Vous êtes sur la page 1sur 7

N ORWEGIAN T UNNELLING S OCIET Y P UBLICATION NO .

16

7.3 KVITEBJØRN RICH GAS PIPELINE PROJECT


KOLLSNES LANDFALL - TUNNEL SHORE APPROACH

Arild Neby
Thomas K. Mathiesen

ABSTRACT: Condensate travels through the Kvitebjørn Oil Pipeline


Pipelines from offshore oil and gas fields in the North (KOR), which ties into the Troll Oil Pipeline II to
Sea are serving several onshore process plants on the Mongstad (see Figure 1). Based on current plans it is
Norwegian west coast. The shore approach itself is expected to recover roughly 55 billion cubic metres of
normally a challenge as the subsea topography off the gas and 22 million cubic metres of condensate.
coast is rugged and seldom facilitates landfall sites
with gently sloping sandy beaches coming up from the The partners in the license are: Statoil ASA (43.55%),
continental shelf and slope. Large diameter bore holes PetoroAS (30%), Norsk Hydro Produksjon a.s (15%), Total
drilled from within the process plant area through the E&P Norge AS (5%) and Enterprise Oil Norge AS (6.45%)
rocky barrier and out in the sea have been a common
solution for landing pipelines where other methods The article covers the civil aspects of the detail design
have not been available. The bored solutions have and construction of the landfall tunnel section at
however often proved to be expensive. Kollsnes as well as going briefly into the conceptual
design discussions.
For the Kvitebjørn Rich Gas Pipeline the conceptual
solution was a bored landfall with an optional tunnel The Kvitebjørn Landfall tunnel was constructed during
solution alternative. During the detail design phase a the period May - September 2002. The drill and blast
feasibility study on a tunnelled solution combined with tunnelling works commenced on 21 May 2002. Final
underwater tunnel piercing techniques, adapted from piercing at depth -66 m was executed 12 September
the hydropower civil works sector, revealed that for 2002. The civil works part of the project was cost esti-
this project the tunnel solution was feasible. Bids were mated to approximately NOK 25 million.
made to both solutions and after evaluation of bids it
was recommended to go ahead with the tunnel alter- The pipeline was pulled in through the landfall tunnel to
native based on an evaluation of economy, technical Kollsnes on 15 May 2003. Production from Kvitebjørn
aspects and HSE. The Kvitebjørn Landfall tunnel was began on 26 September 2004. The field began deliver-
constructed in 4 months during the summer of 2002. ing natural gas through the pipeline on 1 October 2004.

INTRODUCTION
The Kvitebjørn gas and condensate field lies in block
34/11, east of Gullfaks in the Norwegian North Sea,
operated by Statoil. Production from Kvitebjørn began Oil Pipeline (KOR
in 2004. Rich gas and condensate (light oil) from
Kvitebjørn are piped to Kollsnes near Bergen and
Mongstad further north respectively.

Rich gas from Kvitebjørn is piped in the 147 km long Gas Pipeline (KGR)
OD 30’’ (Ø762 mm) Kvitebjørn Rich Gas Pipeline
(KGR) to the process plant at Kollsnes (see Figure 1).
After processing at Kollsnes, the dry gas is piped to
continental Europe. The separated NGL is transported
by pipeline to the Vestprosess plant at Mongstad for Figure 1: Map showing Kvitebjørn Pipelines
fractionation into propane, butanes and naphtha. (Illustration: Statoil)

77
N ORWEGIAN T UNNELLING S OCIET Y P UBLICATION NO . 16

CONCEPTUAL DESIGN ISSUES The main challenge, as civil works were concerned,
At the conceptual design stage the different landfall was the establishment of the landfall borehole or drill
solutions were not described in detail, only the prin- and blast tunnel. The other parts of the landfall involved
ciples of the landfall design. The chosen alternative only ordinary civil work tasks. By using well known
consisted of a borehole from the sea to Storholmen and technology, careful prequalification procedures of con-
an onshore trench at Storholmen and crossing of the tractors for drilling of the borehole (or excavation of the
Njupselsundet strait (See Figure 1). tunnel) and focus on the design solutions, the construc-
tion of the borehole (or the tunnel) was at this stage
considered also to be well within a safe execution.

The feasibility study on the tunnel solution resulted in a


recommendation to go ahead with the tunnel alternative
based on an evaluation of economy, technical aspects
and HSE. The different evaluation aspects for the two
alternatives are summarised in Table 1.

