for different factors. In the present work, the expert judgments possibility of safe suspension by the vessel and break and sinking to the
were used for this purpose. Five related experts from the oil company as seabed depends on the seastate and the motion response of the vessel.
Break below
Blowout
BOP
Riser
OR
failure
Break during
survial
Disconnect
OR
failure Riser soft
Bottom failure Riser recoil Recoil control OR
Hang off
Safe suspension
Wellhead by the vessel
Blowout
failure
48
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
Table 3 human factors. On account of the fact that the corresponding BEs within
Experts information. the operation and time factors may lead to ED failure directly, they play
the most significant role in ED operations. Design and equipment fac-
No. Professional position Service time Educational level
(years)
tors have certain effects on ED failure because the design level and
equipment are usually reliable. Control factors play a minor role in the
1 Drilling rig manager 16 Bachelor failure of ED operations because of the use of the redundant control
2 General drilling supervisor 11 Master logics, PLC, SEM and control software. Human factors can hardly
3 Deepwater operation manager 12 Bachelor
4 Principal engineer 14 Doctor
contribute to the ED failure because the ED will be initiated auto-
5 Senior subsea engineer 10 Master matically in case that the vessel reaches the red alert offset.
49
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
Table 7
Occurrence record of critical BEs in 90 days (Apr–Jun).
BEs
X15 0 0 0 0 0 0
X17 0 0 0 0 0 0
X20 0 0 0 0 1 0
X22 0 0 0 0 0 0
X26 1 1 1 1 1 1
X27 0 0 0 0 0 0
X28 0 0 0 0 0 0
X35 0 0 0 0 0 1
Fig. 6. Comparison between prior and posterior probabilities for critical BEs.
Table 8
Occurrence record of critical BEs in 90 days (Jul–Sep).
wellhead), X20 (Formation of natural gas hydrate at LMRP connector),
Day 0–15 16–30 31–45 46–60 61–75 76–90
X22 (Unreasonable disconnect moment), X26(Internal solitary waves),
X27 (Typhoon), X28 (Local rapidly-developing storm) and X35 (High BEs
unlock pressure in connector induced by leakage of corrosion). More
X15 1 1 1 1 1 1
attention should be paid to all of these critical events during drilling
X17 1 1 1 1 1 1
riser design and ED operations. X20 0 0 0 0 1 0
GeNIe software can also implement strength of influence, through X22 0 0 0 0 1 0
which the probable development paths are found. The most probable X26 0 0 0 0 0 0
accident evolution paths for ED failure were as follows: (i) X15 X27 1 1 1 1 1 1
X28 0 0 0 0 1 0
(Inadequate overpull) and X17 (Large inclination angles of conductor)
X35 0 0 0 0 0 0
and X20 (Formation of natural gas hydrate at the connector) →adverse
operation factors→ED failure; (ii) X22 (Unreasonable disconnect mo-
ment during the heave cycle of the vessel) and X27 (Typhoon) →ad- Table 9
verse time factors→ED failure; (iii) X35 (High unlock pressure in con- Occurrence record of critical BEs in 90 days (Oct–Dec).
nector induced by leakage of corrosion) →malfunction of control
Day 0–15 16–30 31–45 46–60 61–75 76–90
factors→ED failure. The most probable consequence evolution paths of
the ED failure were as follows: (i) ED failure→riser break just above the BEs
LMRP→ safe suspension by the vessel (after anti-recoil operation); (ii)
ED failure→riser break just below the rotary table→riser break above X15 1 1 1 0 0 0
X17 0 0 0 0 0 0
LMRP→ sinking to the seabed.
X20 0 0 0 0 0 1
X22 0 0 0 0 0 0
X26 0 0 0 0 0 0
5.3. Probability adaption X27 1 0 0 0 0 0
X28 1 0 0 0 0 0
X35 0 0 0 0 0 1
Probability adaption, also known as sequence learning, is another
important application of BN. It is used for probability updating based
on the new information accumulated over time where the new in- weather considerations in Liuhua oilfield in the South China Sea. It is
formation could be the occurrences of certain BEs or the accident pre- worth noting that the occurrence record of critical BEs represents
cursors. The critical events for failure of ED were identified by prob- whether the events occur or not, and it is not the actual occurrence
ability updating, and their occurrences were recorded over a period of record of the events. This means that the critical events occur once the
time in this study. A hypothetical case, in which the occurrences of ED is initiated each time. For example, X9 refers to the critical event of
identified critical events in the South China Sea have been recorded for midstroke of TJ being not configured. If this event occurs during the
a time interval of 15 days over one year (Tables 6–9), is included as an installation of drilling riser system, it will exist during the drilling cycle
example to illustrate how to realize probability adaption. Normally, the of the well all along. However, for the basic event of X20(Formation of
average drilling cycle for a well is about 3 months. For this reason, the natural gas hydrate around the LMRP connector), as the hydrate can be
occurrence record of critical events is incorporated with the seasonal removed by ROV once it is observed, the occurrence record may change
during the drilling cycle.
