10 Pile Cap
sb19 Concrete Pumping 1,649.30 cy 1,417.06 cy 232.24 cy 12.78 /cy 12.78 /cy 0.00 /cy 21,073 18,105 2,967
01 Count Pile Caps 269.00 ea 262.00 ea 7.00 ea /ea
02 Clean Up Pile/Projected Dowel 791.00 ea 703.00 ea 88.00 ea 11.65 /ea 11.65 /ea 0.00 /ea 9,214 8,189 1,025
10 Form & Strip Pile Caps 23,425.31 sf 21,524.90 sf 1,900.41 sf 3.863 /sf 3.863 /sf 0.00 /sf 90,480 83,140 7,340
15 Drill/Grout Dowel 3,164.00 each 2,812.00 each 352.00 each 19.65 /each 19.65 /each 0.00 /each 62,166 55,250 6,916
0410 4000 PSI Reg. Wt. 1" Aggregate 1,649.30 cy 1,417.06 cy 232.24 cy 87.01 /cy 87.01 /cy 0.00 /cy 143,506 123,298 20,207
40 Place Concrete At Pile Cap 1,649.30 cy 1,417.06 cy 232.24 cy 9.32 /cy 9.32 /cy 0.00 /cy 15,369 13,205 2,164
20 Finish/Cure Footing/Pile Cap 17,004.39 sf 11,049.74 sf 5,954.65 sf 0.302 /sf 0.302 /sf 0.00 /sf 5,136 3,337 1,798
10 Pile Cap 1,649.30 cy 1,417.06 cy 232.24 cy 210.36 /cy 214.90 /cy (4.54) /cy 346,943 304,524 42,418
14 Elev Pit
45 Blockout Keyway in slab/fdn below 213.50 lf 213.50 lf 0.00 lf 0.79 /lf 0.79 /lf 0.00 /lf 169 169 0
10 Form Pit Base Slab 225.50 sf 225.50 sf 0.00 sf 1.95 /sf 1.95 /sf 0.00 /sf 440 440 0
25 Form Pit Wall 40.00 sf 40.00 sf 0.00 sf 2.50 /sf 2.50 /sf 0.00 /sf 100 100 0
10 Install Keyway in top of wall 1,708.02 lf 1,708.02 lf 0.00 lf 0.83 /lf 0.83 /lf 0.00 /lf 1,418 1,418 0
30 Waterstop - RX Volclay 213.50 lf 213.50 lf 0.00 lf 2.153 /lf 2.153 /lf 0.00 /lf 460 460 0
0410 4000 PSI Reg. Wt. 1" Aggregate 26.03 cy 26.03 cy 0.00 cy 87.01 /cy 87.01 /cy 0.00 /cy 2,265 2,265 0
20 Place Pit Wall 26.03 cy 26.03 cy 0.00 cy 13.75 /cy 13.75 /cy 0.00 /cy 358 358 0
10 Finish / Cure Pit Base 717.12 sf 717.12 sf 0.00 sf 0.383 /sf 0.383 /sf 0.00 /sf 275 275 0
38 Defin/Point Patch Walls 1,708.02 sf 1,708.02 sf 0.00 sf 0.25 /sf 0.25 /sf 0.00 /sf 427 427 0
14 Elev Pit 2.00 ea 2.00 ea 0.00 2,955.10 /ea 2,955.10 /ea 0.00 5,910 5,910 0
16 Plinth
10 Form Square Piers / Pedistals / Plinths 2,476.33 sf 2,435.00 sf 41.33 sf 9.94 /sf 9.94 /sf 0.00 /sf 24,615 24,204 411
10 Furnish Chamfer Materials 800.00 lf 736.00 lf 64.00 lf 0.11 /lf 0.11 /lf 0.00 /lf 88 81 7
0510 5000 PSI Reg. Wt. 1" Aggregate 74.37 cy 75.00 cy -0.63 cy 90.20 /cy 90.20 /cy 0.00 /cy 6,708 6,765 (57)
10 Place Concrete At Piers / Pedistals / Plinths 74.37 cy 75.00 cy -0.63 cy 93.184 /cy 93.184 /cy 0.00 /cy 6,930 6,989 (59)
38 Defin/Point Patch Walls 2,476.33 sf 2,435.00 sf 41.33 sf 1.11 /sf 1.11 /sf 0.00 /sf 2,749 2,703 46
16 Plinth 74.37 cy 75.00 cy -0.63 cy 552.504/cy 543.22 /cy 9.284/cy 41,090 40,742 348
20 SOG
fg10 Place/Finegrade Base-Machine 34.00 sf 34.00 sf 0.00 sf 0.921 /sf 0.921 /sf 0.00 /sf 31 31 0
sb19 Concrete Pumping 2.64 cy 2.64 cy 0.00 cy 273.98 /cy 273.98 /cy 0.00 /cy 723 723 0
15 Form Slab Edge Over 12" 46.00 sf 46.00 sf 0.00 sf 5.652 /sf 5.652 /sf 0.00 /sf 260 260 0
0410 4000 PSI Reg. Wt. 1" Aggregate 2.64 cy 2.64 cy 0.00 cy 87.01 /cy 87.01 /cy 0.00 /cy 230 230 0