For the recommended alternative with a tunnel solution,


a range of risk reducing measures was identified as
Figure 2: Pipeline route longitudinal section - bored solution shown in Table 2.
(Illustration: Statoil / ABB)

Evaluation Aspect Alternative 1 - Borehole Alternative 2 - Tunnel


(Ø914 mm / Ø1200 mm) (A=12-14 m2)
Cost Elements – Ø914 mm: 120 -140 % of tunnel cost – Linear meter tunnel cost = 100 %
– Ø1200 mm: 180 – 200% of tunnel cost
HSE - – Personnel: 5-10 persons. – Personnel: 25 - 30 persons (total for two
Risk Elements – Few moving vehicles or mobile equipment shift)
involved in work execution. One bore – Min. one tunnel rig, one LHD loader
machine (rotating), truck or other lifting and one scaling/rock support truck. Pick-
equipment for handling of drill rods or up truck for transport of explosives and
other equipment. materials. Towboat and barge for muck
– Sea transportation for personnel only and transportation.
for mobilisation/demobilisation. – Personnel staying below sea level
dependent on continuous power supply for
pumps, ventilation and lighting.
– Small cross-section tunnel gives limited
access in case of accidents.
– Transportation and storage of explosives.
Work Execution - – Risks related to the ability of borehole – Risks related to minimal rock cover and
Risk Elements completion within the contract time frame possibility of major water ingress due to
in case of unpredicted conditions. lack of pre-grouting or lining
– The tunnel alternative serves as “Back-up” – No planned “back-up” solution.
solution. – Risks related to failure of piercing blast
and subsequent rectifying underwater
works at - 65 m depth for preparation of
the pull-in operation.
Mobilisation Area – Requires a relatively large rig and – Rig and mobilisation area can be reduced
and Trench Works mobilisation area. to the minimum required by the contractor.
Elements – Possible pipeline alignment line-up or – The tunnel can easily be adapted to the
adaptation will cause additional landscape pipeline alignment without additional cost.
damage at Storholmen Island in order to
optimise strait-crossing of Njupselsundet.
Table 1: Evaluation of shore approach alternatives

78
N ORWEGIAN T UNNELLING S OCIET Y P UBLICATION NO . 16

Area of Risk Alternative 2 - Tunnel (A=12-14 m2)


Reducing
Measures
HSE - – Provide continuous manning of personnel skilled at HSE follow-up at the Kollsnes site.
Risk Reducing – Staff the Client’s site team with necessary engineering geological competence to ensure
Measures safe tunnelling execution.
– Execute “HAZOP” and ”toolbox” meetings related to the various work operations.
– Place a safety container for tunnel excavation works at Storholmen Island.
– Utilisation of Statoil Incident Report Register, to identify accidents and risks from similar
work operations/projects.
– Prepare Emergency Action and Notification Plan in cooperation with the Process Plant
– Quality assurance follow-up on machines and equipment, provide back-up power supply
for pumps, lighting and ventilation.
Work Execution -
Risk Reducing – Ensure correct execution and adequate extent of rock mass pre-grouting.
Measures – Planning and verification of underwater tunnel piercing blast.
– Evaluate the need for computer model analysis of the piercing blast.
– Prepare for possible submerged operations by establishing contact with sub-sea excavation
contractors
Table 2: The Client’s identified risk reducing measures for the tunnel alternative

DETAIL DESIGN
Design Basis
The basis for the landfall tunnel solution is as listed
below:
• Tunnel data:
Length approximately 400 m. Slope 1:6.
Water filled during pull-in.
• Pipeline data:
ID : 710 mm, wall thickness: 28,7 mm
Coating : 6 mm asphalt enamel and 50 mm
concrete weight coating
OD incl. coating : 880 mm
• Level of piercing point shall be between 2.5 and 4.5 m
above sea bottom which is situated at approximately
-68 m depth. Figure 3: Long joints belonging to set 1 intersecting the rock
masses. Some sub-horizontal foliation joints can also be
Geological Conditions seen. (Photo: Statoil / Norconsult)
The geological conditions for the project was based on
surface mapping on the island “Storholmen” and on
information gathered from core drilling. Although a sig-
nificant part of the tunnel, as well as the piercing point,
was under the seabed outside Storholmen, the geology
of the area was generally expected to correspond well
with that which was observed / mapped. However, the
joint orientations were expected to vary to some extent,
due to folding and faulting.