Table 6
The prior probabilities can be adapted after occurrences of these
Occurrence record of critical BEs in 90 days (Jan–Mar).
critical events for each well, and the revised prior probabilities P can be
Day 0–15 16–30 31–45 46–60 61–75 76–90 calculated as follows (Meel and Seider, 2006; Tan et al., 2014; Yang
et al., 2017):
BEs
a+s
P=
X15 0 0 0 1 1 1 n+s (7)
X17 1 1 1 1 1 1
X20 0 0 0 0 0 1 where a and n denote the occurrence records of ED failure and total
X22 0 0 0 0 0 0 records of ED operations respectively for the past wells, and s represents
X26 0 0 0 0 0 0 the occurrence record of the critical events for the ongoing well.
X27 0 0 0 0 0 0
Using the revised probabilities of critical events during a drilling
X28 0 0 0 0 0 0
X35 0 0 0 0 1 1 cycle, i.e., Jan–Mar and Jul–Sep, the probabilities of ED failure were
updated (Fig. 7). From Jan to Mar, it can be clearly seen from Fig. 7 that
50
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
Fig. 9. Probabilities of ED failure consequence (A: blowout) for the whole year.
Table 10
Fig. 7. Failure probability of ED for a well (Jan–Mar and Jul–Sep). Probabilities of ED success for different wells (days).
51
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
China Sea, drilling operation was postponed after the completion of and Technology Program (2016ZX05028-001-05). The first author also
riserless drilling for the coming typhoon season, and the partial reasons would like to express his gratitude to Xinhong Li and Naser Golsanami
for the delay were the possible ED and the increasing possibility of ED for their help in preparation of this paper.
failure.
References
5.4. Model validation
Abimbola, M., Khan, F., Khakzad, N., Butt, S., 2015. Safety and risk analysis of managed
When a new methodology is developed, it requires a careful vali- pressure drilling operation using Bayesian network. Saf. Sci. 76, 133–144.
Ambrose, B.D., Grealish, F., Whooley, V., 2001a. Soft Hangoff Method for Drilling Risers
dation to ensure its robustness. A sensitivity analysis was carried out in in Ultra Deepwater. OTC, Huston, Texas, pp. 13816.
this study to test the proposed model. If the model is robust, the ob- Ambrose, B.D., Childs, M.S., Leppard, S.A., Krohn, R.L., 2001b. Application of a
tained result would be sensitive, but would not show abrupt variations Deepwater Riser Risk Analysis to Drilling Operations and Riser Design. OTC,
Houston, Texas, pp. 12954.
to any minor change of the input parameters (Yang et al., 2013; Cai API RP 16Q, 1993. Recommended Practice for Design, Selection, Operation and
et al., 2013). With the assumption of the prior probability of critical BE Maintenance of Marine Drilling Riser Systems. first ed.. .
X15 being increased by 10%, the probability of ED success decreased Bhandari, J., Abbassi, R., Garaniya, V., Khan, F., 2015. Risk analysis of deepwater drilling
operations using Bayesian network. J. Loss Prev. Process Ind. 38, 11–23.
from 95.09% to 94.97%. When both of the prior probabilities of critical Bobbio, A., Portinale, L., Minichino, M., Ciancamerla, E., 2001. Improving the analysis of
BEs X15 and X17 were increased by 10%, the probability of ED success dependable systems by mapping fault trees into Bayesian networks. Reliab. Eng. Syst.
decreased from 94.97% to 94.91%. When the prior probabilities of Saf. 71, 249–260.
Brekke, J.N., 2001. Key Elements in Ultra-deep Water Drilling Riser Management. SPE/
critical BEs X15, X17 and X22 were increased by 10% simultaneously,
IADC, Amsterdam, The Netherlands, pp. 67812.
the probability of ED success decreased from 94.91% to 94.81%. As Cai, B., Liu, Y., Liu, Z., Tian, X., Dong, X., Yu, S., 2012a. Using Bayesian networks in
expected, a slight increment of prior probabilities for critical BEs in- reliability evaluation for subsea blowout preventer control system. Reliab. Eng. Syst.
duced the decrement of probability of ED success in a reasonable way, Saf. 108, 32–41.