0020 Place Concrete At Slab On Grade-SF 34.00 sf 34.00 sf 0.00 sf 2.79 /sf 2.79 /sf 0.00 /sf 95 95 0
0010 Finish Slab On Grade - Smooth Trowel 34.00 sf 34.00 sf 0.00 sf 7.132 /sf 7.132 /sf 0.00 /sf 242 242 0
01 Membrane Curing Compound 34.00 sqft 34.00 sqft 0.00 sqft 0.71 /sqft 0.71 /sqft 0.00 /sqft 24 24 0
20 SOG 34.00 sf 34.00 sf 0.00 47.23 /sf 47.23 /sf 0.00 1,606 1,606 0
23 Mud Slab
fg10 Place/Finegrade Base-Machine 202,470.00 sf 201,366.00 sf 1,104.00 sf 0.16 /sf 0.16 /sf 0.00 /sf 31,683 31,510 173
sb19 Concrete Pumping 1,968.45 cy 1,957.72 cy 10.730 cy 6.89 /cy 6.89 /cy 0.00 /cy 13,559 13,485 74
10 Form & Strip Slab Edge to 12" 4,224.00 lf 4,180.00 lf 44.00 lf 3.334 /lf 3.334 /lf 0.00 /lf 14,082 13,936 147
c 25 MudSill Conc 2500 psi 1,968.45 cuyd 1,957.72 cuyd 10.730 cuyd 81.00 /cuyd 81.00 /cuyd 0.00 /cuyd 159,444 158,575 869
15 Place/Finish / Cure Mud Sill 202,470.00 sf 201,366.00 sf 1,104.00 sf 0.41 /sf 0.41 /sf 0.00 /sf 83,013 82,560 453
23 Mud Slab 202,470.00 sf 201,366.00 sf 1,104.00 sf 1.49 /sf 1.49 /sf 0.00 301,781 300,066 1,715
30 Typ Column
0000 Column Shop Make-Up 6.00 ea 6.00 ea 0.00 ea 305.76 /ea 305.76 /ea 0.00 /ea 1,835 1,835 0
0000 Column Field Rework 12.00 ea 12.00 ea 0.00 ea 162.912 /ea 162.912 /ea 0.00 /ea 1,955 1,955 0
0000 Furnish Columns Form Assembly 6.00 ea 6.00 ea 0.00 ea 1,159.390 /ea 1,159.390 /ea 0.00 /ea 6,956 6,956 0
0000 Furnish Chamfer Materials 2,930.00 lf 2,930.00 lf 0.00 lf 0.11 /lf 0.11 /lf 0.00 /lf 322 322 0
Estimate Company Variance Report Page 2
Ameristar Lowrise 1/25/2013 3:07 PM
30 Typ Column
0000 Column Forms Lumber Materials 300.00 bdft 300.00 bdft 0.00 bdft 0.75 /bdft 0.75 /bdft 0.00 /bdft 225 225 0
0015 Form & Strip Columns @ 3'-6" Tall 0.00 ea 12.00 ea -12.00 ea 162.912 /ea (162.91) /ea 1,955 (1,955)
0015 Form & Strip Columns @ 5'-0" Tall 10.00 ea 10.00 ea 217.22 /ea 217.22 /ea 2,172 2,172
0015 Form & Strip Columns @ 8'-0" Tall 4.00 ea -4.00 ea 162.913 /ea (162.91) /ea 652 (652)
0015 Form & Strip Columns @ 12'-0" Tall 0.00 ea 14.00 ea -14.00 ea 162.912 /ea (162.91) /ea 2,281 (2,281)
0015 Form & Strip Columns @ 16'-0" Tall 4.00 ea 1.00 ea 3.00 ea 325.83 /ea 325.82 /ea 0.005 /ea 1,303 326 977
0015 Form & Strip Columns @ 24'-0" Tall 14.00 ea 15.00 ea -1.00 ea 597.344 /ea 597.344 /ea 0.00 /ea 8,363 8,960 (597)
0510 5000 PSI Reg. Wt. 1" Aggregate 199.50 cy 231.47 cy -31.97 cy 90.20 /cy 90.20 /cy 0.00 /cy 17,995 20,879 (2,884)
20 Place Columns Concrete 199.50 cy 231.47 cy -31.97 cy 31.061 /cy 31.061 /cy 0.00 /cy 6,197 7,190 (993)
38 Defin/Point Patch Columns 6,216.00 sf 7,680.00 sf -1,464.00 sf 0.381 /sf 0.381 /sf 0.00 /sf 2,370 2,928 (558)
30 Typ Column 199.50 cy 231.47 cy -31.97 cy 249.09 /cy 243.931/cy 5.16 /cy 49,693 56,463 (6,770)
40 Retainer Wll
45 Blockout Keyway in slab/fdn below 1,286.00 lf 1,083.00 lf 203.00 lf 1.103 /lf 1.103 /lf 0.00 /lf 1,418 1,194 224
