Tooling Management
5. PURPOSE
5.6. The purpose of this document is to establish and implement a system for tooling
management, including the identification, storage, retrieval, and disposition of
tooling.
6. SCOPE
6.6. This procedure applies to all tooling maintained by (company name).
7. RESPONSIBILITY
7.6. The Stamping Operations Manager, Vice President of Engineering, and Vice
President / General Manager of Fabrication Division have the primary
responsibility for ensuring compliance of this procedure and to ensure the
necessary resources for successful implementation are provided.
7.7. The Sales, Information Services, Purchasing, Engineering, Tool Room, and
Production Personnel who support the identification, storage, retrieval, and
dispositioning of tooling are responsible for compliance with this procedure.
8. REFERENCE DOCUMENTS
8.6. Quality System Manual
8.7. Quotations (PCS001)
8.8. Order Acceptance (PCS002)
8.9. Order Amendment (PCS003)
8.10. Control of Part Master (PDE003)
8.11. Fabrication Division System Controls (PFD001)
8.12. Information Services (PIS001)
8.13. Advanced Product Quality Planning (PQC004)
8.14. Document & Data Control (PQC008)
8.15. First Article Inspection (PQC007)
8.16. Control of Quality Records (PQC020)
8.17. Tooling Design & Fabrication (PTR002)
8.18. Tooling Repair & Perishable Tooling (PTR003)
9. REQUIRED DOCUMENTS/MATERIAL
9.6. (Company) Computer System
9.6.1. Part Master
9.6.1.1. Tooling Master
Page 1 of 9
SYSTEM PROCEDURE
Tooling Management
Page 2 of 9
SYSTEM PROCEDURE
Tooling Management
Page 3 of 9
SYSTEM PROCEDURE
Tooling Management
22.7.2. The Tool Room shall be responsible for placing the Tool Number
from the (COMPANY NAME) Tooling Master for Tooling utilized in the
Stamping Operations. The Engineering Department for Fabrication
shall be responsible for placing the Tool Number from the
(COMPANY NAME) Tooling Master on Fabrication tooling. The
primary method of placing the Tool Number on the tooling shall be as
follows:
NOTE: Ownership of Tools shall be identified via the WTS Tool Master.
26.6.2. The Jeep Driver shall notify Engineering of the assigned storage
location for the tool after First Article Inspection.
Page 4 of 9
SYSTEM PROCEDURE
Tooling Management
26.7.3. The Tool Room Supervisor / Lead Person shall coordinate with the
Jeep Driver as to the Tools to be serviced or repaired.
29.6.1. If the Customer has not requested that the tools be returned or
scrapped and the tooling has not been used for an extended period
of time, then Sales Engineering or Customer Service shall work with
contact the customer to determine whether the tool is to be:
30. Kept in Service
31. Returned to the Customer or Other Location
32. Scrapped.
Page 5 of 9
SYSTEM PROCEDURE
Tooling Management
32.6.3. The Tool Room Supervisor / Lead Person shall ensure that the
authorized disposition is carried out and the completed actions
documented on the Tooling Disposition Record.
32.6.4. Upon completing the Tooling Disposition Record the Tool Room
Supervisor / Lead Person shall return it to the originating Sales
Engineer or Customer Service.
Page 6 of 9
SYSTEM PROCEDURE
Tooling Management
Tooling Management
35. RECORDS
35.6. (COMPANY NAME) Computer System
35.6.1. Tooling Master
35.6.2. Part Master
35.7. Tool Assignment Log
35.8. Plant Layout Drawing (FDE008)
35.9. New Die Checklist (FTR004)
35.10. Tooling Disposition Record (FTR010)
REVISION DATE OF
SECTIONS DESCRIPTION OF CHANGE
LEVEL REVISION
00 9/14/99 All Re-Issue of Procedure for QS-9000 Registration
The majority of the changes are due to the Organizational
Change where the Tool Room went under the Stamping
Operations Manager from the VP of Engineering. Those
changes that are not are due to corrective and preventive
01 02/19/01 All actions required by CPARs initiated during internal Quality
System Audits.
Section 7 was added to help see the inter-relationships
between the recently established organizational
responsibilities.
Correction The concept of Press Grouping was added to the step
01 7.0
03/05/01 involving the scheduling of the F.A.I.R.
37. AUTHORIZATION
Page 8 of 9
SYSTEM PROCEDURE
Tooling Management
Page 9 of 9