Cai, B., Liu, Y., Liu, Z., Tian, X., Zhang, Y., Ji, R., 2013. Application of Bayesian networks
thus giving a validation of the model. in quantitative risk assessment of subsea blowout preventer operations. Risk Anal. 33
(7), 1293–1311.
6. Summary and conclusions Cai, B., Liu, Y., Fan, Q., Zhang, Y., Liu, Z., Yu, S., Ji, R., 2014. Multi-source information
fusion based fault diagnosis of ground-source heat pump using Bayesian network.
Appl. Energy 114, 1–9.
In the present study, four reasons for ED of DP drilling vessel were Cai, B., Liu, H., Xie, M., 2016. A real-time fault diagnosis methodology of complex sys-
analyzed which include drift-off, drive-off, storms, and internal solitary tems using object-oriented Bayesian networks. Mech. Syst. Signal Process. 80, 31–44.
Cai, S., Xie, J., He, J., 2012b. An overview of internal solitary waves in the South China
waves. Based on the analysis of reasons for ED, the hazards of ED were Sea. Surv. Geophys. 33, 927–943.
identified, which include human, design, operation, time, equipment Chang, Y., 2008. Design Approach and its Application for Deepwater Drilling Risers.
and control factors, and the influencing mechanism of the hazardous University of Petroleum (East China), Dongying.
Chen, Z., Wu, X., Qin, J., 2014. Risk assessment of an oxygen-enhanced combustor using a
factors on ED was investigated. structural model based on the FMEA and fuzzy fault tree. J. Loss Prev. Process Ind.
Considering the specialty of ED operations and the simplicity of 32, 349–357.
accident evolution process of ED failure, failure probability analysis of Ferdous, R., Khan, F., Veitch, B., Amyotte, P., 2009. Methodology for computer aided
fuzzy fault tree analysis. Process Saf. Environ. Prot. 87, 217–282.
drilling riser ED operations were carried out by BN approach. Six ca-
Fenton, S.P., 2012. Riser Emergency Disconnect Control System. US 0067589 A1. .
tegories of influencing factors were modeled and integrated into FT. GeNIe. Decision Systems Laboratory, 1998–2015. Available at: https://dslpitt.org/genie/.
Accident evolution process and three end states induced by ED failure Grønevik, A., 2013. Simulation of Drilling Riser Disconnection-recoil Analysis. Norwegian
were modeled by ESD, and then the integrated FT-ESD model was University of Science and Technology, Trondheim.
Huang, W., 2013. The Investigation on Load and Dynamic Response Characteristics of
mapped into the BN which could consider polymorphism of BEs as well Deep-sea Floating Structures in Internal Solitary Waves. Shanghai Jiao Tong
as conditional dependencies among the primary events of the ED op- University, Shanghai.
erations. However, BN approach demands more expertise in terms of Ju, S., Chang, Y., Chen, G., Liu, X., Xu, L., Wang, R., 2012. Envelopes for connected
operation of the deepwater drilling riser. Petrol. Explor. Dev. 39 (1), 105–110.
prior probability, conditional probability, and network construction Kavanagh, K., Dib, M., Balch, E., Stanton, P., 2002. New Revision of Drilling Riser
based on causal relationships between components. A BN model also Recommended Practice (API RP 16Q). OTC, Houston, Texas, pp. 14263.
helps to identify the most probable path of events leading to an ED Khakzad, N., Khan, F., Amyotte, P., 2013a. Quantitative risk analysis of offshore drilling
operations: a Bayesian approach. Saf. Sci. 57, 108–117.
failure and the most probable paths of consequence caused by ED Khakzad, N., Khan, F., Amyotte, P., 2013b. Dynamic safety analysis of process systems by
failure. mapping bow-tie into Bayesian network. Process Saf. Environ. Prot. 91, 46–53.
The present study indicates that the methodology proposed herein is Kumar, M., Yadav, S.P., 2012. The weakest t-norm based intuitionistic fuzzy fault-tree
analysis to evaluate system reliability. ISA Trans. 51, 531–538. https://doi.org/10.
an alternative approach in failure probability analysis of ED operations
1016/j.isatra.2012.01.004.
for deepwater drilling risers. The study showed that the X15 Lang, D.W., Real, J., Lane, M., 2009. Recent Developments in Drilling Riser Disconnect
(Inadequate overpull), X17 (Large inclination angle of wellhead) and and Recoil Analysis for Deepwater Application. OMAE, Honolulu, Hawaii, pp. 79427.