The project area is located in Middle Precambrian


rocks, i.e. rocks with age 900 to 2500 million years. The
rocks within the project area consist mainly of granitic
gneisses with some minor layers of dark amphibolitic
gneiss. These layers often display de-lamination and are
sometimes accompanied by higher joint density and/or
clay-filled joints. A few pegmatite lenses have been Figure 4: Joints of set 2. The ruler shown is 30 cm long.
observed. (Photo: Statoil / Norconsult)

79
N ORWEGIAN T UNNELLING S OCIET Y P UBLICATION NO . 16

The foliation of the gneiss strikes generally NE-SW Locally, the joints in sets 2 and 3 have only 0.02 - 0.2 m
with a gentle dip (0° - 15°) towards SE. Joints along spacing forming joint zones. The width of such zones is
the foliation form the main joint set 1 with joint spacing most often 0.2 - 3 m. In some zones the spacing between
mainly between 0.2 and 2 metres. the joints is so short that the zone may have the charac-
ter of a crushed zone.
The two other joint sets are steep-dipping and occur
approximately normal to joint set 1. The identified weakness zones generally follow the
direction of the two steep-dipping joint sets.
Set 2 with strike/dip = 140 - 170°/80 - 90º E, joint
spacing 0.3 - 3 m, and Generally the geological conditions were found to be
Set 3 having strike/dip = 30 - 50º /90º and joint spacing relatively good, and hence, favourable for a sub-sea
0.2 - 3 m. tunnel. Uncertainty regarding permeability of the rock
mass, especially in the piercing area, was to be given
The joints occur unevenly distributed, in some areas special attention during construction phase. Thorough
only one joint set occurs, in others all three sets. In gen- and continuous routines for exploratory drilling and
eral, the joints divide the rocks into blocks, which vary grouting, throughout the entire excavation period of the
between 0.1 m³ and 3 m³. Most joints have rough joint landfall tunnel as well as at the piercing itself, were a
surface with slightly undulating joint planes. prerequisite.

Figure 5: Engineering geological map showing pipeline route and location of core-drilled hole. (Illustration: Norconsult)

80
N ORWEGIAN T UNNELLING S OCIET Y P UBLICATION NO . 16

Figure 6: Stereographic pole-plot from joint mapping at Storholmen. The different poles are denoted as follows: F = foliation;
J = joint sets; W = weakness zones/faults. The great circles illustrate the average strike and dip of the three main joint sets.
(Illustration: Norconsult)

LANDFALL TUNNEL DESIGN decline was possible but not found to be beneficial to
Tunnel longitudinal section the project.
The topography dictates the geometrical constraints According to refraction seismic surveys performed in
for tunnel alignment. As the location of the piercing 1990, the rock mass in the area of the sub-sea tunnel is
point must be aligned with the pipeline in the tunnel generally good. However, the maximum rock overbur-
and the piercing point has to be just above the sea bot- den in the sub-sea part of the tunnel is about 26 m, and
tom sediments, as well as the tunnel should start at an a significant length of the tunnel will be excavated with
elevation safe from spring tide sea level, - the straight rock overburden less than 15 m, see Figure 7. This is
line between these geometrical “fix points” has a grade less than a normally used criterion for sub-sea tunnel-
approximately 1:6. Excavating the tunnel at a steeper ling.

Figure 7: Longitudinal section and plan of landfall tunnel. (Illustration: Statoil / Norconsult)

81
N ORWEGIAN T UNNELLING S OCIET Y P UBLICATION NO . 16

Tunnel cross-section Rig and Mobilisation Area


To accommodate the pipeline in the operating phase, the The rig and mobilisation area was established by exca-
cross section of the tunnel should be as small as possi- vating the tunnel entrance open cut large enough to
ble. The pull-in operation was in principle the same as facilitate the contractor’s need for rig and mobilisation
for the 1 m diameter borehole. The optimum size of the space. The rock masses from the submerged trench
tunnel cross-section would therefore be determined by and the entrance cut excavation was used to temporary
the space requirements for the tunnelling equipment and round off the adjacent terrain formations for later re-
ventilation duct in the construction phase. Towards the allocation to natural terrain.
piercing point, where the overburden was thinner, the
cross section was to be reduced. Tunnel Excavation
The tunnel was constructed by the Norwegian contrac-
tor NCC Construction for the purpose of hosting one
pipeline with an approximate outer diameter of 900
mm. The contractor chose an approximate 3 x 4 m cross
section (width/height) as an optimal dimension based
on the tunnelling equipment to be used, - resulting in
an average cross-section of about 15-16 m2. The total
length of the tunnel is 407 m, starting in a pit at eleva-
tion -0.8 m with an average decline of 1:6.2.

Due to the small rock cover thickness at certain portions


of sub-sea tunnel and expected water bearing weakness
zones, exploratory drilling to both sides of the tunnel as
well as above the crown, was performed through-out the
sub-sea tunnel length. At positions where exceptionally
low rock cover was expected, holes were drilled out
into the sea for verification purposes. Special packers
were used to plug these holes after penetration of the
sea bottom.

