To,

The Chief Engineer (R&B)
Buildings & Rural roads,
Hyderabad.

(Through proper channel)

Sir,

Sub:   Improvements   to   Pebbair   –   Yaparla   road   from   km   8/6   to   14/4   in


Mahabubnagar District – Extension of Time – Requested – Regarding.

Ref: 1) SE/R&B/MBNR AB.NO.79/2013­14 DT 25.02.2014.
     2) CE/R&B/Buildings & Rural Roads, Hyd Memo.No.RDF(13TH FC)P­Y
road ­11/DCE(B)/EE(B)/DEE2(RR)/AEE­4 (RR)/2012 dt.08.06.15.

***  **  ***

I submit that the above work was let out to me vide reference 1 st  cited, to

complete the work within 6 months i.e., up to 24.08.2014. But the work got delayed

due to Material & Labour problem and also due to heavy rains.

I have completed the WMM work in sanctioned reaches for the above work

and I have completed the BT work in WMM reaches.

The work contract is revoked vide reference 2nd cited, hence I request the Chief

Engineer (R&B) Buildings & Rural roads, Hyderabad to kindly grant EOT for the

above work up to 15.06.2015 without imposing liquidated damages to complete the

work in all respects.
Yours Faithfully,

   (P.Ramesh)

To,
The Chief Engineer (R&B)
Buildings & Rural roads,
Hyderabad.

(Through proper channel)

Sir,

Sub:   Improvements   to   Pebbair   –   Yaparla   road   from   Km.0/0   to   14/2   in


Mahabubnagar District (work in reach from Km.0/0 to 8/6) – Extension
of Time – Requested – Regarding.

Ref: 1) SE/R&B/MBNR AB.No.57/2013­14 Dt:09/01/2014.
       2)   C.E.,   (R&B)   Bldgs,   &   R.R.,   Hyd.,   Memo   No.EDF(13 th  FC)/P­Y
Road  /DCE(B)/EE(B)/DEE­2(RR)/AEE­4(RR)/2012, Dt:08/06/2015. 
***  **  ***

I submit that the above work was let out to me vide reference 1 st  cited, to

complete the work within 6 months i.e., up to 24.08.2014. But the work got delayed

due to Material & Labour problem and also due to heavy rains.

I have completed the WMM work in sanctioned reaches for the above work

and I have completed the BT work in WMM reaches.
The work contract is revoked vide reference 2nd cited, hence I request the Chief

Engineer (R&B) Buildings & Rural roads, Hyderabad to kindly grant EOT for the

above work up to 15.06.2015 without imposing liquidated damages to complete the

work in all respects.

Yours Faithfully,

   (P.Ramesh)
To,
The Engineer­In­Chief,
State roads & CRN,
Errumanzil, Hyderabad.

(Through proper channel)

Sir,

Sub: Widening of Single lane road to Double lane road to connecting Mandal
Head Quarters to District Head Quarters for Nellikondi – Allipur road
from km.0/0 to 15/0 in Mahabubnagar District – Extension of Time –
Requested – Regarding.

Ref: 1) SE/R&B/MBNR AB.No.86/2015­16 Dt:04/01/2016.
 
***  **  ***

I submit that the above work was let out to me vide reference 1 st  cited, to

complete the work within 12 months i.e., up to 03.01.2017. The work is in progress.

But the work got delayed due to several problems like Non availability of Sand,

Labour problem, Land Acquisition problem and Shifting of poles and could not be

completed with in the Agrement period.  

In view of the above circumstances I request the Engineer­In­ chief (R&B)

State roads & CRN, Hyderabad to kindly grant EOT for the above work for a period

of   12   months   i.e.,   up   to   03.01.2018   without   imposing   liquidated   damages   to

complete the work in all respects.

Yours Faithfully,
   (P.Ramesh)
Special Class Contractor.
To,
The Engineer­In­Chief,
State roads & CRN,
Errumanzil, Hyderabad.

(Through proper channel)

Sir,

Sub: Widening of Single lane road to Double lane road to connecting Mandal
Head Quarters to District Head Quarters on Tunkimetla­Narayanpet road
from km.56/0 to 67/137 in Mahabubnagar District – Extension of Time –
Requested – Regarding.

Ref: 1) SE/R&B/MBNR AB.No.87/2015­16 Dt:04/01/2016.
 
***  **  ***

I submit that the above work was let out to me vide reference 1 st  cited, to

complete the work within 12 months i.e., up to 03.01.2017. The work is in progress.

But the work got delayed due to several problems like Non availability of Sand,

Labour problem, alignment of Ghat Section, Land Acquisition problem and Shifting

of poles and could not be completed with in the Agrement period.  

In view of the above circumstances I request the Engineer­In­ chief (R&B)

State roads & CRN, Hyderabad to kindly grant EOT for the above work for a period

of   12   months   i.e.,   up   to   03.01.2018   without   imposing   liquidated   damages   to

complete the work in all respects.

Yours Faithfully,
   (P.Ramesh)
Special Class Contractor.