Lavasani, S.M., Yang, Z., Finlay, J., Wang, J., 2011. Fuzzy risk assessment of oil and gas
X22 (Unreasonable disconnect moment) were the first three critical BEs
offshore wells. Process Saf. Environ. Prot. 89, 277–294.
for the failure of ED operations, and the probabilities of ED failure and Lavasani, S.M., Ramzali, N., Sabzalipour, F., Akyuz, E., 2015a. Utilisation of fuzzy fault
potential consequences caused by ED failure varied with the states of tree analysis (FFTA) for quantified risk analysis of leakage in abandoned oil and
critical BEs. Overall, the failure of ED operations is an event with low natural-gas wells. Ocean Eng. 108, 729–737.
Lavasani, S.M., Zendegani, A., Celik, M., 2015b. An extension to fuzzy fault tree analysis
occurrence probability, and blowout is the consequence with the lowest (FFTA) application in petrochemical process industry. Process Saf. Environ. Prot. 93,
occurrence probability caused by failure of ED operations. The analysis 75–88.
results obtained from this study could provide reference for risk deci- Li, X., Chen, G., Zhu, H., 2016. Quantitative risk analysis on leakage failure of submarine
oil and gas pipelines using Bayesian network. Process Saf. Environ. Prot. 173,
sion-making of ED operations and a better vision of ED safety issues. 163–173.
Li, X., Zhu, H., Chen, G., Zhang, R., 2017. Optimal maintenance strategy for corroded
Acknowledgement subsea pipelines. J. Loss Prev. Process Ind. 49, 145–154.
Luo, P., Hu, Y., 2013. System risk evolution analysis and risk critical event identification
based on event sequence diagram. Reliab. Eng. Syst. Saf. 114, 36–44.
Thanks are given to five anonymous domain experts for their input Ma, P., Pyke, J., Vankadari, A., Whooley, A., 2013. Ensuring Safe Riser Emergency
and insight without which this research would not be possible. Besides, Disconnect in Harsh Environments: Experience and Design Requirements. ISOPE,
Alaska, USA.
the authors gratefully acknowledge the financial support provided by Meel, A., Seider, W.D., 2006. Plant-specific dynamic failure assessment using Bayesian
National Key Basic Research and Development Program theory. Chem. Eng. Sci. 61, 7036–7056.
(2015CB251203), the program for Changjiang Scholars and Innovative Olsen, T., 2001. Safe Disconnect during Drive-off/drift-off when Drilling on DP. IADC,
Stavanger, Norway.
Research Team in University (IRT14R58), and Major National Science
52
Y. Chang et al. Journal of Loss Prevention in the Process Industries 51 (2018) 42–53
Puccio, W.F., Nuttall, R.V., 1998. Riser Recoil during Unscheduled Lower Marine Riser Tan, Q., Chen, G., Zhang, L., Fu, J., Li, Z., 2014. Dynamic accident modeling for high-
Package Disconnects. SPE, Dallas, Texas, pp. 39296. sulfur natural gas gathering station. Process Saf. Environ. Prot. 92, 565–576.
Rausand, M., 2013. Risk Assessment: Theory, Methods, and Applications. John Wiley and Wu, Q., 2005. The ESD Method and Software of Astronautics Carrier System's Risk
Sons. Assessment. National University of Defense Technology, Changsha.
Ren, X., Zhao, X., Cai, Q., 2009. ESD_FT method in the analysis of marine reactor water- Yang, Y., Khan, F., Thodia, P., Abbass, R., 2017. Corrosion induced failure analysis of
loss accident. Chin. J. Ship Res. 4 (5), 49–53. subsea pipelines. Reliab. Eng. Syst. Saf. 159, 214–222.
Shi, L., Shuai, J., Xu, K., 2014. Fuzzy fault tree assessment based on improved AHP for fire Yang, Z., Bonsall, S., Wall, A., Wang, J., Usman, M., 2013. A modified CREAM to human
and explosion accidents for steel oil storage tanks. J. Hazard. Mater. 278, 529–538. reliability quantification in marine engineering. Ocean Eng. 58, 293–303.
Skogdalen, J.E., Vinnem, J.E., 2011. Quantitative risk analysis offshore-Human and or- Zhou, J., Reniers, G., Khakzad, N., 2016. Application of event sequence diagram to
ganizational factors. Reliab. Eng. Syst. Saf. 96, 468–479. evaluate emergency response actions during fire-induced domino effects. Reliab. Eng.
Swaminathan, S., Smidts, C., 1999. The event sequence diagram framework for dynamic Syst. Saf. 150, 202–209.
probabilistic risk assessment. Reliab. Eng. Syst. Saf. 63, 73–90.
53