10 Install Keyway in top of wall 1,286.00 lf 1,083.00 lf 203.00 lf 1.14 /lf 1.14 /lf 0.00 /lf 1,464 1,233 231
0000 Furnish Basement Retainer Walls Form Assembly 2,160.00 sf 2,160.00 sf 0.00 sf 2.70 /sf 2.70 /sf 0.00 /sf 5,832 5,832 0
0210 Form & Strip Basement/Retainer Wall 18,849.00 sf 12,966.00 sf 5,883.00 sf 2.72 /sf 2.72 /sf 0.00 /sf 51,269 35,268 16,002
30 Furnish & Install Waterstop - RX Volclay 1,286.00 lf 1,083.00 lf 203.00 lf 2.71 /lf 2.71 /lf 0.00 /lf 3,479 2,930 549
0410 4000 PSI Reg. Wt. 1" Aggregate 271.02 cy 127.00 cy 144.02 cy 87.01 /cy 87.01 /cy 0.00 /cy 23,581 11,050 12,531
20 Place Wall Concrete 271.02 cy 127.00 cy 144.02 cy 23.30 /cy 23.30 /cy 0.00 /cy 6,314 2,959 3,355
38 Defin/Point Patch Retainer Walls 15,432.00 sf 12,966.00 sf 2,466.00 sf 0.381 /sf 0.381 /sf 0.00 /sf 5,883 4,943 940
40 Retainer Wll 15,432.00 csf 12,966.00 csf 2,466.00 csf 6.431/csf 5.05 /csf 1.39 /csf 99,240 65,408 33,832
41 Strt Wall
45 Blockout Keyway in slab/fdn below 71.00 lf 78.00 lf -7.00 lf 1.103 /lf 1.103 /lf 0.00 /lf 78 86 (8)
10 Install Keyway in top of wall 71.00 lf 78.00 lf -7.00 lf 1.14 /lf 1.14 /lf 0.00 /lf 81 89 (8)
0210 Form & Strip Straight Wall 3,330.00 sf 3,666.00 sf -336.00 sf 2.263 /sf 2.263 /sf 0.00 /sf 7,536 8,296 (760)
30 Waterstop - RX Volclay 142.00 lf 156.00 lf -14.00 lf 2.71 /lf 2.71 /lf 0.00 /lf 384 422 (38)
0510 5000 PSI Reg. Wt. 1" Aggregate 53.93 cy 59.40 cy -5.47 cy 90.20 /cy 90.20 /cy 0.00 /cy 4,864 5,358 (493)
20 Place Wall Concrete 53.93 cy 59.40 cy -5.47 cy 23.30 /cy 23.30 /cy 0.00 /cy 1,256 1,384 (127)
38 Defin/Point Patch Walls 3,330.00 sf 3,666.00 sf -336.00 sf 0.381 /sf 0.381 /sf 0.00 /sf 1,270 1,398 (128)
41 Strt Wall 3,330.00 csf 3,666.00 csf -336.00 csf 4.65 /csf 4.65 /csf 0.00 /csf 15,469 17,032 (1,563)
42 Core Wall
45 Blockout Keyway in slab/fdn below 348.00 lf 237.00 lf 111.00 lf 1.103 /lf 1.103 /lf 0.00 /lf 384 261 122
10 Furnish Chamfer Materials 635.00 lf 435.00 lf 200.00 lf 0.501 /lf 0.501 /lf 0.00 /lf 318 218 100
10 Install Keyway in top of wall 348.00 lf 237.00 lf 111.00 lf 1.14 /lf 1.14 /lf 0.00 /lf 396 270 126
0000 Wallform Assembly Make-Up 2,160.00 csf 2,160.00 csf 0.00 csf 2.73 /csf 2.73 /csf 0.00 /csf 5,897 5,897 0
0000 Furnish Core Walls Form Assembly 2,160.00 sf 2,160.00 sf 0.00 sf 18.644 /sf 18.644 /sf 0.00 /sf 40,271 40,271 0
0210 Form & Strip Elevator Cores 16,776.00 sf 11,221.00 sf 5,555.00 sf 2.72 /sf 2.72 /sf 0.00 /sf 45,631 30,521 15,110
30 Waterstop - RX Volclay 348.00 lf 237.00 lf 111.00 lf 2.71 /lf 2.71 /lf 0.00 /lf 941 641 300
0510 5000 PSI Reg. Wt. 1" Aggregate 270.98 cy 190.61 cy 80.37 cy 90.20 /cy 90.20 /cy 0.00 /cy 24,442 17,193 7,249
20 Place Wall Concrete 270.98 cy 190.61 cy 80.37 cy 31.061 /cy 31.061 /cy 0.00 /cy 8,417 5,921 2,496
38 Defin/Point Patch Core Walls 16,776.00 sf 11,221.00 sf 5,555.00 sf 0.381 /sf 0.381 /sf 0.00 /sf 6,396 4,278 2,118
