Anna University Exams Nov/Dec 2018 – Regulation 2013

Rejinpaul.com Unique Important Questions – BE/BTECH

CE6704 ESTIMATION AND QUANTITY SURVEYING


PART B & PART C IMPORTANT QUESTIONS
PART – B

1. (i) List the general rules of measurements.


(ii) Explain the deductions and additions to be applied in the case of

om
estimation of plastering.
2. From the given figure below calculate the detailed estimate for the
single roomed building (Load bearing type structure) by Longwall-
short wall method.
3.

4. .c
From the given figure calculate the details and abstract estimate for the
single Storied residential building by centre line method.
(i) Calculate the quantity of brickwork in a semi-circular arch of 2.2m span,
ul
50cm rise and 30cm thick. The breadth of the wall is 40cm.
(ii) An arch of 2.5m span subtens an angle of 80 ͦ at the centre. The thickness
pa
of arch is 40cm. Calculate the quantity of arch masonry work.
5. (i) Calculate the quantity of brickwork in a 60 ͦ arch over a door of 1.2m
wide. The thickness of arch is 20cm & that of wall is 30cm.
(ii) Calculate the quantity of brickwork in a semi-circular arch of 2m span,
in

the thickness of arch is 30cm & breadth of wall is 40cm.

6. (i) Describe the different types of estimate.


ej

(ii) Explain the methods used to find the approximate cost of the building.
R

7. Workout the quantities of materials required for the following works:


(i) First class brickwork in CM 1:5-1m3
(ii) Plastering in CM 1:6, 12mm thick-10m2
8. Prepare a detailed estimate of a septic tank with soak pit for 25 users
from the drawing. Septic tankshall be of first class brickwork in 1:4
cememt mortar the foundation and floor shall be of 1:3:6 cement
concrete. Inside of septic tank shall be finished with 12mm cement
plaster & floor shall be finished with 12mm 20mm cement plaster with

Download Important Question from rejinpaul.com & also refer your friends!!
1:3 mortar mixed with standard water proofing compound. Upper &
lower portion of soak pit shall be of second class brickwork in 1:6
cement mortar& middle portion shall be of dry brickwork. Roof
covering slabs & baffle wall shall be of preacst RCC. The length of the
connecting pipe from latrine seat may be taken as 3m.
9. Prepare a detailed estimate of a septic tank with soak pit for 50 users
together with sanitary fittings of one seat of latrine from the given
drawing. Septic tank shall be of first-class brick masonry 1:4 cement

om
mortar over cement concrete 1:3:6 foundation & base, with RB
partition wall & RCC slab cover. Inside of tank including floor shall be
12mm cement plastered 1:2 mortar mixed with water proofing material.
Soak pit shall be of second-class brick masonry with 1:6 cement
mortar. Estimate for water arrangements should also be made with a

.c
250l GI overhead tank connecting flusting cistern of WC & a water tap,
assuming that there is a pipe water supply within 10m of the latrine.
ul
10 A road is to be constructed in a side long ground partly in cutting &
. partly in banning. The formation width of road is 10m, cross slope of
ground is 6:1, side slope in banking 2:1 & in cutting 1.5:1, depth of
pa

cutting at centre is 45cm. calculate the quantity of earthwork in banking


& in cutting for a length of 200m. Estimate the cross cost of the making
formation of road with the rate of the earthwork is Rs. 1500 per m3.
11 Explain Mid sectional area method of calculating earthwork in road
in

. estimating.
12 Prepare a detailed estimate of box culvert-
. • Earthwork excavation
ej

• Brickwork in cement mortar 1:4 in abutment


• RCC 1:2:4 for culvert slab
• Brickwork in cement mortar 1:5 in parapet wall
R

• PCC 1:5:10

DIAGRAMS

Download Important Question from rejinpaul.com & also refer your friends!!
1..

om
.c
ul
pa
in
ej
R

Download Important Question from rejinpaul.com & also refer your friends!!
om
.c
ul
pa
in
ej
R

Download Important Question from rejinpaul.com & also refer your friends!!
om
.c
ul
pa
in
ej
R

Download Important Question from rejinpaul.com & also refer your friends!!
om
.c
ul
.
pa
in
ej
R

Download Important Question from rejinpaul.com & also refer your friends!!
UNIT III, IV & V

1. Prepare a detailed estimate of a masonry well of 2m dia and 14m deep exclusive
the curb, the soil water level being 3.8m below G.L. The steining of well is of 30cm
thick of first class brick masonry in 1:6 CM. The inside and exposed surfaces shall
be pointed with 1:2 CM. The well should be raised 60cm above GL and an apron
of 4cm C.C over 7.5cm L.C. 1 meter wide shall be provided all around the well.