GOVERNMENT OF TELANGANA
ROADS AND BUILDINGS DEPARTMENT

From, TO,
Sri.K.Sardar Singh, B.Tech., District (R&B) Officer,
Dy.Executive Engineer, (R&B) Mahabubnagar District.
Sub­Divn, Kodangal.

 Lr.No.DEE/R&B/Kodangal/       
             
             
             
   Dt.      02.01.2017  .
Sir,

Sub: Widening of Single lane road to Double lane road to connecting Mandal Head
Quarters   to   District   Head   Quarters   on   Tunkimetla­Narayanpet   road   from
km.56/0 to 67/137 in Mahabubnagar District – Extension of Time – Requested
– Regarding.

Ref: 1) SE/R&B/MBNR AB.No.87/2015­16 Dt:04/01/2016.
        2) Representation of Sri.P.Ramesh, Spl.Class contrator Dt.    28.12.2016.

***

I submit that the above work was let out to Sri.P.Ramesh, Spl. Class contractor,
vide reference 1st cited, to complete the work within 12 months i.e., up to 03.01.2017. The
work is in progress and the Contractor could not complete the work within the Agreement
period. 

The Contractor has requested vide reference 2nd cited, to Grant EOT for the above
work for a period of 12 months i.e., up to 03.01.2018 stating that the work got delayed due
to problems like Non availability of Sand, Labour problem, alignment of Ghats Section,
Land Acquisition problem and Shifting of poles.  

In this regard I submit the EOT proposals to Grant EOT for the above work for a
period of 12 months i.e., up to 03.01.2018 without imposing liquidated damages.

This is submitted for favour of further disposal. 

Yours Faithfully,

                Dy.Executive Engineer, 
(R&B)Sub­Divn, Kodangal.
GOVERNMENT OF TELANGANA
ROADS AND BUILDINGS DEPARTMENT

From, TO,
Sri.N.Balaswamy B.E., The Superintending Engineer,
Executive Engineer, (R&B) (R&B) Circle::Mahabubnagar 
Division:: Mahabubnagar.

 Lr.No.DB / D2/ /R&B/Kodangal/ EOT             
             
             
   Dt.      .01.2017  .

Sir,

Sub: Widening of Single lane road to Double lane road to connecting Mandal Head
Quarters   to   District   Head   Quarters   on   Tunkimetla­Narayanpet   road   from
km.56/0 to 67/137 in Mahabubnagar District – Extension of Time – Requested
– Regarding.

Ref: 1) SE/R&B/MBNR AB.No.87/2015­16 Dt:04/01/2016.
        2) Representation of Sri.P.Ramesh, Spl.Class contrator Dt.    28.12.2016.

***

I submit that the above work was let out to Sri.P.Ramesh, Spl. Class contractor,
vide reference 1st cited, to complete the work within 12 months i.e., up to 03.01.2017. The
work is in progress and the Contractor could not complete the work within the Agreement
period. 

The Contractor has requested vide reference 2nd cited, to Grant EOT for the above
work for a period of 12 months i.e., up to 03.01.2018 stating that the work got delayed due
to problems like Non availability of Sand, Labour problem, alignment of Ghats Section,
Land Acquisition problem and Shifting of poles.  

In this regard I submit the EOT proposals to Grant EOT for the above work for a
period of 12 months i.e., up to 03.01.2018 without imposing liquidated damages.
This is submitted for favour of further disposal. 

Yours Faithfully,

              
     Executive Engineer(R&B),
    Division :: Mahabubnagar
GOVERNMENT OF TELANGANA
ROADS AND BUILDINGS DEPARTMENT

From, TO,
Sri.                        , B.Tech., District (R&B) Officer,
Dy.Executive Engineer, (R&B) Mahabubnagar District.
Sub­Divn, Makthal.

 Lr.No.DEE/R&B/Makthal/         
             
             
             
   Dt.       .      .201  .
Sir,

Sub: Widening of Single lane road to Double lane road to connecting Mandal
Head Quarters to District Head Quarters for Nellikondi – Allipur road
from km.0/0 to 15/0 in Mahabubnagar District – Extension of Time –
Requested – Regarding.

Ref: 1) SE/R&B/MBNR AB.No.86/2015­16 Dt:04/01/2016.
        2) Representation of Sri.P.Ramesh, Spl.Class contrator Dt.       .12.2016.

***

I submit that the above work was let out to Sri.P.Ramesh, Spl.Class contrator, vide
reference 1st cited, to complete the work within 12 months i.e., up to 03.01.2017. The work
is in progress and the Contrator could not complete the work with in the Agrement period. 

The Contractor has requested vide reference 2nd cited, to Grant EOT for the above
work for a period of 12 momths i.e., up to 03.01.2018 stating that the work got delayed due
to problems like Non availability of Sand, Labour problem, Land Acquisition problem and
Shifting of poles.  

In this regard I submit the EOT proposals to Grant EOT for the above work for a
period of 12 months i.e., up to 03.01.2018 without imposing liquidated damages.

This is submited for favour of further disposal. 
Yours Faithfully,

                Dy.Executive Engineer, 
(R&B)Sub­Divn, Makthal.