The tunnel was excavated by traditional drill and blast


Figure 8: Cross-section of landfall tunnel. technique with a hydraulic 2-boom tunnel jumbo. The
(Illustration: Statoil / Norconsult) normal drill length in this tunnel was 4.5 m, resulting
in approximately 4 m effective advance per round.
Tunnel internals Mucking out was performed with an LHD (Load-Haul-
The requirements for the internals of the tunnel had to Dump) truck. Approximately half way down the tunnel,
take into consideration both the pull-in phase and the a niche capable of storing about one tunnel blast round
operating phase. of muck was established in order to reduce the time
necessary to clear the face and to make an earlier restart
The tunnel was designed for a 25 years lifetime. For of drilling for the next round possible.
protection of the pipeline, necessary rock support was to
be installed in the tunnel to avoid damage to the pipeline Ground Water Control
from rock down-fall in the pipeline life time. During the whole construction period, grouting material
and equipment was standby on the construction site.
The pipeline was to be pulled in from the lay barge From the point where the tunnel passes the shoreline
through the piercing opening and through the tunnel by and continues sub-sea, 3 exploratory holes of 18 m
a winch, which was eventually located onshore at the length were drilled for every 3rd round. In case of water
Kollsnes side of Njupselsundet. The pipeline should ingress, grouting would be performed as necessary. As a
be protected by a suitable method during the pull-in to guideline criterion, grouting would commence if water
avoid damage to the coating and the anodes. It was sug- ingress exceeded 5 l/min in one hole or 10 l/min in total
gested that the pipeline should be pulled in on a concrete for all the holes at one face.
slab on the tunnel invert, see Figure 8.
The rock mass was found to be almost impermeable
as the discontinuities were mostly filled with fine silt
CONSTRUCTION PHASE and clay. Some clay samples showed slightly swelling
The construction phase was divided in to stages, 1) trench properties but these zones were small and confined in
and rig area excavation and 2) tunnel excavation. between solid rock mass. Throughout the whole tunnel,

82
N ORWEGIAN T UNNELLING S OCIET Y P UBLICATION NO . 16

grouting was only performed at one location, in addition


to the final 5-10 m before the piercing point.

Rock Support
Due to the small cross-section of the tunnel and the
good geological conditions (rock mass quality, water
ingress, stress etc.), the tunnel is mostly unsupported.
Systematic manual scaling after each blast round took
care of the safety aspect and reduced the need of tempo-
rary support to a minimum.

• Approximately 30 bolts are installed in the cut at


the tunnel entrance. The bolts are 2.4 - 3.0 m long,
Ø20 mm, galvanised and end-anchored with polyester
resin. A total of 10 m of galvanised steel band has been
installed between bolts to stabilise larger blocks.

Figure 10: Tunnel portion with repeated parallel clay zones.


(Photos: Statoil / Norconsult)

REFERENCES
Figure 9: Installed rock support in the tunnel entrance open 1. Norconsult Report (26 September 2001):
cut area. (Photo illustration: Norconsult) “Kvitebjørn Rich Gas Project, Kollsnes
Landfall - Civil Engineering, Conceptual Design
• 101 bolts are installed throughout the tunnel mostly in Review”, Project No. 3505000, 8 pages
the roof and northern wall. The bolts are 2.4 - 3.0 m
long, Ø20 mm, galvanised and end-anchored with 2. Norconsult Report (19 November 2001):
polyester resin. 2 m of galvanised steel band has been “Kvitebjørn Gas Pipeline, Kollsnes Landfall - Civil
applied. The Client’s project engaged engineering Engineering, Geological Evaluation Report”, Project
geologist has marked out in detail all bolts installed on No. 3505000, 9 pages
tunnel mapping sheets.
3. Norconsult Report (19 December 2001):
• No shotcrete was applied in the tunnel. “Kvitebjørn Rich Gas Pipeline, Kollsnes Landfall - Civil
Engineering, Underwater Tunnel Piercing Feasibility
Rock Mass Conditions Report”, Project No. 3505000, 14 pages
The tunnel construction work was performed without
any major difficulties. The only few halts were caused 4. Statoil Presentation (2002):
by breakdown of machines and pumps. “Sammenligning borehull - sprengt tunnel”, 8 pages (in
Norwegian)
The most challenging area due to geological conditions
was found over a 20 m long distance between chainage 5. Norconsult Report (6 January 2003):
275 m and 295 m, caused by 3-4 densely jointed distinct “Kvitebjørn Rich Gas Pipeline, Kollsnes Landfall -
zones with clay, silt and crushed rock mass spaced some Civil Engineering, As-Built Documentation Geology”,
4-5 m apart. The excavation in this area was performed Project No. 3505000, 6 pages + Appendices 12 pages
by shorter rounds, 2 - 2.5 m long and thorough scaling
of the roof and walls of the tunnel. 6. NCC Construction Report (27 August 2003):
“Erfaringsoverføringsrapport - Kvitebjørn
landfall, Kollsnes”, Contract No. 4500434160, 13 pages
(in Norwegian)

83

Vous aimerez peut-être aussi