om
The curb shall be of RCC with 75x75x6mm angle iron cutting edge.
2. Prepare a detailed estimate of slab culvert of 1.5m span & 4m roadway from the
given drawing. The general specification are as follows:
Foundation concrete shall be of cement concrete 1:3:6 with stone ballast & coarse
sand. Masonry shall be of first class brick work in 1:4 cement coarse sand

.c
mortars. Slab shall be of RCC 1:2:4 with reinforcement. Exposed surface of brick
masonry shall be cement pointed 1:2. Road shall be provided with cm thick
wearing coat of 1:2:4 cement concrete.
ul
3. Prepare an estimate of 50mm dia tube well 100m deep with deep well pump from
the given drawing. The strainer will consist of 3 pieces of 1.5 m each. The housing
pa

pipe consists of 70mm dia GI pipe 6m in length.


4. What are the characteristics of good specifications?
Write detailed specification of the following cement concrete 1:2:4
in

5. (i)Explain the various types of contract system. (ii)Write short notes on


arbitration and tenders.
ej

6. Discuss about three forms of contractors.


7. Prepare the detailed estimate of quantities for the following items for a 100m
length of retaining wall. (i) Brickwork in CM 1:4 (ii) PCC 1:4:8 (iii)Number of
R

bricks (iv) Number of cement bags


8. (i) Explain the sequential procedure of opening of tenders. (ii)Explain the legal
requirements for arbitration.
9. (i)Explain the principles of specification writing. (ii)Typical specifications for
RCC.
10. Explain the sequential procedure of opening of tenders. (ii) Explain the
legal requirements for arbitration.
11. General specifications of first-class building.
12. General specifications of second- & third-class buildings.

Download Important Question from rejinpaul.com & also refer your friends!!
DIAGRAMS
1.

om
.c
ul
pa
in
ej
R

Download Important Question from rejinpaul.com & also refer your friends!!
2.

om
.c
ul
pa
in
ej
R

3.

Download Important Question from rejinpaul.com & also refer your friends!!
om
.c
ul
pa
in
ej
R

4.

Download Important Question from rejinpaul.com & also refer your friends!!
om
10.

.c
ul
pa
in

13. Explain in detail how you will work out standard rent of a Government
ej

building.
14. Write a report to accompanying an Estimate for a village water supply
R

scheme.
15. (i) Explain different forms of value.(ii) Discuss about a Freehold property
16. (i)An owner occupied property is required to be valued for the wealth tax
purpose on land and building. The following particulars are available. Find the
present value of the property.
Value of the land = Rs. 400000
Cost of the building to put up such

Download Important Question from rejinpaul.com & also refer your friends!!
A building at present = Rs. 1000000
Estimate cost of repairs = Rs. 500000
Depreciation to be allowed for the building = 0.75% per annum
(ii)Explain different forms of value.
17. Calculate the standard rent of a government residential building newly
constructed from the following data.

om
(i) Cost of land- Rs.10,000
(ii) Cost of construction of the building – Rs.40,000
(iii) Cost of road within the compound and fencing – Rs.20000
(iv)
(v)
.c
Cost of electrical installation including fans 8% of cost of building
Municipal house tax-Rs.400 per annum
ul
(vi) Water tax – Rs.250 per annum
(vii) Property tax- Rs.140 per annum
pa

18. What are the methods of determining the depreciations? Explain with an
example Depreciation based method of valuation of a property.
19. Write a model report on estimate of residential buildings.
in

20. Write a model report on estimate of roads.


21. Explain the methods of valuation.
ej

22. Explain the procedure for preparation of reports.


23. Prepare the report on estimate of culvert.
R

24. (i)An old building has been purchased by a person at a cost of Rs.30000
excluding the cost of land. Calculate the amount of annual sinking fund at 4%
interest assuming the future life of the building as 20 years and the scrap value
of the building as 10 % of the cost of purchase.
(ii)Calculate the standard rent of a government residential building newly
constructed from the following data: cost of land-Rs.10000. cost of
construction of the building-Rs. 40000. Cost of roads within the compound and
fencing Rs.20000. Cost of electric installation including fans 8% of the cost of

Download Important Question from rejinpaul.com & also refer your friends!!
the building. Municipal house tax-Rs. 400 per annum. Water tax-Rs.250 per
annum. Property tax- Rs.140 per annum.
25. Discuss the importance of valuation.
26. Factors to be considered in water supply and sanitation installations.

om
.c
ul
pa
in
ej
R