42 Core Wall 16,776.00 csf 11,221.00 csf 5,555.00 csf 7.934/csf 9.40 /csf (1.465)/csf 133,093 105,471 27,622
44 Stem Wall
45 Blockout Keyway in slab/fdn below 117.00 lf 117.00 lf 0.00 lf 1.103 /lf 1.103 /lf 0.00 /lf 129 129 0
10 Install Keyway in top of wall 117.00 lf 117.00 lf 0.00 lf 1.14 /lf 1.14 /lf 0.00 /lf 133 133 0
0000 Furnish Stem Walls Form Assembly 975.08 sf 975.08 sf 0.00 sf 2.70 /sf 2.70 /sf 0.00 /sf 2,633 2,633 0
0210 Form Stem Wall to 8' Tall 975.08 sf 975.08 sf 0.00 sf 4.53 /sf 4.53 /sf 0.00 /sf 4,413 4,413 0
30 Waterstop - RX Volclay 117.00 lf 117.00 lf 0.00 lf 2.71 /lf 2.71 /lf 0.00 /lf 316 316 0
0410 4000 PSI Reg. Wt. 1" Aggregate 14.23 cy 14.23 cy 0.00 cy 87.01 /cy 87.01 /cy 0.00 /cy 1,238 1,238 0
20 Place Wall Concrete 14.23 cy 14.23 cy 0.00 cy 23.30 /cy 23.30 /cy 0.00 /cy 332 332 0
38 Defin/Point Patch Walls 975.08 sf 975.08 sf 0.00 sf 0.381 /sf 0.381 /sf 0.00 /sf 372 372 0
Estimate Company Variance Report Page 3
Ameristar Lowrise 1/25/2013 3:07 PM
44 Stem Wall 975.08 csf 975.08 csf 0.00 9.81 /csf 9.81 /csf 0.00 9,565 9,565 0
50 Formed Deck
sb19 Concrete Pumping 6,742.860 cy 6,688.54 cy 54.320 cy 6.89 /cy 6.89 /cy 0.00 /cy 46,447 46,072 374
oh18 P.E Engineering Review & Stamp Shop Drawings 21.00 week 20.00 week 1.00 week 500.00 /week 500.00 /week 0.00 /week 10,500 10,000 500
oh18 Detailing Shop Drawings 21.00 week 20.00 week 1.00 week 1,747.20 /week 1,747.20 /week 0.00 /week 36,691 34,944 1,747
10 Miscellaneous Ties 258,093.00 tca 250,029.00 tca 8,064.00 tca 0.05 /tca 0.05 /tca 0.00 /tca 12,905 12,501 403
10 Caulk/Foam/Tape 258,093.00 tca 250,029.00 tca 8,064.00 tca 0.02 /tca 0.02 /tca 0.00 /tca 5,162 5,001 161
10 Nails/Form Oil 258,093.00 tca 250,029.00 tca 8,064.00 tca 0.03 /tca 0.03 /tca 0.00 /tca 7,743 7,501 242
10 Furnish & Install Hole/Opening Covers 3.00 each 3.00 each 0.00 each 232.403 /each 232.403 /each 0.00 /each 697 697 0
10 Early Morning Pour Set-Up/Lights Plants 15.00 pour 15.00 pour 0.00 pour 686.37 /pour 686.37 /pour 0.00 /pour 10,296 10,296 0
10 Furnish & Install Access Ladder 12.00 each 12.00 each 0.00 each 247.404 /each 247.404 /each 0.00 /each 2,969 2,969 0
10 Pump Grout Prime 15.00 pour 15.00 pour 0.00 pour 65.00 /pour 65.00 /pour 0.00 /pour 975 975 0
090 Anchor Bolt Templates 211.00 ea 189.00 ea 22.00 ea 29.101 /ea 29.101 /ea 0.00 /ea 6,140 5,500 640
115 Inst.Anchor Bolt-Medium 908.00 ea 756.00 ea 152.00 ea 7.03 /ea 7.03 /ea 0.00 /ea 6,379 5,311 1,068
0010 Install Embeds 20.00 wk 19.00 wk 1.00 wk 2,719.90 /wk 2,719.90 /wk 0.00 /wk 54,398 51,678 2,720
0000 Sides & Edges Shop Make-Up 9,912.00 sf 9,867.00 sf 45.00 sf 2.73 /sf 2.73 /sf 0.00 /sf 27,060 26,937 123
0000 Miscellaneous Field Make-Up 258,093.00 tca 250,029.00 tca 8,064.00 tca 0.014 /tca 0.014 /tca 0.00 /tca 3,504 3,394 109
0000 Scissor Lift 32' 2.00 ea 2.00 ea 0.00 ea 3,664.00 /ea 3,664.00 /ea 0.00 /ea 7,328 7,328 0
0000 Warehouse Forklifts 2.00 ea 2.00 ea 0.00 ea 2,701.00 /ea 2,701.00 /ea 0.00 /ea 5,402 5,402 0
0000 OSHA Railings Lumber Materials 8,415.00 bdft 8,415.00 bdft 0.00 bdft 0.50 /bdft 0.50 /bdft 0.00 /bdft 4,208 4,208 0
0000 Slab Soffit @ Loose (metal sheet) 32,500.00 sf 32,500.00 sf 0.00 sf 1.40 /sf 1.40 /sf 0.00 /sf 45,500 45,500 0
0000 Miscellaneous Lumber 9,243.00 bdft 9,189.00 bdft 54.00 bdft 0.60 /bdft 0.60 /bdft 0.00 /bdft 5,546 5,513 32
0000 Freight for Formwork Materials 7.00 ea 7.00 ea 0.00 ea 1,200.00 /ea 1,200.00 /ea 0.00 /ea 8,400 8,400 0
0000 Freight for Formwork Equipment 9.00 ea 9.00 ea 0.00 ea 1,200.00 /ea 1,200.00 /ea 0.00 /ea 10,800 10,800 0
0000 Steelbeams/Reshores/Scaffold 3.00 ea 3.00 ea 0.00 ea 1,200.00 /ea 1,200.00 /ea 0.00 /ea 3,600 3,600 0
0000 Ground Floor Forklift Operator 25.00 week 24.00 week 1.00 week 1,310.400 /week 1,310.400 /week 0.00 /week 32,760 31,450 1,310
0000 Slab Support w/ Scaffold Rental 32,500.00 sf 32,500.00 sf 0.00 sf 2.05 /sf 2.05 /sf 0.00 /sf 66,625 66,625 0
0000 Slab Support w/ Scaffold Rental (2 Frames) 411.00 sf 411.00 sf 0.00 sf 0.30 /sf 0.30 /sf 0.00 /sf 123 123 0
0410 Form & Strip Elevated Slab Expan. Jt. Form <=12" 287.00 lf 287.00 lf 0.00 lf 3.263 /lf 3.263 /lf 0.00 /lf 936 936 0
0610 Form & Strip Form Depression/Recess <= 12" 1,214.00 lf 1,214.00 lf 0.00 lf 10.051 /lf 10.051 /lf 0.00 /lf 12,202 12,202 0
0060 Form & Strip Construction Joint Bulkheads 10.00 ea 10.00 ea 0.00 ea 1,357.60 /ea 1,357.60 /ea 0.00 /ea 13,576 13,576 0
0060 Form & Strip Exterior Slab Edges 1,002.00 lf 998.00 lf 4.00 lf 2.263 /lf 2.263 /lf 0.00 /lf 2,267 2,258 9
0060 Form & Strip Exterior Over Wall Slab Edges 318.00 lf 311.00 lf 7.00 lf 4.53 /lf 4.53 /lf 0.00 /lf 1,439 1,407 32
0060 Form & Strip OSHA Rails @ Loose 4,300.00 lf 4,211.00 lf 89.00 lf 1.36 /lf 1.36 /lf 0.00 /lf 5,838 5,717 121
0010 Form & Strip Flat Slab Framing (Loose) @ 6'-0" 161,739.00 sf 161,331.00 sf 408.00 sf 3.394 /sf 3.394 /sf 0.00 /sf 548,942 547,557 1,385
0010 Form & Strip Flat Slab Framing (Loose) @ 23'-6" 383.00 sf 370.00 sf 13.00 sf 3.88 /sf 3.88 /sf 0.00 /sf 1,486 1,435 50
2017 Furnish & Install EJ.Dummy 2"Foam Board 244.25 sqft 244.25 sqft 0.00 sqft 1.07 /sqft 1.07 /sqft 0.00 /sqft 260 260 0
0510 5000 PSI Reg. Wt. 1" Aggregate 6,742.860 cy 6,688.54 cy 54.320 cy 90.20 /cy 90.20 /cy 0.00 /cy 608,206 603,306 4,900
05 Blow-Off Deck / Beam Formwork 184,791.00 sf 183,787.00 sf 1,004.00 sf 0.07 /sf 0.07 /sf 0.00 /sf 12,610 12,542 69
0100 Place/Finish Suspended Slabs-Smooth Trowel 184,791.00 sf 183,787.00 sf 1,004.00 sf 0.50 /sf 0.50 /sf 0.00 /sf 92,396 91,894 502
39 Defin/Point Patch Underside of Slab 184,791.00 sqft 183,787.00 sqft 1,004.00 sqft 0.15 /sqft 0.15 /sqft 0.00 /sqft 27,498 27,349 149
01 Membrane Curing Compound 184,791.00 sqft 183,787.00 sqft 1,004.00 sqft 0.043 /sqft 0.043 /sqft 0.00 /sqft 8,001 7,957 43
05 Sloped Premium 9,223.00 sqft 9,223.00 sqft 0.00 sqft 1.29 /sqft 1.29 /sqft 0.00 /sqft 11,898 11,898 0
05 Grout Column Base Plates 211.00 ea 189.00 ea 22.00 ea 30.80 /ea 30.80 /ea 0.00 /ea 6,498 5,820 678
50 Formed Deck 184,791.00 sf 183,787.00 sf 1,004.00 sf 9.612/sf 9.57 /sf 0.042/sf 1,776,209 1,758,841 17,368
55 Beam
sb19 Concrete Pumping 1,691.08 cy 1,653.77 cy 37.31 cy 6.89 /cy 6.89 /cy 0.00 /cy 11,649 11,392 257
0000 Loose Beam Forming Rental 1,873.00 lf 1,873.00 lf 0.00 lf 11.77 /lf 11.77 /lf 0.00 /lf 22,045 22,045 0
0000 Interior Beamsides Lumber Materials 25,121.00 bdft 25,077.00 bdft 44.00 bdft 0.60 /bdft 0.60 /bdft 0.00 /bdft 15,073 15,046 26
0000 Exterior Beamsides Lumber Materials 5,160.00 bdft 5,144.00 bdft 16.00 bdft 0.60 /bdft 0.60 /bdft 0.00 /bdft 3,096 3,086 10
0000 Loose Beam Forming BB-PINE Plywood 351.00 shts 351.00 shts 0.00 shts 28.00 /shts 28.00 /shts 0.00 /shts 9,828 9,828 0
0000 Interior Beamsides BB-PINE Plywood 315.00 shts 314.00 shts 1.00 shts 28.00 /shts 28.00 /shts 0.00 /shts 8,820 8,792 28
0000 Exterior Beamsides BB-PINE Plywood 62.00 shts 61.00 shts 1.00 shts 28.00 /shts 28.00 /shts 0.00 /shts 1,736 1,708 28
0060 Form & Strip Loose Beam @ 5'-6" 6,960.00 lf 6,736.00 lf 224.00 lf 18.101 /lf 18.101 /lf 0.00 /lf 125,985 121,931 4,055
0060 Form & Strip Loose Beam @ 24'-0" 29.00 lf 40.00 lf -11.00 lf 33.94 /lf 33.94 /lf 0.00 /lf 984 1,358 (373)
0060 Form & Strip Interior Beamsides 14,407.00 lf 14,054.00 lf 353.00 lf 6.79 /lf 6.79 /lf 0.00 /lf 97,795 95,399 2,396
Estimate Company Variance Report Page 4
Ameristar Lowrise 1/25/2013 3:07 PM
55 Beam
0060 Form & Strip Exterior Beamsides 2,806.00 lf 2,604.00 lf 202.00 lf 6.79 /lf 6.79 /lf 0.00 /lf 19,047 17,676 1,371
0060 Form & Strip Interior Soffit Drop 1,904.00 lf 1,931.00 lf -27.00 lf 4.53 /lf 4.53 /lf 0.00 /lf 8,616 8,738 (122)
0060 Form & Strip Over Wall Interior Beamsides 0.00 lf 31.00 lf -31.00 lf 13.58 /lf (13.576) /lf 421 (421)
0060 Column Beam/Intersections 28.00 ea 46.00 ea -18.00 ea 13.58 /ea 13.58 /ea 0.00 /ea 380 625 (244)
0060 Form & Strip Over Wall Exterior Beamsides 174.00 lf 298.00 lf -124.00 lf 13.58 /lf 13.58 /lf 0.00 /lf 2,362 4,046 (1,683)
0510 5000 PSI Reg. Wt. 1" Aggregate 1,691.08 cy 1,653.77 cy 37.31 cy 89.20 /cy 89.20 /cy 0.00 /cy 150,844 147,516 3,328
05 Blow-Off Deck / Beam Formwork 648.00 sf 584.00 sf 64.00 sf 0.07 /sf 0.07 /sf 0.00 /sf 44 40 4
0110 Place Concrete At Freestanding Beams 69.45 cy 61.91 cy 7.54 cy 23.88 /cy 23.88 /cy 0.00 /cy 1,658 1,478 180
0140 Finish Freestanding Beam Tops 648.00 sf 584.00 sf 64.00 sf 1.98 /sf 1.98 /sf 0.00 /sf 1,283 1,156 127
55 Beam 8,266.00 lf 8,099.00 lf 167.00 lf 58.22 /lf 58.313/lf (0.09) /lf 481,246 472,280 8,966
60 SOMD
sb19 Concrete Pumping 394.19 cy 301.23 cy 92.96 cy 6.89 /cy 6.89 /cy 0.00 /cy 2,715 2,075 640
10 Form Edge/Opening 1,350.00 lnft 577.00 lnft 773.00 lnft 5.89 /lnft 5.89 /lnft 0.00 /lnft 7,951 3,398 4,553
