Project : BOI Horana STEMS


Design of Combined Footing F3 STEMS CONSULTANTS (PTE) LTD
Date: 16/04/2000
Designed: S A Karunaratne
Reinforcement fy = 460 N/mm2
Materials

Concrete fcu = 25 N/mm2 L1 = X= L3 =


Density of Concrete 24 kN/m3 0.15 2.133 0.417
Allowable Bearing Pressure pall = 100 kN/m 2 W1 = L2 = W2 =
350 4 400
Service Load W1 = 350 Kn
Ultimate Column Load N1 = 1000 kN L = L1+L2+L3 = 4.567
Service Load W2 = 400 Kn BW = 300
Ultimate Column Load N2 = 1200 kN
Data

Distance boundary to column L1 = 0.15 m BD = 600


Distance between columns L2 = 4 m
Assume foundation thickness TF = 250 mm TF =
Depth of beam BD = 600 mm 250 BF = 1795
Width of beam BW = 300 mm

Approximate Pad Area A=(W1+W2)/pall 8.2 m2


C G from W1 X= W2L2/(W1+W2) 2.133 m
For uniform pressure L= 2(L1+X) 4.567 m
Distance from W2 L3 = L-L1-L2 0.417 m
Width of footing BF = A/L 1795 m
Design and Output I

407034065.xls
STEMS

Project : BOI Horana


STEMS
Design of Combined Footing F3 STEMS CONSULTANTS (PTE) LT
Date: 16/04/2000
Designed: S A Karunaratne
Desidn Output II
Design Output III
Design output IV

407034065.xls
STEMS

ANTS (PTE) LTD

407034065.xls

Vous aimerez peut-être aussi