Steps in constructing 3 storey building

1. Clearing and Grubbing


2. Excavation
3. Back fill
4. Footing
 Rebar
 Formworks
 Concreting
5. Columns
 Rebar
 Formworks
 Concreting
6. Groundflr (Slab – Slab on Grade)
 Rebars
 Formworks
 Concreting
7. Groundflr (columns)
 Rebars
 Formworks
 Concreting
8. Groundflr Stairs
 Formworks
 Rebars
 Concreting
9. 2nd flr- Slab/ beam/ girders
 Formworks
 Rebars
 Concreting
10. 2nd fr Columns
 Rebars
 Formworks
 Concreting
nd
11. 2 flr stairs
 Formworks
 Rebars
 Concreting
12. SAME PROCESS FOR 2nd floor and 3rd floor
13. Roof beams, Roof trusses, GI Sheets
14. Architectural
 Groundfloor
1. Masonry works
 Doors & windows
 Finishes (Painting)
 Specialties
2. 2 flr and 3rd flr same with ground flr
nd

15. MEPF (Mechanical, Electrical, Plumbing and Fire proof)


 Electrical and Plumbing
1st, 2nd and 3rd fix