DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY

SNAG LIST (STAFF QUARTERS 1 & 2)


DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT

1 External Graffi Repair of damaged areas

2 Internal Graffi Repair of damaged areas


Shall be cleaned properly & in some areas
3 Internal flooring (Floor Tiles)
motives are missing which shall be fixed
Joint filling to be done properly & proper cleaning
4 Toilets and kitchen area tile work
required
5 Marble for Kitchen slab and door steps/threshold Edges shall be round properly and polished
Proper cleaning required and gasket shall be
6 windows and ventilator installation
fixed on inner face for waterproofing
7 Door frames Cleaning & Polish required

8 Door Shutters Cleaning & Polish required


1: Repair of Shutters and alignment
9 Kitchen Cabnets 2: Proper plaster required in floor mounted
cabnets
10 Wooden carving sections 18" x 60" on external façade Polish final coat required

11 Paint work 1 Coat required

12 MS Wicket door in lawn Paint final coat required

Minor repairs & tests required & Plastic cover


13 Electrical Wiring, Telephone cable and TV cable wiring
sheets shall be fixed on all extra points
Tv sockets to be checked & 5 pin sockets shall
14 Electrical switch board, lights & other fixtures installation
be installed 1 in each room
All connection need to be checked & Tags must
15 Electrical DB
be palced on each breaker
All fixtures shall be cleaned properly & Testing
16 Internal Plumbing work in toilets and Kitchen
required
17 External plumbing works Testing required

18 Rain water pipes To be fixed properly

19 Gas pipe line Testing required

Roof Khurra shall be completed as per drawing &


20 Roof treatment Joint of rainwater pipe with parapet wall shall be
filled with cement sand mortar properly

21 Bottom khurra below rain water pipe Shall be constructed as per drawing

22 Construction of man holes and gully traps Covers shall be fixed properly

23 External hard lanscaping and plinth protection Reapir of cracked areas

24 Valve on toilet supply line Shall be installed outside each toilet

ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS