Testing and Comissioning of Micro & Mini Hydropower Plants
A. Salient Features
B. Technical Status
B.1 Intake
Type of intake: Permanent/Temporary
If permanent, any cracks observed: Yes/No
Any leakage observed: Yes/No
Trash rack at intake: Installed/Not installed
If installed, Clearance: mm,
Any structured cracks observed: Yes/No
Type of Trash rack: metal/local (special)
Flow controlling mechanism: Sluice gate/wooden stop logs/bush-boulder/Others (specify)
Remarks on Intake - Briefly discuss any major defects observed.
B.2 Headrace
Length of headrace (section 1): m Type of headrace (section 1): open earth/open
Rectangular/Trapezoidal/Triangular Cemented, DPE conduit/others (specify)
Length of head race (section 2): m Type of head race (section 2): open earth/open
Rectangular/Trapezoidal/Triangular cemented/HDPE conduit/others (specify)
Length of headrace (section 3): m Type of head race (section 2): open earth/open
Rectangular/Trapezoidal/Triangular cemented/HDPE conduit/others (specify)
Any leakage observed: Yes/No
Any cracks observed: Yes/No
Remarks on Headrace – Briefly discuss any major defects observed
-1-
Testing and Comissioning of Micro & Mini Hydropower Plants
·B.3 Forebay
Type of Forebay: Stone masonry in c/RCC/Others (specify)
Trash rack: Installed/Not installed
If installed, Clearance: mm,
Any structured cracks observed: Yes/No
Type of Trash rack: metal/local (specify)
Spillover: incorporated/not incorporated
Flushing arrangement: Works weIl/defects observed
-2-
Testing and Comissioning of Micro & Mini Hydropower Plants
B.7 Powerhouse
L______m B____ m H _______m
Powerhouse size (internal):
Construction: Stone masonry in c/Dry stone/Others (specify)
Powerhouse roof: Corrugated GI/Plain GI/Others (specify)
Powerhouse floor: Compacted earth/Dry stone slabs/Cemented
Adequate working space for O/M: Yes/No
Cleanliness: Yes/No
Adequate lighting in PH: Yes/No
Free of undue leakages: Yes/No
Tailrace safely disposed off: Yes/No
Earthing done properly: Yes/No (Earth resistance < 10 ohm:)
Remarks on Powerhouse - Briefly discuss any major defects observed
B.8 Tailrace
Construction: Stone masonry in c/Earth/Others (specify)
Section: Rectangular/Trapezoidal/Triangular
Condition of tailrace: good/bad
Any cracks observed in structure: Yes/No
Remarks on Tailrace - Briefly discuss any major defects observed
-3-
Testing and Comissioning of Micro & Mini Hydropower Plants
B.10 Generator
Specification:
Type: Synchronous/Induction
Phase: 3 -phase/ 1-phase Voltage: ______V
Capacity: _______kW PF _______
RPM _______min-1 Full load current: _______A
Frequency: _______Hz
Insulation class: Protection class: _______IP
Manufacturer:
Earthing done properly: Yes/No (Earth resistance < 10 ohm)
Remarks on Generator: - Briefly discuss any major defects observed
-4-
Testing and Comissioning of Micro & Mini Hydropower Plants
-5-
Testing and Comissioning of Micro & Mini Hydropower Plants
-6-
Testing and Comissioning of Micro & Mini Hydropower Plants
Remarks on electrical lines: Briefly discuss any defects observed in construction, finishing, cable jointing
and terminations, service cable tapping, bedding, clearance and safety of transmission and distribution
system.
Transformers:
Type:_________ No:__________
no load________ _________load
no load_________ _________load
-7-
Testing and Comissioning of Micro & Mini Hydropower Plants
Remarks
House Connections:
connection: wires/single/cables/PV cables/other diameter:_____mm²
Meter: No/Mechanic/Electronic _____nominal current A
safety devices installed Yes/No Type: Ordinary fuses/breaker/earth fault current switch
Nominal A:_________ fault current:__________ mA
-8-
Testing and Comissioning of Micro & Mini Hydropower Plants
-9-
Testing and Comissioning of Micro & Mini Hydropower Plants
- 10 -
Testing and Comissioning of Micro & Mini Hydropower Plants
3a Switch OFF village load Time to return to steady state condition: _______ sec
Switch ON village
3b Time to return to steady state condition: _______ sec
load
3c For Micro Hydros: Power factor of village load should be maintained at no worse than 0.8. For this,
if some tube lamps are used, total wattage due to tube lamps should not be more than about one -
third of total wattage due to incandescent lamps (or resistive loads).
Calculate approx. total power produced, P = Generated voltage x Feeder line current x Power
4
factor
Give the Value power produced, P:______ kW
Guaranteed power produced (acceptable) 口
Guaranteed power not produced (not acceptable - critical) 口
For Micro Hydros: Calculate approximate power factor = Cos [tan-1 {P2 x 1.73} / {P 1 + P2}),
5
Where, P1 = total resistive wattage; P2 = total tube lamp wattage; power factor of tube lamp 0.5
6 Calculate water to wire efficiency = P x 102/(Hg x Q) =
- 11 -
Testing and Comissioning of Micro & Mini Hydropower Plants
- 12 -
Testing and Comissioning of Micro & Mini Hydropower Plants
4. Earth fault test trip and simulation test (in case of under ground lines)
a. Successful (acceptable) 口
b. Unsuccessful (not acceptable - non critical) 口
5. 110% sustained over current simulation test result
a. De excites (acceptable) 口
b. Under-voltage operation below 20% (not acceptable - critical) 口
c. Feeder breaker trips (acceptable) 口
d. Generator over heats (not acceptable - critical) 口
e. Nothing happens (acceptable provided feeder load switching off does not cause more than
10% over voltage or excitation breakers trip)
- 13 -
Testing and Comissioning of Micro & Mini Hydropower Plants
D Performance Test
The performance test includes a 36 hour continuous operation for Micro hydropower and 72 hours
continuous operation for Mini hydropower plants.
Operation recorded (hourly basis) in operation diary: Yes/No
Plant operation was well without any defect/interruption in operation Yes/No
if No please specify:
- 14 -
Testing and Comissioning of Micro & Mini Hydropower Plants
Signature of
Signature of Inspector Signature of Owner
Installer/Supplier
Name: Name: Name:
2. Installation conditionally accepted provided all defects are of non-critical type and that they
Signature of
Signature of Insepctor Signature of Owner
Installer/Supplier
Name: Name: Name:
3. Installation not accepted as one or more of the defects are of critical type_
- 15 -
Testing and Comissioning of Micro & Mini Hydropower Plants
Time
05 10 15 20 25 30 35 40 45 50 55 60 Sum
(sec)
1
2
3
Water conductivity in µS
4
5
Minutes
7
8
9
10
TOTAL:
Note that the "Area" here is the area under the graph of conductivity in μS in the vertical axis and
time in second in the horizontal axis excluding the baseline conductivity (i.e., conductivity measure
before pouring the salt solution upstream). Hence, the units of "Area" under the graph are μS*Sec.
Q=Mk/A
Note:
Use separate sheet if other method has been used for flow
measurement.
Give minimum estimated flow using MIP method.
- 16 -
Testing and Comissioning of Micro & Mini Hydropower Plants
Pressure gauge
Valve position
weir height
Discharge
Total
Total
UAN IA pf PA UBN IB pf PB UCN IC pf PC Freq. UAb UBb UCb PA PB PC Ballast Remarks
Power
Power
(V) (A) (kW) (V) (A) (kW) (V) (A) (kW) (kW) (Hz) (V) (V) (V) (kW) (kW) (kW) (kW) (m) (m³/s) (kg/cm²) (%)
1
2
3
4
5
6
Design Flow
Design Head (m): (m³/s): Design Power (kW): Minimum Power requirement (kW):
Actuval Flow
Actual Head (m): (m³/s): Actual Power (kW): Stream Flow at Intake (m³/s):
I/We hereby certify that I/we have measured and ferified power outpur from the MHP.
I/we hereby certify that the measured power output for the design flow of this installation is _______ kW
Inspector: