Extraction Characterization and Evaluation of Phaseolus vulgaris seed mucilage as a binder affecting the

release profile of Metformin HCl tablets


GANTT CHART (REVISED)
Implementation Period: September 3, 2018 – December 21, 2018

WEEK #1 – SEPTEMBER 1 – SEPTEMBER 8


TARGET DATE LATEST DATE C/O
o Collection of Baguio Beans (source, payment, contact) H
SEPT 1 (SAT) SEPT 3 (MON)
o Know the process of Authentication (arrange papers) H,C
o Plant Authentication in DLSUD
ALL
o MX4 FUND: 100 PESOS
SEPT 3 (MON) o Order Reagents for Extraction (Ask Ma’am Ning) C
o List down all glassware/Materials for Extraction ONLY G, A
SEPT 6 (THU) o Search for source of Metformin HCl Standard A
o MX4 FUND: 100 PESOS
o Finalize Extraction Procedure (4th F, Multipurpose) ALL
SEPT 5 (WED) o Finalize PhysicoChemical Procedure and results
o Visit Plant Authentication A
o Follow-up on Plant Authentication A
o Follow-up on Order of Reagents C
SEPT 7 (THU)
o Buy all materials needed (i.e. cheese cloth, tissue) HCG
SEPT 8 (FRI) o Create SchemDi for Extraction and PhysicoChem HCG
o MX4 FUND: 100 PESOS
SEPT 8 (FRI) o Follow-up on Plant Authentication ALL
o Follow-up on Order of Reagents