0410 4000 PSI Reg. Wt. 1" Aggregate 394.19 cy 301.23 cy 92.96 cy 87.01 /cy 87.01 /cy 0.00 /cy 34,298 26,210 8,088
05 Blow-Off Metal Deck 19,460.00 sqft 16,132.00 sqft 3,328.00 sqft 0.05 /sqft 0.05 /sqft 0.00 /sqft 907 752 155
0010 Place/Finish Slab On Metal Deck - Smooth 19,460.00 sf 16,132.00 sf 3,328.00 sf 0.50 /sf 0.50 /sf 0.00 /sf 9,730 8,066 1,664
aTrowel
01 Membrane Curing Compound 19,460.00 sqft 16,132.00 sqft 3,328.00 sqft 0.043 /sqft 0.043 /sqft 0.00 /sqft 843 698 144
60 SOMD 19,460.00 sf 16,132.00 sf 3,328.00 sf 2.901/sf 2.554/sf 0.35 /sf 56,444 41,199 15,245
75 Tpng on Foam
sb19 Concrete Pumping 13.07 cy 13.07 cy 0.00 cy 6.89 /cy 6.89 /cy 0.00 /cy 90 90 0
0100 40 psi HD Foam 1,115.00 cf 1,115.00 cf 0.00 cf 6.432 /cf 6.432 /cf 0.00 /cf 7,172 7,172 0
0410 4000 PSI Reg. Wt. 1" Aggregate 13.07 cy 13.07 cy 0.00 cy 87.01 /cy 87.01 /cy 0.00 /cy 1,137 1,137 0
0010 Place/Finish Topping - Smooth Trowel 669.00 sf 669.00 sf 0.00 sf 0.50 /sf 0.50 /sf 0.00 /sf 335 335 0
01 Membrane Curing Compound 669.00 sqft 669.00 sqft 0.00 sqft 0.043 /sqft 0.043 /sqft 0.00 /sqft 29 29 0
10 Floor CleanUp-Broom 669.00 sqft 669.00 sqft 0.00 sqft 0.11 /sqft 0.11 /sqft 0.00 /sqft 72 72 0
75 Tpng on Foam 669.00 sf 669.00 sf 0.00 13.21 /sf 13.21 /sf 0.00 8,835 8,835 0
95 Hoisting
cr30 Crawler Crane Freight 2.00 each 2.00 each 0.00 each 13,000.00 /each 13,000.00 /each 0.00 /each 26,000 26,000 0
cr35 Crawler Crane Opr/Fuel/Rental 25.00 week 24.00 week 1.00 week 10,937.31 /week 10,937.31 /week 0.00 /week 273,433 262,495 10,937
95 Hoisting 299,433 288,495 10,937
96 Reinforcing
0010 Rebar (Black) (Sub Install) 2,428,838.35 lbs 2,314,281.85 lbs 114,556.50 lbs 0.55 /lbs 0.55 /lbs 0.00 /lbs 1,335,861 1,272,855 63,006
w 20 WWF - 6x6-W2.9/W2.9 SOMD 240.00 sq 192.00 sq 48.00 sq 56.083 /sq 28.271 /sq 27.812 /sq 13,460 5,428 8,032
96 Reinforcing 1,349,321 1,278,283 71,038
98 Misc Work
146 Washout Area - Washing out concrete truck 25.00 week 24.00 week 1.00 week 208.184 /week 208.184 /week 0.00 /week 5,205 4,996 208
sb10 Surface Dewatering 15.00 week 15.00 week 0.00 week 715.92 /week 715.92 /week 0.00 /week 10,739 10,739 0
sb10 Miscellaneous Freight 10.00 ea 10.00 ea 0.00 ea 1,200.00 /ea 1,200.00 /ea 0.00 /ea 12,000 12,000 0
sb10 Plans/Printer 10.00 set 10.00 set 0.00 set 125.00 /set 125.00 /set 0.00 /set 1,250 1,250 0
sb10 Meeting Catering 25.00 week 24.00 week 1.00 week 75.00 /week 75.00 /week 0.00 /week 1,875 1,800 75
sb10 Safety Lunch 10.00 ea 10.00 ea 0.00 ea 500.00 /ea 500.00 /ea 0.00 /ea 5,000 5,000 0
sb10 Trailer Cleaning/Maintenance 25.00 week 24.00 week 1.00 week 35.00 /week 35.00 /week 0.00 /week 875 840 35
sb10 Laydown/Tools Man 25.00 week 24.00 week 1.00 week 1,164.80 /week 1,164.80 /week 0.00 /week 29,120 27,955 1,165
sb10 Ice Drinking Water/Water Technician 25.00 week 24.00 week 1.00 week 1,031.84 /week 1,031.84 /week 0.00 /week 25,796 24,764 1,032
sb10 Printing Cost 1.00 ea 1.00 ea 400.00 /ea 400.00 /ea 400 400
sb10 Estimating 24.00 hrs 24.00 hrs 50.00 /hrs 50.00 /hrs 1,200 1,200
Estimate Company Variance Report Page 5
Ameristar Lowrise 1/25/2013 3:07 PM
98 Safety
15 Safety Supplies (Hard Hats, Harness, Tools, etc) 64,768.00 mhr 60,061.00 mhr 4,707.00 mhr 0.65 /mhr 0.65 /mhr 0.00 /mhr 42,099 39,040 3,060
25 Perimeter Safety Rails And Toe Boards After 4,300.00 lf 4,211.00 lf 89.00 lf 3.842 /lf 3.842 /lf 0.00 /lf 16,520 16,178 342
Forms Removed
26 Maintain Perimeter Safety Rails 25.00 wks 24.00 wks 1.00 wks 431.01 /wks 431.01 /wks 0.00 /wks 10,775 10,344 431
100 OSHA 10 Training 30.00 man 30.00 man 0.00 man 336.21 /man 336.21 /man 0.00 /man 10,086 10,086 0
98 Safety 79,480 75,648 3,832
99 GC's
10 Project Manager (Inluded in Hotel) 27.00 week 26.00 week 1.00 week /week
15 Project Superintendent 27.00 week 26.00 week 1.00 week 2,970.80 /week 2,970.80 /week 0.00 /week 80,212 77,241 2,971
20 Project Engineer 25.00 week 24.00 week 1.00 week 1,731.00 /week 1,731.00 /week 0.00 /week 43,275 41,544 1,731
26 Layout Crew 25.00 week 24.00 week 1.00 week 3,908.20 /week 3,908.20 /week 0.00 /week 97,705 93,797 3,908
35 Non Working Safety Officer 25.00 week 24.00 week 1.00 week 1,826.60 /week 1,826.60 /week 0.00 /week 45,665 43,838 1,827
30 Per Diem (60% direct labor) 716.00 week 700.00 week 16.00 week 200.00 /week 200.00 /week 0.00 /week 143,200 140,000 3,200
12 Temporary Electricity 25.00 week 24.00 week 1.00 week 200.00 /week 200.00 /week 0.00 /week 5,000 4,800 200
24 Telephone Service 25.00 week 24.00 week 1.00 week 75.00 /week 75.00 /week 0.00 /week 1,875 1,800 75
25 Cell Phone 75.00 week 72.00 week 3.00 week 35.00 /week 35.00 /week 0.00 /week 2,625 2,520 105
10 Field Office 25.00 week 24.00 week 1.00 week 100.00 /week 100.00 /week 0.00 /week 2,500 2,400 100
11 Office Furniture/Equipment 25.00 week 24.00 week 1.00 week 75.00 /week 75.00 /week 0.00 /week 1,875 1,800 75
12 Office Supplies 25.00 week 24.00 week 1.00 week 50.00 /week 50.00 /week 0.00 /week 1,250 1,200 50
20 Tool Trailer 25.00 week 24.00 week 1.00 week 30.00 /week 30.00 /week 0.00 /week 750 720 30
05 Baker Trucks 75.00 week 72.00 week 3.00 week 200.00 /week 200.00 /week 0.00 /week 15,000 14,400 600
35 Outside Equipment Rental 25.00 week 24.00 week 1.00 week 2,070.15 /week 2,070.15 /week 0.00 /week 51,754 49,683 2,070
39 Baker Equipment Rental 25.00 week 24.00 week 1.00 week 2,070.15 /week 2,070.15 /week 0.00 /week 51,754 49,683 2,070
40 Tools/Fuel 25.00 week 24.00 week 1.00 week 2,070.15 /week 2,070.15 /week 0.00 /week 51,754 49,684 2,070
ew40 Rubbertire Loader/Hoe 1/2cy 15.00 week 15.00 week 0.00 week 300.00 /week 300.00 /week 0.00 /week 4,500 4,500 0
30 General Clean Up-Labor 25.00 week 24.00 week 1.00 week 1,164.80 /week 1,164.80 /week 0.00 /week 29,120 27,955 1,165
99 GC's 25.00 week 24.00 week 1.00 week 25,192.504/week 25,315.24 /week (122.736)/week 629,813 607,566 22,247
Estimate Totals